You are on page 1of 21

9.

0 FACADE MAINTENANCE STRATEGY

Earls Court Project | Reserved Matters Application


Design and Access Statement - Volume 5 | November 2013
Earls Court Project | Reserved Matters Application
Design and Access Statement - Volume 5 | November 2013
Earls Court
Capco
Faade Access Strategy
RMA Stage Issue
November 2013
Chapter 9.0
Revision P1
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

CONTENTS

1.0 EXECUTIVE SUMMARY 3


2.0 INTRODUCTION 4
3.0 CONCEPT CLEANING STRATEGIES 5
4.0 CONCEPT MAINTENANCE STRATEGIES 13
5.0 DESIGN PARAMETERS 14
6.0 APPENDIX 15

Audit Sheet

Rev. Description Prepared by Reviewed by Date

00 RMA Stage Issue L.Shepherd P. Krausbauer 2013-07-26


01 Updated in line with architects comments L.Shepherd P. Krausbauer 2013-10-10
P0 Updated in line with architects comments L.Shepherd D.Lau 2013-11-13
P1 Updated for DAS issue L.Shepherd D.Lau 2013-11-18

This report is provided for the stated purposes and for the sole use of the named Client. It will be confidential to the Client and the
clients professional advisers. Hoare Lea accepts responsibility to the Client alone that the report has been prepared with the skill,
care and diligence of a competent engineer, but accepts no responsibility whatsoever to any parties other than the Client. Any such
parties rely upon the report at their own risk. Neither the whole nor any part of the report nor reference to it may be included in any
published document, circular or statement nor published in any way without Hoare Leas written approval of the form and content in
which it may appear.

REP-2212100-LS-2013-11-18_RevP1 Page 2 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

1.0 EXECUTIVE SUMMARY will allow these publicly visible faades to be cleaned frequently and a high quality finish to be maintained.

This report evaluates the options for the cleaning and maintenance of the faade cladding of the Earls Court It is proposed that access to clean the main elevations of the high-rise residential blocks is by means of a fully
Village Development located in the Royal Borough of Kensington and Chelsea, London. The mixed-use counterweighted building maintenance unit (BMU). The jib will be a telescopic design allowing the BMU to be as
development will consist of a mixture of low to high-rise residential buildings surrounded by landscaped areas, compact as is practicable when in the parked position.
courtyards, walkways and public roads.
As part of the development is over 40m in height the suspended cradle will need to be restrained. In order to
The site-wide scheme is being designed by 3 architect practices; Kohn Pedersen Fox Associates (KPF), Terry comply with BS-EN-1808 1999+A1 2010 Safety Requirements on Suspended Access Equipment the distance
Farrell and Partners (TFP) and Pilbrow and Partners (P+P). to the first restraint point must be located 20m or less from the top of the roof level parapet. Thereafter a row of
restraints is to be provided every 20m with the last row located 40m above Ground Floor level.
The buildings that comprise the development can be summarised as follows;
It is recommended that the replacement glazing is carried out from a glass replacement unit (GRU) fitted to the
WV04 A, B, C & D (KPF) BMUs which shall be rated suitably to lift the heaviest glass panel.
WV04 F (TFP)
WV06 A (TFP) Where MEWPs are the preferred strategy for cleaning, glass replacement should be from spider type cranes
WV06 B (P+P) operated from the surrounding walkways and roads. Where cleaning is proposed to be carried out internally
WV06 C, D & E (KPF) (KPF) glazing should be designed to allow glass replacement from inside the building. The panels should be suitably
BW05 D, E, F1 & G (KPF) sized to fit within the proposed lifts and permit a clear run through corridors and apartments.
BW05 F2 (P+P)
In instances where the broken pane is higher than the maximum reach of a spider type crane it is proposed that
BW07 A, B, C, D, G (KPF)
a mobile crane is operated adjacent to the faade. Although glass replacement is likely to occur on an infrequent
basis road closures may be required.
The Health & Safety Executive (HSE) information sheet MISC611 Safety in window cleaning using suspended
and powered access equipment states that for every window cleaning job, the choice of access equipment will
It is proposed that lights and other high level services are not positioned in locations that will make them difficult
be determined by the height negotiated, site conditions, duration and extent of work and frequency of access.
to replace and maintain.
Cradles and mobile platforms are an ideal form of access for external window cleaning for many larger buildings.
The faade access concept strategies have been developed in collaboration with the design team; especially in
HSE information sheet MISC612 Safety in window cleaning using rope access techniques further clarifies the
relationship to the M+E plant, the architecture and the design of the various facades.
information provided in MISC611 that for all work at height, the most intrinsically safe means of access should
always be the first consideration. Other safer methods of access, such as cleaning from inside, suspended
1.1 KEY ISSUES
access equipment (SAE) or mobile platforms (MEWP) are preferable.

