S10 Pgina 1

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

OBRAS PROVISIONALES 16,290.41

CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m u 1.00 937.20 937.20


ALMACEN GRAL. DE LA OBRA Y GUARDIANIA m2 84.00 94.49 7,937.16
CAMPAMENTO PROVISIONAL DE LA OBRA glb 1.00 7,416.05 7,416.05
CAPTACIONES DE AYLLUCANCHA, AYAGNIOG Y HUIDCO 29,979.94

TRABAJOS PRELIMINARES 4,096.25

LIMPIEZA DE TERRENO MANUAL m2 43.04 2.03 87.37


TRAZO Y REPLANTEO m2 43.04 2.72 117.07
DEMOLICION DE ESTRUCTURAS EXISTENTES (03 CAPTACIONES) m3 7.93 490.77 3,891.81
MOVIMIENTO DE TIERRAS 1,682.30

EXCAVACION DE ESTRUCTURAS m3 23.01 36.00 828.36


NIVELACION Y COMPACTACION DEL TERRENO PREVIO AL PISO m2 7.40 2.50 18.50
ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 38.66 21.61 835.44
OBRAS DE CONCRETO SIMPLE 1,640.63

SOLADO E=4" m2 11.94 30.72 366.80


CONCRETO f'c=175 kg/cm2 m3 1.82 427.05 777.23

ENCOFRADO Y DESENCOFRADO NORMAL m2 10.29 48.26 496.60


OBRAS DE CONCRETO ARMADO 7,557.45

LOSA DE FONDO 765.88

CONCRETO f'c=210 kg/cm2 PARA LOSAS DE FONDO PISO m3 1.30 420.64 546.83

ACERO fy=4200 kg/cm2 GRADO 60 kg 43.12 5.08 219.05

MUROS 6,147.68

CONCRETO f'c=210 kg/cm2 PARA MUROS REFORZADOS m3 6.04 416.89 2,518.02

ENCOFRADO Y DESENCOFRADO NORMAL m2 66.72 48.26 3,219.91

ACERO fy=4200 kg/cm2 GRADO 60 kg 80.66 5.08 409.75

TECHOS 643.89

CONCRETO f'c=210 kg/cm2 m3 0.59 415.07 244.89

ENCOFRADO Y DESENCOFRADO NORMAL m2 7.71 48.26 372.08

ACERO fy=4200 kg/cm2 GRADO 60 kg 5.30 5.08 26.92

REVOQUES Y ENLUCIDOS 1,601.10

TARRAJEO CON IMPERMEABILIZANTES EN INTERIORES CAPTACION m2 19.80 36.48 722.30

TARRAJEO CON IMPERMEABILIZANTES EN EXTERIORES CAPTACION m2 24.09 36.48 878.80

TUBERIAS Y ACCESORIOS 2,079.93

SUMINISTRO Y COLOCACION DE CANASTILLA DE BRONCE 90mm u 2.00 82.83 165.66

SUMINISTRO Y COLOCACION DE CANASTILLA DE BRONCE 75mm u 1.00 70.62 70.62

SUMINISTRO Y COLOCACION DE TUBERIA PVC SAP D=63mm m 2.00 6.57 13.14

SUMINISTRO Y COLOCACION DE TUBERIA PVC SAP D=4" m 4.00 10.03 40.12

SUMINISTRO Y COLOCACION DE TUBERIA PVC SAP D=2" m 6.60 6.95 45.87


SUMINISTRO Y COLOCACION DE TUBERIA PVC SAP D=1.5" m 2.00 5.47 10.94

SUMINISTRO Y COLOCACION DE VALVULA COMPUERTA DE BRONCE DE 63mm u 2.00 122.68 245.36

SUMINISTRO Y COLOCACION DE VALVULA COMPUERTA DE BRONCE DE 4" u 2.00 163.66 327.32

SUMINISTRO Y COLOCACION DE VALVULA COMPUERTA DE BRONCE DE 2" u 1.00 108.68 108.68

SUMINISTRO Y COLOCACION DE VALVULA COMPUERTA DE BRONCE DE 1.5" u 1.00 99.68 99.68

SUMINISTRO Y COLOCACION DE REDUCCION PVC SAP DE 90mm A 63mm u 2.00 35.46 70.92

SUMINISTRO Y COLOCACION DE REDUCCION PVC SAP DE 6" A 4" u 2.00 52.22 104.44

SUMINISTRO Y COLOCACION DE REDUCCION PVC SAP DE 4" A 2" u 1.00 28.21 28.21

SUMINISTRO Y COLOCACION DE REDUCCION PVC SAP DE 3" A 1.5" u 1.00 28.21 28.21

SUMINISTRO Y COLOCACION DE UNION UNIVERSAL DE 63mm u 2.00 39.65 79.30

SUMINISTRO Y COLOCACION DE UNION UNIVERSAL DE 4" u 2.00 59.07 118.14

SUMINISTRO Y COLOCACION DE UNION UNIVERSAL DE 2" u 1.00 36.65 36.65

SUMINISTRO Y COLOCACION DE UNION UNIVERSAL DE 1.5" u 1.00 31.65 31.65

SUMINISTRO Y COLOCACION DE TEE PVC SAP DE 4" u 2.00 45.04 90.08

SUMINISTRO Y COLOCACION DE TEE PVC SAP DE 2" u 1.00 25.74 25.74

SUMINISTRO Y COLOCACION DE CODO PVC SAP DE 90 DE 4" u 4.00 34.48 137.92

SUMINISTRO Y COLOCACION DE CODO PVC SAP DE 90 DE 2" u 8.00 25.16 201.28

JUNTAS 212.78
S10 Pgina 2

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

JUNTAS CON WATERSTOP m 5.70 37.33 212.78


CERCO PERIMETRICO 3,278.45

TRAZO Y REPLANTEO m 51.00 2.14 109.14


EXCAVACIN DE ZANJAS HMX= 0.40 M m3 1.89 27.01 51.05
ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 2.36 21.61 51.00
CONCRETO PARA DADOS DE POSTES (CONCRETO 1:10 +30% PG) m3 1.89 256.16 484.14
POSTES DE TUBO DE FIERRO NEGRO 2 1/2" u 42.00 33.77 1,418.34

CERCO DE ALAMBRE DE PUAS (SUMINISTRO Y COLOCACION ALAMBRE, m 153.00 5.26 804.78


HILADAS DE ALAMBRE @ 0.30M C/U)
PUERTA SIMPLE DE INGRESO u 3.00 120.00 360.00
VARIOS 1,242.10

TAPA METALICA PARA CAPTACION DE 60cm x 60cm (CAMARA HUMEDA) u 3.00 150.00 450.00
TAPA METALICA PARA CAPTACION DE 50cm x 50cm (CAMARA SECA) u 3.00 140.00 420.00
ENSAYO ROTURA TESTIGOS DE CONCRETO u 6.00 20.00 120.00
DISEO DE MEZCLA F'C=210 KG/CM2 glb 1.00 252.10 252.10
GRAVAS 631.07

