S10 Pgina : 1

CCCEIC Fecha : 21/07/2010 05:35:37p.m.


Precios y cantidades de insumos requeridos
Obra 0302023 SISTEMA DE ALCANTARILLADO DEL DISTRITO DE LUNAHUANA - PRE INVERSION
Frmula 4. CIUDAD DE LUNAHUANA - TRATAMIENTO DE AGUAS SERVIDAS
Fecha 05/07/2010

Cdigo Insumo Unidad Precio Cantidad Parcial Presupuestado

020409 ALAMBRE NEGRO N16 KG 3.00 163.20 489.60 489.58


020410 ALAMBRE NEGRO N8 KG 3.00 120.71 362.13 362.14
021050 PERNO D=3/8" C/ARANDELA UND 1.50 86.00 129.00 129.00
021051 GANCHO PARA ALBACIL UND 3.00 389.35 1,168.05 1,168.05
021099 CLAVOS KG 3.50 365.24 1,278.34 1,279.15
029742 ACERO CORRUGADO KG 3.00 350.00 1,050.00 1,050.00
030101 ACERO CORRUGADO KG 3.00 5,378.73 16,136.19 16,136.18
040000 ARENA FINA M3 50.00 8.99 449.50 449.41
040001 AGUA (SEDAPAL inc. transporte) M3 8.00 18.83 150.64 150.77
040003 AGUA M3 10.00 11.20 112.00 112.00
050003 PIEDRA CHANCADA DE 1/2" M3 55.00 79.12 4,351.60 4,351.94
050104 ARENA GRUESA M3 50.00 57.75 2,887.50 2,887.31
050220 PIEDRA MEDIANA M3 40.00 6.72 268.80 268.80
050221 PIEDRA GRANDE M3 40.00 21.00 840.00 840.00
100184 INODORO COLOR BLANCO PZA 140.00 1.00 140.00 140.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 18.00 1,241.43 22,345.74 22,345.61
260869 BISAGRA ALUMINIZ.CAPUCHINA 2 1/2" UND 0.50 6.00 3.00 3.00
300109 CORDEL M 0.30 10.99 3.30 3.66
300125 ALDABA Y CANDADO UND 20.00 1.00 20.00 20.00
300190 TIZA BLANCA KG 1.50 10.99 16.49 18.32
304835 CINTA SEALIZADORA AMARILLA M 1.00 147.00 147.00 147.00
304836 BOTAS DE JEBE PAR 42.84 15.00 642.60 642.60
304837 CASCOS DE PROTECCION UND 14.28 20.00 285.60 285.60
304838 TAPONES DE OIDOS UND 45.22 3.00 135.66 135.66
304839 LENTES DE PROTECCION UND 57.12 10.00 571.20 571.20
308680 ADITIVO IMPERMEABILIZANTE DE CONCRETO GLN 65.00 77.86 5,060.90 5,061.55
309919 LIJA UND 0.03 25.92 0.78 1.04
340000 GASOLINA 84 OCTANOS GLN 13.00 49.95 649.35 649.42
370005 GARLOPA 50 cm. HM 2.00 13.80 27.60 25.85
370006 SIERRA CIRCULAR ELECTRICA HM 6.50 13.80 89.70 87.89
370007 CIZALLA HM 5.00 143.61 718.05 699.23
380000 HORMIGON M3 50.00 114.32 5,716.00 5,715.99
430103 MADERA TORNILLO P2 4.00 602.09 2,408.36 2,408.36
430104 MADERA PARA ENCOFRADO P2 4.00 2,829.84 11,319.36 11,319.30
430105 ESTACA DE MADERA DE 3/8" (L=50 cm.) 12 USOS UND 3.00 73.28 219.84 219.84
430107 PARANTES DE EUCALIPTO (3.00 m.) UND 12.00 13.00 156.00 156.00
430108 MADERA EUCALIPTO P2 3.80 2.52 9.58 9.80
431398 MADERA BAMBU UND 75.00 840.00 63,000.00 63,000.00
