PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)

01.01.00 TRABAJOS PRELIMINARES


01.01.01 CARTEL DE IDENTIFICACION OBRA DE 3.60m x 2.40m UND 1.00
1 1.00

01.01.02 MOVILIZACION DE EQUIPO Y HERRAMIENTAS GBL 1.00


1 1.00

01.01.03 LIMPIEZA DE TERRENO MANUAL M2 507.98


Plano Topografico Plano 02 1 26.05 19.50 507.98

01.01.04 TRAZO NIVELES Y REPLANTEO M2 507.98


Plano Topografico Plano 02 1 26.05 19.50 507.98

01.02.00 MOVIMIENTO DE TIERRAS


01.02.01 CORTE O EXCAVACION EN MATERIAL SUELTO C/EQUIPO M3 135.09
Plataforma 1 Volumen= 100.55 100.55
Vereda 1 Volumen= 34.54 34.54

01.02.02 RELLENO CON MATERIAL PROPIO C/EQUIPO M3 17.05


Plataforma 1 Volumen= 15.81 15.81
Vereda 1 Volumen= 1.24 1.24

01.02.03 EXCAVACION DE TERRENO MANUAL P/ZAPATAS M3 65.09


Z - 1 Plano 06 13 1.00 1.00 1.50 19.50
Z' - 1 1 1.00 0.95 1.50 1.43
Z-2 13 1.00 0.75 1.50 14.63
Z' - 2 1 1.00 0.70 1.50 1.05
Z-3 1 0.75 0.95 1.50 1.07
Z-4 3 0.75 0.75 1.50 2.53
Z' - 4 1 0.75 0.70 1.50 0.79
Z-5 4 1.10 1.10 1.50 7.26
Z-6 1 0.70 0.70 1.50 0.74
Z-7 2 1.90 0.95 1.50 5.42
Z-8 1 Area= 1.95 0.50 0.98
Z-9 8 0.75 0.80 1.50 7.20
Z' - 9 2 0.55 0.70 1.50 1.16
Z - 10 1 Area= 1.73 0.50 0.87
Ensanche de piso 1 0.65 0.65 0.70 0.46

01.02.04 EXCAVACION DE TERRENO MANUAL P/CIMIENTOS M3. 59.11


1' - 1' 1 1.10 0.45 0.80 0.40
1' - 1' 2 0.75 0.45 0.80 0.54
1' - 1' 5 0.60 0.50 0.80 1.20
1-1 1 14.70 0.45 0.80 5.29
2-2 1 12.43 0.50 0.80 4.97
2' - 2' 1 1.65 0.50 0.80 0.66
2' - 2' 1 6.10 0.50 0.50 1.53
3-3 1 4.00 0.50 0.80 1.60
3' - 3' 1 1.85 0.50 0.80 0.74
4-4 1 1.95 0.50 0.80 0.78
4' - 4' 1 1.85 0.50 0.80 0.74
4' - 4' 1 6.10 0.30 0.40 0.73
5 -5 1 9.11 0.50 0.80 3.64
5 -5 1 2.40 0.50 0.70 0.84
6-6 1 13.95 0.45 0.80 5.02
A'' - A'' 1 4.30 0.50 0.70 1.51
A' - A' 1 5.95 0.45 0.80 2.14
A-A 1 5.50 0.45 0.80 1.98
B' - B' 1 1.95 0.50 0.80 0.78
1 0.65 0.50 0.70 0.23
B-B 1 4.70 0.50 0.80 1.88
1 6.90 0.50 0.70 2.42
C-C 1 5.20 0.50 0.80 2.08
1 3.70 0.50 0.50 0.93
D-D 1 5.20 0.50 0.80 2.08
E-E 1 5.20 0.50 0.80 2.08
1 5.41 0.50 0.50 1.35
E' - E' 1 3.85 0.50 0.80 1.54
1 0.65 0.50 0.70 0.23
F-F 1 5.20 0.45 0.80 1.87
1 0.60 0.50 0.80 0.24
1 5.36 0.50 0.70 1.88
F' - F' 1 5.10 0.45 0.80 1.84
Sardineles 1 16.50 0.30 0.40 1.98
1 2.60 0.50 0.80 1.04
Otros 1 1.00 0.50 0.70 0.35
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
01.02.05 RELLENO CON MATERIAL PROPIO (INC. COMPACTACION MANUAL) M3. 4.80
1' - 1' 1 5.95 0.30 0.10 0.18
1-1 1 16.15 0.30 0.10 0.48
2-2 1 11.55 0.35 0.10 0.40
2' - 2' 1 1.65 0.35 0.10 0.06
3-3 1 6.50 0.35 0.10 0.23
3' - 3' 1 2.65 0.35 0.10 0.09
4-4 1 3.55 0.35 0.10 0.12
4' - 4' 1 2.65 0.35 0.10 0.09
5 -5 1 9.35 0.35 0.10 0.33
6-6 1 18.00 0.30 0.10 0.54
A'' - A'' 1 0.80 0.30 0.10 0.02
A' - A' 1 7.25 0.30 0.10 0.22
A-A 1 7.15 0.30 0.10 0.21
B' - B' 1 3.00 0.35 0.10 0.11
B-B 1 5.25 0.35 0.10 0.18
C-C 1 6.80 0.35 0.10 0.24
D-D 1 7.70 0.35 0.10 0.27
E-E 1 6.80 0.35 0.10 0.24
E' - E' 1 5.85 0.35 0.10 0.20
F-F 1 7.00 0.30 0.10 0.21
F-F 1 1.40 0.35 0.10 0.05
F' - F' 1 7.25 0.30 0.10 0.22
Otros 1 3.15 0.35 0.10 0.11

01.02.06 NIVELACION Y APISONADO MANUAL P/FALSO PISO M2 320.35


Odontologia Plano 01 1 Area= 16.32 16.32
Jefatura 1 Area= 14.72 14.72
Farmacia 1 Area= 14.35 14.35
Archivo 1 Area= 10.92 10.92
Admision 1 Area= 7.34 7.34
Hall 1 Area= 24.17 24.17
Espera 1 Area= 11.90 11.90
Triaje 1 Area= 13.61 13.61
Consultorio 1 Area= 15.63 15.63
Topico 1 Area= 14.35 14.35
Enfermeria 1 Area= 16.37 16.37
Obstetricia 1 Area= 16.32 16.32
Broncopulmonares 1 Area= 12.56 12.56
SSHH - Publicos 1 Area= 5.72 5.72
Pasillo 1 Area= 121.42 121.42
Ingreso 1 Area = 4.65 4.65

01.02.07 ELIMINACION DE MATERIAL EXCEDENTE DPROM 2.6 KM M3 155.22


1.3 124.20 4.80 155.22

01.03.00 OBRAS DE CONCRETO SIMPLE


01.03.01 SOLADO CONCRETO F'c=100 Kg/cm2. E=10CM M2 45.52
Z-1 Plano 06 13 1.00 1.00 13.00
Z' - 1 1 1.00 0.95 0.95
Z-2 13 1.00 0.75 9.75
Z' - 2 1 1.00 0.70 0.70
Z-3 1 0.75 0.95 0.71
Z-4 3 0.75 0.75 1.69
Z' - 4 1 0.75 0.70 0.53
Z-5 4 1.10 1.10 4.84
Z-6 1 0.70 0.70 0.49
Z-7 2 1.90 0.95 3.61
Z-8 1 Area= 1.95 1.95
Z-9 8 0.75 0.80 4.80
Z' - 9 2 0.55 0.70 0.77
Z - 10 1 Area= 1.73 1.73

01.03.02 CONCRETO CH 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS M3. 63.76
1' - 1' 1 5.95 0.45 0.70 1.87
1-1 1 18.40 0.45 0.70 5.80
2-2 1 14.40 0.50 0.70 5.04
2' - 2' 1 2.50 0.50 0.70 0.88
2' - 2' 1 7.63 0.50 0.20 0.76
3-3 1 6.50 0.50 0.70 2.28
3' - 3' 1 2.65 0.50 0.70 0.93
4-4 1 3.55 0.50 0.70 1.24
4' - 4' 1 2.65 0.50 0.70 0.93
4' - 4' 1 7.63 0.50 0.20 0.76
5 -5 1 16.50 0.50 0.70 5.78
6-6 1 18.00 0.45 0.70 5.67
A'' - A'' 1 4.40 0.45 0.70 1.39
A' - A' 1 7.25 0.45 0.70 2.28
A-A 1 6.30 0.45 0.70 1.98
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
B' - B' 1 4.00 0.50 0.70 1.40
B-B 1 14.15 0.50 0.70 4.95
C-C 1 6.80 0.50 0.70 2.38
C-C 1 4.40 0.50 0.20 0.44
D-D 1 7.70 0.50 0.70 2.70
E-E 1 6.80 0.50 0.70 2.38
E-E 1 6.20 0.50 0.20 0.62
E' - E' 1 4.95 0.50 0.70 1.73
E' - E' 1 1.00 0.50 0.70 0.35
F-F 1 7.55 0.45 0.70 2.38
F-F 1 6.50 0.50 0.70 2.28
F' - F' 1 7.25 0.45 0.70 2.28
Otros 1 6.50 0.50 0.70 2.28

01.03.03 CONCRETO C:H 1:8+25% P.M. PARA SOBRECIMIENTOS M3. 8.81


1' - 1' 1 5.95 0.15 0.40 0.36
1-1 1 16.15 0.15 0.40 0.97
2-2 1 11.55 0.15 0.40 0.69
2' - 2' 1 1.65 0.15 0.40 0.10
3-3 1 6.50 0.15 0.40 0.39
3' - 3' 1 2.65 0.15 0.40 0.16
4-4 1 3.55 0.15 0.40 0.21
4' - 4' 1 2.65 0.15 0.40 0.16
5 -5 1 9.35 0.15 0.40 0.56
6-6 1 18.00 0.15 0.40 1.08
A'' - A'' 1 0.80 0.15 0.40 0.05
A' - A' 1 7.25 0.15 0.40 0.44
A-A 1 7.15 0.15 0.40 0.43
B' - B' 1 3.00 0.15 0.40 0.18
B-B 1 5.25 0.15 0.40 0.32
C-C 1 6.80 0.15 0.40 0.41
D-D 1 7.70 0.15 0.40 0.46
E-E 1 6.80 0.15 0.40 0.41
E' - E' 1 4.95 0.15 0.40 0.30
F-F 1 7.00 0.15 0.40 0.42
F-F 1 1.40 0.15 0.40 0.08
F' - F' 1 7.25 0.15 0.40 0.44
Otros 1 3.15 0.15 0.40 0.19