GRAVA CLASIFICADA m3 4.32 146.08 631.07

FLETE EN CAPTACIONES CON ACEMILA 5,957.88

FLETE CON ACEMILA DELALMACEN A LA CAPTACION glb 1.00 5,957.88 5,957.88

RESERVORIO CASETA DE VALVULAS 134,550.54

OBRAS PROVISIONALES 2,716.80

CASETA ADICIONAL P/GUARDIANIA Y/O DEPOSITO m2 30.00 90.56 2,716.80

OBRAS PRELIMINARES 384.75

LIMPIEZA DE TERRENO MANUAL m2 81.00 2.03 164.43

TRAZO Y REPLANTEO PRELIMINAR m2 81.00 2.72 220.32

MOVIMIENTO DE TIERRAS 2,321.12

EXCAVACION DE PLATAFORMA EN TIERRA (LAMPA Y PICO) m3 33.45 42.38 1,417.61

ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 41.81 21.61 903.51

CONCRETO SIMPLE 2,488.32

SOLADO E=4" m2 81.00 30.72 2,488.32

CONCRETO ARMADO 69,851.51

LOSA DE FONDO 18,969.47

CONCRETO f'c=210 kg/cm2 PARA LOSAS DE FONDO PISO m3 35.00 420.64 14,722.40

ENCOFRADO Y DESENCOFRADO PARA LOSAS DE FONDO PISO m2 7.93 35.38 280.56

ACERO fy=4200 kg/cm2 GRADO 60 kg 780.81 5.08 3,966.51

MUROS REFORZADOS 34,425.20

CONCRETO f'c=210 kg/cm2 PARA MUROS REFORZADOS m3 23.38 416.89 9,746.89

ENCOFRADO Y DESENCOFRADO PARA MUROS CILINDRICOS m2 187.15 79.74 14,923.34

ACERO fy=4200 kg/cm2 GRADO 60 kg 1,920.27 5.08 9,754.97

VIGAS DE CONFINAMIENTO 4,647.20

CONCRETO f'c=210 kg/cm2 PARA VIGAS DE CONFINAMIENTO m3 3.09 426.29 1,317.24

ENCOFRADO Y DESENCOFRADO PARA VIGAS CILINDRICAS m2 19.51 79.74 1,555.73

ACERO fy=4200 kg/cm2 GRADO 60 kg 352.03 5.04 1,774.23

TECHO 11,809.64

CONCRETO f'c=210 kg/cm2 m3 7.97 430.72 3,432.84

ENCOFRADO Y DESENCOFRADO PARA CUPULA ESFERICA m2 53.11 91.04 4,835.13

ACERO fy=4200 kg/cm2 GRADO 60 kg 697.18 5.08 3,541.67

CASETA DE VALVULA 11,619.10

TRABAJOSPRELIMINARES 43.28

TRAZO, NIVEL Y REPLANTEO m2 15.91 2.72 43.28

MOVIMIENTO DE TIERRAS 70.41

EXCAVACION DE ZANJAS Y/O ZAPATAS HMAX=1.00M m3 5.45 10.60 57.77

NIVELACION INTERIOR APISONADO MANUAL m2 5.45 2.32 12.64

CONCRETO SIMPLE 1,396.45

SOLADOS CONCRETO f'c=100 kg/cm2 h=2" m2 0.20 16.29 3.26

CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA m3 1.94 221.33 429.38
S10 Pgina 3

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS m3 1.25 250.19 312.74

ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO HASTA 0.30 m2 5.54 40.73 225.64
m
FALSO PISO DE 4" DE CONCRETO 1:10 m2 15.91 26.74 425.43
CONCRETO ARMADO 6,443.25

CONCRETO f'c= 210 kg/cm2 EN ZAPATAS m3 1.03 411.77 424.12


ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS kg 2.55 10.91 27.82
CONCRETO f'c=210 kg/cm2 PARA S/C REFORZADOS m3 0.76 413.03 313.90
ENCOFRADO Y DESENCOFRADO NORMAL PARA S/C REFORZADO m2 16.80 40.73 684.26
ACERO ESTRUCTURAL TRABAJADO PARA S/C REFORZADO kg 11.41 5.08 57.96
CONCRETO f'c=210 kg/cm2 PARA COLUMNAS m3 0.63 429.25 270.43
ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 10.56 50.21 530.22
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 137.37 5.29 726.69
CONCRETO f'c=210 kg/cm2 PARA VIGAS Y DINTELES m3 1.34 432.06 578.96
ENCOFRADO Y DESENCOFRADO PARA VIGAS RECTAS Y DINTELES m2 12.00 62.24 746.88
ACERO ESTRUCTURAL TRABAJADO PARA VIGAS Y DINTELES kg 112.93 5.29 597.40

CONCRETO f'c=210 kg/cm2 PARA LOSAS ALIGERADAS m3 1.02 422.75 431.21


ENCOFRADO Y DESENCOFRADO PARA LOSAS ALIGERADAS m2 11.70 53.03 620.45

ACERO ESTRUCTURAL TRABAJADO PARA LOSAS ALIGERADAS kg 53.64 4.99 267.66

LADRILLO HUECO DE ARCILLA h=12 cm PARA TECHO ALIGERADO u 91.83 1.80 165.29

ALBAILERIA 895.56

MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-CAL-ARENA m2 13.60 65.85 895.56