431653 REGLA DE ALBAIL 1" x 4" x 6" HM 2.00 237.22 474.44 472.87
440322 TRIPLAY 4 x 8 x 4 mm. PLN 22.00 23.00 506.00 506.00
470101 CAPATAZ HH 15.69 298.64 4,685.66 4,666.03
470102 OPERARIO HH 13.64 2,218.08 30,254.61 30,206.17
470103 OFICIAL HH 12.08 454.77 5,493.62 5,478.09
470104 PEON HH 10.91 2,653.46 28,949.25 28,951.12
470158 TOPOGRAFO HH 13.70 3.66 50.14 51.30
470160 CAPATAZ HH 15.69 0.83 13.02 12.60
470162 OFICIAL HH 12.08 8.30 100.26 100.80
470163 PEON HH 10.91 24.89 271.55 271.60
470165 CAPACITAICON Y EDUCACIONAL GLB 10,000.00 1.00 10,000.00 10,000.00
480079 EQUIPO DE PINTURA HM 3.00 27.65 82.95 82.94
480084 ARNES UND 305.00 3.00 915.00 915.00
480101 MEZCLADORA DE CONCRETO TIPO TAMBOR 23 HP, 11-12 P3
HM 20.00 39.00 780.00 779.28
480301 MIRA TOPOGRAFICA HM 2.00 3.66 7.32 7.33
480302 JALON HM 1.50 3.66 5.49 7.33
480430 CAMIONETA PICK-UP 1 Tn HM 100.00 4.57 457.00 457.14
481104 CAMION VOLQUETE 6x4 330 HP 10 M3 HM 80.00 53.20 4,256.00 4,254.97
490301 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 30.00 20.24 607.20 607.20
490409 CARGADOR S/LLANTAS 125 HP 2.5 YD3. HM 160.00 12.17 1,947.20 1,948.88
490704 VIBRADOR DE CONCRETO 4 HP 2.40" HM 6.50 74.01 481.07 481.05
491007 MEZCLADORA DE CONCRETO TIPO TAMBOR 23HP 11-12P3HM 20.00 74.01 1,480.20 1,480.16
491824 WINCHE DE DOS BALDES (350KG)M.E. 3.6HP HM 10.00 74.01 740.10 740.08
S10 Pgina : 2
CCCEIC Fecha : 21/07/2010 05:35:37p.m.
Precios y cantidades de insumos requeridos
Obra 0302023 SISTEMA DE ALCANTARILLADO DEL DISTRITO DE LUNAHUANA - PRE INVERSION
Frmula 4. CIUDAD DE LUNAHUANA - TRATAMIENTO DE AGUAS SERVIDAS
Fecha 05/07/2010

Cdigo Insumo Unidad Precio Cantidad Parcial Presupuestado

498803 TEODOLITO TOPOGRAFICO HM 7.00 3.66 25.62 25.65


530327 THINNER CORRIENTE GLN 15.30 6.01 91.95 91.95
540242 PINTURA ESMALTE GLN 40.00 3.88 155.20 155.08
542121 PINTURA ANTICORROSIVA EPOXICA GLN 55.00 2.88 158.40 158.63
570101 PLANCHA ACERO LAF 1.50x1200x2400mm (1/16) PLN 28.00 9.00 252.00 252.00
590101 PLANCHA AC. ALUMINI. CALAMINON 0.40 mm., 0.93 X 6.50 m.
PLN 45.00 4.00 180.00 180.00

SUB-TOTAL 236,780.71 236,682.50


INSUMOS COMODIN
370101 HERRAMIENTAS MANUALES %MO 3,036.45
470164 MATERIALES VARIOS %MO 4,422.93

SUB-TOTAL 7,459.38

TOTAL 236,780.71 244,141.88


MONTO PARTIDAS ESTIMADAS 0.00

244,141.88

La columna parcial es el producto del precio por la cantidad requerida; y en la ltima columna se muestra el Monto Real que se est