Technical Specification for 65 m3 LPG Tank Trailer

Brand : THOR TRAILER

Chassis : Half chassis made of 6252 Steel quality . Strong and Heavy Duty type.

Axles : 3 x Turkish Axles , German Tv Approved with 14 tons capacity each.

Brakes : Drum Brakes

Suspension : Steel Suspension

Brake System : Two line brake system with WABCO ABS according to European Norms, Automatic Slack Adjusters

Landing Legs : 24 tons each according to the European Norms

Kingpin : 2 changeable to 3,5 according European Standards. King Pin Plate thickness 12 mm

Tyres : 12 + 1 12/R22.5 Bridgestone with Steel Rims

Electrical System : 24 V according to European Norms. ( ADR stop lights, 5 Lights on each side )

Complete Reflectors and Signs 3M Brand , Wheel chocks, 2 x Fire Extuinguisher ADR , 2 Units Food Box, Sunshade on the Tank

Accessoires : Water Tank , Spare wheel carrier


www.thor-trailers.com www.thorcons.com www.odin-grup.com

Tank Specifications :
Project Code : AD2000 Code-PED97/23/EC

Design Temperature : Min -20 C / max. +50 C

Design Pressure : 17,16 bar

Test Pressure : 26,50 bar

Tank Material : P355 GH

Head Type : Elipsoidal

External Tank Diameter : 2.400 mm

Wall Thickness : 10 mm

Total Length of Tank : 13.200 mm

Equipments on Tank :

- 2 inch Safety Relief Valve : REGO 7534G ( 2 Units )


- Rotogauge Rotary Level Indicator ) : REGO ( 1 Unit )
- inch excess Flow Valve for Manometer ( 1 Unit )
- Thermometer (-30/60 C ) : Pakkens ( 1 Unit)
- Manometer ( 0-25 bar ) : Pakkens ( 1 Unit )
- Hydraulic Operator ( 1 Unit )
- 2 inch Hydraulic Valve ( 2 Units )
- 3 inch Hydraulic Valve ( 1 Unit )
- 2 inch Ball Valves : Batu ( 3 Units )
- 2 inch Filler Flanges : M60x4 ( 3 Units )
- ACME Filler Cap : ( 3 Units )
- Filter : Batu ( 1 Unit )
- 16 inch Manhole ( 1 Set )
- Earthing Bar : ( 1 Set )

Paintwork and Sandblasting :

- During painting works of the external tank surface , it will be cleaned properly from any burr, hollow ,oil and dirt.
- Following the cleaning works, sanding will be applied to obtain surface appearance of SA 2 quality.
- Roughness Value of the Surface will be 50 70 Rz
- As First coat will be applied epoxy paint base with surface tolerance and dry film thickness of 180 micron
- As the second coat , arcylic polyurethane top layer with high resistance with a dry film thickness of 70 micron
- Final Coat color of the Tank will be white ( RAL 9010 )
- Total Paint Thickness will be 250 microns

Radiographic Tests :

- Welding Seams of the tank will be subject to radiographic control by 100 % longtidunal values .
- Radiographic images will comply with the EN 1435 standard.
- The Relevant staff will be certified according to EN473.
- Radiographic examinations will be made through high-sensitive , panoramic and linear X-Ray devices.
- These controls will be executed by certified staff

Penetration Test or Magnetic Particle Test :

- Nozzle _Body and Manhole Body Welds will be controlled through penetration or magnetic particle test
method by 100%
www.thor-trailers.com www.thorcons.com www.odin-grup.com

Hydrostatic Test :

- Following the construction , the tanks will be subject to hydrostatic test as per the design rules and standards.
- During hydrostatic Test , clean and fresh water will be used.No Liquid which may react to the tank materials will be used
for hydrostatic test.
- In case the water and ambient temperature is below 15 C, the hydrostatic test will be not performed
- The Hydrostatic test will be accompanied by the independent certification body TURK LYOD .
- Following the hydrostatic test, inside and all internal Pipes of the Tank will be dehydrated.
- Inside of the Gas will be purged with gaseous nitrogen.

Certification :

- The tank will hold a branding / Inspection Report and Certificate issued by an international independent audit
company ( Turk Lyod ) according to the European directive.
- Quality Plan and F Module Certificate
- Inspection Report and Certificate
- Quality Plan
- Sheet Orientation , Material List, Material Certificates
- Material Orientation Plan
- Material List
- Sheet , pipe and flange certificates
- Certificates of the welding materials
- Welding Method Instructions ( WPS )
- Welding Method Tests ( PQR )
- Welder Certificates and Welding Plan
- Plain seaming of the Body Sheet ( WPS )
- Circumferrential welds of the Body ( WPS )
- Nozzle Body Manhole Weldings ( WPS)
- Pipe Pipe,Pipe-Flange Weldings ( WPS )
- PQR
- Welder certificates
- Welding plan
- Dished Heads Reports, Head Treatment Graph and Report
- Dished Heads control report
- Dished Heads magnetic test report
- Heat treatment graph and report
- Welding Test reports of the Construction
- Longitudanl welding seams
- Circumferential welding seams
- Non-destructive test reports
- Eye and measure control report
- Dye penetrant test reports
- Radiography reports
- Hydrostatic Test Report
- Name Plate , Fixture Certificates
- Carbon copy of name plate
- Carbon Copy of the 3 rd party embossed stamp

Baffles :

- Tank will have three Units of Anti-Slosh baffles