You are on page 1of 1

Max Marks:20 marks

Max Time: 1
hours

Attempt any four out of the six questions (each carrying


5 marks)

1. Define Materials Management & describe in brief the objectives of


Materials Management?
2. Write a short note on Centralized & Decentralized Material
Management department with suitable diagrams.
3. Define Aggregate Planning & explain the various basic aggregate
planning strategies?
4. Explain the concept of BOM with the help of a suitable example?
5. Shah Woods a furniture manufacturing company has developed a
product structure for their latest Model of Product X which consist of
two components namely A & B. To manufacture this model they require
2 units of A & 4 units of B. The Planned order release for product X
were 80 units in week 3, 160 units in week 6 & 320 units in week 8 for
the planning horizon of 8 weeks.
Prepare the MRP for only A & B. Shah Woods for both A & B
maintains safety stock of 20 units along with a fixed order quantity of
50 units. The production lead time is 1 week.
6. Describe in brief the procedural steps involved in MRP computation?