You are on page 1of 8

Page 1 of 8 Preprint for Peer Review

Generator Capability Study for Offshore Oil Platform


Peter E. Sutherland, Fellow, IEEE
GE Energy Services
180 Rotterdam Industrial Park
Schenectady, NY 12306
Peter.Sutherland@ieee.org

Abstract—Offshore Production Platform’s two 25 MW turbine  4 x 570kW Electrical Submersible Pumps each
generatorunits were evaluated to determine the safe operating controlled by a VSD
limits of the units, if the entire load is to be carried by one
generator, and to determine whether load shedding will be  1 x 1.7MW kW Raw Sea Water Injection Pump
necessary if only one generator is in operation. The Generator controlled by a VSD
Reactive Capability Curve was constructed based upon limited
data due to the age of the generators. The real power output  1 x 3.5MVA, 13.8kV / 690v transformer
capability of the turbine-generator combination was evaluated  1 x 3MW thyristor controlled heater
based upon the data provided. The generator was rated in
accordance with British Standard BS.2613/1957. The analysis The existing generation consists of two 25MW Generators;
was based upon the requirements the superseding standards, IEC the platform operates one of the two with the idle unit on
60034-1 (2004) and IEC 60034-3 (2005). standby or under maintenance. Each generator has a theoretical
rating of 25MW although the 'safe' operating rating will be
Keywords-component; generator capability; reactive capability; lower. The generators are approximately 30 years old; they
oil platform. were inspected by a field engineer and were reported to be in
good condition and are under a regular maintenance program.
I. INTRODUCTION The field engineer recommended a major overhaul over the
A generator capability study was performed for a facility in next two years including new rotors.
the North Sea. There is no load shedding or power management system as
The scope of the generator capability study included the the maximum load has always been within the capability of a
Production Platform’s two 25 MW turbine generators. single generator. However a new system may be installed as
part of this project to phase down the new loads when reaching
The purpose of the study was to determine the safe the 'safe' operating limit of the generators to safeguard main
operating limit of the units, if the entire load is to be carried by platform production. The platform operations department are
one generator, and to determine whether load shedding will be unlikely to allow operation of both generators simultaneously.
necessary if only one generator is in operation.
The existing platform load is approximately 9 MW
The Generator Reactive Capability Curve will be however this has been up to 15 MW when water injection and
constructed using the data provided. The real power output drilling were running at full capacity. The load profile varies
capability of the generator will be evaluated based upon the between these two figures.
data provided.
The new load imposed by the upgrade project will be a
The generator is rated in accordance with BS.2613 [1]. The maximum of 7.7 MW.
analysis will be based upon the requirements the superseding
standards, IEC 60034-1 [2], and IEC 60034-3 [3]. The study requirement was to carry out a desktop analysis
on the generators to establish the 'safe' operating limit of the
units.
II. SYSTEM DESCRIPTION
Study Methodology
This project involves building new process facilities on the
Production Platform to accommodate tie-in of a new oil & gas The study effort consisted of three tasks:
reservoir. New electrical equipment will be:
1. Generator reactive capability curve. The generator
 Extension to existing 13.8kV Switchboard reactive capability curve was constructed, and the current and
future loading were evaluated.
 1 x 13.8kV Switchboard
2. Unit derating. The rating of the unit was evaluated with
 2 x 1MVA, 13.8kV / 440v transformers regard to IEC Standards 60034-1 and –3. [2] [3]
 1 x 440V Switchboard

1
978-1-4244-3399-5/09/$25.00 © IEEE 2009
Preprint for Peer Review Page 2 of 8

3. Load shedding system. The data results from the previous


two tasks were examined for the possible requirement for a
load shedding system. 1
A Peak Future

III. GENERATOR REACTIVE CAPABILITY CURVE


0.75
The capability of the generator based upon its data sheet
shows a rated maximum power output of 31.25 MW, 36.8 B
MVA (Water at 10°C) at a power factor of 0.85. The turbine 0.5
rated output is 24.5 MW. Thus, the generator can provide no
more than 78% of its rated maximum power output.
0.25
Generator power output capability is limited by the rated
temperature rise of the copper for armature current, and of the

