Peruvian National Interconnected Power Grid Expansion

- An Outlook-
.
COES-SINAC
November, 2014
PERUVIAN POWER SECTOR

The Peruvian power sector normative, regulatory and operation bodies


are the following:
MINEM (Ministry of Energy and Mines)
OSINERGMIN (Supervising Organization for Investment
in Energy)
COES (Economical Operation Committee of the System)

2
COMMITTEE FOR THE ECONOMICAL OPERATION OF THE
SYSTEM (COES)

COES is a technical entity created by law, which includes power


generation, transmission and distribution companies and large
consumers within the Peruvian National Power Grid (Sistema
Elctrico Interconectado Nacional, SEIN).

The purpose of the COES is to coordinate the operation of the


interconnected electrical power system (SEIN) at the lowest cost
while guaranteeing the supply of power and the best use of primary
energy resources.

3
COES MEMBERS (Aug 2014)

11 Distribution companies
42 Generation companies

4 12 Transmission companies 46 Large consumers


MAIN FUNCTIONS OF COES

Program the operation of the Peruvian interconnected power


system (SEIN).

Coordinate the power system operation in real time.

Administration of the Short-Term Market (Valuation of the electric


power transactions.)

Prepare the Transmission Plan Proposal for the SEIN.

COES is supervised by OSINERGMIN, as established in the


Regulations issued by the Ministry of Energy and Mines (MINEM).

5
COES: ORGANIZATION CHART

6
NATIONAL INTERCONNECTED ELECTRICAL SYSTEM (SEIN)

SUMMARY
Installed Power - Year 2014
Total : 8 686 MW
CC.HH. 38,2 %
CC.TT. 59,1 %
RER. 2,7 %

Production of Energy
Year 2013: 39 669 GWh
Year 2014: 41 796 GWh ( : 5,4 %)
% Production 2014:
CC.HH. 48,6%, CC.TT. 48,2%, RER. 3,1%

Maximum Demand
Year 2013: 5 575 MW
Year 2014: 5 737 MW ( : 2,9 %)

Lines in 220 kV
Year 2013 : Length: 10 172 km.
Year 2014: Length: 10 717 km.

Lines in 500 kV
Year 2013: Length: 1 501 km.
Year 2014: Length: 1 845 km.
7
POWER MARKET MODEL - TRANSACTIONS

ENERGY FLOW BUSINESS FLOW

GENERATION (1) GENERATION

$$ Regulated\Bidding
MWh

$$ Contracts/Tolls/Dist. Tolls
COES

$$ Power\Tolls
$$ Spot \ Power

$$ Dist. Tolls
RT Coordination,
Information
TRANSMISSION $$ TRANSMISSION
Tolls+IT
MWh (2)

DISTRIBUTION DISTRIBUTION

Regulated
MWh MWh RC: Regulated Clients
FC: Free Clients
RC COES: Comite de Operacion

$$
FC
Economica del Sistema RC FC

(1) Programming and Evaluation of System Operation and real time operation
(2) Planning the Transmission, Diagnostic Report and approval of the Pre-operating Studies.

8
BREAKDOWN OF ENERGY GENERATION BY ENERGY SOURCE TYPE
2013

GRAFICO N2.4
GRAFICO
RECURSO ENERGTICO DE LA
DISTRIBUCIN POR TIPO DE RECURSO
Energa (GW.h) ENERGA PRODUCIDA
ENERGA PRODUCIDA EN EL 2013
25 000
20 552
51,81%
20 000 17 036
42,94%

Total
Total Produccin SEIN
15 000
39 669,43 GW.h
39 38,23%

10 000

5 000
999
999 837
837
111
111 134
134
2,52% 2,11%
0,28% 0,34%
0
RENOVABLES DIESEL 2 RESIDUAL CARBN GAS NATURAL AGUA

9
MONTHLY ENERGY PRODUCTION: HYDRAULIC, THERMAL AND
SOLAR. YEARS 2012 - 2013.

GRFICO No 5.2 B
GW. PRODUCCIN MENSUAL
PRODUCCIN MENSUAL HIDROELCTRICA TERMOELCTRICA Y SOLAR
HIDROELCTRICA - TERMOELCTRICA SOLAR
GW.h
2100