PISOS Y PAVIMENTOS 819.32

PISO DE CEMENTO PULIDO E=2" f'c 140 kg/cm2 - BRUADO m2 7.54 28.50 214.89

VEREDA DE CONCREO F'C=140KG/CM2 E=10CM, INC. ENCOFRADO m2 11.40 53.02 604.43

CARPINTERIA METALICA 1,237.43

SUMINISTRO Y COLOCACION DE VENTANA DE FIERRO SEGUN DISEO m2 5.64 148.81 839.29

SUMINISTRO Y COLOCACION DE PUERTA METALICA SEGUN DISEO m2 1.98 201.08 398.14

COBERTURAS 713.40

COBERTURA CON LADRILLOPASTELERO EN CASETA DE VALVULAS m2 15.91 44.84 713.40

REVOQUES, ENLUCIDOS Y MOLDURAS 13,848.27

TARRAJEO EN EXTERIORIORES LOSA CUBIERTA - RESERVORIO m2 59.45 27.45 1,631.90

TARRAJEO EN EXTERIORES - MURO RESERVORIO m2 96.50 34.95 3,372.68

TARRAJEO CON IMPERMEABILIZANTE EN MUROS DE RESERVORIO APOYADO m2 90.65 40.51 3,672.23

LOSA DE FONDO TARRAJEO CON IMPERMEABILIZANTE m2 47.79 33.41 1,596.66

TARRAJEO CON IMPERMEABILIZANTE LOSA DE CUBIERTA m2 59.45 40.51 2,408.32

TARRAJEO EN INTERIORES - CASETA DE VALVULAS m2 13.60 27.06 368.02

TARRAJEO EN EXTERIORES - CASETA DE VALVULAS m2 17.10 27.45 469.40

CIELORRASOS C : A - CASETA DE VALVULAS m2 11.02 29.86 329.06


PINTURA 2,302.89

PINTURA EN MUROS INT. CASETA C/LATEX m2 17.10 10.00 171.00

PINTURA VILNILICA EN EXTERIORES - RESERVORIO Y CASETA m2 185.06 11.52 2,131.89

TUBERIAS Y ACCESORIOS 4,658.07

TUBERIAS Y ACCESORIOS SISTEMA DE UDUCCION glb 1.00 1,244.89 1,244.89

TUBERIAS Y ACCESORIOS SISTEMA DE REBOSE Y LIMPIA glb 1.00 2,722.62 2,722.62

TUBERIAS Y ACCESORIOS SISTEMA DE IMPULSION glb 1.00 690.56 690.56

VARIOS 8,524.71

CURADO DE CONCRETO m2 184.06 2.81 517.21

JUNTA WATER STOP 8" m 26.08 36.80 959.74

TAPA METALICA PARA RESERVORIO u 1.00 336.13 336.13

MEJORAMIENTO DE RESERVORIO EXISTENTE glb 1.00 3,980.00 3,980.00

TAPA METALICA PARA EN CASETA DE VALVULAS u 1.00 210.00 210.00

ESCALERA TUBO FIERRO GALVANIZADO CON PARANTES DE 1 1/2" X m 4.10 113.74 466.33
PELDAOS DE 1"
DISEO DE MEZCLA glb 1.00 252.10 252.10

ENSAYO ROTURA TESTIGOS DE CONCRETO u 10.00 20.00 200.00

PRUEBA HIDRAULICA Y DESINFECCION EN RESERVORIO m3 160.00 10.02 1,603.20


S10 Pgina 4

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

FLETE RESERVORIO 15,835.00

FLETE CON ACEMILA AL RESERVORIO glb 1.00 15,835.00 15,835.00


CAMARAS ROMPE PRESION, REUNION Y DISTRIBUCION 9,155.94

OBRAS PRELIMINARES 13.75

TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO m2 5.85 2.35 13.75


MOVIMIENTO DE TIERRAS 182.58

EXCAVACIN MANUAL m3 2.93 35.32 103.49


ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 3.66 21.61 79.09
CONCRETO ARMADO 3,718.84

CONCRETO f'c=175 kg/cm2 m3 4.14 427.05 1,767.99


ENCOFRADO Y DESENCOFRADO NORMAL m2 19.95 48.26 962.79
ACERO fy=4200 kg/cm2 GRADO 60 kg 194.50 5.08 988.06
REVOQUES Y ENLUCIDOS 1,559.15

TARRAJEO FROTACHADO MURO EXTERIOR m2 19.80 27.45 543.51


TARRAJEO CON IMPERMEABILIZANTE EN CAJAS m2 32.10 31.64 1,015.64
TUBERIAS Y ACCESORIOS 2,931.62

TUBERIA DE PVC SAL 4" m 18.40 17.89 329.18


TUBERIA PVC SAL D=2", LIMPIA, REBOSE, VENT. m 4.60 7.50 34.50

SUMINISTRO Y COLOCACIN DE CANASTILLAS glb 1.00 299.81 299.81

ACCESORIOS DE TUBERIA PVC SAP 75mm glb 1.00 180.96 180.96

ACCESORIOS DE TUBERIA PVC SAP 63mm glb 1.00 154.05 154.05

ACCESORIOS DE TUBERIA PVC SAP 4" glb 1.00 786.22 786.22

ACCESORIOS DE TUBERIA PVC SAP 2" glb 1.00 967.33 967.33

ACCESORIOS DE TUBERIA PVC SAP 1 1/2" glb 1.00 106.87 106.87

ACCESORIOS DE TUBERIA PVC SAP 1" glb 1.00 72.70 72.70

VARIOS 750.00

TAPA METALICA 60CMX60CM EN CAMARA ROMPE PRESION u 5.00 150.00 750.00

LINEA DE CONDUCCION 190,078.62

OBRAS PRELIMINARES 4,157.37

TRAZO Y REPLANTEO LINEAL m 3,149.52 1.32 4,157.37

MOVIMIENTO DE TIERRAS 157,656.73

TIERRA COMPACTA 49,694.31

EXCAVACION DE ZANJA MANUAL HASTA H=1.00 M m 1,373.53 19.85 27,264.57

REFINE, NIVELELACION Y FONDOS TUBERIA HASTA 4" m 1,373.53 1.80 2,472.35

CAMA DE APOYO PARA TUBERIAS HASTA 4" m 1,373.53 3.75 5,150.74

RELLENO COMPACTADO ZANJAS CON MATERIAL PROPIO H=1.00M m 1,373.53 10.78 14,806.65

ROCA SUELTA 107,962.42

EXCAVACION DE ZANJA EN ROCA SUELTA CON EQUIPO HASTA H=1.00M m 1,775.99 31.56 56,050.24
REFINE, NIVELELACION Y FONDOS TUBERIA EN ROCA SUELTA HASTA 4" m 1,775.99 2.70 4,795.17

CAMA DE APOYO CON MATERIAL DE PRESTAMO PARA TUBERIAS HASTA 4" m 1,775.99 3.75 6,659.96

RELLENO COMPACTADO ZANJAS CON MATERIAL CLASIFICADO H=1.00M m 1,775.99 22.78 40,457.05

TUBERIAS 26,418.42

TUBERIA DE PVC SAP C-7.5 D=75mm m 1,437.94 6.36 9,145.30

TUBERIA DE PVC SAP C-7.5 D=63mm m 1,255.43 7.95 9,980.67

TUBERIA DE PVC SAP C-10 D=1.5" m 241.71 6.88 1,662.96

TUBERIA DE PVC SAP C-10 D=1" m 214.44 5.69 1,220.16

DOBLE PRUEBA HIDRAULICA Y DESINFECCION m 3,149.52 1.40 4,409.33

ACCESORIOS PARA TUBERIAS 1,163.50

ACCESORIOS DE TUBERIA PVC SAP 75mm glb 1.00 665.37 665.37

ACCESORIOS DE TUBERIA PVC SAP 63mm glb 1.00 396.56 396.56

ACCESORIOS DE TUBERIA PVC SAP 1 1/2" glb 1.00 70.46 70.46

ACCESORIOS DE TUBERIA PVC SAP 1" glb 1.00 31.11 31.11

FLETE L.CONDUCCION 682.60

FLETE CON ACEMILA HACIA LA LINEA DE CONDUCCION glb 1.00 682.60 682.60

RED DE DISTRIBUCION 325,015.38

OBRAS PRELIMINARES 8,945.91


S10 Pgina 5

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

TRAZO Y REPLANTEO LINEAL m 6,255.88 1.43 8,945.91


MOVIMIENTO DE TIERRAS 251,893.13

TIERRA COMPACTA 134,158.20

EXCAVACION DE ZANJA MANUAL HASTA H=1.00 M m 4,282.10 15.00 64,231.50


REFINE, NIVELELACION Y FONDOS TUBERIA HASTA 4" m 4,282.10 1.80 7,707.78
CAMA DE APOYO PARA TUBERIAS HASTA 4" m 4,282.10 3.75 16,057.88
RELLENO COMPACTADO ZANJAS CON MATERIAL PROPIO H=1.00M m 4,282.10 10.78 46,161.04
ROCA SUELTA 80,714.26