Q pu
iron for terminal voltage. The limitations are shown
graphically on a “Reactive Capability Curve.” The calculated 0 0.2 0.4 0.6 0.8 1 1.2
curves for the Production Platform unit are shown in Fig. 1.
The arc AB on the curve represents a line of constant rated
 0.25 D C
field current. The arc BC represents a line of constant rated
armature current. The arc CD represents a line of the
underexcitation limit by armature core end heating. These  0.5
points are also shown on the corresponding Vee Curves in Fig.
2. Reactive capability curves are a commonly used method for
plotting generator characteristics that are often supplied by  0.75
generator manufacturers. When they are not available,
methods for calculating the curves are well documented in the
literature. [4] 1
The rated field current curve A-B may be drawn as a circle
with its center at  jVa2 X d , and a radius of Va Ei X d where: P pu
Field Current Limit
 Va = per-unit generator terminal voltage. Va = 1.0
(assumed). Armature Current Limit
Armature Current Limit
 Xd = per-unit generator synchronous reactance. Xd = 2.34 PF = 0.85 Lag
from generator data sheet. PF = 0.95 lead
 pB = per-unit rated real power output = 0.85 Underexcitation Limit
SSSL1
 qB = per-unit rated reactive power output = 0.526.
SSSL2
 Ei = per-unit generator field current. At rated terminal 25MW, 0.8pf
voltage, armature current and power factor, PF = 0.8 Lag

Ei = p 2B  (q B  X d ) 2 = 2.99. (1)
Figure 1. Generator capability curve of Production Platform unit.

This value of Ei is for the constant field current segment, A to


B. Expression (1) is valid for rated terminal voltage, armature
current, that is, the range from points B to C. The radius of the circle is r = 1.0 x 2.99/2.34 = 1.278 pu =
47.0 MVA. The equation of the circle is:
The equation of the circle is:
1.278 2 P 2  Q  0.4272
r x  x 0   y  y 0 
2 2 2

or Q 1.278 2  P 2  0.427
2 2
Va E i V2 Thus, the start of the arc at point A is located at: Q=1.278-

 P2 
Q  a 

X 
Xd  0.427= 0.85 pu = 31.3 MVAr. This value of Q is equal to the
d  
rated MVA output of the machine. The end of the arc at point
2 B is where the power factor is 0.85. This is at the start of the
V E V2
Q

a i   P2  a (2)
Xd

 X d
second segment, where Q 1.2782  0.85 2  0.427 0.527 = 19.4
MVAr.
The center of the circle is located at Q = -1/ Xd = -0.4274
pu = -15.7 MVAr.

2
978-1-4244-3399-5/09/$25.00 © IEEE 2009
Page 3 of 8 Preprint for Peer Review

The rated armature current is plotted as a circle with a center at This is plotted on the negative Q axis of the capability curve.
the origin and a radius of rated MVA. The equation of the The curve between them is normally transferred point by point
circle is the familiar: from the Vee curve. On the Vee Curve axes of Ia vs Ei, the line
can be written using the point-slope formula for a line:
S2 P 2  Q 2 (3)
I a m(E i  0.25)  I 0.25 , where
In this case, S = 1 pu =36.8 MVA. The equation of the circle 1  Q 0.25 1.3205 (9)
is: m 0.6636
E iC  0.25 2.24  0.25
1.0 P 2  Q 2
or,
The starting point B is at the intersection with the first circle. Ia 0.6636Ei  0.25  0.3205 (10)
The intersection of two circles whose centers are on the vertical
This equation verifies that point C on the Vee curves is Ei =
axis:
2.24 and Ia = 1.0 and point D is Ei = 0.25 and Ia = -0.3205. A
r12 x 2  y 2 line or curve may be drawn between these two points as an
approximation of the true function.
and (4)
 
r22 x 2  y  y 2 2 Synchronous Generator Vee Curves

subtracting
C B
r12  r22 y 2  y  y 2 2 1


y 2  y 2  2 yy 2  y 22  (5)