1800

1500

1200

900

600

300

0
Enero Febrero Marzo Abril Mayo Junio Julio NoviembreDiciembre
Agosto Setiembre Octubre Noviembre Diciembre

HIDROELCTRICA 2013 HIDROELCTRICA 2012 TERMOELCTRICA 2013


TERMOELCTRICA 2012 SOLAR 2012 SOLAR 2013

10
GENERATION PER TYPE OF FUEL AND TECHNOLOGY IN MAXIMUM
DEMAND DAY OF YEAR 2013 (DECEMBER 11, 2013)
GRFICO
GRFICO N 5.9
Potencia
DESPACHO
DESPACHO POR TIPO DE COMBUSTIBLE
COMBUSTIBLE Y TECNOLOGA
TECNOLOGA EN EL
(MW)
DA DE
DE MXIMA DEMANDA
DEMANDA DEL
DEL AO 2013
6 000 5 575,2 MW
( 11 DE DICIEMBRE
DICIEMBRE DE 2013 )
5 500

5 000

4 500

4 000

3 500

3 000

2 500

2 000

1 500

1 000
20:15 Hrs
500

0
0:15 1:45 3:15 4:45 6:15 7:45 9:15 10:45 12:15 13:45 15:15 16:45 18:15 19:45 21:15 22:45

TG COGEN - GN SDF ENERGA SOLAR HIDRO RER


TV - BZ AIPSAA TV - BZ MAPLE M. DIESEL - BG PETRAMAS
HIDRO TG - GN SDE PIURA TG - GN EGASA
CCOMB - GN ENERSUR M. DIESEL - GN EGESUR CCOMB - GN EDEGEL
CCOMB - GN KALLPA TG - GN EDEGEL TG - GN TERMOCHILCA
TG - GN TERMOSELVA TV - CARBN TG - GN EEPSA
11 TV - R500 TG - D2
ANNUAL GROWTH IN POWER CONSUMPTION
2004 - 2013

GRAFICO No 2.2
CRECIMIENTO ANUAL DEL CONSUMO
CRECIMIENTO CONSUMO DE
ELECTRICIDAD 2004 - 2013
ELECTRICIDAD
12%
011%
10,76%
10%
009%
8,79%
008%
8,33% 010%
10,06% 008%
8,45% 009%
8,61%
8%
008%
8,35%
006% 008%
7,66% 007%
6,65%
5,87%006%
5,56% 006%
6,30%
6%
006%
5,88% 006%
5,94% 005%
5,97%5,37%
006%
006%
5,60%
4% 005%
5,01% 003%
2,95%

2%
Energia Demanda
001%
0,84%
0%
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
12
SEINs LOAD FACTOR
2000 - 2013

GRFICO N 4.2
FACTORES DE CARGA DEL COES 2000 - 2013
Factor de carga
0,85
001
001
0,81 001
0,81 001
0,81
001
0,80 001
0,80 001
0,80
001
0,79 001
0,79 001
0,79 001
0,80
001 001
0,79 0,79
001
0,77
001
0,75
0,75
001

0,70
001
001
0,67
0,65
001

0,60
001

0,55
001

0,50
001
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

13 SEIN: NATIONAL INTERCONNECTED ELECTRICAL SYSTEM


ANNUAL AND MONTHLY AVERAGE MARGINAL COST

14
LONG TERM MAXIMUM DEMAND FORECAST

14 000 13 523
13 000 12 333
12 000
11 000 10 985
11
10 000
MW
MW

9 000
8 000
7 000
6 000
5 000
4 000
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
Pesimista Base Optimista

15
TRANSMISSION SYSTEM: PROJECTS THROUGH 2019

PROJECT
LT 220 kV Carhuaquero-Cajamarca-
Caclic-Moyobamba: May-2016

PROJECT
LT 220 kV Moyobamba-Iquitos: Feb-2019

PROJECT
LT 220 kV Friaspata-Moyepata: Jan-2017

PROJECT PROJECT
LT 500 kV Trujillo-La LT 220 kV MachuPicchu-Abancay-Cotaruse: Apr-2015
Nia: May-2014

PROJECT
LT 220 kV MachuPicchu-Quencoro-
Onocora-Tintaya: Aug-2016

PROJECT PROJECT
LT 500 kV Mantaro-Marcona- LT 220 kV Azngaro-Juliaca-
Socabaya-Montalvo: Jan-2017 Puno: May-2017
PROJECT
LT 220 kV Tintaya-
Socabaya: Apr-2014 PROJECT
LT 220 kV Moquegua-
16 Los Hroes: Jan-2017
GENERATION: PROJECTS THROUGH 2018

