Professional Documents
Culture Documents
Throughput Accounting
1.Just-In-Time System
Q1. C: 1 and 3
Q2. B: 2 only
Q3. C: 1, 2 and 3
2.Throughput
Q5. D: $8
Workings:
Throughput = Selling Price Direct Material Cost
= $10 - $2 = $8
Q6. A: $21,300
Workings:
Throughput = Selling Price Direct Material Cost
Direct Material Cost = Selling Price Throughput
= $85,000 - $63,700 = $$21,300
3.Theory of Constraints
Q7. C: 1, 2 and 3
Q8. C: 1 and 2
Total salon hours in a year = 8 hours x 6 days x 50 weeks = 2,400 hours per year
Capacity of Assistants:
No. of cuts per year = (2,400 hours / 0.1 hours per cut) x 2 assistants = 48,000 cuts per year
No. of treatments per year = (2,400 hours / 0.3 hours per treatment) x 2 assistants = 16,000
treatments per year
No. of cuts per year = (2,400 hours / 1 hours per cut) x 3 senior stylists = 7,200 cuts per year
No. of treatments per year = (2,400 hours / 1.5 hours per treatment) x 3 senior stylists = 4,800
treatments per year
No. of cuts per year = (2,400 hours / 0.5 hours per cut) x 2 junior stylists = 9,600 cuts per year
No. of treatments per year = (2,400 hours / 0.5 hours per treatment) x 2 junior stylists = 9,600
treatments per year
Since the total number of cuts and treatments which can be completed by the senior stylist is less
than the number which can be completed by the other staff members, the senior stylists time is the
bottleneck activity.
The total processing hours of the factory is given but can be proven as follows:
18 hours x 5 days x 50 weeks x 50 production lines = 225,000 hours.
Given this, the production capacity for pressing must be 225,000 hours/05 hours per metre =
450,000 metres. Using this method the production capacity for all processes is as follows:
The bottleneck is clearly the pressing process which has a lower capacity for each product. The
other processes will probably be slowed to ensure smooth processing.
Clearly an alternative approach is simply to look at the original table for processing speed and pick
out the slowest process. This is pressing. (full marks available for that explained observation)
Q12. B: False
4.Theory of Constraints
Q15. A: True
A: 1.33
Q20. B: False
(ii) A TPAR of less than one indicates that the rate at which product C generates throughput (sales
revenue less material cost) is less than the rate at which Yam incurs fixed cost. So on a simple
level, producing a product which incurs fixed cost faster than it generates throughput does not
seem to make commercial sense. Clearly the TPAR could be improved (using the methods above)
before cessation is considered any further.
However, cessation decisions involve consideration of many wider issues (only three required).
Long-term expected net cash flows from the product allowing for the timing of those cash
flows (NPV) are an important factor in cessation decisions.
Customer perception could be negative in that they will see a reduction in choice.
Lost related sales: if product C is lost will Yam lose customers that bought it along with
another product?
What use could be made of the excess capacity that is created.
Throughput assumes that all costs except raw materials are fixed; this may not necessarily
be the case and only avoidable fixed costs need to be taken into account for a cessation
decision. If few fixed costs can be avoided then product C is making a contribution that will
be lost if the product ceased.
Working 1:
No. of units = (2,700-600)/1.4 = 1,500
Generally speaking, throughput can be increased by increasing sales volumes or prices on the one
hand, or by cutting costs on the other hand. In the case of S Co, it is not possible to increase sales
prices as the company has guaranteed not to increase them for three years. From our answer to
(b) above, we can see that S Co has unsatisfied demand for both small panels and large panels.
There are customers out there who the company is unable to supply because of its restricted
machine capacity. Therefore, it would be worthwhile for S Co to focus on increasing production
volumes and thus sales volumes.
In order to increase production volumes without making any additional capital expenditure, the
company needs to focus on how it could increase the productivity of Machine M. We are told that
there is plenty of spare capacity on Machines C and A. Some suggestions to increase Machine Ms
capacity are as follows:
Machine M is currently only fully functional 90% of the time. This means that 300 hours of
time are lost whilst the machine is being maintained or workers are not available to man it.
If the maintenance work could be carried out outside the usual working day (i.e. either
before 7 am or after 8 pm), some additional time could be freed up. This should be possible
given that we are told that the maintenance contractors work around the clock.
Workers could be trained to use more than one of the machines. This would then mean
that, if some workers were absent, one of the other workers could step in and work on
another machine in order to keep it running. Again, this would help to keep the lost 300
hours productive.
The most obvious machine time which is being lost is the one hour per day at lunchtime.
This amounts to 250 lost production hours per year. These additional 250 hours could be
used to produce an extra 178 large panels (250/14 hours.) Large panels should be made
first in preference to small panels since they generate a higher throughput per machine
hour. If workers were trained to use all three machines then, if their lunchtimes were
staggered, it may be possible to keep machine M running for the whole working day.
However, even after doing this, there would still be 590 additional hours of time required on
Machine M if the full market demand is going to be satisfied. Therefore, more time needs to
be made available.
Finally then, in order to increase productive hours on M, the working hours of the factory
would need to be increased. Either the working day could be made longer, given that
workers must already be working shifts, or maybe the factory could open for one extra day
per week.