2 yy 2  y 22 A

solving
r 2  r22  y 22 1
r 2  r22 
kVA output, pu

(6)
y 1
y2  1
2y 2 2
y 2 

0.5
setting
r1 S 1.0
Va E i
r2 1.277 D
Xd
r22 1.6307

V2
y 2  a 0.4274
Xd

solving
0
1 1  1.6307 0 1 2 3
y
 0.4274   0.526
2  0.4274  Field Current, pu
This is the value of Q at point B. The corresponding value of P V-curve P=1
must be 0.85, the rated power factor, thus P = 0.85S = 31.3 0.95 lead
MW and Q = 0.526S = 19.4 MVAr. The ending point C is at 0.85 lag
leading power factor of 0.95. Here P = 0.95S = 35.0 MW and Rated current
Q = -0.312S = -11.5 MVAr. At points C: Rated field
Unity pf
Ei=0.25
EiC = p 2  (q  X d ) 2 0.95 2  (0.312  2.34) 2 2.240.
V-curve P=0
End-Iron Heating Limit
The underexcited heating limit is a curve, which goes from
point C to point D. On the Vee Curve for zero power output,
point D is at 0 PF lead and one fourth of the no-load field Figure 2. Calculated Vee Curves for Generator
current IFNL.
The steady state stability limit (SSSL) is a circle with a
EiD = IFNL/ 4 = 0.25 pu; (7) Va2 1 1 Va2 1 1


.
The reactive power is then:
center at
2
X X  and a radius of
2
X  X  The
e d  e d 
Q0.25 = Va(Ei-Va)/Xd = 1.0(0.25-1.0)/2.34 (8) external reactance Xe, calculated from circuit impedances, is
10.8% in the existing case, and 8.9% with the planned
= -0.3205 pu = -11.8 MVAr additions. These are plotted as SSSL1 and SSL2, respectively

3
978-1-4244-3399-5/09/$25.00 © IEEE 2009
Preprint for Peer Review Page 4 of 8

in Figure 2. With this unit, the center is at 4.416 pu = 162.5 7. Occasional excess current shall not exceed 1.5 times rated
MVAr, while the radius is 4.843 pu = 178.2 MVA for Xe= for 30 seconds. (IEC 60034-3, 4.16)
0.108. Thus, the SSSL starts at 162.5-178.2 = -15.7 MVAr,
and passes near point C. The SSSL is outside of the reactive 8. Harmonic content of terminal voltage shall not exceed 5%
capability curve. The output of the generator is therefore not Total Harmonic Distortion (THD). (IEC 60034-1, 9.11.2)
constrained by the steady state stability limit. The THD is defined as:

The maximum real power output of the generator with the 100
attached turbine is 24.5 MW. The field current limit occurs at THD U
n 2
2
n
24.0 MVAr, thus the minimum lagging power factor at this
loading is 0.70.
where Un is the voltage at harmonic order n. Harmonic
The peak load before the additions is 15 MW, and after is 22.7 measurements have not been taken, so this factor is
MW. These are all indicated on the figure. The current peak unknown.
load is 61% of the turbine rating of 24.5 MW, increasing to In order to apply these conditions, details about the
93% with the future load. construction of the generator need to be known, such as:
 Which is the primary or secondary coolant (water or air)
IV. UNIT DERATING
 Whether cooling is direct or indirect
The generators were rated in accordance with BS.2613 [1].
This standard has been superseded by IEC 60034-1 [2], and  The rated temperature or temperature rise of the windings.
IEC 60034-3 [3]. The generator is assumed to be typically If none of these conditions apply, the generator does not
rated for continuous (S1) duty. (IEC 60034-1, 5.2.1) need to be derated. Because the generator is operating at 78%
Generators should be derated under the following of its rated power output, even if it was derated, this should not
conditions: affect the maximum power output with the existing turbine.
1. When operated at an altitude above 1000 m. These units Combustion gas turbines should be derated when the
are at sea level. (IEC 60034-1, 6.2) temperature of the ventilating air exceeds 15 °C. The output
ratings of turbines and generators may differ due to their
2. When the temperature of the ventilating air exceeds 40 °C different temperature ratings.
or is less than -5 °C. (IEC 60034-3, 7.2.2), except that
because the generator has The temperature limits can be observed from the weather
records. The location of Production Platform is offshore of
a. > 3.3 MVA/1000 rpm Aberdeen.
b. Water as a coolant 16.0
14.0
the minimum temperature is 0 °C. (IEC 60034-1, 6.4)
Average Air Temp. (C)

12.0
10.0
3. When operated with cooling water inlet temperature 8.0
differing from the rated value of 10 °C. The temperature 6.0
4.0
range is –20 to 60 °C, with derating of the winding 2.0
temperature rise below 10 °C. (IEC 60034-3, 7.4.3) 0.0
Jan- Feb- Mar- Apr- May- Jun- Jul- Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar-
4. Harmonic content of load currents, shall not exceed 5% 07 07 07 07 07 07 07 07 07 07 07 07 08 08 08

Harmonic Current Factor (HCF). (IEC 60034-1, 7.2.2) The Jan- Feb- Mar- Apr- May- Jun- Jul- Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar-
07 07 07 07 07 07 07 07 07 07 07 07 08 08 08
HCF is defined as:
Monthly 7.3 5.9 7.1 8.5 9.7 13.5 14.2 14.9 12.9 11.3 8.2 7.0 6.5 6.4 5.1
Annual 9.2 9.2 9.2 9.2 9.2 9.2 9.2 9.2 9.2 9.2 9.2 9.2 9.2 9.2 9.2
13
HCF 
n 2
I 2n
Figure 3. Average air temperature for Ecofisk platform. Data from [5].

where In is the current at harmonic order n. Harmonic Available weather records from the Norwegan Ekofisk
measurements have not been taken, so this factor is platform, located to the southeast of Production Platform,
unknown. indicate an annual average temperature of 9.2 °C. Monthly
weather data [5] is shown in Fig. 3. Seawater temperature for
5. Negative or zero sequence currents shall not exceed 5%. the North Sea is very similar to the air temperature, typically
(IEC 60034-1, 7.2.3) The generators feed delta-connected being 1-2 °C higher.
primaries of distribution transformers, so this should not
occur. Therefore, the air temperature is within the range of 5-40
°C, and the average water temperature is approximately 10 °C.
6. Operate outside a zone of ±5% in terminal voltage or ±2% However, because the water temperature is at times less than
in frequency. (IEC 60034-1, 7. 3) 10 °C, the maximum temperature or temperature rise of the
windings may be limited. Reference should be made to the
standards for the appropriate derating formula. Given these