Based on the guidance within these documents and the construction of the building facades, which feature a Maximum panel weights to be confirmed.
number of steps at roof level, terraces and balconies; it is proposed that the most practicable method of access Road closures may be required when MEWPs and cranes are in operation.
to clean and maintain the faades is by means of MEWP. The proposed MEWPs will be required to deploy on
surrounding roads and walkways in order to access areas of the faades when deployed in the working position.
The point loads of the machines should be considered when designing the surrounding landscape.

In areas where this is not practicable due to traffic flow and surrounding landscape it is proposed that windows
are designed to be openable to allow cleaning and glass replacement to be carried out from inside the
apartments.

The spatial requirements for the setting out of the MEWPs have been co-ordinated in detail with the landscape
architect.

In addition to cleaning from inside the apartments a number of areas are proposed to be cleaned by alternative
methods to maintain a high quality finish. A number of terraces are to be provided and it is proposed that the
glazing will be cleaned by means of a rigid long handled squeegee with cleaners working from the floor level of
the terrace.

In order to provide access for cleaning to the proposed glazed balustrades which envelop the residential
balconies it is recommended that suitable cleaning tools with cranked heads, to mitigate the risks associated
with leaning over the balcony, are issued as part of a tenants pack. Residential balconies should only be utilised
for cleaning by the tenant unless a cleaning contractor is permitted access through the apartment, in which case
they should be accompanied by a concierge.

For each building cleaning access to glazing below 5m can be achieved effectively with long handled tools; this

REP-2212100-LS-2013-11-18_RevP1 Page 3 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

2.0 INTRODUCTION Physical contact with the building surfaces and associated wear and tear

This report evaluates the options for the proposed faade access and maintenance systems for the Earls Court The options proposed have been benchmarked against the following standards:
Village Development. The buildings have large areas of faade which are clad with glass and therefore require
safe and efficient faade access systems to ensure the appearance remains suitable for a prestigious residential BS 6037-1:2003 Permanently Installed Suspended Access Equipment
development. EN 1808 (1999) Safety Requirements on Suspended Access Equipment
BS 7985:2009 Code of practice for the use of rope access methods for industrial purposes
Although the primary objective of any solution is for access to the entire building, it is not the only objective that
is to be considered. Secondary objectives are also to be considered so as to achieve maximum benefit from any
solution. In total all these functions can be summarised as follows:

Routine cleaning of the building fabric externally.


Long term inspection & maintenance of the faade such as the replacement of cladding panels/glazing.

EC Health & Safety directives and legislation play a direct role in the manner and application of access systems
to buildings along with the CDM Regulations 2007. Under section 11 the regulations state that designers must
avoid foreseeable risks to the H&S of any person involved in the cleaning of windows. The designer shall
eliminate hazards which may give rise to risks; and reduce risks from any remaining hazard.

The strategy for selection of the systems should therefore be to find an economical solution that is easy to
operate and provides adequate access according to the HSE guidelines set out in information sheets MISC611,
MISC612.

HSE information sheet MISC611 Safety in window cleaning using suspended and powered access equipment
states that for every window cleaning job, the choice of access equipment will be determined by the height
negotiated, site conditions, duration and extent of work and frequency of access. Cradles and mobile platforms
are an ideal form of access for external window cleaning for many larger buildings.

HSE information sheet MISC612 Safety in window cleaning using rope access techniques clarifies that for all
work at height, the most intrinsically safe means of access should always be the first consideration. Other safer
methods of access, such as cleaning from inside, suspended access equipment (BMU) or mobile platforms are
preferred.

