Professional Documents
Culture Documents
Overview
The CMAR Process: Where We Are
Middle School Design and Budget: Comparative Analysis
Elementary School Budget: Comparative Analysis
Sun Valley Site Analysis
Utility Cost Comparison
1
WCSD CMAR Process Overview
BOT Approval of
CMAR Selection
Current Step
Sub Contractor
Faire/Solicitation Bid Opening
of Pre-Qualified and Scrubbing
Creation of Bidders Creation of
Board of
Project Budget Guaranteed
(50-60% Design Maximum Price
Trustees Final
GMP Approval
Submittal) (GMP)
Project Budget Project Budget
Approval by
CFPC
Approval by
WCSD BOT
Independent
Cost Estimate/3rd
Party Review/ Construction
Reconciliation
2
Reno-Sparks Area Construction Cost Escalation
60.0%
51.7%
50.0%
45.2%
38.3%
40.0%
Escalation Rate
30.0%
25.7%
20.0% 16.4%
10.9%
10.00%
8.00%
10.0% 6.4%
5.00% 5.00%
4.20% 4.50%
2.5%
0.0% 0.0%
3.80%
0.0%
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Total: $58,594,629
Escalated & Updated Depoali MS
4
DEPOALI MS BUILDING MODIFICATION COMPARISON DETAILS
BUILDING UPGRADES VALUE ENGINEERING SAVINGS
- Plumbing Code & Program Upgrades: $1,114,443
- Revise Interior Stairways to Exterior: ($235,081)
- HVAC Bldg. Code & Program Upgrades: $1,315,258
- Revise Stack Bond to Running Bond: ($68,108)
- HVAC Building Controls Upgrade: $189,754
- Reduce Overhang Area A: ($212,413)
- Electrical Code & Program Upgrades, LED Lighting,
- Reduce Roof Slop Area A: ($80,995)
and Technology: $1,878,201
- Revise Composite Metal Panel Cladding to
- Fire Alarm Code Upgrades: $47,071
Preformed Metal Panels: ($99,087)
- Gender Neutral Restrooms: $491,412
- Reduce Glazing Area, Revise Framing Systems, Add
- Safety & Security Upgrades: $313,123
Bullet Resistant Window Film, Metal Screens on Exterior Doors &
Operable Windows & Blinds: ($1,091,463)
Windows, and Exterior Door Key Card System - Revise Skylight Design: ($130,321)
- Corridor Windows & Blinds: $179,771 - Reduce Science Room Fit & Finish: ($181,814)
- Academic Student Hub Areas: $23,695 Revise Cabinetry to Open Shelves, Revise Countertops
- Clock & Paging System Upgrade: $120,372 - Reduce Base & Wall Cabinets: ($351,756)
- Audio Enhancement System Upgrade: $71,607 - Reduce Drop Facia & Soffit Conditions: ($125,361)
- Video Surveillance System Upgrade: $46,567 - Delete Motorized Wrestling Mat Lift: ($25,591)
- Audio Visual Systems: $80,873 - Reduce Window Shades: ($19,798)
- Emergency Responder Radio System: $150,000 - Deletion of Computer Lab Wiring: ($138,149)
$2,177,372
$7,274,247
Total: $14,472,765
Escalated & Updated Depoali MS
6
SITE COST COMPARISON OF
SVMS BUDGET REQUEST WITH DEPOALI MS AS-BUILT COST
SVMS SITE BUDGET REQUEST:
$19,387,078
SITE MODIFICATIONS
Escalation Rate to 60% SUBMITTAL PROJ. ESTIMATE
Depoali MS Site
December, 2017 Project Construction Design Contingency: $540,986
As-Built Cost
(45.2%) See Sheet 3 Escalation to 2018 Const. Contingency: $216,394
(2008)
Site Additions: $10,819,717
$4,817,195 $324,592 See Sheet 8
$2,177,372
$11,577,097
Total: $18,896,256
Escalated & Updated Depoali MS
7
DEPOALI MS SITE MODIFICATION COMPARISON DETAILS
COMPARATIVE MIDDLE SCHOOLS PROJECT COSTS - BENCHMARKED TO RENO, NV & BID DATE OF DECEMBER 2017
Original Construction Costs Location Escalation Escalated Construction Costs - Reno, NV Escalated Construction Costs - Reno, NV