01.03.04 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTOS M2 58.60


1' - 1' 1 5.95 0.40 2.38
1-1 1 16.15 0.40 6.46
2-2 1 11.55 0.40 4.62
2' - 2' 1 1.65 0.40 0.66
3-3 1 6.50 0.40 2.60
3' - 3' 1 2.65 0.40 1.06
4-4 1 3.55 0.40 1.42
4' - 4' 1 2.65 0.40 1.06
5 -5 1 9.35 0.40 3.74
6-6 1 18.00 0.40 7.20
A'' - A'' 1 0.80 0.40 0.32
A' - A' 1 7.25 0.40 2.90
A-A 1 7.15 0.40 2.86
B' - B' 1 3.00 0.40 1.20
B-B 1 5.25 0.40 2.10
C-C 1 6.80 0.40 2.72
D-D 1 7.70 0.40 3.08
E-E 1 6.80 0.40 2.72
E' - E' 1 4.95 0.40 1.98
F-F 1 7.00 0.40 2.80
F-F 1 1.40 0.40 0.56
F' - F' 1 7.25 0.40 2.90
Otros 1 3.15 0.40 1.26

01.03.05 FALSO PISO DE E= 4" CON MORTERO CEMENTO HORMIGON 1:10 M2 320.35
Odontologia Plano 01 1 Area= 16.32 16.32
Jefatura 1 Area= 14.72 14.72
Farmacia 1 Area= 14.35 14.35
Archivo 1 Area= 10.92 10.92
Admision 1 Area= 7.34 7.34
Hall 1 Area= 24.17 24.17
Espera 1 Area= 11.90 11.90
Triaje 1 Area= 13.61 13.61
Consultorio 1 Area= 15.63 15.63
Topico 1 Area= 14.35 14.35
Enfermeria 1 Area= 16.37 16.37
Obstetricia 1 Area= 16.32 16.32
Broncopulmonares 1 Area= 12.56 12.56
SSHH - Publicos 1 Area= 5.72 5.72
Pasillo 1 Area= 121.42 121.42
Ingreso 1 Area = 4.65 4.65
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
01.04.00.0 OBRAS DE CONCRETO ARMADO
01.04.01.0 ZAPATAS
01.04.01.1 CONCRETO F'C=210 KG/CM2. PARA ZAPATAS M3 23.25
Z - 1 Plano 06 13 1.00 1.00 0.50 6.50
Z' - 1 1 1.00 0.95 0.50 0.48
Z-2 13 1.00 0.75 0.50 4.88
Z' - 2 1 1.00 0.70 0.50 0.35
Z-3 1 0.75 0.95 0.50 0.36
Z-4 3 0.75 0.75 0.50 0.84
Z' - 4 1 0.75 0.70 0.50 0.26
Z-5 4 1.10 1.10 0.50 2.42
Z-6 1 0.70 0.70 0.50 0.25
Z-7 2 1.90 0.95 0.50 1.81
Z-8 1 Area= 1.95 0.50 0.98
Z-9 8 0.75 0.80 0.50 2.40
Z' - 9 2 0.55 0.70 0.50 0.39
Z - 10 1 Area= 1.73 0.50 0.87
Ensanche de piso 1 0.65 0.65 0.70 0.46

01.04.01.2 ACERO F'Y 4200 KG/CM2 EN ZAPATAS KG 616.11


Z-1 Plano 06 1/2" 91.00 0.90 1.02 83.54
Z-1 1/2" 91.00 0.90 1.02 83.54
Z' - 1 1/2" 7.00 0.85 1.02 6.07
Z' - 1 1/2" 7.00 0.90 1.02 6.43
Z-2 1/2" 65.00 0.65 1.02 43.10
Z-2 1/2" 91.00 0.90 1.02 83.54
Z' - 2 1/2" 6.00 0.60 1.02 3.67
Z' - 2 1/2" 7.00 0.90 1.02 6.43
Z-3 1/2" 7.00 0.85 1.02 6.07
Z-3 1/2" 5.00 0.65 1.02 3.32
Z-4 1/2" 15.00 0.65 1.02 9.95
Z-4 1/2" 15.00 0.65 1.02 9.95
Z' - 4 1/2" 5.00 0.60 1.02 3.06
Z' - 4 1/2" 5.00 0.65 1.02 3.32
Z-5 1/2" 28.00 1.00 1.02 28.56
Z-5 1/2" 28.00 1.00 1.02 28.56
Z-6 1/2" 6.00 0.60 1.02 3.67
Z-6 1/2" 6.00 0.60 1.02 3.67
Z-7 1/2" 14.00 0.85 1.02 12.14
Z-7 1/2" 24.00 1.80 1.02 44.06
Z-8 1/2" 10.00 1.50 1.02 15.30
Z-8 1/2" 10.00 1.40 1.02 14.28
Z-9 1/2" 56.00 0.70 1.02 39.98
Z-9 1/2" 56.00 0.65 1.02 37.13
Z' - 9 1/2" 14.00 0.65 1.02 9.28
Z' - 9 1/2" 14.00 0.50 1.02 7.14
Z - 10 1/2" 7.00 1.90 1.02 13.57
Z - 10 1/2" 7.00 0.95 1.02 6.78

01.04.02.0 VIGAS DE CIMENTACION


01.04.02.1 CONCRETO F'C=210 KG/CM2. PARA VIGAS DE CIMENTACION M3. 2.34
V-C 2 7.65 0.30 0.30 1.38
V-C 1 6.20 0.30 0.30 0.56
V-C 1 4.40 0.30 0.30 0.40

01.04.02.2 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE CIMENTACION M2 15.54


V-C 4 7.65 0.30 9.18
V-C 2 6.20 0.30 3.72
V-C 2 4.40 0.30 2.64

01.04.02.3 ACERO F'Y 4200 KG/CM2 EN VIGAS DE CIMENTACION KG 1,067.83


V-C 1/2" 12.00 8.85 1.02 108.32
3/8" 108.00 8.15 0.59 519.32
V-C 1/2" 6.00 7.40 1.02 45.29
3/8" 44.00 8.15 0.59 211.57
V-C 1/2" 6.00 5.60 1.02 34.27
3/8" 31.00 8.15 0.59 149.06

01.04.03.0 COLUMNAS
01.04.03.1 CONCRETO F'C=210 KG/CM2. PARA COLUMNAS M3. 21.44
C-1 Plano 04, 06 y 07 20 0.30 0.30 3.80 6.84
C' - 1 4 0.30 0.30 3.80 1.37
C-2 6 0.30 0.30 3.80 2.05
C-3 5 0.15 0.35 3.80 1.01
C-4 6 0.30 0.30 3.80 2.05
C-5 17 0.30 0.20 3.80 3.88
C' - 5 2 0.25 0.15 3.80 0.29
C-6 2 0.45 0.15 3.80 0.51
C - CF 17 0.15 0.15 3.80 1.45
C - CF' 1 0.15 0.15 3.80 0.09
P-1 2 0.25 1.00 3.80 1.90
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
01.04.03.2 ENCOFRADO Y DESENCOFRADO EN COLUMNAS M2 316.44
C-1 Plano 04, 06 y 07 80 0.30 3.80 91.20
C' - 1 16 0.30 3.80 18.24
C-2 24 0.30 3.80 27.36
C-3 5 0.94 3.80 17.91
C-4 24 0.24 3.80 21.89
C-5 34 0.30 3.80 38.76
C-5 34 0.20 3.80 25.84
C' - 5 4 0.25 3.80 3.80
C' - 5 4 0.15 3.80 2.28
C-6 4 0.45 3.80 6.84
C-6 4 0.15 3.80 2.28
C - CF 68 0.15 3.80 38.76
C - CF' 4 0.15 3.80 2.28
P-1 4 0.25 3.80 3.80
P-1 4 1.00 3.80 15.20

01.04.03.3 ACERO F'Y 4200 KG/CM2 EN COLUMNAS KG 3,917.21


C-1 Plano 04, 06 y 08 5/8" 80.00 5.65 1.55 700.60
3/8" 40.00 5.65 0.59 133.34
3/8" 720.00 1.30 0.59 552.24
C' - 1 5/8" 16.00 5.65 1.55 140.12
3/8" 144.00 1.30 0.59 110.45
C-2 5/8" 24.00 5.65 1.55 210.18
1/2" 12.00 5.65 1.02 69.16
3/8" 180.00 1.30 0.59 138.06
C-3 5/8" 25.00 5.65 1.55 218.94
3/8" 215.00 1.00 0.59 126.85
C-4 5/8" 24.00 5.65 1.55 210.18
3/8" 216.00 1.30 0.59 165.67
C-5 1/2" 68.00 5.65 1.02 391.88
1/4" 612.00 1.05 0.25 160.65
C' - 5 1/2" 8.00 5.65 1.02 46.10
1/4" 66.00 1.40 0.25 23.10
C-6 3/8" 12.00 5.65 0.59 40.00
1/4" 12.00 1.40 0.25 4.20
C - CF 3/8" 34.00 5.65 0.59 113.34
1/4" 510.00 0.45 0.25 57.38
C - CF' 3/8" 4.00 5.65 0.59 13.33
1/4" 30.00 0.45 0.25 3.38
P-1 1/2" 24.00 5.65 1.02 138.31
3/8" 16.00 5.65 0.59 53.34
3/8" 70.00 1.10 0.59 45.43
3/8" 32.00 2.70 0.59 50.98

