MG ING LUIS DIAZ HUIZA

CIP#36994
TELF.4754256-99004184

PRESUPUESTO

OBRA: AMPLIACIN DE LABORATORIO FECHA: Aug-12


PROPIETARIO: CAD UBICACIN: JESUS MARIA
CONTRATISTA: NQT CONTRATISTAS SAC AREA GEOGRFICA:02

ITEM DESCRIPCIN UND. CANT. P. UNIT. PARCIAL IMPORTE


1.00 CONCRETEO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO FC= 175 KG/CM2 M3 12.00 333.94 4,007.28
1.01.02 ENCOFRA. - DESENCOF. M2 60.00 42.00 2,520.00
1.01.03 ACERO CORRUGADO KG 800.00 4.94 3,952.00 10,479.28
1.02 VIGA
1.02.01 CONCRETO FC= 175 KG/CM2 M3 8.00 305.15 2,441.20
1.02.02 ENCOFRA. - DESENCOF. M2 40.00 46.53 1,861.20
1.02.03 ACERO CORRUGADO KG 500.00 4.94 2,470.00 6,772.40
1.03 LOSA ALIGERADA
1.03.01 CONCRETO FC= 175 KG/CM2 M3 9.00 279.22 2,512.98
1.03.02 ENCOFRA. - DESENCOF. M2 120.00 33.07 3,968.40
1.03.03 ACERO CORRUGADO KG 700.00 4.94 3,458.00
1.03.04 LADRILLO O.15x0.30x0.30 UND 1020.00 2.67 2,723.40 12,662.78 29,914.46
2.00 MUROS
2.01 LADRILLO KK 18 HCO. SOGA M2 30.00 48.84 1,465.20
2.02 LADRILLO KK 18 HCO. CABEZA M2 48.00 76.09 3,652.32 5,117.52
COSTO DIRECTO 35,031.98
GASTOS GENERALES ( 15% ) 5,254.80
UTILIDAD ( 10 % ) 3,503.20
SUBTOTAL 43,789.98
IGV 7,882.20
TOTAL 51,672.18
01.- DADO LAS ACTIVIDADES QUE SE INDICAN, SE PIDE ELABORAR EL DIAGRAMA DE GANTT.
CONSIDERAR:
ALBAILERA CONFINADA
MURO PORTANTE DE CABEZA
EL PROYECTO SE VA REALIZAR EN LOS AIRES DEL SEGUNDO PISO.

ITEM DESCRIPCIN UND. CANT. Ru Tu TU1 Tp


1.00 CONCRETEO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO FC= 175 KG/CM2 M3 12.00 6 2 2 1
1.01.02 ENCOFRA. - DESENCOF. M2 60.00 12 5 5 3
1.01.03 ACERO CORRUGADO KG 800.00 240 3.3333 4 2
1.02 VIGA
1.02.01 CONCRETO FC= 175 KG/CM2 M3 8.00 7 1.1429 1 1
1.02.02 ENCOFRA. - DESENCOF. M2 40.00 10 4 4 2
1.02.03 ACERO CORRUGADO KG 500.00 240 2.0833 2 2
1.03 LOSA ALIGERADA
1.03.01 CONCRETO FC= 175 KG/CM2 M3 9.00 12.5 0.72 1 1
1.03.02 ENCOFRA. - DESENCOF. M2 120.00 15 8 8 6
1.03.03 ACERO CORRUGADO KG 700.00 240 2.9167 3 1
1.03.04 LADRILLO O.15x0.30x0.30 UND 1020.00 160 6.375 7 4
2.00 MUROS
2.01 LADRILLO KK 18 HCO. SOGA M2 30.00 9.4 3.1915 3 2
2.02 LADRILLO KK 18 HCO. CABEZA M2 48.00 7 6.8571 7 5

NOTA.-
Ru= RENDIMIENTO UNITARIO
Tu= TIEMPO UNITARIO= METTRADO/ Ru
Tp= TIEMPO PROGRAMADO= TIEMPO QUE ESTIMA EL PROFESIONAL QUE LO ELABORA.
f= FACTOR DE MULTIPLICIDAD= Tu/Tp
C. BASE C. REQUERIDO
CAP. OP. OFIC. PE. f CAP. OP. OFIC. PE.