A B C D E F G H I J K
Original Location Escalation Escalated Escalated Escalated Escalated
Original Site Original Escalated Site Escalated Site
Building Adjustment Rate to Bid Building Construction Building Total
Construction Construction Construction Construction
Construction Factor - Date Dec Construction Cost - Total Construction Construction
Cost Cost - Total Cost (2017$) Cost (2017$)
Cost Reno, NV 2017 Cost (2017$) (2017$) Cost (2017$) Cost (2017$)
School Project Location Date Bid Building Area =A+B =A*D*(1+E) =B*D*(1+E) =F+G Cost/SF Cost/SF Cost/SF
Spanish Springs MS (BUDGET) Sparks, NV Dec-17 190,548 sf $57,919,499 $14,838,357 $72,757,856 1.00 0.0% $57,919,500 $14,838,400 $72,757,900 $303.96 $77.87 $381.84
Sun Valley MS (BUDGET) Reno, NV Dec-17 190,548 sf $57,919,499 $19,387,078 $77,306,577 1.00 0.0% $57,919,500 $19,387,100 $77,306,600 $303.96 $101.74 $405.71
Mann Middle School Addition San Diego, CA Jan-17 40,700 sf $24,367,200 $1,270,800 $25,638,000 0.86 4.6% $25,488,100 $1,329,300 $26,817,400 $626.24 $32.66 $658.90
Main Street Middle School Soledad, CA Oct-16 92,684 sf $43,848,000 Incl $43,848,000 0.82 7.6% $47,180,400 Incl $47,180,400 $509.05 Incl $509.05
Salish Middle School Lacey, MS Jun-15 110,020 sf $29,206,400 Incl $29,206,400 0.93 20.1% $35,076,900 Incl $35,076,900 $318.82 Incl $318.82
Islander Middle School Mercer Island, WA Feb-15 93,000 sf $38,759,500 Incl $38,759,500 0.89 24.0% $48,061,800 Incl $48,061,800 $516.79 Incl $516.79
Barack Obama Global Prep Academy Los Angeles, CA Mar-10 170,000 sf $78,900,000 Incl $78,900,000 0.83 36.0% $107,304,000 Incl $107,304,000 $631.20 Incl $631.20
Painted Hills Middle School Palm Springs, CA May-09 137,718 sf $32,096,900 $7,503,100 $39,600,000 0.85 42.8% $45,834,400 $10,714,400 $56,548,800 $332.81 $77.80 $410.61
White Cliffs Middle School Kingman, AZ Sep-08 87,000 sf $18,195,100 Incl $18,195,100 1.08 32.6% $24,126,700 Incl $24,126,700 $277.32 Incl $277.32
Adelson Educational Campus Las Vegas, NV Jul-06 173,200 sf $45,395,600 Incl $45,395,600 0.90 35.7% $61,601,800 Incl $61,601,800 $355.67 Incl $355.67
Pioneer Middle School Dupont, WA Jun-06 107,889 sf $25,098,900 Incl $25,098,900 0.93 36.6% $34,285,100 Incl $34,285,100 $317.78 Incl $317.78
Lincoln Crossing Middle School Lincoln, CA Jan-06 105,953 sf $28,967,000 $13,251,000 $42,218,000 0.83 49.2% $43,218,800 $19,770,500 $62,989,300 $407.91 $186.60 $594.50
Rio Vista Middle School Oxnard, CA Sep-05 74,000 sf $29,070,200 Incl $29,070,200 0.85 48.8% $43,256,500 Incl $43,256,500 $584.55 Incl $584.55
Twelve Bridges Middle School Lincoln, CA Sep-04 107,683 sf $25,995,400 $12,521,600 $38,517,000 0.83 88.8% $49,079,300 $23,640,800 $72,720,100 $455.78 $219.54 $675.32
20th Annual School Const. Report Reg.11 (NV,AZ,CA,HI) 2014 95,000 sf $35,000,000 Incl $35,000,000 1.00 24.7% $43,645,000 Incl $43,645,000 $459.42 Incl $459.42
* Location Factor per RS Means Building Construction Costs 2017 Average Const Cost/SF: $473.17
10
COMPARATIVE ELEMENTARY SCHOOL PROJECT COSTS
COMPARATIVE ELEMENTARY SCHOOLS PROJECT COSTS - BENCHMARKED TO RENO, NV & BID DATE OF DECEMBER 2017
11
WCSD SCHOOL UTILITY COSTS
Based on 2013 NV Energy Audit of WCSD
14
Bottom Line
Well-designed
Cost-effective
Needed
15