EXCAVACION DE ZANJA EN ROCA SUELTA CON EQUIPO HASTA H=1.00M m 1,461.95 28.38 41,490.14
REFINE, NIVELELACION Y FONDOS TUBERIA EN ROCA SUELTA HASTA 4" m 1,461.95 2.70 3,947.27
CAMA DE APOYO CON MATERIAL DE PRESTAMO PARA TUBERIAS HASTA 4" m 1,461.95 3.75 5,482.31
RELLENO COMPACTADO ZANJAS CON MATERIAL CLASIFICADO H=1.00M m 1,461.95 20.38 29,794.54
ROCA FIJA 37,020.67

EXCAVACION DE ZANJA EN ROCA FIJA CON EQUIPO HASTA H=1.00M m 511.83 45.50 23,288.27
REFINE, NIVELELACION Y FONDOS TUBERIA EN ROCA FIJA HASTA 4" m 511.83 2.70 1,381.94
CAMA DE APOYO CON MATERIAL DE PRESTAMO PARA TUBERIAS HASTA 4" m 511.83 3.75 1,919.36

RELLENO COMPACTADO ZANJAS CON MATERIAL CLASIFICADO H=1.00M m 511.83 20.38 10,431.10
TUBERIAS 53,992.02

TUBERIA PVC SAP C-7.5 D=90mm m 451.57 11.60 5,238.21

TUBERIA PVC SAP C-7.5 D=75mm m 435.26 6.36 2,768.25

TUBERIA PVC SAP C-7.5 D=63mm m 2,861.67 7.95 22,750.28

TUBERIA PVC SAP C-10 D=1 1/2" m 104.05 6.88 715.86

TUBERIA PVC SAP C-10 D=1" m 1,325.25 5.69 7,540.67

TUBERIA PVC SAP C-10 D=3/4" m 1,078.08 5.77 6,220.52

DOBLE PRUEBA HIDRAULICA Y DESINFECCION m 6,255.88 1.40 8,758.23

ACCESORIOS PARA TUBERIAS 2,614.71

ACCESORIOS DE TUBERIA PVC SAP 90mm glb 1.00 577.05 577.05

ACCESORIOS DE TUBERIA PVC SAP 75mm glb 1.00 379.74 379.74

ACCESORIOS DE TUBERIA PVC SAP 63mm glb 1.00 1,395.68 1,395.68

ACCESORIOS DE TUBERIA PVC SAP 1" glb 1.00 144.00 144.00

ACCESORIOS DE TUBERIA PVC SAP 1 1/2" glb 1.00 21.30 21.30

ACCESORIOS DE TUBERIA PVC SAP 3/4" glb 1.00 96.94 96.94

VARIOS 7,569.61

CINTA SEALADORA DE SEGURIDAD m 6,255.88 1.21 7,569.61

CAMARA DE VALVULAS REGULADORAS DE PRESION 32,030.25

TRABAJOS PRELIMINARES 42.16

TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO m2 17.94 2.35 42.16

MOVIMIENTO DE TIERRAS 1,102.02

EXCAVACION PARA ESTRUTURAS m3 17.04 37.66 641.73

ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA (50M) m3 21.30 21.61 460.29

CONCRETO SIMPLE 935.52

SOLADO DE CONCRETO FC=100KG/CM2 m2 1.79 16.29 29.16

CONCRETO FC=140 KG/CM2 + ENCOFRADO PARA ANCLAJES DE ACCESORIOS u 28.00 32.37 906.36

CONCRETO ARMADO 8,006.36

CONCRETO FC=175 KG/CM2 PARA ESTRUCTURAS m3 6.29 427.05 2,686.14

ENCOFRADO Y DESENCOFRADO NORMAL PARA ESTRUC. m2 77.60 49.48 3,839.65

ACERO FY=4200 KG/CM2 . GRADO 60 kg 291.45 5.08 1,480.57

REVOQUES Y ENLUCIDOS 2,883.62

TARRAJEO MEZCLA 1:5 EN CAMARA DE VALVULAS m2 77.60 37.16 2,883.62

TUBERIAS Y ACCESORIOS 16,462.17

ACCESORIOS DE 90mm glb 2.00 3,493.31 6,986.62

ACCESORIOS DE 63mm glb 3.00 2,561.31 7,683.93

ACCESORIOS DE 1" glb 1.00 507.31 507.31

ACCESORIOS DE 3/4" glb 1.00 1,284.31 1,284.31

VARIOS 2,598.40

TAPA DE INSPECCION DE CAMARA u 7.00 257.68 1,803.76


S10 Pgina 6

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

ESCALERA TIPO MARINERA EN CAMARA u 7.00 113.52 794.64


CONEXIONES DOMICILIARIAS 170,251.83

OBRAS PRELIMINARES 4,135.33

TRAZO Y REPLANTEO LINEAL m 2,491.16 1.66 4,135.33


MOVIMIENTO DE TIERRAS 74,012.37

EXCAVACION DE ZANJA MANUAL HASTA H=1.00 M m 2,491.16 14.41 35,897.62


REFINE, NIVELELACION Y FONDOS TUBERIA HASTA 4" m 2,491.16 1.80 4,484.09
CAMA DE APOYO PARA TUBERIAS HASTA 4" m 2,491.16 2.72 6,775.96
RELLENO COMPACTADO ZANJAS H=1.00M m 2,491.16 10.78 26,854.70
TUBERIAS Y ACCESORIOS 58,291.76

TUBERIA PVC SAP C-10 D=1/2" m 2,491.16 5.00 12,455.80


TUBERIA PVC SAP C-10 D=4" (RECUBRIMIENTO DE TUBERIA) m 2,491.16 11.51 28,673.25
ABRAZADERA DE 90mm + VALVULA CORPORATION DE 1/2" u 40.00 41.62 1,664.80
ABRAZADERA DE 75mm + VALVULA CORPORATION DE 1/2" u 36.00 38.02 1,368.72
ABRAZADERA DE 63mm + VALVULA CORPORATION DE 1/2" u 216.00 36.84 7,957.44
ABRAZADERA DE 1" + VALVULA CORPORATION DE 1/2" u 21.00 25.57 536.97

ABRAZADERA DE 3/4" + VALVULA CORPORATION DE 1/2" u 37.00 25.44 941.28


CODO PVC SAP PARA AGUA DE 1/2" x 45 u 700.00 4.49 3,143.00

CODO PVC SAP PARA AGUA DE 1/2" x 90 u 350.00 4.43 1,550.50

VARIOS 33,812.37

CAJA PARA CONEXION DOMICILIARIA pza 350.00 85.46 29,911.00

CINTA SEALADORA DE SEGURIDAD m 3,224.27 1.21 3,901.37

FLETE 7,343.42

FLETE TERRESTRE AL ALMACEN DE OBRA glb 1.00 7,343.42 7,343.42

RED COLECTOR 544,420.09

TRABAJOS PRELIMINARES 8,058.61

TRAZO, NIVELACION Y REPALNTEO EN OBRAS DE SANEAMIENTO m 5,635.39 1.43 8,058.61

MOVIMIENTO DE TIERRAS 399,815.98

TIERRA COMPACTA 264,736.71

EXCAVACIN DE ZANJA PARA TUBERAS A=0.60 HMX=2.00M EN TERRENO m 4,160.22 30.01 124,848.20
NORMAL
EXCAVACIN DE ZANJA PARA TUBERAS PARA ALTURAS MAYORES A 2.00M EN m 122.33 36.00 4,403.88
TERRENO NORMAL (MANUAL)
REFINE, NIVELELACION DE ZANJAS TERRENO NORMAL m 4,282.55 2.31 9,892.69

