Professional Documents
Culture Documents
111111111111I11111111111
ABSTRACT inadequately structured for warranty situations. This paper
addresses the needs.
Reliability performance is currently receiving significant
attention in the bid requests for new gas turbine generating The word "reliability" is frequently used in the broad sense.
units. Reliability guarantees backed by liquidated damages "Reliability" warranties may typically apply to any of the
clauses are becoming the rule rather than the exception. But following specific measurements:
the power generation industry does not have a universally
accepted set of reliability measurements and the more STARTING RELIABILITY:
commonly used measurements are not sufficiently refined for The expected likelihood that a generating unit can
the warranty situation. successfully start on demand and/or within a given time
period.
This paper is intended to provide the guidance, structure
and refinement needed for meaningful reliability warranties. RUNNING RELIABILITY:
The expected likelihood that a generating unit can
Four key areas of reliability measurement: starting relia- provide electricity when requested. Measurements of
bility, running reliability, availability and equivalent availability running reliability deal with unplanned events and
are separately addressed. And within each of these areas generally exclude all outages associated with scheduled
there is the flexibility, the methodology and the need to adapt maintenance activities.
the measurement system to the varied operating regimes and
philosophies encountered such as: peaking vs. continuous AVAILABILITY:
service, attended vs. unattended sites, different levels of The expected portion of period time (typically a year) that
maintenance intensity, chargeable vs. non-chargeable outage a generating unit is capable of providing electricity.
events and emotional/political/optical acceptability (i.e., 3% Availability considers all outage activity, both planned and
Forced Outage Factor vs. 40% Forced Outage Rate). unplanned.
Warranty structuring rationale and suggested contract
language are provided to address such needs as a rigorous EQUIVALENT AVAILABILITY:
and explicit operating log, certification of data, measurement Similar to Availability (above) but corrected to reflect
accuracy, statistical confidence, assurance of readiness and capacity adjustments. It becomes the expected portion
risk assessment. of energy available over a period of time (typically one
year) and it is most applicable to situations involving
The suggestions presented herein have been constructed reduced capacity operating modes. The concept of
with logic and fairness. This paper will be beneficial to all "Equivalent..." can also be applied to running reliability .
Architect Engineers, Utilities, Independent Power Producers measurements.
and OEM's that become involved with the structuring of
reliability warranties.
CURRENT STANDARDS AND
DATA COLLECTION SYSTEMS
INTRODUCTION
Technically speaking, the domestic (USA) electric utility
It has been said that gas turbine value is measured in industry has one formal standard for reliability terminology. It is
terms of performance and reliability. And to ensure the receipt ANSI/IEEE Std 762-1987, entitled "IEEE Standard Definitions for
of that value, the electric utility industry is increasingly seeking Use in Reporting Electric Generating Unit Reliability, Availability,
warranties on both performance and reliability in its contracts and Productivity". It was written for base-loaded power plants
for new gas turbine power plants. But common practices and and defines no less than 66 reliability-related terms plus some
the available standards for measuring reliability are 25 performance indexes [none of which are explicitly named
100
Fa ilure Duration Ho urs
10
0.1
0.01 I I I I I 1
0 10 20 30 40 50 60 70 80 90 100
% Starting Failures Source: SPS - ORAP
Figure 1. Starting Failure Outage Times Cumulative Distribution - M57001 E/EA Units 1978 to 1989
2
Downloaded From: https://proceedings.asmedigitalcollection.asme.org/ on 07/12/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use
Starting time allowance period A Qualifying Starting Attempt is the action intended to bring
a unit from shutdown to the in-service state under conditions
Operator or procedural errors that qualify for inclusion in the warranty. Repeated initiations
of the starting sequence within the allowable specified starting
Start sequence aborts by operator or dispatcher time period or without accomplishing corrective repairs are
discretion with no equipment failure counted as a single attempt.