Based on the information published by the HSE it is our understanding that where practicable internal cleaning
access, temporary access equipment (MEWPs) and permanent suspended access equipment (BMU) should be
provided for the buildings of this development.

The design of any suspended access equipment is required to meet the safety regulations set out in BS EN
1808 1999+A1 2010.

Overall the facade access strategy options use strategies which are already tried and tested in the public
domain and minimise the risk to cleaning operatives in the maintenance of the facades.

Key considerations in the selection of the options have been;

Compliance with all legislation and codes or practice


Added value the system could deliver
Simplicity of operation
Minimising the cost of cleaning the faade
Environmentally acceptable both visually and in materials used and waste products generated
Having the ability to access and clean a wide range of building surfaces during a use

Other items which should be considered as the design progresses are:

Building and structural requirements


Life cycle costs

REP-2212100-LS-2013-11-18_RevP1 Page 4 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

3.0 CONCEPT CLEANING STRATEGIES

The site wide strategy diagram below outlines the proposed methods of cleaning access to each individual elevation based on HSE regulations and industry best practice. All methods including MEWP, BMU and internal cleaning have been
described in detail within this report.

Image 1 Indicative Site Wide Cleaning Strategy Diagram

REP-2212100-LS-2013-11-18_RevP1 Page 5 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

The roof plan below shows the parked special requirements of the 2No.BMUs proposed to access the two high rise residential towers. Refer to section 3.1 for further BMU information.

Image 3 Indicative BMU Roof Plans

REP-2212100-LS-2013-11-18_RevP1 Page 6 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

Industry good practice for safety in window cleaning using suspended and powered access equipment suggests The BMU jibs will be a 3 stage telescopic design allowing the jib to be as compact as is practicable in the parked
that for every window cleaning job, the choice of access equipment will be determined by the height negotiated, position and to also allow a suitable minimum reach.
site conditions, duration and extent of work and frequency of access. Building Maintenance Units (BMU) and
mobile platforms are an ideal form of access for external window cleaning for many larger buildings. The jib will be approximately 23,000mm long when fully extended and will be capable of slewing the cradle over
the mechanical plant and parapet.
In addition to this it is deemed that for all work at height, the most intrinsically safe means of access should
always be the first consideration. Safe methods of access, such as cleaning from inside, suspended access The suspended cradle can only ascend and descend in vertical lines. Unless the suspended cradle is situated at
equipment (SAE) or mobile platforms (MEWP) are preferable over rope access techniques. and engaging the limit switches on the jib head the jib arm cannot be slewed or extended.

Based on this good practice advice and the construction of the building facades it is proposed that the primary The BMU design has been based on the contractors drawings below. Please note that the dimensions provided
method of access to clean and maintain the main site-wide elevations is from a large reach MEWP. The below are not project specific
proposed unit is capable off accessing up to 35500mm in height at an outreach of 13900mm.

A number of elevations which envelop buildings WV04E and WV06A exceed the maximum reach capabilities of
the large reach MEWP recommended for site-wide access. It is therefore proposed that an ultra large reach
MEWP is utilised to allow operatives hand contact to the highest sections of facade.

It is likely that the proposed MEWPs will be required to deploy on surrounding roads and walkways in order to
access certain areas of the faade when in the working position. The point loads of the machines should be
considered when designing the surrounding landscape. Loadings and spatial requirements for each of the
proposed units have been provided within the appendix and co-ordinated with the landscape architect.

Specific elevations where MEWP access is not practicable due to traffic flow and surrounding landscape it is
proposed that windows are designed to be openable to allow cleaning and glass replacement to be carried out
from inside the apartments. Cleaning diagrams have been provided within this report to demonstrate the
recommended methods of access to open able windows/balconies.

A number of terraces are to be provided and it is proposed that the glazing will be cleaned by means of a rigid Image 4 Example Contractors BMU Elevation
long handled squeegee with cleaners working from the floor level of the terrace.