CAMA DE APOYO PARA TUBERIAS TERRENO NORMAL m 4,282.55 4.84 20,727.54

RELLENO CON MARTERIAL ZARANDEADO PARA PROTECCION DE EJE CLAVE m 4,282.55 9.11 39,014.03

RELLENO COMPACTADO C/ PLANCHA COMP. H=1.50 A 2.00M m 4,160.22 14.81 61,612.86

RELLENO COMPACTADO C/ PLANCHA COMP. H=2.00 HASTA 6.00M m 122.33 34.64 4,237.51

ROCA SUELTA 104,402.29

EXCAVACION DE ZANJAS T. SEMIROCOSO HASTA H=2.00M m 1,117.29 35.29 39,429.16

REFINE, NIVELELACION DE ZANJAS EN TERRENO SEMIROCOSO m 1,117.29 3.50 3,910.52

CAMA DE APOYO PARA TUBERIAS m 1,117.29 4.84 5,407.68

RELLENO CON MARTERIAL ZARANDEADO PARA PROTECCION DE EJE CLAVE m 1,117.29 14.20 15,865.52

RELLENO COMPACTADO C/ PLANCHA COMP. H=1.50 A 2.00M m 1,117.29 17.19 19,206.22

ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA D=2KM m3 1,072.60 19.19 20,583.19

ROCA FIJA 30,676.98

EXCAVACION DE ZANJAS T. ROCOSO HASTA H=2.00M m 235.56 62.59 14,743.70

REFINE, NIVELELACION DE ZANJAS T. ROCOSO m 235.56 7.00 1,648.92

CAMA DE APOYO PARA TUBERIAS m 235.56 4.84 1,140.11

RELLENO CON MARTERIAL ZARANDEADO PARA PROTECCION DE EJE CLAVE m 235.56 14.20 3,344.95

RELLENO COMPACTADO C/ PLANCHA COMP. H=1.50 A 2.00M m 235.56 22.41 5,278.90

ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA D=2KM m3 235.56 19.19 4,520.40

TUBERIAS 126,007.32

TUBERA DE PVC- U UF ISO 4435 DN 200MM INCLUYE ANILLO m 5,635.39 22.36 126,007.32

PRUEBAS HIDRAULICAS 10,538.18

PRUEBA ZANJA ABIERTA O ZANJA TAPADA P/TUB.DESAGUE 8" m 5,635.39 1.87 10,538.18

RED EMISOR 14,452.94


S10 Pgina 7

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

TRABAJOS PRELIMINARES 251.49

TRAZO, NIVELACION Y REPALNTEO EN OBRAS DE SANEAMIENTO m 175.87 1.43 251.49


MOVIMIENTO DE TIERRAS 9,940.12

EXCAVACIN DE ZANJA PARA TUBERAS A=0.60 HMX=2.00M EN TERRENO m 175.87 24.00 4,220.88
NORMAL
REFINE, NIVELELACION DE ZANJAS m 175.87 2.40 422.09
CAMA DE APOYO PARA TUBERIAS m 175.87 4.84 851.21

RELLENO CON MARTERIAL ZARANDEADO PARA PROTECCION DE EJE CLAVE m 175.87 9.11 1,602.18
RELLENO COMPACTADO C/ PLANCHA COMP. H=1.50 A 2.00M m 184.66 15.40 2,843.76
TUBERIAS 3,932.45

TUBERA DE PVC - UF ISO 4435 DN 200MM INCLUYE ANILLO m 175.87 22.36 3,932.45
PRUEBAS HIDRAULICAS 328.88

PRUEBA ZANJA ABIERTA O ZANJA TAPADA P/TUB.DESAGUE 8" m 175.87 1.87 328.88
BUZONES 347,002.07

TRABAJOS PRELIMINARES 882.56

TRAZO, NIVELACION Y REPLANTEO EN BUZONES, NIVELES u 197.00 4.48 882.56

MOVIMIENTO DE TIERRAS 41,617.85

EXCAVACION PARA BUZONES T. NORMAL HASTA H=3.00M m3 327.60 29.39 9,628.16

EXCAVACION PARA BUZONES T. NORMAL HASTA H=6.00M m3 127.40 51.44 6,553.46

EXCAVACION PARA BUZONES T. SEMIROCOSO HASTA H=3.00M m3 154.00 41.15 6,337.10

EXCAVACION PARA BUZONES T. ROCOSO HASTA H=3.00M m3 33.60 56.37 1,894.03

REFINE, NIVELELACION DE ZANJAS m 994.85 1.80 1,790.73

ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA D=2KM m3 803.25 19.19 15,414.37

BUZONES DE CONCRETO 303,439.06

BUZN DE CONCRETO D=1.60M, HASTA =1.50M, E=0.15M u 179.00 1,417.43 253,719.97

BUZN DE CONCRETO D=1.60M, HASTA = 3.50M, E=0.15M u 13.00 1,732.62 22,524.06

BUZN DE CONCRETO D=1.60M, HASTA >= 3.50M, E=0.15M u 3.00 3,549.75 10,649.25

BUZNETA DE CONCRETO u 2.00 1,695.06 3,390.12

DADO DE CONCRETO PARA EMPALME DE BUZN (0.40X0.40X0.40) F'C=175 u 394.00 33.39 13,155.66
KG/CM2
PRUEBAS DE CONCRETO 1,062.60