Load level reached for a "Successful Start" A Chargeable Startina Success is the occurrence of
bringing a unit through a qualifying starting attempt to the in-
To illustrate the importance of the above "special service state within a specified period, as evidenced by
considerations" consider the concept of the starting time maintained closure of the generator breaker to the system.
allowance period as incorporated in the IEEE standard but not
in the NERC GADS or standard ORAP definitions. IEEE A Chargeable Starting is the inability to bring a unit
allows that repeated initiations of the starting sequence, within through a qualifying starting attempt to the in-service state
a user-specified period (typically 20 or 30 minutes) be counted within a specified period for failure reasons chargeable to the
as a single attempt. The significance of this distinction is warranty. Repeated failures within the specified starting period
evident by the fact that 74% of the starting failures (Fig. 1) are to be counted as a single starting failure.
reported in the ORAP data base under the NERC definition are
followed by a successful start within six minutes time of the In structuring a warranty for Starting Reliability, the desires
"failure" and have minimal impact to the service demand are to address the maintenance-readiness environment and to
request. When a five-year ORAP history of GE MS7001E/EA assure a statistically appropriate measurement such that
units was assessed the starting reliability averaged 93% by the financial penalties are not incurred simply due to the natural
NERC definition but 98.2% by the IEEE Std 762 definition! randomness of starting failures. Here are some examples of
SR warranty considerations:
The IEEE Std 762 collection of definitions also enables fair
treatment of all the "special situations" described previously. 1. Repair verification starts and failures-to-start from
This is accomplished by first making a subtle formula change to: equipment not furnished under the contract should not be
chargeable to the warranty.
Starting Reliability = SS (2)
SS + SF 2. If the equipment has not been successfully started within
Where: a reasonable period (e.g., 30 days) then, for compromise
SS = [Chargeable] Starting Successes of readiness, the next starting attempt should not be
SF = [Chargeable] Starting Failures considered a qualifying start attempt.
IEEE Std 762 then offers some basic qualifications through 3. In order to realize the significantly higher SR levels
its definitions. But warranty situations require expanded associated with the IEEE starting time allowance clause,
qualification as suggested here along the lines of IEEE Std 762: there should be technically competent supervision and
Starting Reliability
MS7001 Domestic Units
100
IEEE SW 762
95 ......70.00.....0.00 ....
' - ORAP - NE-RC/GA- DS
v44..
80
ORAP Data
Strategic Power Systems
75 1 1 1 1 1 1 1 I I I I I I I I I
1976 '78 '80 '82 '84 '86 '88 '90 '92
Year
PERIOD HOURS
AVAILABLE UNAVAILABLE
1
RESERVE IN UNPLANNED OUTAGES PLANNED
SHUTDOWN SERVICE OUTAGES
SF Ut U2 U3 MO PO
10
. . _...
ORAP Data Base
Strategic Power Systems Model 7E
I I I I I I 1 I
0
1976 '78 '80 '82 '84 '86 '88 '90 '92
Year
problem is that all forced outage hours (FOH) are And also:
debited even though a large percentage of the FOH
might occur during periods of non-demand. Available Hours [European Vers 3] (12)
RR _
PH-F0H-S0H-AOH Available Hours + FOH
D. RR - PH - SOH - AOH [European formula] (10)
MTBF
E Reliability = [textbook formula] (13)
where: PH = feriod Hours (one year - 8760 hours) MTBF + MTTR
FOH = forced Outage Hours
SOH = Scheduled Qutage Hours where: MTBF = Mean lime Setween failures
AOH = Administrative Outage Hours MTTR = Mean l- ime 10 Hepair
This formula, seen frequently in European bid specs, is This classical textbook formula (Calabro, SR.,
variously called "Forced Outage Availability" or "Running Belablujyirigthaisa_aaciaactices McGraw-Hill, 1962)
Availability" or just plain "Availability". It is the truest is used in the EPRI UNIRAM program and is often
measure of the time-based probability for avoidance of applied to components or subsystems. It originated as
forced outages and it is fully suitable as a warranty a measurement of reliability for systems that were
measure for units of any service application whether expected to be in continuous service such as telephone
peaking or continuous service. The "Administrative and communications systems. If the MTBF is measured
Outage Hours" (AOH) category admirably covers any in period time (clock/calendar hours), the result
number of "stop-the-clock" provisions for outage events numerically approximates the GT traditional formula (3).
that should not be charged against the equipment. To If the MTBF is measured in service hours, the result
continue the example: if the machine with 175 forced numerically approximates the utility FOR formula (8).
outage hours and 100 service hours also had 200 This formula and the terms MTBF and MTTR are more
scheduled outage hours plus 20 administrative outage often tools of the reliability engineer than the power
hours, its annual "reliability" would be 97.95%. plant operator. There are at least two reasons why this
is not a good formula, or measure, for warranty
The European formula also has alternate forms that purposes: 1) the terms MTBF and MTTR are derived,
sometimes appear in customers' specifications: rather than directly-measured values and 2) it tends to
be overly sensitive to event rate.