In order to provide access for cleaning to the proposed glazed balustrades which envelop the residential
balconies it is recommended that suitable cleaning tools with cranked heads, to mitigate the risks associated
with leaning over the balcony, are issued as part of a tenants pack. Residential balconies should only be utilised
for cleaning by the tenant unless a cleaning contractor is permitted access through the apartment, in which case
they should be accompanied by a concierge.

It is proposed that access to clean the main elevations of the high-rise hotel and high-rise residential block
faades is by means of fully counterweighted building maintenance units (BMU) as described in section 3.1.

For each building cleaning access to glazing below 5m can be achieved effectively with long handled tools; this
will allow these publicly visible faades to be cleaned frequently and a high quality finish to be maintained.
Image 5 Example Contractors BMU Plan
3.1 BUILDING MAINTENANCE UNITS
3.1.1 Building Maintenance Unit Parked Position
It is proposed that the baseline strategy to access and clean the main elevations of the faades of the high-rise It is proposed that the baseline BMU will measure c. 12,200mm in length when the jib is retracted for parking and
buildings BW05 F and BW07 B is by means of fixed, fully counterweighted, telescopic building maintenance will sit below the maximum planning parameter of 3300mm. In order to ensure that planning conditions are met
units with a large reach. the BMU is proposed to be mounted on top of a screw-jack type lifting table (Please see image below). This will
ensure that the unit sits below the maximum planning restriction when not in use and can be raised in to
BW05 F Maximum Reach 23,000mm / Minimum Reach 5,000mm operation, ensuring the cradle does not clash with any plant or parapet when being slewed in to the working
BW07 B Maximum Reach 23,000mm / Minimum Reach 5,000mm position. The lifting table should measure a maximum of 3700mm (L) x 3700mm (W).

As the proposed units for both buildings are currently the same, the following text applies to both machines. 3.1.2 Access to the Building Maintenance Unit

The maximum radius of the counterweight swing will be 6800mm from the centre of the wheel base unit and It is proposed that access to the BMU is from the main stair core which rises to roof level. The currently proposed
suitable clearance should be provided to avoid clashes with the structure and surrounding plant. parapets and plant screens provide adequate passive height safety whilst persons prepare the equipment for
use.

REP-2212100-LS-2013-11-18_RevP1 Page 7 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

3.1.4 Flues

Limit stops will be fitted to the BMU to ensure the jib does not pass over the boiler flues where there is a risk of a
stream of hot gas.

3.1.5 Budget Dead Load

The BMU proposed for the scheme will be bespoke and the load and distribution of weight is subject to detailed
design.

We have referenced a number of example building maintenance units, from each of our preferred suppliers, with
specifications similar to those proposed for the high-rise buildings in order to develop a realistic set of
assumptions.

The total weight of the BMU will be in the region of 57 tonnes however this load is approximate and may vary
dependant on the appointed contractor.

3.1.6 Power

A weather proof IP65 3PH/N/PE ~50Hz 400/230V isolator and RCD protected supply is to be provided by the
electrical contractor to a connection box adjacent to the parking position of each BMU. All connections from this
point are by the permanent faade access supplier. The mains power required is a maximum of 10kVa.
Image 6 Example Contractors Lifting Table
The mobile platforms proposed are driven by an on-board diesel motor and the boom is operated by means of
3.1.3 Emergency Rescue an on-board electric motor.

The evacuation procedure from the cradle in the event of a fire or other incident is dependent upon the location 3.1.7 Restraints
of the cradle and the emergency. In most cases we propose that the operatives return to the roof and evacuate
from there. As part of the development is over 40m in height the suspended cradle will need to be restrained. In order to
comply with BS-EN-1808 1999+A1 2010 Safety Requirements on Suspended Access Equipment the distance
In the event of a fire the operatives in the suspended cradle are warned by a radio call. They will be informed as to the first restraint point must be located 20m or less from the top of the roof level parapet. Thereafter a row of
to where the fire is, and asked their location. Based on this information the building manager will advise the restraints is to be provided every 20m with the last row located 40m above Ground Floor level.
safest method of escape. There are only two safe methods of escape, return to the roof or descend to Ground
Floor Level. We would propose a detail similar to that shown below,

If the fire is on another elevation to the suspended cradle position, the operatives should if practicable, return to
the roof and descend from there. The operatives should climb out of the cradle when it has landed on the roof, in
the parked position, switch the isolator off on the cradle and evacuate the building via a suitable stair and route.