PRUEBA DE RESISTENCIA A LA COMPRESION DEL CONCRETO u 42.00 25.30 1,062.60

CONEXIONES DOMICILIARIAS 197,494.16

TRABAJOS PRELIMINARES 3,358.53

TRAZO, NIVELACION Y REPALNTEO EN OBRAS DE SANEAMIENTO m 2,348.62 1.43 3,358.53

MOVIMIENTO DE TIERRAS 84,973.08

EXCAVACION DE ZANJA MANUAL HASTA H=1.00 M m 2,348.62 19.85 46,620.11

REFINE, NIVELELACION Y FONDOS TUBERIA HASTA 4" m 2,348.62 1.80 4,227.52

CAMA DE APOYO PARA TUBERIAS HASTA 4" m 2,348.62 3.75 8,807.33

RELLENO COMPACTADO ZANJAS H=1.00M m 2,348.62 10.78 25,318.12

TUBERIAS 57,471.05

TUBERA DE PVC - UF ISO 4435 DN 110MM m 2,348.62 15.23 35,769.48

CONEXIONES DOMICILIARIAS SIMPLE DE DESAGE 110/200 MM u 350.00 52.61 18,413.50

PRUEBA HIDRAULICA m 2,348.62 1.40 3,288.07

CAJA DE REGISTRO 51,691.50

CAJA DE REGISTRO DE DESAGUE 12" X 24" pza 350.00 147.69 51,691.50

FLETE 28,878.96

FLETE AL ALMACEN DE OBRA glb 1.00 28,878.96 28,878.96

CAMARA DE REJAS 9,493.04

TRABAJOS PRELIMINARES 28.56

TRAZO Y REPLANTEO m2 10.50 2.72 28.56

MOVIMIENTO DE TIERRAS 426.35

EXCAVACION MANUAL m3 7.53 27.01 203.39

ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 9.19 21.61 198.60

NIVELACION INTERIOR APISONADO MANUAL m2 10.50 2.32 24.36

CONCRETO SIMPLE 623.53

SOLADO E=4" MEZCLA 1:10 C:H INC CURADO m2 10.50 27.58 289.59
S10 Pgina 8

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

CONCRETO f'c=140 kg/cm2 PARA LOSA BYPASS m3 1.05 318.04 333.94


CONCRETO ARMADO 6,973.42

LOSAS 970.51

CONCRETO f'c=210 kg/cm2 PARA LOSAS DE FONDO PISO m3 1.58 420.64 664.61
ENCOFRADO Y DESENCOFRADO NORMAL m2 2.75 48.26 132.72
ACERO fy=4200 kg/cm2 GRADO 60 kg 34.09 5.08 173.18
MUROS 5,932.03

CONCRETO f'c=210 kg/cm2 PARA MUROS REFORZADOS m3 5.11 416.89 2,130.31


ENCOFRADO Y DESENCOFRADO NORMAL m2 65.32 48.26 3,152.34
ACERO fy=4200 kg/cm2 GRADO 60 kg 127.83 5.08 649.38
VIGAS 70.88

CONCRETO FC=210KG/CM2 EN VIGA m3 0.05 416.14 20.81


ENCOFRADO Y DESENCOFRADO EN VIGA m2 0.56 33.62 18.83
ACERO fy=4200 kg/cm2 GRADO 60 kg 6.15 5.08 31.24
TARRAJEO Y ACABADOS 1,241.08

TARRAJEO CON IMPERMEABILIZANTES m2 32.66 38.00 1,241.08

VARIOS 200.10

REJILLA METALICA SEGUN DISEO m2 0.58 345.00 200.10

DESARENADOR 2,385.34

TRABAJOS PRELIMINARES 14.85

TRAZO Y REPLANTEO m2 5.46 2.72 14.85

MOVIMIENTO DE TIERRAS 219.15

EXCAVACION MANUAL m3 3.82 27.01 103.18

ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 4.78 21.61 103.30

NIVELACION INTERIOR APISONADO MANUAL m2 5.46 2.32 12.67

CONCRETO SIMPLE 73.36

SOLADO E=4" MEZCLA 1:10 C:H INC CURADO m2 2.66 27.58 73.36

CONCRETO ARMADO 1,649.34

LOSAS 497.63

CONCRETO f'c=210 kg/cm2 PARA LOSAS DE FONDO PISO m3 0.66 420.64 277.62

ENCOFRADO Y DESENCOFRADO NORMAL m2 0.82 48.26 39.57

ACERO fy=4200 kg/cm2 GRADO 60 kg 35.52 5.08 180.44

MUROS 1,151.71

CONCRETO f'c=210 kg/cm2 PARA MUROS REFORZADOS m3 0.75 416.89 312.67

ENCOFRADO Y DESENCOFRADO NORMAL m2 11.25 48.26 542.93

ACERO fy=4200 kg/cm2 GRADO 60 kg 58.29 5.08 296.11

TARRAJEO Y ACABADOS 428.64

TARRAJEO CON IMPERMEABILIZANTES m2 11.28 38.00 428.64


TANQUE IMHOFF 170,541.59

TRABAJOS PRELIMINARES 198.67

TRAZO Y REPLANTEO m2 73.04 2.72 198.67

MOVIMIENTO DE TIERRAS 36,132.92

EXCAVACION MANUAL m3 642.75 27.01 17,360.68

RELLENO CON MATERIAL PROPIO m3 80.34 15.44 1,240.45

ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 803.44 21.61 17,362.34

NIVELACION INTERIOR APISONADO MANUAL m2 73.04 2.32 169.45

CONCRETO SIMPLE 2,014.44

SOLADO E=4" MEZCLA 1:10 C:H INC CURADO m2 73.04 27.58 2,014.44

CONCRETO ARMADO 88,305.67

LOSAS 16,446.26

CONCRETO f'c=210 kg/cm2 PARA LOSAS DE FONDO PISO m3 8.90 420.64 3,743.70

ENCOFRADO Y DESENCOFRADO NORMAL m2 139.31 48.26 6,723.10

ACERO fy=4200 kg/cm2 GRADO 60 kg 1,177.06 5.08 5,979.46

MUROS 71,859.41

CONCRETO f'c=210 kg/cm2 PARA MUROS REFORZADOS m3 70.47 416.89 29,378.24

ENCOFRADO Y DESENCOFRADO NORMAL m2 464.31 48.26 22,407.60


S10 Pgina 9

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

ACERO fy=4200 kg/cm2 GRADO 60 kg 3,951.49 5.08 20,073.57


TARRAJEO Y ACABADOS 15,275.78

TARRAJEO EN EXTERIORES m2 202.74 26.32 5,336.12


TARRAJEO CON IMPERMEABILIZANTES m2 261.57 38.00 9,939.66
INSTALACIONES SANITARIAS 7,770.06

SUMINISTRO E INSTALACIN DE TUBERA DE PVC- U UF ISO 4435 DN 200MM m 30.00 23.97 719.10
INCLUYE ANILLO
VALVULAS COMPUERTA DE FIERRO FUNDIDO BB DE 8" glb 2.00 2,960.26 5,920.52
TEE PVC SAL DE 8" u 2.00 445.48 890.96
CODO PVC SAL SP DE 8" u 2.00 119.74 239.48
VARIOS 2,079.30

ESCALERA TIPO MARINERA m 30.00 69.31 2,079.30


CERCO PERIMETRICO 18,764.75

TRAZO Y REPLANTEO m 205.00 1.43 293.15


MURO DE TAPIAL ANCHO=60cm m2 615.00 29.84 18,351.60
PUERTA SIMPLE DE INGRESO u 1.00 120.00 120.00
LECHO DE SECADO 162,770.60