01.04.04.0 VIGAS
01.04.04.1 CONCRETO F'C=210 KG/CM2. PARA VIGAS M3. 22.24
VP - 1 Plano 07 1 18.25 0.25 0.40 1.83
VP - 1 1 19.60 0.25 0.40 1.96
VP - 1 4 4.40 0.25 0.40 1.76
VP' - 1 1 3.60 0.20 0.30 0.22
VP - 2 1 19.45 0.25 0.40 1.95
VP - 2 2 13.05 0.25 0.40 2.61
VP - 2 1 8.70 0.25 0.40 0.87
VP - 2 1 8.65 0.25 0.40 0.87
VP - 2 1 19.60 0.25 0.40 1.96
VP - 2 2 6.20 0.25 0.40 1.24
VS - 1 6 6.05 0.25 0.30 2.72
VS - 1 2 6.95 0.25 0.30 1.04
VS - 2 2 6.05 0.25 0.30 0.91
VS - 2 2 3.40 0.25 0.30 0.51
V - CH 2 3.25 0.25 0.20 0.33
V - CH 6 0.90 0.25 0.20 0.27
V - CH 1 1.05 0.25 0.20 0.05
V - CH 1 3.60 0.25 0.20 0.18
V - CH 1 3.05 0.25 0.20 0.15
V - CH' 1 0.65 0.10 0.10 0.01
V - CH' 2 1.25 0.10 0.10 0.03
V-b 1 6.30 0.15 0.20 0.19
V-b 1 1.50 0.15 0.20 0.05
V-b 2 3.40 0.15 0.20 0.20
V-b 2 2.20 0.15 0.20 0.13
V - b' 2 3.25 0.15 0.20 0.20

01.04.04.2 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS M2 242.85


VP - 1 Plano 07 2 18.25 0.40 14.60
1 18.25 0.25 4.56
VP - 1 2 19.60 0.40 15.68
1 19.60 0.25 4.90
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
VP - 1 8 4.40 0.40 14.08
4 4.40 0.25 4.40
VP' - 1 2 3.60 0.40 2.88
1 3.60 0.25 0.90
VP - 2 2 18.25 0.40 14.60
1 18.25 0.25 4.56
VP - 2 4 13.05 0.40 20.88
2 13.05 0.25 6.53
VP - 2 2 8.70 0.40 6.96
1 8.70 0.25 2.18
VP - 2 2 8.65 0.40 6.92
1 8.65 0.25 2.16
VP - 2 2 19.60 0.40 15.68
1 19.60 0.25 4.90
VP - 2 4 6.05 0.40 9.68
2 6.05 0.25 3.03
VS - 1 12 6.05 0.30 21.78
6 6.05 0.25 9.08
VS - 1 4 6.95 0.30 8.34
2 6.95 0.25 3.48
VS - 2 4 6.05 0.25 6.05
2 6.05 0.30 3.63
VS - 2 4 3.40 0.25 3.40
2 3.40 0.30 2.04
V - CH 4 3.25 0.20 2.60
2 3.25 0.25 1.63
V - CH 12 0.90 0.20 2.16
6 0.90 0.25 1.35
V - CH 2 1.05 0.20 0.42
1 1.05 0.25 0.26
V - CH 2 3.60 0.20 1.44
1 3.60 0.25 0.90
V - CH 2 3.05 0.20 1.22
1 3.05 0.25 0.76
V - CH' 2 1.90 0.10 0.38
V-b 2 6.30 0.20 2.52
1 6.30 0.15 0.95
V-b 2 1.50 0.20 0.60
1 1.50 0.15 0.23
V-b 4 3.40 0.20 2.72
2 3.40 0.15 1.02
V-b 2 2.20 0.20 0.88
1 2.20 0.15 0.33
V - b' 4 3.25 0.20 2.60

01.04.04.3 ACERO F'Y 4200 KG/CM2 EN VIGAS KG 3,106.47


VP - 1 Plano 07 5/8" 6.00 19.45 1.55 180.89
3/8" 104.00 1.50 0.59 92.04
VP - 1 5/8" 6.00 20.80 1.55 193.44
3/8" 130.00 1.50 0.59 115.05
VP - 1 5/8" 24.00 5.60 1.55 208.32
3/8" 112.00 1.50 0.59 99.12
VP' - 1 5/8" 4.00 20.65 1.55 128.03
1/2" 1.00 20.65 1.02 21.06
3/8" 55.00 1.50 0.59 48.68
VP - 2 5/8" 4.00 20.65 1.55 128.03
1/2" 1.00 20.65 1.02 21.06
3/8" 110.00 1.30 0.59 84.37
VP - 2 5/8" 8.00 14.25 1.55 176.70
1/2" 2.00 14.25 1.02 29.07
3/8" 150.00 1.30 0.59 115.05
VP - 2 5/8" 4.00 9.90 1.55 61.38
1/2" 1.00 9.90 1.02 10.10
3/8" 50.00 1.30 0.59 38.35
VP - 2 5/8" 4.00 9.85 1.55 61.07
1/2" 1.00 9.85 1.02 10.05
3/8" 50.00 1.30 0.59 38.35
VP - 2 5/8" 4.00 20.80 1.55 128.96
1/2" 1.00 20.80 1.02 21.22
3/8" 130.00 1.30 0.59 99.71
VP - 2 5/8" 8.00 7.40 1.55 91.76
1/2" 2.00 7.40 1.02 15.10
3/8" 70.00 1.30 0.59 53.69
VS - 1 1/2" 24.00 7.25 1.02 177.48
3/8" 6.00 7.25 0.59 25.67
1/4" 288.00 1.20 0.25 86.40
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
VS - 1 1/2" 8.00 8.15 1.02 66.50
3/8" 2.00 8.15 0.59 9.62
1/4" 112.00 1.20 0.25 33.60
VS - 2 1/2" 8.00 7.25 1.02 59.16
1/4" 100.00 1.20 0.25 30.00
VS - 2 1/2" 8.00 4.60 1.02 37.54
1/4" 56.00 1.20 0.25 16.80
V - CH 1/2" 8.00 4.45 1.02 36.31
1/4" 68.00 1.20 0.25 20.40
V - CH 1/2" 24.00 2.10 1.02 51.41
1/4" 60.00 1.20 0.25 18.00
V - CH 1/2" 4.00 2.25 1.02 9.18
1/4" 11.00 1.20 0.25 3.30
V - CH 1/2" 4.00 4.80 1.02 19.58
1/4" 15.00 1.20 0.25 4.50
V - CH 1/2" 4.00 3.25 1.02 13.26
1/4" 15.00 0.50 0.25 1.88
V - CH' 3/8" 2.00 4.15 0.59 4.90
1/4" 66.00 0.50 0.25 8.25
V-b 3/8" 4.00 7.50 0.59 17.70
1/4" 66.00 0.50 0.25 8.25
V-b 3/8" 4.00 2.70 0.59 6.37
1/4" 16.00 0.50 0.25 2.00
V-b 3/8" 8.00 4.60 0.59 21.71
1/4" 72.00 0.50 0.25 9.00
V-b 3/8" 4.00 2.90 0.59 6.84
1/4" 34.00 0.50 0.25 4.25
V - b' 3/8" 8.00 3.70 0.59 17.46
1/4" 68.00 0.50 0.25 8.50

01.04.05.0 LOSA MACIZA


01.04.05.1 CONCRETO F'C=210 KG/CM2. PARA LOSAS MACIZAS M3. 0.06
1 0.70 0.90 0.10 0.06

01.04.05.2 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MAZIZAS M2 0.79


1 0.70 0.90 0.63
1 0.90 0.10 0.09
1 0.70 0.10 0.07

01.04.05.3 ACERO F'Y 4200 KG/CM2 EN LOSAS MACIZAS KG 10.74


3/8" 10.00 1.10 0.59 6.49
3/8" 8.00 0.90 0.59 4.25

01.04.06.0 LOSA ALIGERADA


01.04.06.1 CONCRETO F'C=210 KG/CM2. PARA LOSAS ALIGERADAS M3. 23.87
Plano 07 2 3.50 3.83 0.05 1.34
20 3.50 0.10 0.15 1.05
2 2.35 3.83 0.05 0.90
20 2.35 0.10 0.15 0.71
2 3.50 3.88 0.05 1.36
20 3.50 0.10 0.15 1.05
2 2.35 3.88 0.05 0.91
20 2.35 0.10 0.15 0.71
2 3.50 3.70 0.05 1.30
18 3.50 0.10 0.15 0.95
2 2.35 3.70 0.05 0.87
18 2.35 0.10 0.15 0.63
1 2.75 6.31 0.05 0.87
16 2.75 0.10 0.15 0.66
Volado 1 0.45 6.31 0.05 0.14
16 0.45 0.10 0.15 0.11
1 2.73 3.50 0.05 0.48
9 2.73 0.10 0.15 0.37
1 3.25 2.73 0.05 0.44
9 3.25 0.10 0.15 0.44
1 3.10 3.25 0.05 0.50
8 3.25 0.10 0.15 0.39
1 3.15 4.50 0.05 0.71
11 3.15 0.10 0.15 0.52
1 2.70 4.50 0.05 0.61
11 2.70 0.10 0.15 0.45
1 2.40 4.50 0.05 0.54
11 2.40 0.10 0.15 0.40
1 3.73 3.50 0.05 0.65
9 3.50 0.10 0.15 0.47
1 3.73 3.25 0.05 0.61
9 3.25 0.10 0.15 0.44
1 2.72 3.25 0.05 0.44
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
7 3.25 0.10 0.15 0.34
1 3.50 3.50 0.05 0.61
9 3.50 0.10 0.15 0.47
3 0.90 1.30 0.05 0.18
9 0.90 0.10 0.15 0.12
1 1.05 1.30 0.05 0.07
3 1.30 0.10 0.15 0.06

01.04.06.2 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS M2 129.26


Plano 07 20 3.50 0.15 10.50
20 2.35 0.15 7.05
20 3.50 0.15 10.50
20 2.35 0.15 7.05
18 3.50 0.15 9.45
18 2.35 0.15 6.35
16 2.75 0.15 6.60
16 0.45 0.15 1.08
9 2.73 0.15 3.69
9 3.25 0.15 4.39
8 3.25 0.15 3.90
11 3.15 0.15 5.20
11 2.70 0.15 4.46
11 2.40 0.15 3.96
9 3.50 0.15 4.73
9 3.25 0.15 4.39
7 3.25 0.15 3.41
9 3.50 0.15 4.73
9 0.90 0.15 1.22
3 1.30 0.15 0.59
18 2.35 0.15 6.35
16 2.75 0.15 6.60
16 0.45 0.15 1.08
9 2.73 0.15 3.69
9 3.25 0.15 4.39
8 3.25 0.15 3.90

