Professional Documents
Culture Documents
The 1-D equation of consolidation cannot be solved analytically except for some very simple
situations. For more difficult cases it is necessary to use approximate numerical techniques. One
numerical technique that can be used for consolidation problems is the finite difference approach.
In this method the solution is evaluated at a number of points at different times as indicated on
the figure below.
The 1-D consolidation equation and the boundary conditions are approximated by finite
difference formulae. These can be derived by referring to the figure below and taking local axes at
B:
A u = uA z = - z
B u = uB z = 0
u
z
C u = uC z = + z
u a1 a 2 z a 3z 2 (1a)
The constants in this equation can be related to the values of the excess pore pressures at points
A, B, C. Taking B as the origin for z gives:
uA a 1 a 2 z a 3 z 2
uB a1 (1b)
uC a 1 a 2 z a 3 z 2
so that
a1 uB
uC uA
a2 (1c)
2 z
u A u C 2u B
a3
2 z 2
u uC uA
z
B 2 z
(1d)
u2
u A u C 2u B
2
z B z 2
2u u q
cv
z 2 t t
(2a)
where q is the change in total stress, due to applied loads, from the initial equilibrium situation
when the excess pore pressures were zero.
When this equation is evaluated at any point in the soil it is equivalent to evaluating the equation
at point B, and hence the finite difference formulae developed above can be introduced so the
equation becomes:
u q
c u A u C 2u B
t t v (2b)
B B z 2
if the above equation is now integrated from times t to t+t it is found that:
t t
cv
u B q B
z 2 [u A u C 2 u B ]dt (2c)
t
where u B u B (t t ) u B (t ) and q B q B (t t ) q B ( t )
3
Error in approximation
F(t)
t t
F( t)dt F(t )t
t
t
t
t t
Fig. 3 Approximate integral evaluation
Fig 3 Approximation of integral
If the integral appearing in equation (2c) is now approximated as indicated in Fig. 3, it is found
that:
uB q B [ u A ( t ) u C ( t ) 2 u B ( t )] (2d)
cv t
where
z2
Or
u B ( t t ) q B u B ( t ) [ u A ( t ) u C ( t ) 2u B ( t )]
(2e)
Suppose the solution for u has been found up to time t. The applied load will be known at time t
+ t and so the quantity q is known. This means all the quantities on the right hand side of
equation (2e) are known and thus that u at time t + t can be calculated. Thus a knowledge of
the distribution of u at time t means that the distribution of u at time t + t can be inferred. Now
the initial distribution of u can always be determined and thus the solution can be found by
marching forward in time.
11.3 Stability
There is an important restriction on the use of equation (2e) to obtain a numerical solution of the
equation of consolidation, this is
cv t 1
2
z 2
At a free draining boundary there is no impediment to flow and so the pore pressure remains
constant and thus the excess pore water pressure is zero, this is illustrated in figure 4a.
Saturated soil
Saturated soil
A .
z
B .
.
z Impermeable barrier
C
Suppose that a 4m layer of clay, shown in figure 5, which is free to drain at its upper boundary
and rests on an impermeable base, is subjected to a surface loading of 64 kPa.
q = 64 kPa
4 sub-layers
4m
cv = 2 m2/year
mv = 0.0003 m2/kN
Impermeable bedrock
u A (t ) u C (t )
u B ( t t ) q (4)
2
In the case under consideration the surcharge is applied at t = 0 and remains constant thereafter
so that q = 0
Step 1: Divide the deposit into layers - this fixes the value of z.
In this case the deposit is divided into 4 sub-layers (all with the same thickness) and thus
z = 1m
c v t 2 t 1
2
z 12 2
thus
t 0.25 years
6
Step 3: Calculate the initial pore pressure
u( t 0 ) q ( t 0) 64 kPa
Step 5: March the solution forward using the finite difference equation and
introducing the boundary conditions
Thus
H
1 1
u dz
2
( u 0 u 1 ) z ( u n 1 u n ) z
2
0
u u n (6)
z 0 u 2 u n 1
2
where
ui u i ( z, t )
36 mm
The settlement at other times can be similarly calculated from the excess pore pressures hence the
values can be determined as shown in the table below.