TRABAJOS PRELIMINARES 538.70

TRAZO Y REPLANTEO m2 198.05 2.72 538.70

MOVIMIENTO DE TIERRAS 950.62

EXCAVACION MANUAL m3 15.78 27.01 426.22

ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 19.72 21.61 426.15

NIVELACION INTERIOR APISONADO MANUAL m2 42.35 2.32 98.25

CONCRETO SIMPLE 2,781.13

SOLADOS CONCRETO f'c=100 kg/cm2 H=4" m2 57.14 16.29 930.81

CIMIENTOS CORRIDOS DE CONCRETO F'C=140 KG/CM2 m3 8.36 221.33 1,850.32

CONCRETO ARMADO 50,706.19

ZAPATAS 3,123.38

CONCRETO f'c=210 kg/cm2 m3 6.14 423.30 2,599.06

ACERO fy=4200 kg/cm2 GRADO 60 kg 103.01 5.09 524.32

COLUMNAS 9,257.62

CONCRETO f'c=210 kg/cm2 m3 5.25 423.30 2,222.33

ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 85.28 50.21 4,281.91

ACERO fy=4200 kg/cm2 GRADO 60 kg 540.94 5.09 2,753.38

VIGAS 5,344.68

CONCRETO f'c=210 kg/cm2 m3 2.86 423.30 1,210.64

ENCOFRADO Y DESENCOFRADO PARA VIGAS RECTAS Y DINTELES m2 45.72 62.24 2,845.61

ACERO fy=4200 kg/cm2 GRADO 60 kg 253.13 5.09 1,288.43

CANALETAS 9,287.66

CONCRETO f'c=175 kg/cm2 m3 4.47 427.05 1,908.91

ENCOFRADO Y DESENCOFRADO CANALES m2 32.93 47.47 1,563.19

ACERO fy=4200 kg/cm2 GRADO 60 kg 173.98 5.09 885.56

LOSA PREFABRICADA REMOVIBLE SOBRE CANALETA DE DRENAJE u 116.00 42.50 4,930.00

LOSAS SALPICADORAS 347.45

CONCRETO f'c=210 kg/cm2 m3 0.04 423.30 16.93

ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS m2 3.17 47.23 149.72

ACERO fy=4200 kg/cm2 GRADO 60 kg 35.52 5.09 180.80

APOYOS 297.32

CONCRETO f'c=175 kg/cm2 PARA ANCLAJES Y/O DADOS m3 0.28 343.46 96.17

ENCOFRADO Y DESENCOFRADO NORMAL PARA ESTRUCTURAS DE m2 3.05 49.48 150.91


CONCRETO
ACERO fy=4200 kg/cm2 GRADO 60 kg 9.87 5.09 50.24

MUROS REFORZADOS 21,815.04

CONCRETO f'c=210 kg/cm2 m3 17.23 415.91 7,166.13

ENCOFRADO Y DESENCOFRADO NORMAL PARA ESTRUCTURAS DE m2 229.74 49.48 11,367.54


CONCRETO
ACERO fy=4200 kg/cm2 GRADO 60 kg 644.67 5.09 3,281.37
S10 Pgina 10

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

CAJAS DE RECEPCION 1,233.04

CONCRETO f'c=210 kg/cm2 m3 0.94 423.30 397.90

ENCOFRADO Y DESENCOFRADO NORMAL PARA ESTRUCTURAS DE m2 10.32 62.33 643.25


CONCRETO
ACERO fy=4200 kg/cm2 GRADO 60 kg 37.70 5.09 191.89
TARRAJEO Y ACABADOS 13,475.07

TARRAJEO CON IMPERMEABILIZANTES COLUMNAS m2 94.80 35.06 3,323.69


TARRAJEO CON IMPERMEABILIZANTE VIGAS m2 34.20 31.22 1,067.72
TARRAJEO CON IMPERMEABILIZANTE CANALETA m2 23.20 31.47 730.10
TARRAJEO CON IMPERMEABILIZANTE SALPICADOR m2 7.68 33.10 254.21
TARRAJEO CON IMPERMEABILIZANTE APOYOS m2 4.20 33.41 140.32
TARRAJEO CON IMPERMEABILIZANTE DE MUROS LATERALES m2 280.94 28.33 7,959.03
ESTRUCTURAS DE MADERA 11,141.70

VIGA DE MADERA 2"X6" m 75.20 85.61 6,437.87


CORREAS DE MADERA 2" X3" p2 257.04 18.30 4,703.83
COBERTURAS 6,385.68

COBERTURA DE TECHO CON CALAMINA GALVANIZADA DE 0.80X1.80M m2 216.00 27.58 5,957.28


CUMBRERA DE CALAMINA m 24.00 17.85 428.40

INSTALACIONES SANITARIAS 8,541.69

SUMINISTRO E INSTALACIN DE TUBERA DE PVC- U UF ISO 4435 DN 200MM m 69.30 24.90 1,725.57
INCLUYE ANILLO
CODO PVC SAL SP DE 8" u 16.00 119.74 1,915.84

TEE PVC SAL DE 8" u 11.00 445.48 4,900.28

FILTROS 68,249.82

GRAVA CLASIFICADA m3 276.12 146.08 40,335.61

FILTRO DE ARENA m3 222.30 125.57 27,914.21

POZO PERCOLADOR Y CAJA DE DISTRIBUCION 161,675.72

TRABAJOS PRELIMINARES 673.34

TRAZO Y REPLANTEO m2 247.55 2.72 673.34

MOVIMIENTO DE TIERRAS 43,389.96

EXCAVACION MANUAL m3 817.70 27.01 22,086.08

RELLENO CON MATERIAL PROPIO m3 117.41 15.44 1,812.81

ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 875.37 21.61 18,916.75

NIVELACION INTERIOR APISONADO MANUAL m2 247.55 2.32 574.32

CONCRETO SIMPLE 3,187.42

CONCRETO f'c=140 kg/cm2 + ENCOFRADO PARA CIMIENTO m3 12.74 250.19 3,187.42

CONCRETO ARMADO 97,208.52

ANILLO CILINDRICO 13,802.22

CONCRETO f'c=210 kg/cm2 m3 10.76 427.05 4,595.06

ENCOFRADO Y DESENCOFRADO NORMAL EN ANILLO CIRCULAR m2 178.75 47.82 8,547.83

ACERO fy=4200 kg/cm2 GRADO 60 kg 129.79 5.08 659.33

COLUMNAS 6,734.01

CONCRETO f'c=210 kg/cm2 m3 5.38 423.30 2,277.35

ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 2.94 62.24 182.99

ACERO fy=4200 kg/cm2 GRADO 60 kg 839.62 5.09 4,273.67

MUROS 49,767.04

CONCRETO f'c=210 kg/cm2 PARA MUROS REFORZADOS m3 3.56 416.89 1,484.13

ENCOFRADO Y DESENCOFRADO NORMAL m2 47.52 48.26 2,293.32

ACERO fy=4200 kg/cm2 GRADO 60 kg 379.44 5.11 1,938.94

LADRILLO HUECO DE ARCILLA 0.23x0.11X0.09 PARA MUROS u 27,946.55 1.39 38,845.70

MORTERO CEMENTO ARENA 1:10 m3 21.13 246.33 5,204.95

TECHOS 26,905.25

CONCRETO f'c=210 kg/cm2 PARA TECHOS m3 22.10 437.69 9,672.95

ENCOFRADO Y DESENCOFRADO NORMAL m2 208.08 38.08 7,923.69

ACERO fy=4200 kg/cm2 GRADO 60 kg 1,414.60 5.11 7,228.61

TAPA CUADRADA 0.90m x 0.90m DE CONCRETO u 6.00 125.00 750.00

TAPA DE F F CIRCULAR 0.60m u 14.00 95.00 1,330.00


S10 Pgina 11

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

TARRAJEOS Y ACABADOS 1,200.27

TARRAJEO CON IMPERMEABILIZANTE m2 49.68 24.16 1,200.27


FILTROS 16,016.21

GRAVA CLASIFICADA m3 109.64 146.08 16,016.21


TANQUE SEPTICO 41,845.17

TRABAJOS PRELIMINARES 74.85

TRAZO Y REPLANTEO m2 27.52 2.72 74.85


MOVIMIENTO DE TIERRAS 2,952.21

EXCAVACION MANUAL m3 85.31 27.01 2,304.22


RELLENO CON MATERIAL PROPIO m3 13.76 15.44 212.45
ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 17.20 21.61 371.69
NIVELACION INTERIOR APISONADO MANUAL m2 27.52 2.32 63.85
CONCRETO SIMPLE 6,885.23