SH + RSH [European Version 2] (11)
RR =
SH + RSH + FOH F. RR = (1-CFOR) [corrected FOR formula] (14)
where: CFOR = Corrected Forced Outage Rate
where SH = In Service Hours (fired hours)
RSH = Reserve Shutdown Hours CFOR -
(FOH)(DDF) (15)
FOH = forced Outage Hours (FOH)(DDF) + SH
6
Downloaded From: https://proceedings.asmedigitalcollection.asme.org/ on 07/12/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use
and: FOH = forced Qutage Hours I. RR = (Pavail)(SR)(PmIssIon) [demand rel.] (18)
DDF a Daily Duty factor
= (Fired Hours per Start)/24 where: Pavail a probability of being available using
SH a Service Hours the European formula (10)
SR = Starting Reliability
The Corrected Forced Outage Rate (CFOR) is an emission a probability of completing the
attempt to more fairly apply the concept of Forced mission using the Mission Reliability
Outage Rate (FOR) to low usage situations such as formula (16)
"peaking" duty. It is an easily applied approximation of
a four-state Markov model (which some utilities are This Demand Reliability formula is receiving increased
experimenting with); and through the Daily Duty Factor usage by utilities as a planning tool for peaking and daily.
(DDF) it recognizes that much of the forced outage cycling units. It is both specific and encompassing in
repair time is applied when the unit is not in demand. nature, and is an excellent collective measure for most
For the original example machine of 175 Forced generating units. 11 has a disadvantage of producing
Outage Hours and 100 Service Hours, we might poor appearing numbers for units that target for very long
ascertain that the average fired hours per start is 4.0. continuous runs (thousands of hours). It is also
That gives a Daily Duty Factor of 0.167, a CFOR of somewhat complex for implementation as a warranty
6.8% and a "Reliability" of 93.2%. Not as optically measurement. If the base case "example" machine has
pleasing a number as the GT and European formulas a starting reliability of 96%, then the Demand Reliability
produce but tremendously better than the 36.4% is (.9795)(.96)(.984) = 92.5%. This is perhaps the best
associated with the uncorrected Forced Outage Rate measure of the probability that a generating unit in
formula (8). This is a fair reliability warranty peaking service will provide electricity on demand.
measurement for peaking units but it depends on a
derived (or arbitrary) correction factor. It has seen little The dilemma of multiple formulas is tacitly acknowledged by
exposure and even less acceptance. the two leading USA norms, ANSNEEE Std 762 and NERC
GADS, in that neither attempts to provide a specific mathematical
G. RR = cr(lambda)t [mission reliability] (16) formula for the terms "reliability" or "running reliability".
where: e a the base of the natural log (2.71828) The author has provided his rating of the applicability of the
Lambda a the failure rate in events per hour different Running Reliability formulas for use in different
which is also equivalent to 1/MTBF warranty and engineering situations (Fig. 5). The basic criteria
t= mission time in hours for the ratings on warranty measurements are as follows:
Mission Reliability is a classical reliability measure- 1.The measure should have a tangible feeling; that is it
ment tool and represents the probability that a mission should be a simple measure calculated directly from counting
of time (t) will be successfully completed once started. hours and/or events.
Mission Reliability is extensively used in military and
aerospace design and is most applicable to 2.The measure should closely describe the probability of the
continuously functioning components or systems machine being able to achieve service when it is expected to
where there is no opportunity for in-service repair. be in service.
Unlike all of the foregoing reliability definitions (or
formulas), Mission Reliability is oblivious to the repair 3.There should be zero or minimum dependence on arbitrary
or outage time. But it is still useful to estimate the or approximated factors.
probability of completing a run or to predict component
failures. If the "example" machine has a 250 service 4.Tfie resulting number should have political and emotional
hour MTBF in peaking service, then the probability of acceptability; i.e., if it is a measure of "reliability" it should read
completing a 4 hour run is 98.4%; and that would be above 90%.
called the Mission Reliability. Mission Reliability is an
excellent design or system planning tool but a poor Warranties on Running Reliability are reasonable for all
warranty measurement device. service applications from peaking to continuous duty if the
proper formula is selected. Warranty structuring for Running
Reliability guarantees is concerned with good record keeping
H. RR 1 - SF + FOE
SF + SS [P.R. Index] (17) and careful outage management (including correct
categorization of the forced outage events and the elements of
restoration time). Furthermore, it is well to decide when writing
where: SF a Starting failures the warranty terms whether the warranty is basically intended to
FOE a forced Qutage Events nominally cover the equipment only or the equipment plus the
(from the running state) user's and/or manufacturer's service system. Most
SS = Starting Successes manufacturers are not keen to pay liquidated damages for
downtime hours where the user applied his limited maintenance
The "Peaking Reliability Index" (PRI) is a fairly new resources to other projects because of other priorities.
approach that is quite attractive as a single, simple, fair
and overall measure for peaking or cycling duty units. It The Appendix B includes a generic sample warranty
is strictly an "events" based extension of starting statement (plus qualifying clauses) for a Running Reliability
reliability that views the probability of not only starting, warranty based on the "European" formula.
but completing a run. The simplicity of the measure-
ment offers strong argument; particularly for warranty
purposes. In the continuing example: as the peaking MAINTENANCE INTENSITY
"example" machine sees 25 successful starts and 100
service hours, it likely endured one starting failure and The time-based measurements of Availability and Running
maybe one forced outage event (a trip) from the running Reliability generally enumerate the bulk total elapsed outage
condition. The corresponding PRI Reliability is easily hours without differentiating for inspection need or actual applied
calculated at 92.3%. repair time. Some critical peaking or cycling units are overly
Abbreviations:
V.G. = Very Good
VP = Very Poor
NA. = Not Applicable
maintained. And some minor two-hour repair tasks are logged at Maintenance intensity effect is such a significant factor that
over a hundred outage hours because of low maintenace priority. it must be addressed with every time-based Availability or
Waiting time for replacement parts can have an even more Running Reliability warranty situation. All maintenance may be
serious effect. "Availability" can become more a measure of the performed by the equipment supplier, or agreement reached
service system than the inherent disposition of the equipment to on specific maintenance conduct, or a warranty qualification
perform. In reviewing ORAP data for many machines it becomes set up to exclude excessive inspection events and excessive
obvious that the maintenance intensity effect is a very significant waiting time. The additional sub classifications of outage time
-
factor, it is driven by the operators's need for the equipment and it necessitate more detailed record keeping and a separate set
can be correlated to the service application. Figure 6 (from the of warranty performance measurements that will be
following data table) exquisitely illustrates this effect. numerically different from the normal ORAP or NERC GADS
measurements. 'Two (or three) sets of books", so to speak.
Service Application
Service FH per # of Insp. Outage
Mkt Facto( 5.tati 1nso. interval Hours AVAILABILITY
Continuous 80- 100 >120 28 8675 88 Availability is the popular measure of the portion of time
Base Load 30 - 80 >60 178 5048 276 that a unit is available to serve load because it is not on Forced
Cycling 10 - 50 10 - 20 160 3206 339 Outage, Maintenance Outage or Planned Outage. Both NERC
Peaking 2-10 3 - 10 120 1072 355 GADS and ANSI/IEEE Std 762-1987 recognize Availability as
Standby 0-2 <4 2 1073 529 a key performance index and more specifically call it the
"Availability Factor" (AF).
The combustion inspection is a fairly standard gas turbine
maintenance inspection yet some operators perform it more
often than others; and the average elapsed period hours taken Availability Factor - Available Hours
Period Hours (19)
to accomplish this inspection vary by 6 to 1 across the service
application categories! From all 488 inspections the average where: Available Hours (AH) = PH - FOH - MOH - POH
hours to complete is 306. But is the "average" representative?
How about the manufacturer's instruction book? GE and: PH = Eeriod Hours (one year - 8760 hours)
publication GER-3620 "Gas Turbine Operating and Main- FOH = Eorced Qutage Hours
tenance Instructions" estimates 12 eight-hour shifts (or as little MOH = (unplanned) Maintenance Qutage Hours
as 96 clock/period hours) for the M57001 combustion POH = Banned Qutage Hours (scheduled
inspection. The data indicate that this is reasonably well in advance)
demonstrated by the continuous duty units where the need and
maintenance intensity are high, where three-shift maintenance Sometimes the "availability" label is applied to a more
is often employed and where a "replace-then-repair" parts limited measurement, one that removes scheduled outage
correction technique is applied. hours or some other element. These situations have been
Continuous 1/4 \
Baseload
Cycling
Peaking
Standby
10,000 8000 6000 4000 2000 0 100 200 300 400 500 600
Data: SPS-ORAP Fired Hours Maintenance Hours
addressed under the "Running Reliability" measurements MOH . (unplanned) Maintenance Qutage Hours
section. And when "Availability" becomes concerned with POH . Planned Qutage Hours (scheduled
capacity levels or deratings or plant-level ratings (as it should well in advance)
with multi-shaft combined cycle units) it belongs to the AOH . Administrative Qutage Hours
"Equivalent Availability" measurements section. (non-chargeable hours)
It should also be pointed out that while Availability is an Fig. 7 traces the average annual Availability performance of
excellent measure for high usage machines it is a relatively the domestic (USA) M570015 participating in the SPS-ORAP
poor measure to be applied to low usage machines. In periods data system. Appendix C includes a generic sample of an
of low equipment need there is little incentive to accomplish Availability warranty statement with qualifying terms.
scheduled or even essential maintenance in an expeditious
manner. The inevitable stretch of outage time accrues
unfavorably to the measurement. If the service application is EQUIVALENT AVAILABILITY
low usage peaking service, it is advisable to consider a more
appropriate Running Reliability guarantee along the lines of the When the term "Equivalent" is applied to Availability or
"European" formula (10) or the Peaking Reliability Index" (17) Reliability it could mean several things. Under IEEE Std 762-
or perhaps just a Starting Reliability guarantee. 1987 and NERC GADS it extends the concept of availability or
reliability to account for varying capacity levels and in effect
The structuring of Availability warranties is similar to the becomes a measure of energy availability. This is the context
structuring of Running Reliability warranties. For both, the advocated by this author. In other uses, the term "equivalent"
focus is on the management of outage time; but for is sometimes associated with an approximation type
Availability there must also be some control over the measurement that may have nothing to do with capacity.
conduct of planned maintenance. And, in recognition of the Sometimes, the term "equivalent" might be used to distinguish
fact that there will be non-chargeable outage time, the the subsystem level or component level from the full system
warranty version of the availability formula is preferably generation level. For example, the reliability performance of a
written as follows: problematic limit switch might be described in terms of its
Equivalent Forced Outage Rate (EFOR) which was deduced
AH from its MTTR divided by its (MTTR + MTBF). This paper,
Warranted Availability (20) with its focus on warranty conditions, will look at three types
PH - AOH
(or levels) of system Equivalent Availability measurements
where: Available Hours (AH) also equals which increasingly accommodate the capacity element.
PH - FOH - MOH - POH - AOH
EaulyaieniAyailabilitijEAL-seyell "Block Method"
and: PH . Period Hours (one year - 8760 hours) The SPS-ORAP system has for many years been
FOR =forced Qutage Hours measuring the "Equivalent Availability" of combined cycle
EAF -
available hours - equiv. derated hours (21) Equivalent Availability - Level 2 "Proportional Block Derating"
period hours
A second example illustrates the "Proportional" derafing
where: method which goes beyond the previous "Block Method" by
considering deratings due to partial equipment failures. If
Available Hours (AH) = PH - FOH - MOH - POH another gas turbine generator in the same four-unit combined
cycle plant had a generator rotor heating problem that
Equiv. Derated Hours (EDH) = EUDH + EPDH + ESEDH prescribed a limit on output power to 92% of its rated
10
11
10
0
80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100
TEE 1/92 Availability (Percent)
12
13
[Project/Contract Title]
[Date]
A. Starting Reliability Statement A Chargeable Starting Failure (SF) is the inability to
bring a unit through a qualifying starting attempt to the
The average Starting Reliability of the [Model/Type] gas in-service state within a specified period for failure
turbine-generator units furnished under this contract is reasons chargeable to the warranty. Repeated failures
guaranteed to be not less than [96.7%] over the warranty within the specified starting period are to be counted as
measurement period as measured in accordance with the a single starting failure.
