Road Map chedule for ILIN-PJ TIME DURATION June 2010 to May 2012

S.NO STEPS ITEM Action Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11
stage 1: (A) After receving the offer letter from MIDC the following jobs - Prioritze by ILIN-PJ
pre-requirement A-1 1. Soil conditioning test and Hydraulic test ( duration 10 days) AGENCY
2. Soil test result and approval ( duration 10 days) CERT.LAB

A-2 Approval of industrial license from SIA ( ministy of industries - cental Govt) SIA
Apply in the prescribed form IEM ( 6 sets )

Stage 2: (B) After receving the Allotment letter from MIDC the following jobs- Prioritze by ILIN-PJ
Basic B-1 Clearance from director of industry for setting up industrial unit of Idemitsu under DIA
a. Application for the registration of the project ( project details to be submiited)
DIA
b. Copies of allotment order/letter and possession receipt with measurement plan MIDC

stage 3: ( C ) Building plan approval MIDC


pre-construction C-1 4 copies of propsed building plan ( by licensed surveyor, structural engineeror , ARICHTECT
requirement registered architect) location map, land layout plan, service plan, details drawing of
proposed factory building 4 sets and drainage connection 3 sets.
C-2 Application for Drainage plan approval MIDC
C-3 Application for drainage connection approval MIDC
C-4 Application for excise department approval EXCISE
C-5 Department of explosive approval ( from petroleum/chemical industries) under CCE
a. Application for the storage of fuel for DG set and boiler
b. Application for setting up packaged boiler 2 units
c. Application for setting up emergency DG set approval
d. Furnish MSDS for raw meterials and finsihed products (if required)
C-6 Provisional NOC from Maharashtra Pollution control board's air and water consent MPCB
C-7 Department of Industrial safety health approval DISH
C-8 food and drug administartion ( to be confirm with authority , it is requireed or not)F&D
C-9 Provisional NOC from fire dept, (CFO & FA , MiDC Andheri, mumbai 400093) CFO & FA
check list for getting provisional NOC from fire department
a. layout plan including floorwise area calculationsheet, undergorund & overhead tanks,
raw and finished goods storage area
b. Elevation plan with fire prevention and protection system, fire extinguishers, buckets
c. Fire hydrant systems, Sprinklers, detection system, alarm system
d. List of raw materials and finished products with their quantity for storage.

(D) Application for Mega project : STATE GOVT

(E) Construction start up


stage 4: E-1 Application for temorary water connection MIDC
construction E-2 Application for permenant water connection MIDC
startup E-3 Application for temorary power/electricity connection MSEB
E-4 Application for permenant power/electricity connection MSEB
E-5 Application to labour department for starting the construction FA/LABOUR
E-6 Commencement of construction approval (land filling, leveling etc) MIDC
E-7 level of permission for structure building etc MIDC

Stage 5 : (F) BUILDING COMPLETION CERTIFICATE (BCC) AND DCC APPROVAL MIDC
construction F-1 completion certificate from arichtect or licensed surveyor for both BCC and DCC CONTRACTOR
completion F-2 structural stability certificate by structural engineer CONTRACTOR
F-3 factory inpector's approval and factory license FACTORY
F-4 Food and drugs authority approval ( if applicable) F&D
F-5 Application for boiler inspection and certificate approval DDB
F-6 Explosive department approval EXPLOSIVE
F-7 consent/NOC from M.P.C.B for air and water MPCB
F-8 Final NOC from fire department CFO & FA
F-9 Application for tree plant ation certificate ( 1 tree for 100 SQM) MIDC
F-9 Applicationfor the employment contract worker / Labour welfare and clearances FA/LABOUR
F-10 Application for the completion of construction of manufacturing Facilitties. DIA

Stage 6: (G) plant production startup


plant startup G-1 Application for the start date of commercial production DIA
G-2 application for the registration under employee state insurance act ESI
G-3 Application for the registration under providend fund act PF
G-4 Application for under standard weights and measure acts Std & Wt
G-5 Application for registration under excise act excise
G-6 Application for registartion under sales act and central and local VAT-sales
G-7 Application for registration under service act service act
G-8 Application of updation of importer and exporter code/ no bounding of tanks customs
May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12
APPLICATION SET UP FOR GETTING VARIOUS APPROVAL FROM MIDC AND OTHER DEPARTMENT for ILIN-PJ
S.NO STEPS ITEM Action
stage 1: (A) After receving the offer letter from MIDC the following jobs - Prioritze by ILIN-PJ
pre-requirement A-1 1. Soil conditioning test and Hydraulic test ( duration 10 days) AGENCY
2. Soil test result and approval ( duration 10 days) CERT.LAB
A-2 Approval of industrial license from SIA ( ministy of industries - cental Govt) SIA
Apply in the prescribed form IEM ( 6 sets )