CONCRETO f'c=140 kg/cm2 + ENCOFRADO PARA CIMIENTO m3 27.52 250.19 6,885.23


CONCRETO ARMADO 18,835.88

LOSAS 2,824.77

CONCRETO f'c=210 kg/cm2 m3 5.50 421.02 2,315.61


ACERO fy=4200 kg/cm2 GRADO 60 kg 99.64 5.11 509.16

MUROS 12,731.36

CONCRETO f'c=210 kg/cm2 PARA MUROS m3 14.18 424.82 6,023.95

ENCOFRADO Y DESENCOFRADO NORMAL m2 140.34 42.70 5,992.52

ACERO fy=4200 kg/cm2 GRADO 60 kg 139.90 5.11 714.89

TECHOS 3,279.75

CONCRETO f'c=210 kg/cm2 PARA TECHOS m3 3.78 437.69 1,654.47

ENCOFRADO Y DESENCOFRADO NORMAL m2 28.62 38.08 1,089.85

ACERO fy=4200 kg/cm2 GRADO 60 kg 86.19 5.11 440.43

TAPA DE F F CIRCULAR 0.60m u 1.00 95.00 95.00

TARRAJEO Y ACABADOS 1,553.49

TARRAJEO CON IMPERMEABILIZANTE m2 64.30 24.16 1,553.49

CERCO PERIMETRICO 10,832.10

TRAZO Y REPLANTEO m 117.78 1.43 168.43

MURO DE TAPIAL ANCHO=60cm m2 353.34 29.84 10,543.67

PUERTA SIMPLE DE INGRESO u 1.00 120.00 120.00

VARIOS 711.41

GRAVA CLASIFICADA m3 4.87 146.08 711.41

FLETE 23,497.97

FLETE AL ALMACEN DE OBRA EN PLANTA DE TRATAMIENTO glb 1.00 23,497.97 23,497.97

LETRINAS Y TANQUE DIGESTOR 138,588.41

TRABAJOS PRELIMINARES 5,900.84

TRAZO Y REPLANTEO m2 84.00 2.72 228.48

EXCAVACION MANUAL m3 105.00 27.01 2,836.05

ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 131.25 21.61 2,836.31

CONCRETO SIMPLE 45,720.92

LOSA DE FONDO 45,720.92

CONCRETO f'c=175 kg/cm2 m3 54.83 427.05 23,415.15

ENCOFRADO Y DESENCOFRADO NORMAL m2 462.20 48.26 22,305.77

CASETA DE LETRINA CON DRYWALL 34,945.40

SUMINISTRO Y COLOCACION DE CASETA DE LETRINA SEGUN DISEO u 28.00 1,248.05 34,945.40

TUBERIAS Y ACCESORIOS 3,460.52

SALIDA DE AGUA FRIA CON TUB.SAP D=1/2" pto 28.00 28.14 787.92

SALIDA DE VENTILACION PVC SAL D=2" pto 28.00 27.76 777.28

SALIDA DE DESAGUE PVC SAL D=4" pto 28.00 67.69 1,895.32

TANQUE DIGESTOR 48,560.73

MOVIMIENTO DE TIERRAS 2,906.58

EXCAVACION PARA EL TANQUE DIGESTOR Y ZANJAS DE INFILTRACION m3 27.50 30.30 833.25

RELLENO DE ZANJA CON MATERIAL FILTRANTE m 19.00 70.02 1,330.38


S10 Pgina 12

0701033

Item Descripcin Und. Metrado Precio S/. Parcial S/.

ELIMINACION DE MATERIAL EXCEDENTE CON CARRETILLA m3 34.38 21.61 742.95


SISTEMA DE TANQUE DIGESTOR 45,654.15

SUMINISTRO E INSTALACION DE TANQUE DIGESTOR u 19.00 1,800.00 34,200.00


SUMINISTRO Y COLOCACIN DE CAMARA DE LODOS u 19.00 242.76 4,612.44
SUMINISTRO Y COLOCACIN DE CAMARA DE LIQUIDOS u 19.00 166.26 3,158.94
SUMINISTRO Y COLOCACIN DE CAMARA DE INFILTRACION u 19.00 193.83 3,682.77
FLETE 2,580.00

FLETE AL ALMACEN DE OBRA EN LETRINAS glb 1.00 2,580.00 2,580.00


PROTECCION Y CONSEVACION DEL MEDIO AMBIENTE 54,801.10

EDUCACION AMBIENTAL 20,200.00

CHARLAS A LA COMUNIDAD BENEFICIARIA u 16.00 950.00 15,200.00


CHARLA PARA PERSONAL DE OBRA glb 6.00 500.00 3,000.00
BOLETINES INFORMATIVOS u 200.00 10.00 2,000.00
MANEJO DE CAMPAMENTO 6,750.70

INSTALACION DE CONTENEDORES DE BASURA u 12.00 129.35 1,552.20


LETRINAS SANITARIAS glb 4.00 773.40 3,093.60

MICRO RELLENO SANITARIO glb 4.00 173.88 695.52


ELIMINACION DE SUELOS AFECTADOS POR RESIDUOS DE COMBUSTIBLE m3 14.00 15.92 222.88

ESCARIFICADO, REGADO Y COMPACTADO m2 50.00 2.16 108.00

LETREROS INFORMATIVOS u 15.00 71.90 1,078.50

REACONDICIONAMIENTO Y REVEGETACION 610.00

SIEMBRA DE PLANTONES u 200.00 3.05 610.00

MANEJO DE BOTADEROS 1,563.00

ESCARIFICADO, REGADO Y COMPACTADO m2 300.00 2.16 648.00

SIEMBRA DE PLANTONES u 300.00 3.05 915.00

SEALIZACION 25,677.40

FABRICACION DE SEALES INFORMATIVAS R=40 und/da u 140.00 148.09 20,732.60

EXCAVACION Y COLOCACION R=30 und/da u 140.00 35.32 4,944.80

FLETE 33.71

FLETE AL ALMACEN DE OBRA EN IMPACTO AMBIENTAL glb 1.00 33.71 33.71

COSTO DIRECTO 2,815,157.20

GASTOS GENERALES (8.65%) 243,511.10

UTILIDAD (7.35%) 206,914.05


--------------------

SUB TOTAL 3,265,582.35

IMPUESTO GENERAL A LAS VENTAS (18%) 587,804.82


--------------------

PRESUPUESTO TOTAL 3,853,387.17