FECHA PROYECTO MW FECHA PROYECTO MW


jul-2014 Central Elica Talara 30.00 ene-2017 CH Maran 88.00
jul-2014 Central Elica Cupisnique 80.00 ene-2017 CH Zaa 1 13.20
ago-2014 CH Santa Teresa - G1 49.06 ene-2017 CH Colca 12.05
nov-2014 CT Fenix - TG11 268.00 ene-2017 CH Yarucaya 16.50
nov-2014 Central Biomasa La Gringa V 2.00 ene-2017 CH Santa Lorenza I 18.70
ene-2015 CH Runatullo III 20.00 ene-2017 CH Carhuac 15.80
ene-2015 CH Machupicchu II 99.86 ene-2017 CH Potrero 19.90
ene-2015 Central Solar Moquegua FV 16.00 ene-2017 CH Hydrika 1-5 38.60
ene-2015 CH Canchayllo 5.20 ene-2017 CH Karpa 19.00
mar-2015 Reserva Fra - Planta Puerto Maldonado 18.00 ene-2017 CH Laguna Azul 20.00
mar-2015 Reserva Fra - Planta Pucallpa 40.00 mar-2017 CH Cola 1 10.40
abr-2015 CH Runatullo II 19.00 mar-2017 CT Ilo - Nodo Energtico del Sur 500.00
abr-2015 CH Santa Teresa - G2 49.06 abr-2017 CT Santo Domingo de los Olleros - TV 86.00
abr-2015 CH Quitaracsa 111.80 ene-2018 CH Pucar 149.80
jun-2015 Reserva Fra - Planta de Eten 219.00 ene-2018 CH Angel III 19.95
ago-2015 CH Tingo 8.80 ene-2018 CH Angel I 19.95
ene-2016 Parque Elico Tres Hermanas 97.15 ene-2018 CH Angel II 19.95
ene-2016 CH 8 de Agosto 19.00 ene-2018 CH Tulumayo IV 40.00
ene-2016 CH El Carmen 8.40 ene-2018 CH Tulumayo V 65.00
ene-2016 CH Cheves I 168.00 ene-2018 CH Macon 10.00
ene-2016 CH Chancay 19.20 ene-2018 CH Langui II 2.90
may-2016 CT Mollendo - Nodo Energtico del Sur 500.00 ene-2018 CH Huasicancha 6.25
jul-2016 CH Manta 19.78 ene-2018 CH Chilcay 12.01
jul-2016 CH Cerro del guila 525.00 ene-2018 CH Pallca 10.10
ago-2016 CH RenovAndes H1 19.99 ene-2018 CH Muchcapata 8.10
ago-2016 CH Chaglla 456.00 ene-2018 CH Nueva Esperanza 9.34
nov-2016 CH Huatziroki I 11.08 jul-2018 Central Solar Fotovoltaica La Joya 18.00
17 nov-2016 CH Carpapata III 12.80 jul-2018 Central Solar Fotovoltaica Pampa de Siguas 19.00
dic-2016 CH La Virgen 64.00 jul-2018 CH Las Cruces 14.60
500 KV FUTURE INTERCONNECTION ECUADOR - PERU

S.E. LA NIA S.E. CHORRILLOS


1era. Etapa
SEIN 80 km 239 km 2da. Etapa 70 km 185 km SNT
500 kV
S.E. NVA.
S.E. PIURA SAN FRANCISCO

18
POSSIBLE ENERGY INTERCHANGE ECUADOR - PERU

Potencial de Intercambio de Energa Entre Ecuador y Per (1) (2)


Peru to Ecuador
600

400

200
GWh

-200

-400

-600
Ecuador to Peru
ene-19

ene-20
ene-17

ene-18

ene-21

ene-22
oct-17

oct-18

oct-22
oct-19

oct-20

oct-21
jul-17

jul-18

jul-21

jul-22
jul-19

jul-20
abr-17

abr-20

abr-21
abr-18

abr-19

abr-22
Per-Ecuador Ecuador-Per

(1) Without restrictions in transmission systems


(2) Operation of Colombia Ecuador and Peru

Possible power interchange:


From Ecuador to Peru: 750 - 1 000 MW
19 From Peru to Ecuador: 500 - 1 000 MW
FUTURE INTERCONNECTIONS CHILE - PERU

MEDIUM TERM LONG TERM


BACK-TO-BACK 220 KV TACNA-ARICA 500 KV CC LINE MONTALVO-CRUCERO

- Tacna

100-150 MW

1000 MW

Arica

20 Crucero
Source: Estudio SINEA AF - MERCADOS EMI SIGLA, Julio 2014
FUTURE INTERCONNECTIONS CHILE - PERU

21
Fuente: Actualizacin del Plan de Transmisin 2015.2024, COES-SINAC, Mayo 2014 21
500 KV FUTURE INTERCONNECTION BRASIL - PERU

PER
Large Hydro
Development: BRASIL
6 700 MW RIO MADEIRA

TAMBO 60

TAMBO 40
PAQUITZAPANGO
LIMA
MAINIQUE

COLECTORA INAMBARI
CENTRO

COLECTORA
SUR
MARCONA

22
Renewable Energy

23
PROMOTION ON INVESTMENT ON RENEWABLE
GENERATION (LEGISLATIVE DECREE 1002 YEAR 2008)

MINEM sets the non-conventional renewable energy percentage


share every 5 years (wind, solar, biomass, geothermal, tidal and
wave. It does not include small hydro).

Current share is 5% of the national energy consumption.

Priority dispatch and access to transmission and distribution grids.

Guaranteed income for the bidden energy.

24
ENERGY PRODUCTION 2013

ENERGY PRODUCTION 2013

18,1 TWh
46%

20,6 TWh
52%
1,0 TWh
3%
Hydroelectric Thermoelectric Renewable
Note: Renewable includes small hydro

25
RENEWABLE ENERGY PRODUCTION 2013

RENEWABLE ENERGY PRODUCTION 2013

577 GWh 197 GWh


58% 20%

226 GWh
23%
Hydro Solar Biomass

26
RENEWABLE GENERATION INSTALLED CAPACITY
2013 - 2018

CURRENT GENERATION CAPACITY


Biomass Solar Wind Hydro Total
Year
MW MW MW MW MW
2013 47 80 0 179 306

NEW GENERATION CAPACITY (2014 2018)

Biomass Solar Wind Hydro Total


Year
MW MW MW MW MW
2014 142
2015 2 16 53 71
2016 97 110 207
2017 184 184
2018 87 133 220
TOTAL 2 103 239 481 824

27
Transmission Plan

28
TRANSMISSION PLANNING:
UNCERTAINTY IN DEMAND AND GENERATION

PLANIFICACIN DE LA EXPANSIN DE
LA TRANSMISIN:

INCERTIDUMBRE EN EL CRECIMIENTO DE LA INCERTIDUMBRE EN EL DESARROLLO DE LA EXPANSIN DE


DEMANDA EN MAGNITUD Y LOCACIN: LA GENERACIN EN TAMAO Y LOCACIN:
PROYECTOS MAYORES DE DEMANDA PROYECTOS MAYORES DE GENERACIN
PROSPECTOS MINEROS PROSPECTOS DE APROVECHAMIENTOS HIDROELCTRICOS
IMPLEMENTACIN DE PROYECTOS: POR DECISIONES DE
29
COMPETENCIA DE LOS AGENTES EN EL MERCADO
TRANSMISSION PLANNING:
UNCERTAINTY IN POWER FLOW
NAME CODIGO ANO Plan Limites

Sum of MW

Lnea Mantaro - Marcona 500 kV Ao 2018


1400
1200

UNCERTAINTY
1000
800
600
400
200
0
-200
-400
-600
B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3
ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC
CASO

1asf79S0 1asf92S0 1asf99S0 1bnf79S0 1bnf92S0 1bnf99S0 1bsf79S0 1bsf92S0


1bsf99S0 2asf79S0 2asf92S0 2asf99S0 2bsf79S0 2bsf92S0 2bsf99S0 3asf79S0
NAME CODIGO ANO Plan Limites
3asf92S0 3asf99S0 3bnf79S0 3bnf92S0 3bnf99S0 3bsf79S0 3bsf92S0 3bsf99S0
Sum of MW
MES Bloque

1400
Lnea Mantaro - Marcona 500 kV Ao 2022
1200

1000

800

600

400

200

-200

-400

-600
B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3 B1 B2 B3
ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC

CASO
1anf79S0 1anf92S0 1anf99S0 1asf79S0 1asf92S0 1asf99S0 1bnf79S0 1bnf92S0 1bnf99S0 1bof79S0 1bof92S0 1bof99S0
1bsf79S0 1bsf92S0 1bsf99S0 2asf79S0 2asf92S0 2asf99S0 2bnf79S0 2bnf92S0 2bnf99S0 2bof79S0 2bof92S0 2bof99S0
30 2bsf79S0 2bsf92S0 2bsf99S0 3anf79S0 3anf92S0 3anf99S0 3asf79S0 3asf92S0 3asf99S0 3bnf79S0 3bnf92S0 3bnf99S0
3bof79S0 3bof92S0 3bof99S0 3bsf79S0 3bsf92S0 3bsf99S0 4asf79S0 4asf92S0 4asf99S0
MES Bloque
TRANSMISSION PLANNING:
TRANSMISSION LINE MANTARO MARCONA SOCABAYA MONTALVO

L.T. Mantaro - Marcona Nueva Socabaya


500 kV

L.T. Nueva Socabaya - Moquegua 500 kV

Transformador 500/220 kV en Moquegua

Inversin del Proyecto:


380 Millones US$
Longitud en 500 kV: 900 km
Fecha de Entrada: 2017

Segundo circuito a 500 kV al sur, para conformar


un esquema de transmisin fuerte y de gran
capacidad
Suficiente para atender los incrementos de
demanda del Sur y grandes proyectos trmicos e
hidroelctricos
31
TRANSMISSION PLANNING:
TRANSMISSION LINE MANTARO NUEVA YANANGO CARAPONGO

L.T. Mantaro - Nueva Yanango 500 kV

L.T. Nueva Yanango - Carapongo 500 kV.

L.T. Yanango - Nueva Yanango 220 kV

Inversin a nivel de anteproyecto :


185 Millones US$
Longitud 500 : 360 km
Longitud 220 : 15 km
Fecha de Entrada : 2019

32
TRANSMISSION PLANNING:
TRANSMISSION LINE NUEVA HUNUCO NUEVA YANANGO

S.E. Nueva Yanango 500/220 kV.


L.T. Nueva Yanango - Nueva Hunuco 500 kV.
S.E. Nueva Hunuco 500/220/138 kV.
L.T. Tingo Mara - Nueva Hunuco 220 kV.(86)
L.T. Nueva Hunuco - Huaricashash 220
kV.(21)
L.T. Tingo Mara - Chaglla 220 kV.(40)
Seccionamiento en S.E. Hunuco de L.T.
Chaglla - Paragsha 220 kV.(34)
Seccionamiento en S.E. Hunuco de L.T. Tingo
Mara - Vizcarra 220 kV.
L.T. Nueva Hunuco - Amarilis 138 kV.

Inversin a nivel de anteproyecto :