definitions and concepts of ANSI/IEEE Std.762-1957. The
warranty measurement period for each machine shall 2. On an annual basis or at each accumulation of 500
commence on the date of first commercial operation and qualifying start attempts (whichever is greater), the
expire [three years) from that date. Starting Reliability shall be calculated collectively as a
B. taa n e y Warranty Context single average measurement of all of the contract units
that are within the warranty measurement period. If the
1. The ANSI/IEEE Std.762-1987 provides definitions and a calculated average Starting Reliability falls below the
formula for Starting Reliability that allow for the fact that guarantee level, it shall be remedied in accordance with
not all failures-to-start or incomplete start attempts are the terms set forth [in the Commercial section].
chargeable to equipment failure or to the warranty.
Starting Reliability is to be measured by the IEEE formula
as follows: 3. A rigorous and explicit operating log shall be
maintained from which the starting reliability
measurement is to be determined. The log shall be
Starting Reliability = SS periodically reviewed and jointly certified with a
SS + SF [Supplier] technical representative.
Where:
SS = Chargeable Starting Successes 4. Test Starts and failures to start from equipment not
SF = Chargeable Starting Failures furnished under this contract by [Supplier] shall not be
counted as start attempts, failures or successes.
And:
5. As a general assurance of readiness; if a unit has not
A Qualifying Starting Attempt is the action intended to experienced a successful start during the prior thirty (30)
bring a unit from shutdown to the in-service state under days, then the start attempt shall be considered as a
conditions that qualify for inclusion in the warranty. non-warranty "test start" and shall not be counted.
Repeated initiations of the starting sequence within the
allowable specified starting time period or without 6. Procedural errors that do not constitute equipment failure
accomplishing corrective repairs are counted as a single involving repair shall not be counted as failures-to-start.
attempt.
7. The units shall be operated within the design conditions.
A Chargeable Starting Success (SS) is the occurrence of specified in the contract and maintained in accordance
bringing a unit through a qualifying starting attempt to the with [Supplier] recommended procedures with particular
in-service state within a specified period, as evidenced by attention to maintenance inspection intervals and
maintained closure of the generator breaker to the system. preventative maintenance activities.
14
Downloaded From: https://proceedings.asmedigitalcollection.asme.org/ on 07/12/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use
APPENDIX B
A. [Running Reliability Statement determined. The log shall clearly identify the cause and
the amount of waiting time and/or idle maintenance time
Running Reliability shall be guaranteed in terms of the associated with each and every outage event and be
ratio of actual available hours to planned available hours. The periodically reviewed and jointly certified with a
Running Reliability for the gas turbine-generator units [Supplier] technical representative.
furnished under this contract is guaranteed to average not less
than [97.2%] over the warranty measurement period. The 3. With [Supplier] assistance and concurrence, the
measurement period shall commence on successful equipment operator shall have a documented
completion of the two-week reliability readiness test. It shall maintenance program which covers scheduled
expire [two years] after the date of first commercial operation. maintenance plans, a work schedule agreement and
well-planned replacement parts support.
