You are on page 1of 30

4.

Contracts and Pricing


Arrangements

ENCI 619.93
S. Zwierzchowski
University of Calgary MEng Program in Iran

ENCI
619.93
SJZ
Issues and Underlying Principles
Opening Discussion

ENCI
619.93
SJZ
Issues
n At a basic level how is it ensured that the
owner and the contractor/supplier perform
their obligation and responsibilities?

n What contract pricing arrangement minimizes


the financial risk to the owner?

n What contract pricing arrangement minimizes


the financial risk to the supplier/contractor?
ENCI
619.93
SJZ
Issues
n What contract pricing arrangement provides
the best incentive for contractor/supplier
performance and quality?

n Does the type of contract price arrangement


affect the number of bidders for a given
project procurement?

ENCI
619.93
SJZ
Contracts

ENCI
619.93
SJZ
What Is a Contract
n A set of promises and obligations between
two or more parties that is enforceable under
the law

n Written or verbal or a mix


n Complex contracts consist of many documents

ENCI
619.93
SJZ
Contracts Enforceable Under the
Law
n Breach of Contract
n Not fulfilling a promise or obligation required
under the contract
n Non-defaulting party can recover damages
incurred because of the breach or obtain
other remedies to mitigate the breach through
the courts

ENCI
619.93
SJZ
Contracts - Termination
n Contract is brought to an end by:
n Performance
n Mutual agreement
n Frustration
n Breach
n Operation of the law

ENCI
619.93
SJZ
Project Procurement
Contracts

ENCI
619.93
SJZ
In General
n Projects concerned with the construction of
infrastructure and the procurement of plant
and equipment tend to have high values and
a large degree of complexity
n Contracts can be complex and extensive
n Promises and obligations are defined in many
documents

ENCI
619.93
SJZ
Master Agreement
n In the body or in schedules or through
references to other documents would define
n general scope of work to be performed
n the price and price arrangement for the work,
payment terms
n overall schedule
n key schedule milestones
n general terms and conditions

ENCI
619.93
SJZ
Other Documents Forming the
Contract
n Documents, drawings and datasheets
defining technical requirements
n Change orders
n Inspection and test plans and procedures
n Correspondence
n Meeting minutes, and on.
n Unless explicitly stated otherwise, the
documents, correspondence, and meeting
minutes used in the bidding process
ENCI
619.93
SJZ
Contract Pricing
Arrangements

ENCI
619.93
SJZ
Pricing Arrangements
n Fixed Price (Lump Sum)
n Fixed Price with Price Adjustments
n Unit Price
n Time and Materials/ Unit Rate
n Reimbursable with Fixed or Percentage Fee
n Target Price
n Reimbursable with Incentive Fees

ENCI
619.93
SJZ
Fixed Price (Lump Sum)
n Contractor/supplier is paid a fixed price for a
defined scope of work or a defined equipment
specification
n Included is overhead and profit
n Contractor/ supplier can incur a loss
n Costs are greater than price

ENCI
619.93
SJZ
Fixed Price (Lump Sum)
n Scope of work must be accurately and
completely defined
n Extra charges by the contractor for scope
changes
n Each change requires negotiation
n Rules must be defined in contract
n Relative to other price arrangements, fixed
price requires greater effort to define work
scope and technical requirements
ENCI
619.93
SJZ
Fixed Price (Lump Sum)
n Contractor assumes the risk associated with
the price of the work
n Variations in labor and material costs
n The need for extra labor beyond what was
estimated
n Technical difficulties in meeting defined work
scope and technical objectives
n Contractors/suppliers add a contingency to
price
ENCI
619.93
SJZ
Fixed Price (Lump Sum)
n Contractor is motivated to reduce costs
n Contractors profit is increased
n Contractor has no incentive to incur additional
costs
n such as schedule acceleration through
overtime
n providing greater quality in the work or
equipment than the minimum required to meet
contract requirements

ENCI
619.93
SJZ
Fixed Price with Price Adjustment
n Similar to straight fixed price except
n Adjustments can be made to the price over
time if some of the contractor/suppliers costs
change
n Normally be used to offset the effects of
inflation or price volatility in a commodity
n Increases in labor and material costs
n Method or formula defined in the contract
using published statistics for inflation
n Reduces the contractors/suppliers risk
ENCI
619.93
SJZ
Unit Price
n Each unit of work/equipment/material provided at a
fixed price
n Exact quantity of units not specified and may not be
known with certainty
n Price for each unit will cover the contractor/suppliers
direct costs plus overhead and profit.
n Contractor/supplier assumes the price risk on a per
unit basis
n Owner/purchaser assumes the price risk for
variations/increases in the quantity of units required.

ENCI
619.93
SJZ
Unit Price
n Examples:
n supply and installation of racking on a per module

basis
n supply and installation of lighting on a per fixture basis

n manufacture and supply of valves

n manufacture and supply of pressure vessels

n supply and installation of piping on a per length basis

n excavation on a per volume basis

n Still important to accurately and completely define the


requirements and specifications for each unit.

ENCI
619.93
SJZ
Time and Materials/Unit Rate
n Contractor is paid for the amount of time
required of labour and other resources
n Hourly, daily or weekly rates per labour
category or per chargeable resource item
such as equipment and tools
n Senior engineer; drafter; master electrician;
journeyman welder; and on
n Cranes; excavators; scaffolding; and on.

ENCI
619.93
SJZ
Time and Materials/Unit Rate
n Rates include overheads and profits
n Rates fixed for the contract
n Contractor assumes price risk relative to
costs associated with the rate increasing
n Schedule of rates is included in the contract
n Cost of materials and other expenses at cost
plus a percentage markup
n A type of reimbursable contract

ENCI
619.93
SJZ
Time and Materials/Unit Rate
n Disadvantage
n The contractor has no incentive to quickly
complete the work
n The longer the contractor must work on the
project, the more money the contractor earns
n Advantages
n The quality of work can be high
n The scope of work, technical requirements,
and design do not have to be defined in detail
ENCI
619.93
SJZ
Reimbursable with Fixed or
Percentage Fee
n Similar to a time and materials contract except
the contractor is paid for actual costs
Advantages and disadvantages the same
n In addition, a fee that is a percentage of the
actual costs to cover overhead and profit is paid
n could be a fixed fee
n Contractor bears no price risk whatsoever
n Administration is very difficult
n actual costs incurred by the contractor must be
ENCI
documented and verified
619.93
SJZ
Target Price Contract Types
n A form of reimbursable contract but with an incentive
based on total costs that the contractor charges for
the work.
n If the costs are below the target price, contractor is
paid a percentage of the difference as a bonus.
n If the costs are above the target price, contractor is
only paid a portion of the difference
n Costs can either be fixed rates or can be the actual
costs incurred
n Administratively rates are easier to work with and than
trying to determine the actual costs.

ENCI
619.93
SJZ
Reimbursable with Incentive Fees

n Contractor is paid for the actual costs


incurred or according to rates established for
the work provided.
n The contractor is paid an incentive fee based
on performance
n Schedule
n Quality
n Cost
n Other
ENCI
619.93
SJZ
Issues and Underlying Principles
Concluding Discussion

ENCI
619.93
SJZ
Issues
n At a basic level how is it ensured that the
owner and the contractor/supplier perform
their obligation and responsibilities? Through
contracts and contract law.
n What contract pricing arrangement minimizes
the financial risk to the owner? Fixed price.
n What contract pricing arrangement minimizes
the financial risk to the supplier/contractor?
Reimbursable with percentage fee.
ENCI
619.93
SJZ
Issues
n What contract pricing arrangement provides
the best incentive for contractor/supplier
performance and quality? Reimbursable with
incentive fee.
n Does the type of contract price arrangement
affect the number of bidders for a given
project procurement? Yes, some
organizations will not undertake fixed price
contracts because of the risk of financial loss
in performing the work.
ENCI
619.93
SJZ

You might also like