0.1 1 1 5 2.0 0.2 2 2 10


0.1 1 1 1.7 0.2 1.7 1.7
0.3 1 1 2.0 0.6 2 2

0.1 1 0.5 5 1.0 0.1 1 0.5 5


0.1 1 1 2.0 0.2 2 2
0.3 1 1 1.0 0.3 1 1

0.2 1.5 1 6.5 1.0 0.2 1.5 1 6.5


0.1 1 1 1.3 0.1 1.3 1.3
0.3 1 1 3.0 0.9 3 3
0.1 1 1.8 0.2 1.8

0.1 1 0.8 1.5 0.2 1.5 1.2


0.1 1 0.8 1.4 0.2 1.4 1.1
S-1
ITEM DESCRIPCIN UND. CANT. Tp L M MI J V
1.00 CONCRETEO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO FC= 175 KG/CM2 M3 12.00 1
1.01.02 ENCOFRA. - DESENCOF. M2 60.00 3
1.01.03 ACERO CORRUGADO KG 800.00 2
1.02 VIGA
1.02.01 CONCRETO FC= 175 KG/CM2 M3 8.00 1
1.02.02 ENCOFRA. - DESENCOF. M2 40.00 2
1.02.03 ACERO CORRUGADO KG 500.00 2
1.03 LOSA ALIGERADA
1.03.01 CONCRETO FC= 175 KG/CM2 M3 9.00 1
1.03.02 ENCOFRA. - DESENCOF. M2 120.00 6
1.03.03 ACERO CORRUGADO KG 700.00 1
1.03.04 LADRILLO O.15x0.30x0.30 UND 1020.00 4
2.00 MUROS
2.01 LADRILLO KK 18 HCO. SOGA M2 30.00 2
2.02 LADRILLO KK 18 HCO. CABEZA M2 48.00 5
PLANIFICACIN: DIAGRAMA DE GANTT

S-2 S-3 S-4


S L M MI J V S L M MI J V S L M MI
J V S
MG ING LUIS DIAZ HUIZA
CIP#36994
TELF.4754256-99004184

ANALISIS DE COSTO

PARTIDA: 1.01.01 UND.: M3


DESCRIPCIN: CONCRETO FC=175 KG/M2 . COLUMNA FECHA: AGO 2012
CUADRILLA: 0.1 CAP +1 OP + 1 OF + 5 P ELABORADO POR: DHL
RENDIMIENTO: 6M3/DIA

IU MATERIALES UND CANT. P.UNIT P.PARCIAL IMPORTE


004 Arena gruesa M3. 0.5100 30.00 15.30
005 Piedra chancada M3. 0.7600 45.00 34.20
021 Cemento Bls. 8.6600 15.25 132.07

181.57

IU MANO DE OBRA UND CANT. P.UNIT P.PARCIAL IMPORTE


047 Cap. H-H 0.1333 18.47 2.46
047 Op. H-H 1.3333 15.92 21.23
047 Ofic. H-H 1.3333 13.65 18.20
047 Ay. H-H 6.6667 12.31 82.07

123.96

IU MAQUINARIA-EQUIPO UND CANT. P.UNIT P.PARCIAL IMPORTE


048 Mezcladora de 11p3. H-M 0.6700 20.00 13.40
048 Vibradora H-M 0.6700 15.00 10.05
037 Herr. % 4.0000 123.96 4.96

28.41

P. UNIT. 333.94

ANALISIS DE COSTO

PARTIDA: 1.01.02 UND.: M2


DESCRIPCIN: ENCOF/DESENC - COLUMNA FECHA: AGO 2012
CUADRILLA: 0.1 CAP +1 OP + 1 OF ELABORADO POR: DHL
RENDIMIENTO: 12 M2/DIA

IU MATERIALES UND CANT. P.UNIT P.PARCIAL IMPORTE


002 Alambre negro N8 Kg. 0.2000 3.50 0.70
043 Madera tornillo p2. 4.4800 4.20 18.82
002 Clavo Kg. 0.2000 3.50 0.70
20.22

IU MANO DE OBRA UND CANT. P.UNIT P.PARCIAL IMPORTE


047 Cap. H-H 0.0667 18.47 1.23
047 Op. H-H 0.6667 15.92 10.61
047 Ofic. H-H 0.6667 13.65 9.10
20.94

IU MAQUINARIA-EQUIPO UND CANT. P.UNIT P.PARCIAL IMPORTE


037 Herr. % 4.0000 20.94 0.84
MG ING LUIS DIAZ HUIZA
CIP#36994
TELF.4754256-99004184

0.84

P. UNIT. 42.0

ANALISIS DE COSTO

PARTIDA: 1.01.03 UND.: KG


DESCRIPCIN: ACERO CORRUGADO - COLUMNA FECHA: AGO 2012
CUADRILLA: 0.3 CAP +1 OP + 1 OF ELABORADO POR: DHL
RENDIMIENTO: 240 KG/DIA