If the fire is on the elevation where they are located, the method of evacuation is dependent upon the time to
evacuate. If the fire is below them, we would recommend they ascend to the roof. If the fire is above them then
provided they can safely pass to one side of the fire, they should preferably ascend. This decision is based on
the vertical and horizontal distances, bearing in mind the time taken to raise the suspended cradle and the
distance the fire may spread.

If the cradle must descend, then the cradle will lower until it reaches the lowest point of travel, which may be a
canopy. If the operatives cannot leave the cradle to a place of safety they should remain in the cradle until
rescued.

Due to planning constraints there are limits to the cradle lowering to the ground in public areas. If the cradle is to Image 7 - Typical Faade Restraint Pin
descend, it will reach a level approximately 3,000 mm above the ground from where the operatives will require to
be rescued. In the case of private property or canopies, the cradle cannot reach the lowest level and the It is proposed that the suspended platforms are provided with wind speed indicators and the crew are to check
operatives will require to be rescued from that point. the wind conditions regularly. If the wind exceeds 13m/s the crew are to return to the roof.

REP-2212100-LS-2013-11-18_RevP1 Page 8 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

3.1.8 Building Maintenance

During design development due consideration has been made to the repair and / or replacement of the faade
panels and M&E equipment. Whilst this is likely to be carried out on an infrequent basis, the principles have
been considered.

It is recommended that the replacement glazing is carried out from a glass replacement unit (GRU) fitted to the
BMUs which shall be rated suitably to lift the heaviest glass panel.

Due to the fact that the maximum panel weights have not been provided at the time of writing this report we have
based the weights on the assumption that the safe working load (SWL) will be in the region of 300kg. If the
maximum panel and ancillary lifting equipment exceeds this value and the SWL is required to increase the BMU
design will have to be developed to accommodate the additional loads. This is likely to increase the dead load of
the unit as provided in section 3.1.5.

3.2 MOBILE ELEVATED WORK PLATFORM

A large reach mobile elevated work platform capable of accessing the majority of the external elevations is a Leo
36T from Teupen which will access 36m in height at 13.9 m outreach and is able to work from a slope of up to
30%. This unit has a crawler base to cross landscaped areas and 4 outriggers (the load per outrigger is 35kN).
To spread the loads spreader plates can be used on each of the outriggers.

The point loads of the machines, which can be found in the appendix at the rear of this report, should be
considered when designing the surrounding landscape. Co-ordination will also be required with the architect
regarding landscape arrangements to ensure sufficient access is permitted adjacent to the facades.

Image 9 illustrates the dimensions of the proposed MEWP in the travelling and working positions. In order to
access the highest elevation (BW07 B) at approximately 35,000mm the MEWP is required to be positioned a
minimum of 7,500mm or a maximum of 9,000mm from the faade. When accessing lower elevations the unit
can be positioned closer to the faade and can operate at angles which will minimize disruption to surrounding
roads etc.

Mobile Platform Technical Data:


Reach = 36,000 mm
Safe Working Load = 200 Kg
Gross Vehicle Weight = 4,850 Kg
Live Load in Working Position = 2.4 kN/m
Max Outrigger Clear Area (W) = 5,500 mm

For further details on the proposed large reach MEWP please refer to the data sheet provided within the
appendix.

The spatial requirements for the setting out of the MEWPs have been co-ordinated in detail with the landscape
architect.

A small proportion of the facades exceed the maximum reach capabilities of the Leo36T. Although it is not
recommended to provide cleaning access from a unit with a reach exceeding 36m an ultra large reach MEWP
such as the Leo50T could be considered to access these elevations. Due to the increased reach the units can
operate from fewer working positions however it should be noted that controlling movement of the jib arm from
the basket can be extremely difficult and disorientating from such a height. This could potentially result in
clashes with the faade and ancillary services.

