S10 Pgina 1

Presupuesto
Presupuesto 0701053 CREACION DE LOSA RECREATIVA MULTIUSOS CIUDAD ETEN, DISTRITO DE ETEN, CHICLAYO - LAMBAYEQUE
Subpresupuesto 004 TRIBUNAS
Cliente MUNICIPALIDAD DISTRITAL DE CIUDAD ETEN Costo al 17/11/2016
Lugar LAMBAYEQUE - CHICLAYO - ETEN

Item Descripcin Und. Metrado Precio S/. Mano de Obra Material Equipo Subcontrato Parcial S/.

05 TRIBUNAS (GRADERIAS) 14,114.17 27,523.15 2,016.51 43,654.67

05.01 MOVIMIENTO DE TIERRAS 2,557.20 2,465.14 591.89 5,614.35

05.01.01 EXCAVACION MANUAL EN MATERIAL SUELTO m3 25.10 20.24 493.27 14.80 508.02

05.01.02 REFINE, NIVELACION Y COMPACTACION DE BASES m2 35.85 2.84 85.12 16.89 101.81

05.01.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 93.91 48.32 1,525.51 2,465.14 546.60 4,537.73

05.01.04 ELIMINACION DE MATERIAL EXCEDENTE D=30M m3 31.37 14.88 453.30 13.60 466.79

05.02 CONCRETO SIMPLE 1,068.46 1,657.30 72.21 2,798.16

05.02.01 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS m3 17.93 156.06 1,068.46 1,657.30 72.21 2,798.16

05.03 CONCRETO ARMADO 2,607.72 7,589.71 171.19 10,369.27

05.03.01 CONCRETO fc=175kg/cm2 EN GRADERIAS m3 26.68 252.97 1,361.03 5,264.24 123.83 6,749.24

05.03.02 ENCOFRADO Y DESENCOFRADO P/TRIBUNAS Y ESCALERAS m2 64.99 47.42 1,105.74 1,943.14 33.16 3,081.83

05.03.03 ACERO Fy=4200 kg/cm2 PARA GRADERIAS kg 149.50 3.60 140.95 382.33 14.20 538.20

05.04 REVOQUES, ENLUCIDOS 3,611.22 1,134.08 108.34 4,855.24

05.04.01 TARRAJEO PULIDO EN (GRADAS Y GRADERIAS) m2 170.18 28.53 3,611.22 1,134.08 108.34 4,855.24

05.05 ESTRUCTURA METALICA Y COBERTURAS 4,269.57 14,676.92 1,072.88 20,017.65

05.05.01 COLUMNAS DE ESTRUCTURA METALICA m 71.50 77.94 2,413.13 2,634.83 525.20 5,572.71

05.05.02 CORREAS METALICAS DE 2"x2" EN TECHO m 182.67 38.75 1,644.24 4,932.09 503.44 7,078.46

05.05.03 CUBIERTA DE PLANCHA DE POLICARBONATO INLCLUYE ACCESORIOS m2 130.00 50.40 6,552.00 6,552.00

05.05.04 BARANDA C/TUBO FG : PASAMANO 2" Y PARANTE 2"x1.00 m DE ALTURA m 8.00 101.81 212.20 558.00 44.24 814.48

06 IMPACTO AMBIENTAL 1,500.00 1,500.00

06.01 MITIGACION AMBIENTAL 1,500.00 1,500.00

06.01.01 MITIGACION DE IMPACTO AMBIENTAL GLB 1.00 1,500.00 1,500.00 1,500.00

COSTO DIRECTO 45,154.67

GASTOS GENERALES 8.4%) 3,792.99

UTILIDAD (5%) 2,257.73

========

SUB TOTAL 51,205.39

IGV (18%) 9,216.97

========

COSTO DE OBRA 60,422.36

SON : SESENTA MIL CUATROCIENTOS VEINTIDOS Y 36/100 NUEVOS SOLES

Fecha : 01/12/2016 02:54:28p.m.