4
978-1-4244-3399-5/09/$25.00 © IEEE 2009
Page 5 of 8 Preprint for Peer Review

conditions, the generator and the turbine should be operating Because load does not exceed generation, in fact the
within their rated temperature ranges. No derating due to maximum peak future load is 93% of the rated turbine power
temperature is required. output, no load shedding system is required at present.
However, should the future load exceed the total unit
V. LOAD SHEDDING SYSTEM capability, a load shedding system should be considered.
Any part of a power system will begin to deteriorate if there
is an excess of load over available generation. [6] The prime VI. CONCLUSIONS
movers and their associated generators begin to slow down as It was found that the unit would be operating within 93% of
they attempt to carry the excess load. Tie lines to other parts of its 24.5 MW capability, with a minimum power factor of 70%
the system, or to other power systems across a power pool, lagging. The steady state stability limit is outside of the
attempt to supply the excess load. This combination of events generator capability curve, and thus is not a factor in generator
can cause the tie lines to open from overload or the various output. The rating of the unit was evaluated with regard to IEC
parts of the systems to separate due to power swings and Standards 60034-1 and –3. It was found based on available
resulting instability. The result may be one or more electrically data , the unit was operating within its rated capabilities, and no
isolated islands in which load may exceed the available derating was required. Because load does not exceed
generation. [7] generation, in fact the maximum peak future load is 93% of the
rated turbine power output, no load shedding system is required
There are two major types of load shedding systems [8] in at present. Should the future load exceed the total unit
use, the under-frequency relay and the PLC system: capability, a load shedding system should be considered.
 With the under-frequency relay, the load is shed in
predetermined blocks after the frequency has fallen below REFERENCES
certain setpoints. Time delay is built in to avoid [1] British Standard BS.2613/1957, Electrical performance of rotating
misoperation during normal frequency variations. The machines.
combination of fixed blocks of load shed with a time delay [2] IEC 60034-1 (2004). Rotating electrical machines – Part 1: Rating and
can result in a continued mismatch of load and generation performance
if the rate of change of frequency does not match the rate [3] IEC 60034-3 (2005) Rotating electrical machines – Part 3: Specific
of load shedding. requirements for cylindrical rotor synchronous machines.
[4] M. Harry Hesse, Principles of Electric Power System Analysis, Notes for
 With the PLC system, the breaker positions, generator 34.682, Rensselaer Polytechnic Institute, Troy, NY, Spring 1994.
status, and power flows are continuously monitored. The [5] Website www.tutiempo.net ??
PLC maintains a table of scenarios and calculated [6] Sutherland, P.E.; Roubach, V.; Riani, L.M., “Stability Requirements for
responses. For each of these responses, the load will be Implementation of Grid Separation Scheme in a Steel Mill with Internal
matched to the generation once the switching is executed. Generation,” IEEE 2008 IAS Annual Meeting, Edmonton, Alberta,
PLC systems are superior to under-frequency relays in the October, 2008.
accuracy and speed of their response. However, there are [7] Load Shedding, Load Restoration and Generator Protection Using
difficulties with PLC systems, which often lead to under- Solid-state and Electromechanical Underfrequency Relays, GE
Publication GET-6449.
frequency relays being used as a back up for PLC systems.
[8] John P. Fievet, “The use of programmable logic controllers in paper mill
These are: load shed systems,” TAPPI Journal, Vol. 80, No. 3, March 1997
1. In a complex system with a large number of
possible switching combinations, scenarios may BIOGRAPHY
occur which are not programmed into the PLC,
resulting in a failure to respond when load- Peter E. Sutherland (Fellow, IEEE) received the B.S. degree in Electrical
shedding is required. In this case, a back up Engineering from the University of Maine, Orono, and the Ph.D. degree in
under frequency system is beneficial. Electric Power Engineering at Rensselaer Polytechnic Institute, Troy, NY.
In 1987, he joined General Electric Company, Schenectady, NY, and held
2. The generation and load must be accurately a variety of positions, becoming a Senior Engineer in the GE Power Systems
characterized at the time the switching occurred. Energy Consulting Department. In 2001, he joined SuperPower, Inc.,
Schenectady, N.Y., where he worked on applications of superconductivity to
This may be difficult, if, for example, a generator electric power systems. Dr. Sutherland then joined EPRI PEAC Corporation’s
tripped on reverse power, or in the case of a (now EPRI Solutions, Inc.), Schenectady, NY office as a Consulting Engineer.
rapidly varying motor load. He is currently a Lead Consultant with GE Energy Services in Schenectady
NY. Author of numerous technical papers, he is active in the IEEE Industry
The nature of the load should be carefully examined before Applications Society, and in the IEEE Schenectady Section. Dr. Sutherland is
a load shedding system is chosen. a member of CIGRE and the IET (formerly IEE). He is a Registered
Professional Engineer in Pennsylvania, Maine and New York.

5
978-1-4244-3399-5/09/$25.00 © IEEE 2009
Preprint for Peer Review Page 6 of 8


        

   

978-1-4244-3399-5/09/$25.00 © IEEE 2009


Page 7 of 8 Preprint for Peer Review

!
"  #"$   
 ! 

978-1-4244-3399-5/09/$25.00 © IEEE 2009


Preprint for Peer Review Page 8 of 8

%
&   '$( 
  )*+

 ,* 

978-1-4244-3399-5/09/$25.00 © IEEE 2009

You might also like