For further details on the proposed ultra large reach MEWP please refer to the data sheet provided within the
appendix.
Image 8 Example Large Reach Spider Type MEWP

REP-2212100-LS-2013-11-18_RevP1 Page 9 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

3.2.1 Cleaning Time Analysis

The cleaning times provided are preliminary and based upon access to the glazed elements of faade by means
of the faade access equipment noted within this report. The cleaning times proposed are based on continuous
operation of a unit.

The calculation below has been provided for a sample section of faade 32m (L) x 28m (H) using a mobile
elevated work platform.

Not allowing for inclement weather it is proposed that the sample section of glazing can be cleaned in
approximately 1 day.

These times may be extended based upon the frequency and cleaning method used for the various faades.
The recommended setup times provided by permanent faade access contractor will also vary.

WV06A - Example Elevation

Input Variables Units


Safe working load 200 kg
Number of Persons 2
Glass replacement unit N/A
Cradle dimension 1400 x 700 x 1000 mm
Hoisting height 28 m
Faade Length 31 m
Initial setting up times 30 min
Setting up times 4 min
Hoisting speed 10 m/min
Cladding Coverage 75 %
Cleaning speed (approx)/ man 75 m2/hr

Calculated Results
Number of Hoists 22
Hoisting Time 2.80 Min
Cleaning Time per Drop 14.56 Min
0.24 Hrs

Total Cleaning Time 8.27 Hrs


0.97 Days

These times are theoretical but based on our experience in the


access industry and verified on similar buildings

REP-2212100-LS-2013-11-18_RevP1 Page 10 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

The following diagram indicates the approximate tree spacing required to allow a Leo36T MEWP access to the faade without having to close the adjacent road.

Image 9 - Indicative MEWP / Tree Spacing Diagram

REP-2212100-LS-2013-11-18_RevP1 Page 11 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

3.3 INTERNAL CLEANING ACCESS

The images below outline various methods of internal cleaning to the residential elevations and also cleaning from ground/terrace level using long and short handled cleaning tools. The first study illustrates low level/terrace cleaning up to 5m
from a long handled cleaning tool. The other diagrams demonstrate the maximum reach of a person using a 750mm, cranked head cleaning tool when accessing common window types such as Juliet balconies and tilt and turn. The images
should be read in conjunction with the site wide strategy plan in section 3.0 which specifies the areas in which internal access is required.

Image 10 Internal Cleaning Diagrams

REP-2212100-LS-2013-11-18_RevP1 Page 12 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

4.0 CONCEPT MAINTENANCE STRATEGIES 4.1.2 Spider Crane

During the design development of the faade, due consideration should be made to the repair and / or A large reach spider type crane capable of accessing the majority of the external elevations is a UNIC 10T from
replacement of the faade panels and panes of glazing. Whilst this is likely to be carried out on an infrequent GGR Group which will access 30.7m in height at a maximum of 24m outreach This unit has a crawler base to
basis, the principle will be considered and provision made. cross landscaped areas and 4 outriggers (the dead load is approximately 14000kg). To spread the loads
spreader plates can be used. When in the travelling position the unit will occupy a 2m wide zone (This does not
4.1.1 Internal Replacement include clearance).

In areas where internal cleaning is to be carried out it is recommended that glazing is replaced from inside the
building. The panels should be suitably sized to fit within the proposed lifts and permit a clear run through
corridors and apartments.

Limit glazing to 2275m (H) to fit within standard 13 person deep lift cars.

Image 12 Indicative Example Spider Crane

Mobile Crane (Large Reach)Technical Data:


Reach = 30,700 mm
Safe Working Load = 700 Kg
Gross Vehicle Weight = 14,000 Kg
Image 11 Proposed Maximum Glazing Dimension Outrigger Clear Area = 7,230 mm

REP-2212100-LS-2013-11-18_RevP1 Page 13 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

4.1.3 Mobile Crane 5.0 DESIGN PARAMETERS

In order to access areas of faade greater than 30,700mm (maximum spider crane working height) an ultra large The faade access systems and associated equipment will be designed in accordance with the relevant British
reach mobile crane is proposed which will have a footprint of approximately 11245mm (L) x 6300mm (W) when and European Standards Codes and recommendations, Health and Safety Legislation and EC Directives, A
in the working position. selection of these documents are listed as follows:

It is likely that the crane will be required to hoist replacement kit from the surrounding roadways to avoid the jib BS 2830:1994 Suspended Access Equipment
clashing with the parapet. It is likely that a road closure permit will be necessary. (Please refer to appendix for BS 2853:1957 Design and Testing of Steel Overhead Runway Beams
further details on the proposed unit) BS 302-5:1987 Stranded Steel Wire Ropes
BS EN 1993-1 Specifications for the use of Structural Steel in Buildings
PD 5304 Safe use of machinery
BS EN ISO 12944-5 Corrosion protection of steel structures by protective paint systems
BS 7883:1997 Code of practice for application and use of anchor devices
BS 5950-2:2001 Structural use of steelwork in building
BS 6037-1:2003 Suspended Access Equipment
BS EN 1808:1999+A1:2010 Safety Requirements on Suspended Access Equipment
BS 6180:1995 Code of Practice for barriers in and about buildings
BS EN 1991-1-1:2002 Actions on structures
BS ISO 4309:2004+A1:2008 Wire ropes care, maintenance, installation, examination and discard
BS EN 62305-1 Protection against lightning
BS 7079:2009 General introduction to standards for preparation of steel substrates
BS EN ISO 1461:1999 Hot dip galvanised coatings on iron and steel articles
BS 7543:2003 Guide to durability of buildings and building elements
BS 7671:2008+A1:2011 Requirements for electrical installations - IEE wiring regulations
BS EN ISO 2063:2005 Thermal spraying. Metallic and other inorganic coatings
BS EN 60204-1:2006+A1:2009 Safety of machinery - Electrical equipment of machines
BS EN 795:1997 Protection against falls from a height Anchor devices
BS EN ISO 12100:2010 Safety of machinery - General principles for design
BS EN ISO 13850:2008 Safety of machinery - Emergency stop - Principles for design
BS EN 60529:1992 Degrees of protection provided by enclosures (IP-Code)
BS EN 614-1:2006+A1:2009 Safety of machinery - Ergonomic design principles
Image 13 Indicative Example Mobile Crane BS EN ISO 13849-1:2008 Safety of machinery - Safety-related parts of control systems
BS EN ISO 4413:2010 Hydraulic fluid power - General rules and safety requirements for systems
PD 6484:1979 Commentary on corrosion at bimetallic contacts and its alleviation
BS EN 341:2011 Personal fall protection equipment - Descender devices for rescue
BS EN 353:2002 Guided type fall arresters including a rigid anchor line
BS EN 354:2010 Lanyards
BS EN 355:2002 Energy absorbers
BS EN 358:2000 Belts for work positioning and restraint and work positioning lanyards
BS EN 360:2002 Retractable type fall arresters
BS EN 361:2002 Full body harnesses
BS EN 362:2004 Connectors
BS EN 363:2008 Personal fall protection systems

END OF REPORT

Image 14 Example Large Reach mobile Crane

REP-2212100-LS-2013-11-18_RevP1 Page 14 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

6.0 APPENDIX 6.2 HSE INFORMATION SHEET MISC611; PAGE 1

6.1 SECTION 11 OF THE CDM REGULATIONS 2007

REP-2212100-LS-2013-11-18_RevP1 Page 15 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

6.3 HSE INFORMATION SHEET MISC612; PAGE 1 6.4 EXAMPLE LARGE REACH MOBILE PLATFORM FOR CLEANING

REP-2212100-LS-2013-11-18_RevP1 Page 16 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

6.5 EXAMPLE ULTRA LARGE REACH MOBILE PLATFORM FOR CLEANING

REP-2212100-LS-2013-11-18_RevP1 Page 17 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

6.6 EXAMPLE MOBILE CRANE FOR GLASS REPLACEMENT

REP-2212100-LS-2013-11-18_RevP1 Page 18 of 19
Earls Court, London
Capco

Faade Access Strategy, RMA Stage Issue


Revision P1

6.7 EXAMPLE SPIDER CRANE FOR GLASS REPLACEMENT

REP-2212100-LS-2013-11-18_RevP1 Page 19 of 19

You might also like