B. Running Reliability Warranty Context 4. The unit shall be operated and maintained in
accordance with [Supplier] recommended procedures
1. In recognition of the fact that there will be non- with particular attention to maintenance inspection
chargeable outage time, the warranty version of the intervals and preventative maintenance activities.
running reliability formula shall be as follows:
5. A two-week (minimum) reliability demonstration period
AH including no less than 5 start-stop cycles, 50 fired hours
Running Reliability
PH - POH - AOH and mutually acceptable results shall precede the
Running Reliability warranty measurement period.
where: Available Hours (AH) also equals
PH-F0H-MOH-POH-AOH 6. For purposes of the warranty measurement; inspections,
maintenance and repair shall be gauged on a high
and PH = Eeriod Hours priority, high need basis. To achieve this, waiting time
(usually one year - 8760 hours) and inactive maintenance time in excess of four hours
FOH = forced Qutage Hours per outage event shall be considered as Administrative
MOH = (unplanned) Maintenance Qutage Hours Outage Hours (AOH). As such, they shall have "stop-
POH Planned Qutage Hours the-clock" treatment and effectively not be counted as
(scheduled well in advance) outage hours, derated hours or included in the period
AOH = Administrative Qutage Hours hours base.
(non-chargeable)
7 Outage hours associated with the [Supplier] furnished
and: The above terms (except AOH) are more fully equipment but not directly chargeable to equipment
conceptualized and defined by ANSI/IEEE failure shall be considered as Administrative Outage
Std 762-1987 Hours (AOH).
2. A rigorous and explicit operating log shall be maintained 8 Operator shall operate the gas turbine unit within the
from which the Running Reliability measurement is to be design conditions specified in the contract.
15
[Project/Contract Title]
[Date]
A. Availability m warranty measurement period. If the calculated average
Availability Factor falls below the guarantee level, it shall
Availability shall be guaranteed in terms of the Availability be remedied in accordance with the terms set forth in the
Factor as described in the definitions and concepts of [Commercial] agreements.
ANSI/IEEE Std 762-1987. The average Availability Factor for
the [ff/model] gas turbines generator sets furnished under this 4. With [Supplier] assistance and concurrence, the
contract is guaranteed to average not less than [95]% over the equipment operator shall have a documented main-
warranty measurement period. The measurement period shall tenance program which covers scheduled maintenance
commence on successful completion of the two-week reliability plans, a work schedule agreement and well-planned
readiness test. It shall expire [three] years after the date of replacement parts support.
first commercial operation.
5. The unit shall be operated and maintained in
accordance with [Supplier] recommended procedures
B. Availability Warranty Context with particular attention to maintenance inspection
intervals and preventative maintenance activities.
1. In recognition of the fact that there will be non-
chargeable outage time, the warranty version of the 6. A two-week (minimum) reliability demonstration period
availability formula shall be as follows: including no less than 5 start-stop cycles, 50 fired hours
and mutually acceptable results shall precede the
Warranted Availability Factor -
AH availability warranty measurement period.
PH - AOH
7. For purposes of the warranty measurement;
where Available Hours (AH) also equals inspections, maintenance and repair shall be gauged on
PH-F0H-MOH-POI-AOH a high priority, high need basis. To achieve this, waiting
time and inactive maintenance time in excess of four
and: hours per outage event shall be considered as
PH = Period Hours Administrative Outage Hours (AOH). As such, they
(usually one year - 8760 hours) shall have "stop-the-clock" treatment and effectively not
FOH = forced Outage Hours be counted as outage hours, derated hours or included
MOH = (unplanned) Maintenance Qutage Hours in the period hours base.
POH = Elanned Outage Hours
(scheduled well in advance) 8. Outage hours associated with the [Supplier] Furnished
AOH = Administrative Outage Hours equipment but not directly chargeable to equipment
(non-chargeable) failure shall be considered as Administrative Outage
Hours (AOH).
2. A rigorous and explicit operating log shall be maintained
from which the Availability measurement is to be 9. Planned outage inspections shall be performed on a
determined. The log shall clearly identify the cause and "replace then repair" basis with all needed replacement
the amount of waiting time and/or idle maintenance time parts on hand at the start of the inspection. NDE
associated with each and every outage event and be inspections, repairs and cleaning up of removed
periodically reviewed and jointly certified with a components is to be done separately from the
[Supplier] technical representative. outage/inspection activities.
3. On an annual basis the Availability Factor shall be 10. Operator shall operate the gas turbine unit within the
calculated collectively as a single average measurement design conditions specified in the contract.
of all the contract units that are within the availability
16
Downloaded From: https://proceedings.asmedigitalcollection.asme.org/ on 07/12/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use
APPENDIX D
17
18