IU MATERIALES UND CANT. P.UNIT P.PARCIAL IMPORTE


003 Fierro de construccin Kg. 1.0700 3.40 3.64
002 Alambre N16 Kg. 0.0250 3.50 0.09
3.73

IU MANO DE OBRA UND CANT. P.UNIT P.PARCIAL IMPORTE


047 Cap. H-H 0.0100 18.47 0.18
047 Op. H-H 0.0333 15.92 0.53
047 Ofic. H-H 0.0333 13.65 0.45
1.16

IU MAQUINARIA-EQUIPO UND CANT. P.UNIT P.PARCIAL IMPORTE


037 Herr. % 4.0000 1.16 0.05
0.05

IGUAL PARA ACERO EN VIGAS Y LOSA ALIGERADA P. UNIT. 4.94

ANALISIS DE COSTO

PARTIDA: 1.02.01 UND.: M3


DESCRIPCIN: CONCRETO FC>175 KG/M2 - VIGA FECHA: AGO 2012
CUADRILLA: 0.1 CAP +1 OP + 0.5 OF + 5 P ELABORADO POR:DHL
RENDIMIENTO: 7M3/DIA

IU MATERIALES UND CANT. P.UNIT P.PARCIAL IMPORTE


004 Arena gruesa M3. 0.5100 30.00 15.30
005 Piedra chancada M3. 0.7600 45.00 34.20
021 Cemento Bls. 8.6600 15.25 132.07
181.57

IU MANO DE OBRA UND CANT. P.UNIT P.PARCIAL IMPORTE


047 Cap. H-H 0.1143 18.47 2.11
047 Op. H-H 1.1429 15.92 18.19
047 Ofic. H-H 0.5714 13.65 7.80
047 Ay. H-H 5.7143 12.31 70.34
98.44

IU MAQUINARIA-EQUIPO UND CANT. P.UNIT P.PARCIAL IMPORTE


048 Mezcladora de 11p3. H-M 0.4000 20.00 8.00
048 Winche H-M 0.4000 18.00 7.20
048 Vibradora H-M 0.4000 15.00 6.00
037 Herr. % 4.0000 98.44 3.94
MG ING LUIS DIAZ HUIZA
CIP#36994
TELF.4754256-99004184

25.14

P. UNIT. 305.15

ANALISIS DE COSTO

PARTIDA: 1.02.02 UND.: M2


DESCRIPCIN: ENCOFRADO Y DESENCO - VIGA FECHA: AGO 2012
CUADRILLA: 0.1 CAP +1 OP + 1OF ELABORADO POR:DHL
RENDIMIENTO: 10M2/DIA

IU MATERIALES UND CANT. P.UNIT P.PARCIAL IMPORTE


002 Alambre N8 Kg. 0.1000 3.50 0.35
002 Clavo Kg. 0.1800 3.50 0.63
043 Madera tornillo p2. 4.6200 4.20 19.40
20.38

IU MANO DE OBRA UND CANT. P.UNIT P.PARCIAL IMPORTE


047 Cap. H-H 0.0800 18.47 1.48
047 Op. H-H 0.8000 15.92 12.74
047 Ofic. H-H 0.8000 13.65 10.92
25.14

IU MAQUINARIA-EQUIPO UND CANT. P.UNIT P.PARCIAL IMPORTE


037 Herr. % 4.0000 25.14 1.01
1.01

P. UNIT. 46.53

ANALISIS DE COSTO

PARTIDA: 1.03.01 UND.: M3


DESCRIPCIN: CONCRETO FC>175 KG/M2 - LOSA FECHA: AGO 2012
CUADRILLA: 0.2 CAP +1.5 OP + 1 OF + 6.5 P ELABORADO POR: DHL
RENDIMIENTO: 12.5M3/DIA

IU MATERIALES UND CANT. P.UNIT P.PARCIAL IMPORTE


004 Arena gruesa M3. 0.5100 30.00 15.30
005 Piedra chancada M3. 0.7600 45.00 34.20
021 Cemento Bls. 8.6600 15.25 132.07
181.57

IU MANO DE OBRA UND CANT. P.UNIT P.PARCIAL IMPORTE


047 Cap. H-H 0.1280 18.47 2.36
047 Op. H-H 0.9600 15.92 15.28
047 Ofic. H-H 0.6400 13.65 8.74
047 Ay. H-H 4.1600 12.31 51.21
77.59

IU MAQUINARIA-EQUIPO UND CANT. P.UNIT P.PARCIAL IMPORTE


048 Mezcladora de 11p3. H-M 0.3200 20.00 6.40
048 Winche H-M 0.3200 18.00 5.76
048 Vibradora H-M 0.3200 15.00 4.80
MG ING LUIS DIAZ HUIZA
CIP#36994
TELF.4754256-99004184