Suppose now the previous example is solved using a step size of 2 months but keeping the
number of layers the same. If this is the case =1/3. The numerical solution proceeds as above
but now using the more complex form of the finite difference equation, viz. equation (2e), the
solution is shown in the table below:
t(mths) 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00
settlement(mm) 0.00 9.60 16.00 20.27 23.82 26.90 29.67 32.20 34.54 36.73
q(kPa) 64.00 64.00 64.00 64.00 64.00 64.00 64.00 64.00 64.00 64.00
z=0 64.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
z=1m 64.00 64.00 42.67 35.56 30.81 27.65 25.28 23.44 21.92 20.61
z=2m 64.00 64.00 64.00 56.89 52.15 48.20 45.04 42.32 39.92 37.74
z=3m 64.00 64.00 64.00 64.00 61.63 59.26 56.63 53.99 51.39 48.86
z=4m 64.00 64.00 64.00 64.00 64.00 62.42 60.31 57.85 55.28 52.68
dummy 64.00 64.00 64.00 64.00 61.63 59.26 56.63 53.99 51.39 48.86
u B ( t t ) q B u B ( t ) [ u A ( t ) u C ( t ) 2u B ( t )]
u B ( t t ) 0 + 59.26 + 0.3333 [48.20 + 62.42 - 2 59.26] = 56.63
The results for the two analyses are quite close. After 18 months the settlement predicted in
example 1 is 36 mm, which compares well with the settlement calculated in example 2, viz.
36.7mm.
Suppose fill having unit weight 20 kN/m3 is placed at a rate of 0.5 m/month for 12 months after
which no more load is applied, the analysis only differs from that in the previous examples in that
8
the value of q needs to be included in the finite difference equation. Choosing = 0.5 with 4
layers gives a time step of 0.25 years as before. The results are shown in the table below.
Note that when the load is applied gradually the excess pore pressure at the permeable upper
boundary remains at zero. This is because there is no instantaneous change in load.
If the calculation is repeated for the case in which there are 5 sub-layers, and a time step of 0.1
years is adopted, this gives = 0.3125 and the results are shown below:
t (years) 0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00
settlement(mm) 0.00 1.44 3.78 6.74 10.21 14.13 18.45 23.13 28.16 33.50 39.15
q(kPa) 0.00 12.00 24.00 36.00 48.00 60.00 72.00 84.00 96.00 108.00 120.00
z=0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
z=0.8m 0.00 12.00 20.25 27.09 33.04 38.38 43.27 47.80 52.04 56.05 59.85
z=1.6m 0.00 12.00 24.00 34.83 44.78 54.00 62.64 70.78 78.50 85.86 92.90
z=2.4m 0.00 12.00 24.00 36.00 47.63 58.86 69.66 80.07 90.11 99.81 109.18
z=3.2m 0.00 12.00 24.00 36.00 48.00 59.89 71.60 83.10 94.35 105.33 116.04
z=4.0m 0.00 12.00 24.00 36.00 48.00 60.00 71.93 83.72 95.33 106.72 117.85
dummy 0.00 12.00 24.00 36.00 48.00 59.89 71.60 83.10 94.35 105.33 116.04
Again the settlements at 1.5 years are quite similar. Thus although greater refinement of the grid
leads to more accurate excess pore pressures and settlements there is, in practice, little advantage
of using 0.5.
9
Example - Abrupt change of load
Suppose that in the case detailed in example 1 a further surcharge of 32 kPa is added after 12
months. The solution in this case is best handled in two stages.
Stage 1 follows exactly the path outlined in example 1 and is detailed in the table below. Just after
1 year the load is abruptly increased, and since there can be no instantaneous volume strain there
can be no increase in effective stress and no change in settlement. This means that the increase or
decrease in applied stress must be matched by a corresponding increase or decrease in pore water
pressure. This enables the excess pore water pressure to be calculated.
Stage 2 of the calculation then proceeds in the same way as in stage 1 or in example 1. This is
shown in the table given below: