LIST WPS & PQR

Project : PLTU Malinau 2x3 MW Item : Left Wall Panel Report No. : 005/X/ZII/QC
Job No. : SC 12016 Unit :- Revision :0
PT. ZUG INDUSTRY INDONESIA Costumer : PT. PLN Location : Malinau (Site) Date : October 8, 2
Material & P No. AWS
No. PQR No. WPS No. Range Thickness F No. Process Preheating PWHT
Material A Material B Classification

Preheat 20C
1 001/PQR/SMAW R.0 001/WPS/SMAW R.1 SA 516 Gr. 70 (P1) SA 516 Gr. 70 (P1) 5 up to 24 mm E 7016 & E 7018 F4 SMAW None
Interpass 225C

Preheat 20C
2 002/PQR/GTAW R.0 002/WPS/GTAW R.1 SA 106 Gr.B (P1) SA 106 Gr.B (P1) 1.5 up to 17.4 mm ER70S-6 F6 GTAW None
Interpass 200C

Remark :

Prepared by : Reviewed by : Approved by : Client:


Welding Engineer QA/QC Coordinator QA/QC Manager
LIST WPS & PQR
: 005/X/ZII/QC-LWP/2014

: October 8, 2014
Approved
Remarks
By

Lloyd's Reg.
-
& Depnaker

Lloyd's Reg.
-
& Depnaker