01.04.06.3 ACERO F'Y 4200 KG/CM2 EN LOSAS ALIGERADAS KG 2,366.17


1/2" 40 6.50 1.02 265.20
3/8" 40 3.00 0.59 70.80
1/2" 40 2.60 1.02 106.08
Temperatura 1/4" 15 12.50 0.25 46.88
1/2" 40 6.50 1.02 265.20
3/8" 40 3.00 0.59 70.80
1/2" 40 2.60 1.02 106.08
Temperatura 1/4" 15 12.50 0.25 46.88
1/2" 36 6.50 1.02 238.68
3/8" 36 3.00 0.59 63.72
1/2" 36 2.60 1.02 95.47
Temperatura 1/4" 50 12.50 0.25 156.25
3/8" 16 3.10 0.59 29.26
1/2" 16 3.90 1.02 63.65
Temperatura 1/4" 15 4.00 0.25 15.00
1/2" 9 7.20 1.02 66.10
3/8" 9 2.70 0.59 14.34
1/2" 9 2.80 1.02 25.70
Temperatura 1/4" 28 3.00 0.25 21.00
1/2" 8 3.40 1.02 27.74
3/8" 8 1.30 0.59 6.14
1/2" 8 1.40 1.02 11.42
Temperatura 1/4" 14 3.30 0.25 11.55
1/2" 11 9.10 1.02 102.10
3/8" 11 1.80 0.59 11.68
1/2" 11 4.80 1.02 53.86
Temperatura 1/4" 35 8.70 0.25 76.13
1/2" 9 8.60 1.02 78.95
3/8" 9 2.05 0.59 10.89
1/2" 9 2.80 1.02 25.70
Temperatura 1/4" 28 4.00 0.25 28.00
1/2" 9 7.50 1.02 68.85
3/8" 9 2.50 0.59 13.28
1/2" 9 2.80 1.02 25.70
Temperatura 1/4" 28 3.50 0.25 24.50
3/8" 9 1.30 0.59 6.90
3/8" 9 1.10 0.59 5.84
Temperatura 1/4" 12 1.40 0.25 4.20
3/8" 3 1.30 0.59 2.30
3/8" 3 1.10 0.59 1.95
Temperatura 1/4" 4 1.40 0.25 1.40
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
01.04.06.4 LADRILLO HUECO/ARCILLA 15X30X30 P/TECHO ALIGERADO UND 2,240.00
Odontologia y Obstetricia 2 3.83 3.50 8.33 223.33
Jefatura y Enfermeria 2 3.93 3.50 8.33 229.16
Farmacia y Topico 2 3.75 3.50 8.33 218.66
Archivo 1 2.73 3.50 8.33 79.59
Pasillo 2 3.83 2.35 8.33 149.95
Pasillo 2 3.93 2.35 8.33 153.86
Pasillo 2 3.75 2.35 8.33 146.82
Pasillo 1 3.10 3.25 8.33 83.92
Pasillo 1 3.13 4.50 8.33 117.33
Pasillo 1 3.73 3.25 8.33 100.98
Admision 1 1.98 3.25 8.33 53.60
Hall 1 2.68 4.50 8.33 100.46
Hall 1 2.39 4.50 8.33 89.59
Espera 1 2.73 3.25 8.33 73.91
Triaje 1 3.50 3.50 8.33 102.04
Consultorio 1 3.73 3.50 8.33 108.75
Bronco Pulmonares 1 2.77 6.31 8.33 145.60
Volado 1 0.45 6.31 8.33 23.65
Ss.hh 4 0.90 1.30 8.33 38.98

01.04.07.0 DERRAME DE VENTANAS ARMADAS


01.04.07.1 CONCRETO F'C=210 KG/CM2. PARA COLUMNAS M3. 2.21
Farmacia 2 2.10 0.20 0.12 0.10
2 0.20 0.12 1.46 0.07
Columna Confinamiento 2 0.15 0.15 1.70 0.08
Viga Confinamiento 1 0.15 0.15 2.40 0.05
Archivo 2 2.30 0.20 0.12 0.11
2 0.20 0.12 1.56 0.07
Columna Confinamiento 2 0.15 0.15 1.80 0.08
Viga Confinamiento 1 0.15 0.15 3.40 0.08
Admision 2 1.80 0.20 0.12 0.09
2 0.20 0.12 1.56 0.07
Columna Confinamiento 2 0.15 0.15 1.80 0.08
Viga Confinamiento 1 0.15 0.15 1.95 0.04
Bronco Pulmonares 2 2.30 0.20 0.12 0.11
2 0.20 0.12 1.46 0.07
Columna Confinamiento 2 0.15 0.15 1.70 0.08
Viga Confinamiento 1 0.15 0.15 4.30 0.10
Obstetricia 2 1.20 0.20 0.12 0.06
2 0.20 0.12 1.66 0.08
Columna Confinamiento 2 0.15 0.15 1.90 0.09
Viga Confinamiento 1 0.15 0.15 2.33 0.05
Topico 2 1.20 0.20 0.12 0.06
2 0.20 0.12 1.66 0.08
Columna Confinamiento 2 0.15 0.15 1.90 0.09
Viga Confinamiento 1 0.15 0.15 3.70 0.08
Triaje 2 2.30 0.20 0.12 0.11
2 0.20 0.12 1.56 0.07
Columna Confinamiento 2 0.15 0.15 1.80 0.08
Viga Confinamiento 1 0.15 0.15 3.40 0.08

01.04.07.2 ENCOFRADO Y DESENCOFRADO NORMAL EN DERRAMES ARMADOS M2. 35.03


Farmacia 1 2.10 0.12 0.25
2 1.70 0.20 0.68
2 0.20 1.46 0.58
2 2.10 0.12 0.50
2 1.70 0.12 0.41
Columna Confinamiento 6 0.15 1.70 1.53
Viga Confinamiento 2 2.40 0.15 0.72
Archivo 1 2.30 0.12 0.28
2 1.80 0.20 0.72
2 0.20 1.56 0.62
2 2.30 0.12 0.55
2 1.80 0.12 0.43
Columna Confinamiento 6 0.15 1.80 1.62
Viga Confinamiento 2 3.40 0.15 1.02
Admision 1 1.80 0.12 0.22
2 1.80 0.20 0.72
2 0.20 1.56 0.62
2 1.80 0.12 0.43
2 1.80 0.12 0.43
Columna Confinamiento 6 0.15 1.80 1.62
Viga Confinamiento 2 1.95 0.15 0.59
Bronco Pulmonares 1 2.30 0.12 0.28
2 1.70 0.20 0.68
2 0.20 1.46 0.58
2 1.70 0.12 0.41
2 1.70 0.12 0.41
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
Columna Confinamiento 6 0.15 1.70 1.53
Viga Confinamiento 2 4.30 0.15 1.29
Obstetricia 1 1.20 0.12 0.14
2 1.90 0.20 0.76
2 0.20 1.66 0.66
2 1.90 0.12 0.46
2 1.90 0.12 0.46
Columna Confinamiento 6 0.15 1.90 1.71
Viga Confinamiento 2 2.33 0.15 0.70
Topico 1 1.20 0.12 0.14
2 1.90 0.20 0.76
2 0.20 1.66 0.66
2 1.90 0.12 0.46
2 1.90 0.12 0.46
Columna Confinamiento 6 0.15 1.90 1.71
Viga Confinamiento 2 3.70 0.15 1.11
Triaje 1 2.30 0.12 0.28
2 1.80 0.20 0.72
2 0.20 1.56 0.62
2 1.80 0.12 0.43
2 1.80 0.12 0.43
Columna Confinamiento 6 0.15 1.80 1.62
Viga Confinamiento 2 3.40 0.15 1.02

01.04.07.3 ACERO F'Y 4200 KG/CM2 EN DERRAMES ARMADOS KG 262.19


Farmacia 3/8" 4.00 2.30 0.59 5.43
3/8" 14.00 0.35 0.59 2.89
3/8" 4.00 2.10 0.59 4.96
3/8" 22.00 0.50 0.59 6.49
3/8" 14.00 0.50 0.59 4.13
Columna Confinamiento 3/8" 4.00 2.10 0.59 4.96
1/4" 64.00 0.35 0.25 5.60
Viga Confinamiento 3/8" 2.00 2.70 0.59 3.19
1/4" 36.00 0.35 0.25 3.15
Archivo 3/8" 4.00 2.50 0.59 5.90
3/8" 18.00 0.35 0.59 3.72
3/8" 4.00 2.10 0.59 4.96
3/8" 22.00 0.50 0.59 6.49
3/8" 14.00 0.50 0.59 4.13
Columna Confinamiento 3/8" 4.00 2.10 0.59 4.96
1/4" 64.00 0.35 0.25 5.60
Viga Confinamiento 3/8" 2.00 3.70 0.59 4.37
1/4" 51.00 0.35 0.25 4.46
Bronco Pulmonares 3/8" 4.00 2.60 0.59 6.14
3/8" 18.00 0.35 0.59 3.72
3/8" 4.00 2.10 0.59 4.96
3/8" 22.00 0.50 0.59 6.49
3/8" 14.00 0.50 0.59 4.13
Columna Confinamiento 3/8" 4.00 2.10 0.59 4.96
1/4" 64.00 0.35 0.25 5.60
Viga Confinamiento 3/8" 2.00 3.70 0.59 4.37
1/4" 51.00 0.35 0.25 4.46
Obstetricia 3/8" 4.00 1.50 0.59 3.54
3/8" 16.00 0.35 0.59 3.30
3/8" 4.00 2.10 0.59 4.96
3/8" 20.00 0.50 0.59 5.90
3/8" 12.00 0.50 0.59 3.54
Columna Confinamiento 3/8" 4.00 2.10 0.59 4.96
1/4" 64.00 0.35 0.25 5.60
Viga Confinamiento 3/8" 2.00 2.55 0.59 3.01
1/4" 65.00 0.35 0.25 5.69
Topico 3/8" 4.00 1.50 0.59 3.54
3/8" 16.00 0.35 0.59 3.30
3/8" 4.00 2.10 0.59 4.96
3/8" 20.00 0.50 0.59 5.90
3/8" 12.00 0.50 0.59 3.54
Columna Confinamiento 3/8" 4.00 2.10 0.59 4.96
1/4" 64.00 0.35 0.25 5.60
Viga Confinamiento 3/8" 2.00 3.90 0.59 4.60
1/4" 85.00 0.35 0.25 7.44
Triaje 3/8" 4.00 2.60 0.59 6.14
3/8" 24.00 0.35 0.59 4.96
3/8" 4.00 2.10 0.59 4.96
3/8" 20.00 0.50 0.59 5.90
3/8" 12.00 0.50 0.59 3.54
Columna Confinamiento 3/8" 4.00 2.10 0.59 4.96
1/4" 64.00 0.35 0.25 5.60
Viga Confinamiento 3/8" 2.00 3.50 0.59 4.13
1/4" 85.00 0.35 0.25 7.44
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
01.05.00 MUROS
01.05.01 MURO DE LADRILLO BLOCKER II SOGA CON MORTERO CEMENTO:ARENA M2 411.77
A' - A' 1 0.76 2.80 2.13
A' - A' 1 0.93 2.80 2.60
-1 0.30 0.30 -0.09
A' - A' 1 1.58 2.80 4.42
-1 1.00 2.00 -2.00
A' - A' 1 0.60 2.80 1.68
A-A 1 3.40 2.80 9.52
-1 2.00 1.80 -3.60
A-A 1 0.93 2.80 2.60
-1 0.30 0.30 -0.09
A-A 1 1.58 2.80 4.42
-1 1.00 2.00 -2.00
A-A 1 0.45 2.80 1.26
A-A 1 9.40 2.60 24.44
Parapeto 1 4.00 0.30 1.20
1 3.25 0.60 1.95
1 8.50 1.10 9.35
1 4.40 0.60 2.64
1 3.85 0.30 1.16
B-B 1 2.15 1.80 3.87
B-B 1 1.95 2.80 5.46
B-B -1 1.65 1.80 -2.97
B-B 1 1.15 2.80 3.22
B-B -1 1.15 1.80 -2.07
B-B 1 2.10 2.80 5.88
B-B 1 0.90 2.80 2.52
C-C 2 3.40 2.80 19.04
Parapeto 1 6.80 0.90 6.12
D-D 2 3.40 2.80 19.04
D-D 1 0.90 2.80 2.52
E-E 2 3.40 2.80 19.04
Parapeto 1 6.80 0.90 6.12
E' - E' 1 3.16 2.80 8.85
E' - E' -1 1.00 1.70 -1.70
E' - E' 1 1.75 2.80 4.90
E' - E' -1 1.75 0.80 -1.40
E' - E' 1 0.90 2.80 2.52
E' - E' 2 0.25 2.80 1.40
F- F 1 2.55 2.80 7.14
F- F -1 1.80 1.70 -3.06
F- F 1 3.40 2.80 9.52
F- F 1 0.90 2.80 2.52
F- F -1 0.90 0.80 -0.72
F' - F' 1 1.30 2.80 3.64
F' - F' 1 4.16 2.80 11.65
-1 2.00 1.70 -3.40
-1 1.00 0.80 -0.80
F' - F' 1 1.75 2.80 4.90
F' - F' -2 1.00 0.80 -1.60
Parapeto 1 20.41 0.30 6.12
1' - 1' 3 1.25 2.80 10.50
1-1 1 2.18 2.80 6.10
1-1 1 1.10 2.80 3.08
-1 1.10 1.90 -2.09
1-1 1 1.33 2.80 3.72
1-1 1 1.35 2.80 3.78
-1 0.90 0.90 -0.81
1-1 1 1.05 2.80 2.94
-1 1.10 1.90 -2.09
1-1 1 2.50 2.80 7.00
-1 1.10 1.90 -2.09
1-1 1 1.53 2.80 4.28
1-1 1 1.35 2.80 3.78
-1 0.90 0.90 -0.81
1-1 1 1.05 2.80 2.94
-1 1.05 1.90 -2.00
1-1 1 1.68 2.80 4.70
Parapeto 1 13.80 0.80 11.04
2-2 1 0.45 2.80 1.26
2-2 1 3.67 2.80 10.28
-4 1.80 1.70 -12.24
2-2 1 2.40 2.80 6.72
2-2 1 2.57 2.80 7.20
2-2 1 2.43 2.80 6.80
2' - 2' 1 1.65 2.80 4.62
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
Parapeto 1 8.45 0.90 7.61
3-3 1 0.95 2.80 2.66
3-3 1 1.10 2.80 3.08
3-3 1 2.62 2.80 7.34
3-3 1 1.80 2.80 5.04
3' - 3' 1 2.65 2.80 7.42
4-4 1 1.02 2.80 2.86
4-4 1 1.62 2.80 4.54
4' - 4' 1 2.65 2.80 7.42
Parapeto 1 8.45 0.90 7.61
5-5 1 0.65 2.80 1.82
5-5 1 1.28 2.80 3.58
5-5 1 2.40 2.80 6.72
-1 1.80 1.70 -3.06
5-5 1 2.58 2.80 7.22
-1 1.80 1.70 -3.06
5-5 1 2.43 2.80 6.80
5' - 5' 1 1.55 2.80 4.34
5' - 5' 1 0.90 2.80 2.52
-1 0.90 1.00 -0.90
6-6 1 2.73 2.80 7.64
6-6 1 3.08 2.80 8.62
6-6 1 3.70 2.80 10.36
6-6 1 3.88 2.80 10.86
6-6 1 3.72 2.80 10.42
6-6 1 0.90 2.80 2.52
Parapeto 1 1.20 1.10 1.32

01.06.00 REVOQUES Y ENLUCIDOS


01.06.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO C/MORTERO 1:5 M2. 44.84
SS.HH Odontologia 1 3.75 1.20 4.50
SS.HH Jefatura 1 4.30 1.20 5.16
SS.HH Bronco Pulmonares 1 4.00 1.20 4.80
SS.HH 1 13.62 1.20 16.34
SS.HH 3 3.90 1.20 14.04

01.06.02 TARRAJEO INTERIOR Y EXTERIOR C/MORTERO CEMENTO:ARENA M2. 992.55


1' - 1' 1 9.70 4.30 41.71
1' - 1' 1 7.30 4.30 31.39
-4 1.10 2.75 -12.10
1-1 1 20.48 3.00 61.44
1-1 1 17.51 3.00 52.53
-4 0.90 1.90 -6.84
-4 1.10 1.90 -8.36
-4 0.90 0.90 -3.24
Parapeto 1 13.80 0.80 11.04
2-2 1 15.60 3.00 46.80
2-2 1 13.65 3.00 40.95
2-2 -8 1.80 1.70 -24.48
2' - 2' 1 7.95 3.00 23.85
2' - 2' 1 2.85 3.00 8.55
Parapeto 1 8.45 0.90 7.61
3-3 1 6.32 3.00 18.96
3-3 1 6.78 3.00 20.34
3-3 1 5.20 3.00 15.60
3' - 3' 1 3.85 3.00 11.55
3' - 3' 1 3.55 3.00 10.65
1 3.65 3.00 10.95
4-4 1 5.30 3.00 15.90
4-4 1 2.31 3.00 6.93
4' - 4' 1 8.06 3.00 24.18
4' - 4' 1 3.25 3.00 9.75
Parapeto 1 8.45 0.90 7.61
5-5 1 12.80 3.00 38.40
5-5 1 14.10 3.00 42.30
-4 1.80 1.70 -12.24
6-6 1 21.17 3.00 63.51
A-A 1 19.20 3.00 57.60
A-A 1 17.90 3.00 53.70
-2 2.00 1.80 -7.20
Parapeto 1 4.00 0.30 1.20
1 3.25 0.60 1.95
1 8.50 1.10 9.35
1 4.40 0.60 2.64
1 3.85 0.30 1.16
B-B 1 10.00 3.00 30.00
B-B 1 10.75 3.00 32.25
-2 1.50 1.80 -5.40
-2 1.00 1.80 -3.60
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
C-C 1 6.95 3.00 20.85
C-C 1 6.80 3.00 20.40
Parapeto 1 6.80 0.90 6.12
D-D 1 8.30 3.00 24.90
D-D 1 7.70 3.00 23.10
E-E 1 10.20 3.00 30.60
E-E 1 7.25 3.00 21.75
Parapeto 1 6.80 0.90 6.12
E' - E' 1 6.31 3.00 18.93
E' - E' 1 5.96 3.00 17.88
-2 1.00 1.70 -3.40
-2 1.75 0.80 -2.80
F-F 1 7.15 3.00 21.45
F-F 1 7.90 3.00 23.70
-2 1.80 1.70 -6.12
-2 0.90 0.80 -1.44
F' - F' 1 8.00 3.00 24.00
F' - F' 1 9.35 3.00 28.05
-2 0.90 1.00 -1.80
-2 2.00 1.70 -6.80
-6 1.00 0.80 -4.80
Parapeto ingreso 2 0.15 1.10 0.33
2 1.20 1.10 2.64

01.06.03 CIELO RASO CON MORTERO CEMENTO:ARENA M2. 268.96


Odontologia y Obstetricia 2 3.83 3.50 26.81
Jefatura y Enfermeria 2 3.93 3.50 27.51
Farmacia y Topico 2 3.75 3.50 26.25
Archivo 1 2.73 3.50 9.56
Pasillo 2 3.83 2.35 18.00
Pasillo 2 3.93 2.35 18.47
Pasillo 2 3.75 2.35 17.63
Pasillo 1 3.10 3.25 10.08
Pasillo 1 3.13 4.50 14.09
Pasillo 1 3.73 3.25 12.12
Admision 1 1.98 3.25 6.44
Hall 1 2.68 4.50 12.06
Hall 1 2.39 4.50 10.76
Espera 1 2.73 3.25 8.87
Triaje 1 3.50 3.50 12.25
Consultorio 1 3.73 3.50 13.06
Bronco Pulmonares 1 2.77 6.31 17.48
Volado 1 0.45 6.31 2.84
Ss.hh 4 0.90 1.30 4.68

01.07.00 PISOS
01.07.01 PISO CERAMICO BLANCO 30x30 Cm M2 13.46
SS.HH Odontologia 1 0.90 1.40 1.26
SS.HH Jefatura 1 1.55 1.00 1.55
SS.HH Bronco Pulmonares 1 1.40 0.90 1.26
SS.HH 2 2.95 0.95 5.61
SS.HH 3 1.40 0.90 3.78