173 Millones US$
Longitud 500 : 180 km
Longitud 220 : 181 km
Fecha de Entrada : 2019

33
2024 TRANSMISSION PLAN

Plan de Largo Plazo 2024


Proyecto Enlace 500 kV Mantaro - Nueva Yanango - Carapongo: Proyecto Enlace 500 kV Nueva Hunuco - Tocache - Celendn - Trujillo, subestaciones,
L.T. Mantaro - Nueva Yanango 500 kV. lneas y ampliaciones asociadas:
L.T. Nueva Yanango - Carapongo 500 kV. S.E. 500 kV Tocache
L.T. Yanango - Nueva Yanango 220 kV. S.E. 500/220 kV Celendn
L.T. Nueva Hunuco - Tocache 500 kV.
S.E. Nueva Yanango 500/220 kV.
L.T. Tocache - Celendn 500 kV.
Proyecto Enlace 500 kV Nueva Yanango - Nueva Hunuco:
L.T. Celendn - Trujillo 500 kV.
L.T. Nueva Yanango - Nueva Hunuco 500 kV.
L.T. Cajamarca - Celendn 220 kV (doble terna).
S.E. Nueva Hunuco 500/220/138 kV.
Proyecto Enlace 500 kV Nueva Hunuco - Nueva Paramonga:
L.T. Tingo Mara - Nueva Hunuco 220 kV.
SE 500 kV Paramonga
L.T. Nueva Hunuco Yungas 220 kV. Seccionamiento en S.E. Nueva Paramonga de L.T. Carabayllo - Chimbote 500 kV
SE Yungas 220 kV. L.T. Nueva Hunuco - Nueva Paramonga 500 kV
L.T. Tingo Mara - Chaglla 220 kV. Otros Proyectos en 500 kV:
Seccionamiento en S.E. Hunuco de L.T. Chaglla - Paragsha 220 kV. Ampliacin 500/220 kV en S.E. Montalvo (segundo transformador).
Seccionamiento en S.E. Hunuco de L.T. Tingo Mara - Vizcarra 220 kV. Otros Proyectos en 220 kV y 138 kV:
L.T. Nueva Hunuco - Amarilis 138 kV. LT Tintaya - Azngaro 220 kV.(*)
Proyecto Cambio nivel de tensin a 500 kV L.T. Chilca - Planicie - Carabayllo 220 kV: Repotenciacin a 250 MVA L.T. Chiclayo - Carhuaquero 220 kV.
Reconfiguracin de L.T. Chilca - Planicie - Carabayllo de dos circuitos de 220 kV a uno de Repotenciacin a 250 MVA L.T. Oroya - Carhuamayo 220 kV.
500 kV y ampliaciones asociadas. Repotenciacin a 250 MVA L.T. Mantaro - Huancavelica 220 kV.
Ampliacin 500/220 kV en S.E. Chilca (segundo transformador). Repotenciacin a 250 MVA L.T. Huancavelica - Independencia 220 kV.
Ampliacin 500/220 kV en S.E. Planicie (nuevo patio a 500 kV y dos Seccionamiento en S.E. La Nia de L.T. Piura - Chiclayo 220 kV.
transformadores). Ampliacin 220/138 kV en S.E. Socabaya (tercer transformador).
Ampliacin 500/220 kV en S.E. Carapongo (segundo transformador). SE Nueva Carhuaquero 220 kV.(**)
Proyecto Repotenciacin a 1000 MVA de L.T. Carabayllo - Chimbote - Trujillo 500 kV: L.T Aguaytia - Pucallpa 138 kV (segundo circuito). (*)
Repotenciacin a 1000 MVA L.T Carabayllo - Chimbote 500 kV con inclusin de Proyectos de Compensacin Reactiva:
compensacin de capacitores serie. Compensador Reactivo Variable (SVC o similar) +400/-100 MVAR en 220 kV en S.E.
Planicie. (**)
Repotenciacin a 1000 MVA L.T Chimbote - Trujillo 500 kV con inclusin de compensacin Banco de reactores de 100 MVAR en 500 kV en S.E. La Nia. (**)
de capacitores serie.
Banco de condensadores de 20 MVAR en 60 kV en S.E. Zorritos. (**)
Compensador Reactivo Variable (SVC o similar) +400/-150 MVAR en 500 kV en S.E. Trujillo. Nota: Todos los costos fueron estimados de acuerdo a los mdulos de precios de Osinergmin
(**) (*) Sustentado por el criterio N-1 de la Norma
(**) Sustentado por anlisis elctricos

34 Source: Proposed Transmission Plan Update 2015-2024


Costo de Inversin 1073 Millones U$S
2024 AND 2020 TRANSMISSION PLANS
PLAN DE TRANSMISIN (2024) PLAN VINCULANTE (2020)

35
LONG TERM 500 KV TRANSMISSION SYSTEM OBJECTIVE

INTERCONEXIN
ECUADOR-COLOMBIA

INTERCONEXIN
BRASIL

36
INTERCONEXIN
CHILE
2013 PERUS SEIN

(*1) Source: Propuesta


Definitiva de Actualizacin
del Plan de Transmisin,
Periodo 2015-2024

37
37
2020 VISION OF PERUS SEIN

(*1) Source: Propuesta


Definitiva de Actualizacin
del Plan de Transmisin,
Periodo 2015-2024

38
2024 VISION OF PERUS SEIN

(*1) Source: Propuesta


Definitiva de Actualizacin
del Plan de Transmisin,
Periodo 2015-2024

39
LONG TERM VISION OF PERUS SEIN

(*1) Source: Propuesta


Definitiva de Actualizacin
del Plan de Transmisin,
Periodo 2015-2024

40
THANKS