Stage 2: (B) After receving the Allotment letter from MIDC the following jobs- Prioritze by ILIN-PJ
Basic B-1 Clearance from director of industry for setting up industrial unit of Idemitsu under DIA
a. Application for the registration of the project ( project details to be submiited)
DIA
b. Copies of allotment order/letter and possession receipt with measurement plan MIDC

stage 3: ( C ) Building plan approval MIDC


pre-construction C-1 4 copies of propsed building plan ( by licensed surveyor, structural engineeror , ARICHTECT
requirement registered architect) location map, land layout plan, service plan, details drawing of
proposed factory building 4 sets and drainage connection 3 sets.
C-2 Application for Drainage plan approval MIDC
C-3 Application for drainage connection approval MIDC
C-4 Application for excise department approval EXCISE
C-5 Department of explosive approval ( from petroleum/chemical industries) under CCE
a. Application for the storage of fuel for DG set and boiler
b. Application for setting up packaged boiler 2 units
c. Application for setting up emergency DG set approval
d. Furnish MSDS for raw meterials and finsihed products (if required)
C-6 Provisional NOC from Maharashtra Pollution control board's air and water consent MPCB
C-7 Department of Industrial safety health approval DISH
C-8 food and drug administartion ( to be confirm with authority , it is requireed or not)F&D
C-9 Provisional NOC from fire dept, (CFO & FA , MiDC Andheri, mumbai 400093) CFO & FA
check list for getting provisional NOC from fire department
a. layout plan including floorwise area calculationsheet, undergorund & overhead tanks,
raw and finished goods storage area
b. Elevation plan with fire prevention and protection system, fire extinguishers, buckets
c. Fire hydrant systems, Sprinklers, detection system, alarm system
d. List of raw materials and finished products with their quantity for storage.

(D) Application for Mega project : STATE GOVT

(E) Construction start up


stage 4: E-1 Application for temorary water connection MIDC
construction E-2 Application for permenant water connection MIDC
startup E-3 Application for temorary power/electricity connection MSEB
E-4 Application for permenant power/electricity connection MSEB
E-5 Application to labour department for starting the construction FA/LABOUR
E-6 Commencement of construction approval (land filling, leveling etc) MIDC
E-7 level of permission for structure building etc MIDC

Stage 5 : (F) BUILDING COMPLETION CERTIFICATE (BCC) AND DCC APPROVAL MIDC
construction F-1 completion certificate from arichtect or licensed surveyor for both BCC and DCC CONTRACTOR
completion F-2 structural stability certificate by structural engineer CONTRACTOR
F-3 factory inpector's approval and factory license FACTORY
F-4 Food and drugs authority approval ( if applicable) F&D
F-5 Application for boiler inspection and certificate approval DDB
F-6 Explosive department approval EXPLOSIVE
F-7 consent/NOC from M.P.C.B for air and water MPCB
F-8 Final NOC from fire department CFO & FA
F-9 Application for tree plant ation certificate ( 1 tree for 100 SQM) MIDC
F-9 Applicationfor the employment contract worker / Labour welfare and clearances FA/LABOUR
F-10 Application for the completion of construction of manufacturing Facilitties. DIA

APPLICATION SET UP FOR GETTING VARIOUS APPROVAL FROM MIDC AND OTHER DEPARTMENT for ILIN-PJ
S.NO STEPS ITEM Action
Stage 6: ( G ) plant production startup
plant startup G-1 Application for the start date of commercial production DIA
G-2 application for the registration under employee state insurance act ESI
G-3 Application for the registration under providend fund act PF
G-4 Application for under standard weights and measure acts Std & Wt
G-5 Application for registration under excise act EXCISE
G-6 Application for registartion under sales act and central and local VAT-sales
G-7 Application for registration under service act SERVICE ACT
G-8 Application of updation of importer and exporter code/ no bounding of tanks CUSTOMS

ABBREVIATION USED
SIA: SECRETARIATE FOR INDUSTRIAL APPROVAL ( MINISTRY OF INDUSTRIES)
DIA: DIRECTORATE OF INDUSTRIAL APPROVAL
MIDC: MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION
MPCB: MAHARASHTRA POLLUTION CONTROL BOARD
MSEB: MAHARASHTRA STATE ELECTRICITY BOARD
CCE: CHIEF CONTROLLER OF EXPLOSIVE
CFO & FA: CHIEF FIRE OFFICER AND FIRE ADVISOR
DISH : DEPARTMENT OF INDUSTRIAL SAFETY AND HEALTH
ESI: EMPLOYEE STATE INSURANCE
PF: PROVIDENT FUND
Std & wt STANDARD WEIGHT AND MEASURES ACT
F&D: FOOD AND DRUG ADMINISTRATION
DDB: DEPUTY DIRECTOR OF BOILER AND SMOKE NUISANCE OF THE AREA