01.07.02 PISO DE CEMENTO PULIDO E= 4" M2 179.90


Archivo 1 2.95 3.70 10.92
Admision 1 2.20 3.40 7.48
Hall 1 2.95 4.70 13.87
Hall 1 2.80 1.22 3.42
Hall 1 2.09 3.50 7.32
Triaje 1 3.60 3.40 12.24
Pasillo 1 Area = 120.00 120.00
Ingreso 1 Area = 4.65 4.65

01.07.03 PISO DE LOSETA VINILICA 30x30 M2 126.16


Odontologia 1 4.10 3.70 15.17
Jefatura 1 2.48 3.70 9.18
1 1.55 2.55 3.95
Farmacia 1 3.85 3.70 14.25
Bronco Pulmonares 1 2.95 3.26 9.62
1 1.40 1.05 1.47
Obstetricia 1 4.10 3.70 15.17
Enfermeria 1 4.10 3.70 15.17
Topico 1 3.90 3.70 14.43
Consultorio 1 3.90 3.70 14.43
Triaje 1 3.60 3.70 13.32
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
01.08.00 ZOCALOS Y CONTRAZOCALOS
01.08.01 ZOCALO DE CERAMICO BLANCO H=0.10m M2 3.74
SS.HH Odontologia 1 3.75 0.10 0.38
SS.HH Jefatura 1 4.30 0.10 0.43
SS.HH Bronco Pulmonares 1 4.00 0.10 0.40
SS.HH 1 13.62 0.10 1.36
SS.HH 3 3.90 0.10 1.17

01.08.02 CONTRAZOCALO H=1.20m M2 67.27


SS.HH Odontologia 1 3.75 1.80 6.75
SS.HH Jefatura 1 4.30 1.80 7.74
SS.HH Bronco Pulmonares 1 4.00 1.80 7.20
SS.HH 1 13.62 1.80 24.52
SS.HH 3 3.90 1.80 21.06

01.09.00 CARPINTERIA DE MADERA


01.09.01 PUERTAS TIPO TABLERO DE CEDRO M2 28.69
P-3 1 1.80 2.70 4.86
-2 0.65 0.80 -1.04
-2 0.65 1.10 -1.43
P-4 Plano 05 7 1.00 2.60 18.20
P-5 3 1.00 2.70 8.10

01.09.02 PUERTA CONTRAPLACADA 35MM C/TRIPLAY 4MM MARCO CEDRO 2x3" M2 17.20
P-6 1 0.80 2.60 2.08
P-7 4 0.70 2.80 7.84
P-8 4 0.70 2.60 7.28

01.10.00 CARPINTERIA METALICA


01.10.01 PUERTA TIPO SISTEMA M2 9.35
1 3.34 2.80 9.35

01.10.02 VENTANA TIPO SISTEMA M2 60.58


V - 1 Plano 05 3 2.00 1.80 10.80
V-2 7 1.80 1.70 21.42
V-3 1 1.60 1.50 2.40
V-4 1 1.15 1.80 2.07
V-5 6 0.90 0.90 4.86
V-6 3 0.90 1.90 5.13
V - 6' 1 1.00 1.90 1.90
V-7 2 1.10 1.90 4.18
V-8 5 0.90 0.80 3.60
V-9 1 0.45 1.50 0.68
V - 9' 3 0.43 0.45 0.58
V - 10 1 1.70 0.82 1.39
V - 11 2 0.80 0.70 1.12
V - 12 1 0.90 0.50 0.45

01.11.00 CERRAJERIA
01.11.01 BISAGRA CAPUCHINA DE 3 1/2" X 3 1/2" PZA 84.00
P-3 1 8.00 8.00
P-4 7 4.00 28.00
P-5 3 4.00 12.00
P-6 1 4.00 4.00
P-7 4 4.00 16.00
P-8 4 4.00 16.00

01.11.02 CERRADURA TIPO PARCHE 3 GOLPES PZA 1.00


P-3 Plano 05 1 1.00 1.00

01.11.03 CERRADURA PARA PUERTAS DOS GOLPES UND 10.00


P-4 Plano 05 7 7.00
P-5 3 3.00

01.11.04 CERRADURA TIPO PERILLA PZA 9.00


P-6 Plano 05 1 1.00
P-7 4 4.00
P-8 4 4.00

01.12.00 VIDRIOS
01.12.00 VIDRIOS SEMIDOBLES NACIONALES P2 42.61
2 2.14 3.62 15.46
2 2.14 2.63 11.24
3 2.30 1.05 7.26
4 1.64 1.32 8.65
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
01.13.00 PINTURA
01.13.03 PINTURA LATEX EN CIELO RASO M2 314.87
Odontologia 1 4.10 3.70 15.17
Jefatura 1 2.48 3.70 9.18
1 1.55 2.55 3.95
Farmacia 1 3.85 3.70 14.25
Bronco Pulmonares 1 2.95 3.26 9.62
1 1.40 1.05 1.47
Obstetricia 1 4.10 3.70 15.17
Enfermeria 1 4.10 3.70 15.17
Topico 1 3.90 3.70 14.43
Consultorio 1 3.90 3.70 14.43
Triaje 1 3.60 3.70 13.32
Archivo 1 2.95 3.70 10.92
Admision 1 2.20 3.40 7.48
Hall 1 2.95 4.70 13.87
Hall 1 2.80 1.22 3.42
Hall 1 2.09 3.50 7.32
Triaje 1 3.60 3.40 12.24
Pasillo 1 Area = 120.00 120.00
SS.HH Odontologia 1 0.90 1.40 1.26
SS.HH Jefatura 1 1.55 1.00 1.55
SS.HH Bronco Pulmonares 1 1.40 0.90 1.26
SS.HH 2 2.95 0.95 5.61
SS.HH 3 1.40 0.90 3.78

01.13.02 PINTURA LATEX EN MUROS COLUMNAS Y VIGAS, INTERIORES Y EXTERIORES M2 1031.27


1' - 1' 1 9.70 4.30 41.71
1' - 1' 1 7.30 4.30 31.39
-4 1.10 2.75 -12.10
1-1 1 20.48 3.00 61.44
1-1 1 17.51 3.00 52.53
-4 0.90 1.90 -6.84
-4 1.10 1.90 -8.36
-4 0.90 0.90 -3.24
Parapeto 1 13.80 0.80 11.04
2-2 1 15.60 3.00 46.80
2-2 1 13.65 3.00 40.95
2-2 -8 1.80 1.70 -24.48
2' - 2' 1 7.95 3.00 23.85
2' - 2' 1 2.85 3.00 8.55
Parapeto 1 8.45 0.90 7.61
3-3 1 6.32 3.00 18.96
3-3 1 6.78 3.00 20.34
3-3 1 5.20 3.00 15.60
3' - 3' 1 3.85 3.00 11.55
3' - 3' 1 3.55 3.00 10.65
1 3.65 3.00 10.95
4-4 1 5.30 3.00 15.90
4-4 1 2.31 3.00 6.93
4' - 4' 1 8.06 3.00 24.18
4' - 4' 1 3.25 3.00 9.75
Parapeto 1 8.45 0.90 7.61
5-5 1 12.80 3.00 38.40
5-5 1 14.10 3.00 42.30
-4 1.80 1.70 -12.24
6-6 1 21.17 3.00 63.51
A-A 1 19.20 3.00 57.60
A-A 1 17.90 3.00 53.70
-2 2.00 1.80 -7.20
Parapeto 1 4.00 0.30 1.20
1 3.25 0.60 1.95
1 8.50 1.10 9.35
1 4.40 0.60 2.64
1 3.85 0.30 1.16
B-B 1 10.00 3.00 30.00
B-B 1 10.75 3.00 32.25
-2 1.50 1.80 -5.40
-2 1.00 1.80 -3.60
C-C 1 6.95 3.00 20.85
C-C 1 6.80 3.00 20.40
Parapeto 1 6.80 0.90 6.12
D-D 1 8.30 3.00 24.90
D-D 1 7.70 3.00 23.10
E-E 1 10.20 3.00 30.60
E-E 1 7.25 3.00 21.75
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
Parapeto 1 6.80 0.90 6.12
E' - E' 1 6.31 3.00 18.93
E' - E' 1 5.96 3.00 17.88
-2 1.00 1.70 -3.40
-2 1.75 0.80 -2.80
F-F 1 7.15 3.00 21.45
F-F 1 7.90 3.00 23.70
-2 1.80 1.70 -6.12
-2 0.90 0.80 -1.44
F' - F' 1 8.00 3.00 24.00
F' - F' 1 9.35 3.00 28.05
-2 0.90 1.00 -1.80
-2 2.00 1.70 -6.80
-6 1.00 0.80 -4.80
Parapeto ingreso 2 0.15 1.10 0.33
2 1.20 1.10 2.64
Farmacia 2 2.10 0.20 0.84
2 1.70 0.20 0.68
2 0.20 1.46 0.58
2 2.10 0.12 0.50
2 1.70 0.12 0.41
Columna Confinamiento 6 0.15 1.70 1.53
Viga Confinamiento 2 2.40 0.15 0.72
Archivo 2 2.30 0.20 0.92
2 1.80 0.20 0.72
2 0.20 1.56 0.62
2 2.30 0.12 0.55
2 1.80 0.12 0.43
Columna Confinamiento 6 0.15 1.80 1.62
Viga Confinamiento 2 3.40 0.15 1.02
Admision 2 1.80 0.20 0.72
2 1.80 0.20 0.72
2 0.20 1.56 0.62
2 1.80 0.12 0.43
2 1.80 0.12 0.43
Columna Confinamiento 6 0.15 1.80 1.62
Viga Confinamiento 2 1.95 0.15 0.59
Bronco Pulmonares 2 2.30 0.20 0.92
2 1.70 0.20 0.68
2 0.20 1.46 0.58
2 1.70 0.12 0.41
2 1.70 0.12 0.41
Columna Confinamiento 6 0.15 1.70 1.53
Viga Confinamiento 2 4.30 0.15 1.29
Obstetricia 2 1.20 0.20 0.48
2 1.90 0.20 0.76
2 0.20 1.66 0.66
2 1.90 0.12 0.46
2 1.90 0.12 0.46
Columna Confinamiento 6 0.15 1.90 1.71
Viga Confinamiento 2 2.33 0.15 0.70
Topico 2 1.20 0.20 0.48
2 1.90 0.20 0.76
2 0.20 1.66 0.66
2 1.90 0.12 0.46
2 1.90 0.12 0.46
Columna Confinamiento 6 0.15 1.90 1.71
Viga Confinamiento 2 3.70 0.15 1.11
Triaje 2 2.30 0.20 0.92
2 1.80 0.20 0.72
2 0.20 1.56 0.62
2 1.80 0.12 0.43
2 1.80 0.12 0.43
Columna Confinamiento 6 0.15 1.80 1.62
Viga Confinamiento 2 3.40 0.15 1.02

01.13.03 PINTURA BARNIZ EN CARP. DE MADERA M2 91.78


P-3 2 1.80 2.70 9.72
-4 0.65 0.80 -2.08
-4 0.65 1.10 -2.86
P-4 Plano 05 14 1.00 2.60 36.40
P-5 6 1.00 2.70 16.20
P-6 2 0.80 2.60 4.16
P-7 8 0.70 2.80 15.68
P-8 8 0.70 2.60 14.56
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
01.14.00 APARATOS SANITARIOS Y ACCESORIOS Plano 08
01.14.01 INODORO TANQUE BAJO BLANCO C/ACCES. UND 8.00
SS.HH Odontologia 1 1.00
SS.HH Jefatura 1 1.00
SS.HH Bronco Pulmonares 1 1.00
SS.HH 2 2.00
SS.HH 3 3.00

01.14.02 LAVATORIO DE LOSA BLANCO 16" x 20" UND 8.00


SS.HH Odontologia 1 1.00
SS.HH Jefatura 1 1.00
SS.HH Bronco Pulmonares 1 1.00
SS.HH 2 2.00
SS.HH 3 3.00

01.14.03 COLOCACION DE APARATOS SANITARIOS UND 8.00


SS.HH Odontologia 1 1.00
SS.HH Jefatura 1 1.00
SS.HH Bronco Pulmonares 1 1.00
SS.HH 2 2.00
SS.HH 3 3.00

01.14.04 COLOCACION DE ACCESORIOS SANITARIOS UND 8.00


SS.HH Odontologia 1 1.00
SS.HH Jefatura 1 1.00
SS.HH Bronco Pulmonares 1 1.00
SS.HH 2 2.00
SS.HH 3 3.00

01.14.05 LAVADERO DE ACERO INOXIDABLE UND 2.00


Odontologia 1 1.00
Topico 1 1.00

01.14.06 TANQUE DE POLIETILENO 1000 LT C/ACCESORIOS UND 1.00


1 1.00

01.14.07 TOALLERA C/SOPORTE DE LOSA Y BARRA PLASTICA, COLOR BLANCO UND 8.00
8 8.00

01.14.08 PAPELERA DE LOSA Y BARRA PLASTICA, COLOR BLANCO UND 8.00


8 8.00

01.14.09 JABONERA DE LOSA COLOR BLANCO UND 8.00


8 8.00

01.15.00 INSTALACIONES SANITARIAS Plano 08


01.15.01 SALIDA DE DESAGUE PVC 4" PTO 17.00
SS.HH Odontologia 3 3.00
SS.HH Jefatura 2 2.00
SS.HH Bronco Pulmonares 2 2.00
SS.HH 3 3.00
SS.HH 6 6.00
Topico 1 1.00

01.15.02 SALIDA DE DESAGUE PVC 2" PTO 8.00


SS.HH Odontologia 1 1.00
SS.HH Jefatura 1 1.00
SS.HH Bronco Pulmonares 1 1.00
SS.HH 2 2.00
SS.HH 3 3.00

01.15.03 RED DESAGUE 4" ML 75.00


SS.HH 1 75.00 75.00

01.15.04 RED DESAGUE 2" ML 13.00


SS.HH 1 13.00 13.00

01.15.05 SALIDA DE VENTILACION 2" PVC PTO 8.00


SS.HH 8 8.00

01.15.06 REGISTROS DE BRONCE DE 4" PZA 7.00


SS.HH 7 7.00

01.15.07 SUMIDERO DE BRONCE DE 2" PZA 8.00


SS.HH 8 8.00

01.15.08 CAJA DE REGISTRO DE DESAGUE 12" X 24" PZA 3.00


Plano 09 3.00 3.00
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
01.16.00 SISTEMA AGUA FRIA Plano 08
01.16.01 SALIDA DE PUNTO DE AGUA FRIA PTO 21.00
SS.HH Odontologia 3 3.00
SS.HH Jefatura 2 2.00
SS.HH Bronco Pulmonares 2 2.00
SS.HH 4 4.00
SS.HH 6 6.00
Topico 1 1.00
Jardines 3 3.00

01.16.02 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP M 58.00


SS.HH 58 58.00

01.16.03 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP M 37.00


SS.HH 31 31.00

01.16.04 VALVULA DE COMPUERTA 1/2" DE BRONCE UND 12.00


SS.HH 12 12.00

01.16.05 LLAVE DE GRIFO DE 1/2" UND 13.00


SS.HH Odontologia 2 2.00
SS.HH Jefatura 1 1.00
SS.HH Bronco Pulmonares 1 1.00
SS.HH 2 2.00
SS.HH 3 3.00
Topico 1 1.00
Jardines 3 3.00

01.17.00 INSTALACIONES ELECTRICAS Plano 09


01.17.01 ACOMETIDA MONOFASICA AEREA UND 1.00
1 1.00

01.17.02 SALIDA PARA CENTROS DE LUZ CIRCULAR 20W PTO 21.00


21 21

01.17.03 SALIDA PARA CENTROS DE LUZ CIRCULAR 20W, CONTROL DOBLE PTO 3.00
3 3

01.17.04 SALIDA PARA CENTROS DE LUZ C/ARTEFACTO FLUORESCENTE TUBULAR 2x36 PTO 11.00
11 11

01.17.05 SALIDA PARA CENTROS DE LUZ C/ARTEFACTO FLUORESCENTE TUBULAR 2x36 PTO 2.00
2 2

01.17.06 SALIDA PARA BRAQUET 20W PTO 2.00


2 2

01.17.07 SALIDA PARA BRAQUET 20W, CONTROL DOBLE PTO 18.00


18 18

01.17.08 SALIDA PARA BRAQUET C/LUMINARIA T/M 80 W UND 2.00


2 2

01.17.09 SALIDA PARA CAJA DE PASO PZA 4.00


4 4

01.17.10 SALIDA PARA TOMACORRIENTE DOBLE C/PUESTA A TIERRA PZA 40.00


40 40

01.17.11 SALIDA PARA TIMBRE PZA 1.00


1 1

01.17.12 SALIDA PARA TELEFONO PZA 4.00


4 4

01.17.13 SALIDA PARA TELEVISION PZA 2.00


2 2

01.17.14 INST. TABLERO DE DISTRIBUCION (TD) UND 1.00


1 1

01.17.15 INST. TABLERO DE DISTRIBUCION (TD1) UND 1.00


1 1

01.17.16 INST. DE POZO DE PUESTA A TIERRA UND 1.00


1 1

01.17.17 PRUEBAS ELECTRICAS GBL 1.00


1 1
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
01.18.00 VARIOS
01.18.01 BARANDA METALICA DE F N 2", H=0.90M. ML 5.00
5 5

02.00.00 CERCO PERIMETRICO


02.01.00 TRABAJOS PRELIMINARES Plano 12
02.01.01 LIMPIEZA DE TERRENO MANUAL Plano M2 18.40
1 36.70 0.50 18.40

02.01.02 TRAZO NIVELES Y REPLANTEO M2 18.40


1 36.70 0.50 18.40

02.02.00 MOVIMIENTO DE TIERRAS Plano 12


02.02.01 EXCAVACION DE TERRENO MANUAL P/CIMIENTOS M3 13.28
1 32.70 0.50 0.80 13.08
1 0.50 0.50 0.80 0.20

02.02.02 RELLENO CON MATERIAL PROPIO (INC. COMPACTACION MANUAL) M3 2.29


1 32.70 0.35 0.20 2.29

02.02.03 ELIMINACION DE MATERIAL EXCEDENTE DPROM 3.0 KM M3 14.29


1.3 13.28 2.29 14.29

02.03.00 OBRAS DE CONCRETO SIMPLE Plano 12


02.03.01 CONCRETO C:H 1:10+30% P.G. PARA CIMIENTOS CORRIDOS M3 10.52
1 30.05 0.50 0.70 10.52

02.03.02 CONCRETO C:H 1:8+25% P.M. PARA SOBRECIMIENTOS M3 1.80


Cerco Muro Ladrillo 1 30.05 0.15 0.40 1.80

02.03.03 ENCOFRADO Y DESENCOFRADO CARAVISTA PARA SOBRECIMIENTOS Plano 0 M2. 24.04


Cerco Muro Ladrillo 2 30.05 0.40 24.04

02.04.00 OBRAS DE CONCRETO ARMADO Plano 12


02.04.01.0 COLUMNA
02.04.01.1 CONCRETO F'C= 175 KG/CM2 EN COLUMNAS M3 1.55
12 0.20 0.15 3.20 1.15
2 0.25 0.25 3.20 0.40

02.04.01.2 ENCOFRADO Y DESENCOFRADO EN COLUMNAS M2 21.76


24 0.20 3.20 15.36
8 0.25 3.20 6.40

02.04.01.3 ACERO FY=4200 KG/CM2 EN COLUMNAS KG 294.05


1/2" 48.00 3.80 1.02 186.05
1/4" 360.00 1.20 0.25 108.00

02.04.01.4 JUNTAS DE DILATACION M 16.00


1 16.00 16.00

02.04.02.0 VIGAS
02.04.02.1 CONCRETO F'C= 175 KG/CM2 EN VIGAS M3 0.66
1 0.95 0.15 0.15 0.02
7 3.00 0.15 0.15 0.47
1 3.05 0.15 0.15 0.07
1 2.15 0.15 0.15 0.05
1 0.90 0.15 0.15 0.02
1 1.45 0.15 0.15 0.03

02.04.02.2 ENCOFRADO Y DESENCOFRADO EN VIGAS M2 8.87


2 0.95 0.15 0.29
14 3.00 0.15 6.30
2 3.05 0.15 0.92
2 2.15 0.15 0.65
2 0.90 0.15 0.27
2 1.45 0.15 0.44