037 Herr. % 4.0000 77.59 3.10


20.06

P. UNIT. 279.22

ANALISIS DE COSTO

PARTIDA: 1.03.02 UND.: M2


DESCRIPCIN: ENCOFRADO Y DESC.- LOSA FECHA: AGO 2012
CUADRILLA: 0.1 CAP +1 OP + 1 OF ELABORADO POR: DHL
RENDIMIENTO: 15M2/DIA

IU MATERIALES UND CANT. P.UNIT P.PARCIAL IMPORTE


002 Alambre N8 Kg. 0.1000 3.50 0.35
002 Clavo Kg. 0.1000 3.50 0.35
043 Madera tornillo P2. 3.5600 4.20 14.95
15.65

IU MANO DE OBRA UND CANT. P.UNIT P.PARCIAL IMPORTE


047 Cap. H-H 0.0533 18.47 0.98
047 Op. H-H 0.5333 15.92 8.49
047 Ofic. H-H 0.5333 13.65 7.28

16.75

IU MAQUINARIA-EQUIPO UND CANT. P.UNIT P.PARCIAL IMPORTE


037 Herr. % 4.0000 16.75 0.67
0.67

P. UNIT. 33.07

ANALISIS DE COSTO

PARTIDA: 1.03.04 UND.: UND


DESCRIPCIN: LADRILLO .15x.30x.30- LOSA ALIG. FECHA: AGO 2012
CUADRILLA: 0.1 CAP +1 P ELABORADO POR: DHL
RENDIMIENTO: 160UND/DIA

IU MATERIALES UND CANT. P.UNIT P.PARCIAL IMPORTE


017 Ladrillo arcilla 15x30x30 Und. 1.0900 1.80 1.96
1.96

IU MANO DE OBRA UND CANT. P.UNIT P.PARCIAL IMPORTE


047 Cap. H-H 0.0050 18.47 0.09
047 Ay. H-H 0.0500 12.31 0.62
0.71

IU MAQUINARIA-EQUIPO UND CANT. P.UNIT P.PARCIAL IMPORTE


037

P. UNIT. 2.67
MG ING LUIS DIAZ HUIZA
CIP#36994
TELF.4754256-99004184

ANALISIS DE COSTO

PARTIDA: 2.01 UND.: M2


DESCRIPCIN: LADRILLO KK 18H SOGA - MURO FECHA: AGO 2012
CUADRILLA: 0.1 CAP +1 OP + 0.8 P ELABORADO POR: DHL
RENDIMIENTO: 9.40M2/DIA

IU MATERIALES UND CANT. P.UNIT P.PARCIAL IMPORTE


017 Lad.K.K. 18H mquina 9x1 Und. 37.0000 0.50 18.50
004 Arena gruesa M3. 0.0290 30.00 0.87
021 Cemento Bls. 0.2360 15.25 3.60
043 Madera tornillo p2. 0.3300 4.20 1.39
002 Clavo Kg. 0.0110 3.50 0.04

24.39

IU MANO DE OBRA UND CANT. P.UNIT P.PARCIAL IMPORTE


047 Cap. H-H 0.0851 18.47 1.57
047 Op. H-H 0.8511 15.92 13.55
047 Ay. H-H 0.6809 12.31 8.38

23.50

IU MAQUINARIA-EQUIPO UND CANT. P.UNIT P.PARCIAL IMPORTE


037 Herr. % 4.0000 23.50 0.94

0.94

P. UNIT. 48.84

ANALISIS DE COSTO

PARTIDA: 2.02 UND.: M2


DESCRIPCIN: LADRILLO KK 18H CABEZA - MURO FECHA: AGO 2012
CUADRILLA: 0.1 CAP +1 OP + 0.8 P ELABORADO POR: DHL
RENDIMIENTO: 7M2/DIA

IU MATERIALES UND CANT. P.UNIT P.PARCIAL IMPORTE


002 Clavo Kg. 0.0110 3.50 0.04
017 Lad.K.K. 18H mquina 9x1 Und. 68.0000 0.50 34.00
004 Arena gruesa M3. 0.0580 30.00 1.74
021 Cemento Bls. 0.4000 15.25 6.10
043 Madera tornillo p2. 0.3300 4.20 1.39

43.26

IU MANO DE OBRA UND CANT. P.UNIT P.PARCIAL IMPORTE


047 Cap. H-H 0.1143 18.47 2.11
047 Op. H-H 1.1429 15.92 18.19
047 Ay. H-H 0.9143 12.31 11.26

31.56
MG ING LUIS DIAZ HUIZA
CIP#36994
TELF.4754256-99004184

IU MAQUINARIA-EQUIPO UND CANT. P.UNIT P.PARCIAL IMPORTE


037 Herr. % 4.0000 31.56 1.26

1.26

P. UNIT. 76.09