02.04.02.3 ACERO FY=4200 KG/CM2 EN VIGAS KG 134.73


1/2" 3.00 1.75 1.02 5.36
1/4" 7.00 0.70 0.25 1.23
1/2" 21.00 3.80 1.02 81.40
1/4" 22.00 0.70 0.25 3.85
1/2" 3.00 3.85 1.02 11.78
1/4" 23.00 0.70 0.25 4.03
1/2" 3.00 2.95 1.02 9.03
1/4" 16.00 0.70 0.25 2.80
1/2" 3.00 1.70 1.02 5.20
1/4" 7.00 0.70 0.25 1.23
1/2" 3.00 2.25 1.02 6.89
1/4" 11.00 0.70 0.25 1.93
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
02.05.00 MUROS
02.05.01 MURO DE LADRILLLO BLOCKER II SOGA CON MORTERO CEMENTO ARENA M2 64.90
Plano 08 1 0.95 2.20 2.09
7 3.00 2.20 46.20
1 3.05 2.20 6.71
1 2.15 2.20 4.73
1 0.90 2.20 1.98
1 1.45 2.20 3.19

02.06.00 CARPINTERIA METALICA


02.06.01 PUERTA C/MARCO DE TUBO FN DE 2" Y 2 1/2",MALLA N.12 X 2", A=4.00 H=2.35m UND 1.00
Plano 08 1 1.00

03.00.00 VEREDA DE SEGURIDAD


03.01.00 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO EN FORMA MANUAL M3 29.96
Plano 09 1 65.65 1.20 0.15 11.80
1 10.90 1.00 0.15 1.60
1 5.00 1.80 0.15 1.40
Rampa 1 1.33 2.35 0.15 0.50
1 3.80 3.30 0.15 1.90
Martillo 1 Area= 24.25 0.15 3.64
1 1.45 3.45 0.15 3.45
1 Area= 8.45 0.15 1.27
Rampa 1 2.50 1.40 0.15 0.21
Ingreso Principal 1 Area= 27.95 0.15 4.19

03.01.02 EXCAVACION DE ZANJAS PARA SARDINEL M3 1.74


Plano 09 1 65.65 0.12 0.08 0.63
1 65.65 0.20 0.12 0.42
1 10.90 0.12 0.08 0.10
1 10.90 0.20 0.12 0.07
1 5.00 0.12 0.08 0.05
1 5.00 0.20 0.12 0.03
1 1.33 0.12 0.08 0.01
1 1.33 0.20 0.12 0.01
1 3.80 0.12 0.08 0.04
1 3.80 0.20 0.12 0.02
1 1.45 0.12 0.08 0.01
1 1.45 0.20 0.12 0.01
1 2.50 0.12 0.08 0.02
1 2.50 0.20 0.12 0.02
1 12.00 0.12 0.08 0.12
1 12.00 0.20 0.12 0.08
1 6.45 0.12 0.08 0.06
1 6.45 0.20 0.12 0.04

03.01.03 TERRAPLEN VEREDA E=0.10 m M2 238.60


Plano 09 1.3 65.65 1.20 102.40
1.3 10.90 1.00 14.20
1.3 5.00 1.80 11.70
1.3 1.33 2.35 4.10
1.3 3.80 3.30 16.30
1.3 1.45 3.45 6.50
1.3 2.50 1.40 4.60
1.3 Area= 24.25 31.50
1.3 Area= 8.45 11.00
Ingreso Principal 1.3 Area= 27.95 36.30

03.01.04 ELIMINACION DE MATERIAL EXCEDENTE D PROM 3.0 KM M3 10.20


1.3 31.70 23.86 10.20

03.02.00 CONCRETO SIMPLE


03.02.01 CONCRETO F'C= 140 Kg/Cm2 EN SARDINEL PREMEZCLADO M3 1.74
Plano 09 1 65.65 0.12 0.08 0.63
1 65.65 0.20 0.12 0.42
1 10.90 0.12 0.08 0.10
1 10.90 0.20 0.12 0.07
1 5.00 0.12 0.08 0.05
1 5.00 0.20 0.12 0.03
1 1.33 0.12 0.08 0.01
1 1.33 0.20 0.12 0.01
1 3.80 0.12 0.08 0.04
1 3.80 0.20 0.12 0.02
1 1.45 0.12 0.08 0.01
1 1.45 0.20 0.12 0.01
1 2.50 0.12 0.08 0.02
1 2.50 0.20 0.12 0.02
1 12.00 0.12 0.08 0.12
1 12.00 0.20 0.12 0.08
1 6.45 0.12 0.08 0.06
1 6.45 0.20 0.12 0.04
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
03.02.02 VEREDA DE PIEDRA LAVADA CONCRETO F'C = 140 Kg/Cm2 e=10 Cm C/CONC M2 183.50
Plano 09 1 65.65 1.20 78.78
1 10.90 1.00 10.90
1 5.00 1.80 9.00
1 1.33 2.35 3.13
1 3.80 3.30 12.54
1 Area= 24.25 24.25
1 1.45 3.45 5.00
1 Area= 8.45 8.45
1 2.50 1.40 3.50
1 Area= 27.95 27.95

03.02.03 ENCOFRADO Y DESENCOFRADO PARA VEREDAS M2 26.82


Plano 09 1 65.65 0.20 13.13
1 10.90 0.20 2.18
1 5.00 0.20 1.00
1 1.33 0.20 0.27
1 3.80 0.20 0.76
1 1.45 0.20 0.29
1 2.50 0.20 0.50
1 12.00 0.20 2.40
1 6.45 0.20 1.29
1 25.00 0.20 5.00

03.03.00 VARIOS
03.03.01 JUNTAS RELLENAS CON ASFALTO M 74.33
Plano 09 17 1.20 20.40
4 1.00 4.00
2 1.80 3.60
1 2.35 2.35
2 3.30 6.60
1 3.45 3.45
2 1.40 2.80
3 3.45 10.35
1 1.76 1.76
1 1.02 1.02
1 18.00 18.00

03.03.02 CURADO DE VEREDAS C/ADITIVO M2 183.55


Plano 09 1 65.65 1.20 78.80
1 10.90 1.00 10.90
1 5.00 1.80 9.00
1 1.33 2.35 3.10
1 3.80 3.30 12.50
1 Area= 24.25 24.30
1 1.45 3.45 5.00
1 Area= 8.45 8.50
1 2.50 1.40 3.50
1 Area= 27.95 27.95

04.00.00 SARDINEL PERALTADO PARA JARDINES


04.01.00 CIMIENTO P/SARDINEL PERALTADO : CONCRETO PREMEZCLADO F'C=100 KG/ M3 2.34
1 26.00 0.30 0.30 2.34

04.02.00 SARDINEL PERALTADO : CONCRETO PREMEZCLADO F'C=140 KG/CM2 M3 1.38


H=0.30m 1 17.55 0.10 0.40 0.70
H=0.70m 1 8.45 0.10 0.80 0.68

04.03.00 SARDINEL PERALTADO : ENCOFRADO CARAVISTA M2 27.56


H=0.30m 2 17.55 0.40 14.04
H=0.70m 2 8.45 0.80 13.52

04.04.00 SARDINEL PERALTADO : ACERO FY=4200 KG/CM2 KG 167.82


3/8" 89.00 0.95 0.59 49.88
1/4" 6.00 25.00 0.25 37.50
3/8" 43.00 1.20 0.59 30.44
1/4" 8.00 25.00 0.25 50.00

04.05.00 PINTURA ESMALTE EN SARDINEL PERALTADO M2 13.80


1 17.55 0.30 5.27
1 17.55 0.10 1.76
1 8.45 0.70 5.92
1 8.45 0.10 0.85

04.06.00 IMPERMEABILIZACION DE SARDINELES CON BREA M2 29.20


1 17.55 0.40 7.02
1 8.45 0.80 6.76
1 25.70 0.60 15.42
PLANILLA DE METRADOS

PROYECTO: MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL P.S HABITAT


ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNA
FECHA : AGOSTO 2005

CANT DIMENSIONES
ITEM DESCRIPCION UNID. PARCIAL TOTAL
VECES LARGO (L) ANCHO (B) ALTO (H)
05.00.00 ESTACIONAMIENTO
05.01.00 CORTE DE TERRENO EN FORMA MANUAL M3 15.45
1 Area= 68.00 0.15 10.20
1 Area= 35.00 0.15 5.25

05.02.00 PERFILADO Y COMPACTADO C/PLANCHA COMPACTADORA M2 103.00


1 Area= 68.00 68.00
1 Area= 35.00 35.00

05.03.00 ELIMINACION DE MATERIAL EXCEDENTE DPROM 3.5 KM M3 20.09


1.3 15.45 20.09

05.04.00 BASE GRANULAR E=0.15 M2 103.00


1 Area= 68.00 68.00
1 Area= 35.00 35.00

05.05.00 LIMPIEZA DE VIAS CON EQUIPO M2 103.00


1 Area= 68.00 68.00
1 Area= 35.00 35.00

05.06.00 MPRIMACION MANUAL M2 103.00


1 Area= 68.00 68.00
1 Area= 35.00 35.00

05.07.00 CARPETA ASFALTICA E= 1 1/2" M2 103.00


1 Area= 68.00 68.00
1 Area= 35.00 35.00

06.00.00 AREAS VERDES


06.01.00 MULLIDO DE CAMPO M2 123.55
1 Area= 63.10 63.10
1 Area= 51.40 51.40
1 Area= 5.15 5.15
2 Area= 1.95 3.90

06.01.01 PREPARACION DE TERRENO P/CESPED M2 123.55


1 Area= 63.10 63.10
1 Area= 51.40 51.40
1 Area= 5.15 5.15
2 Area= 1.95 3.90

06.01.02 SUM. Y COLOC. TIERRA DE CHACRA M2 123.55


1 Area= 63.10 63.10
1 Area= 51.40 51.40
1 Area= 5.15 5.15
2 Area= 1.95 3.90

06.01.03 SUM. E INST. DE CESPED M2 123.55


1 Area= 63.10 63.10
1 Area= 51.40 51.40
1 Area= 5.15 5.15
2 Area= 1.95 3.90