1. ZONE 1
a. Step 1. Install Hanging Slab Panels 1-4 & 47-48 Note :
1. Boom length is 43 m with 72°
STEEL BOX PANEL STEEL BOX PANEL
2. Weight panel 1/2/3/4 is 500 kg
PANEL 3 PANEL 4
3. Weight panel 47/48 is 282.3 kg
PANEL 47
ZONE 1
Image 1. Top View
Page 1 of 12
No. Description
Cycle Times for panel 1/3 :
1. Lifting time = 15 min
2. Hanging formwork = 30 min +
Total = 45 min
U-ditch 60 cm U-ditch 60 cm
25900
b. Step 2. Moving Mobile Crane to Zone 2 & Preparation Stock Yard Panel
Cycle Times for move to next
PANEL 3 PANEL 4 STEEL BOX PANEL STEEL BOX PANEL zone is 30 min.
PANEL 47
Page 2 of 12
No. Description
2. ZONE 2
a. Step 1. Install Hanging Slab Panels 5-8 & 43-46 Note :
1. Boom length is 39 m with 72°
STEEL BOX PANEL STEEL BOX PANEL 2. Weight panel 5/6/7/8 is 500 kg
PANEL 7 PANEL 8
3. Weight panel 43/44/45/46 is
282.3 kg
PIER HEAD PANEL 46 PANEL 45 PIER HEAD
PILE CAP PILE CAP
AREA AREA
STOCK PANEL
PANEL 44 PANEL 43
PANEL 5 PANEL 6
STEEL BOX PANEL STEEL BOX PANEL
ZONE 2
Image 1. Top View
Page 3 of 12
No. Description
Cycle Times for panel 5/6/7/8 :
1. Lifting time = 30 min
2. Hanging formwork = 15 min +
Total = 45 min
U-ditch 60 cm U-ditch 60 cm
25900
b. Step 2. Moving Mobile Crane to Zone 3 & Preparation Stock Yard Panel
Cycle Times for move to next
PANEL 3 PANEL 4 PANEL 7 PANEL 8 STEEL BOX PANEL STEEL BOX PANEL
zone is 30 min.
PANEL 1 PANEL 2 PANEL 5 PANEL 6 STEEL BOX PANEL STEEL BOX PANEL
ZONE 2
Page 4 of 12
No. Description
3. ZONE 3
a. Step 1. Install Hanging Slab Panels 9-12 & 39-42 Note :
1. Boom length is 39 m with 72°
2. Weight panel 9/10/11/12 is 500
STEEL BOX PANEL STEEL BOX PANEL
kg
PANEL 11 PANEL 12
3. Weight panel 39/40/41/42 is
282.3 kg
PIER HEAD PANEL 42 PANEL 41 PIER HEAD
PILE CAP PILE CAP
AREA AREA
STOCK PANEL
PANEL 40 PANEL 39
PANEL 9 PANEL 10
STEEL BOX PANEL STEEL BOX PANEL
ZONE 3
Image 1. Top View
Page 5 of 12
No. Description
Cycle Times for panel 9/10/11/12 :
1. Lifting time = 30 min
2. Hanging formwork = 15 min +
Total = 45 min
U-ditch 60 cm U-ditch 60 cm
25900
b. Step 2. Moving Mobile Crane to Zone 4 & Preparation Stock Yard Panel
Cycle Times for move to next
PANEL 3 PANEL 4 PANEL 7 PANEL 8 PANEL 11 PANEL 12 STEEL BOX PANEL STEEL BOX PANEL
zone is 30 min.
PANEL 1 PANEL 2 PANEL 5 PANEL 6 PANEL 9 PANEL 10 STEEL BOX PANEL STEEL BOX PANEL
Page 6 of 12
No. Description
4. ZONE 4
a. Step 1. Install Hanging Slab Panels 13-16 & 35-38 Note :
1. Boom length is 39 m with 72°
2. Weight panel 13/14/15/16 is
STEEL BOX PANEL
PANEL 15 PANEL 16 500 kg
3. Weight panel 35/36/37/38 is
PIER HEAD PANEL 38 PANEL 37 PIER HEAD 282.3 kg
PILE CAP PILE CAP
AREA AREA
PANEL 36 PANEL 35
PANEL 13 PANEL 14
STEEL BOX PANEL
ZONE 4
Image 1. Top View
Page 7 of 12
No. Description
Cycle Times for panel 13/14/15/16
:
1. Lifting time = 30 min
2. Hanging formwork = 15 min +
Total = 45 min
U-ditch 60 cm U-ditch 60 cm
25900
b. Step 2. Moving Mobile Crane to Zone 5 & Preparation Stock Yard Panel
Cycle Times for move to next
PANEL 3 PANEL 4 PANEL 7 PANEL 8 PANEL 11 PANEL 12 PANEL 15 PANEL 16 zone is 30 min.
Page 8 of 12
No. Description
5. ZONE 5
a. Step 1. Install Hanging Slab Panels 17-20 & 31-34 Note :
STEEL BOX PANEL
1. Boom length is 39 m with 72°
PANEL 19 PANEL 20
2. Weight panel 17/18/19/20 is
500 kg
PIER HEAD PANEL 34 PANEL 33 PIER HEAD 3. Weight panel 31/32/33/34 is
PILE CAP PILE CAP 282.3 kg
AREA AREA
STOCK PANEL
PANEL 32 PANEL 31
PANEL 17 PANEL 18
ZONE 5
Image 1. Top View
Page 9 of 12
No. Description
Cycle Times for panel 17/18/19/20
:
1. Lifting time = 30 min
2. Hanging formwork = 15 min +
Total = 45 min
U-ditch 60 cm U-ditch 60 cm
25900
b. Step 2. Moving Mobile Crane to Zone 6 & Preparation Stock Yard Panel
Cycle Times for move to next
PANEL 3 PANEL 4 PANEL 7 PANEL 8 PANEL 11 PANEL 12 PANEL 15 PANEL 16 PANEL 19 PANEL 20 STEEL BOX PANEL
zone is 30 min.
PIER HEAD PANEL 48 PANEL 46 PANEL 45 PANEL 42 PANEL 41 PANEL 38 PANEL 37 PANEL 34 PANEL 33 PIER HEAD
PILE CAP PILE CAP
AREA AREA
PANEL 1 PANEL 2 PANEL 5 PANEL 6 PANEL 9 PANEL 10 PANEL 13 PANEL 14 PANEL 17 PANEL 18
Page 10 of 12
No. Description
6. ZONE 6
a. Step 1. Install Hanging Slab Panels 21-24 & 25-30 Note :
1. Boom length is 39 m with 72°
STEEL BOX PANEL
PANEL 23 PANEL 24 2. Weight panel 21/22/23/24 is
500 kg
PIER HEAD PANEL 30 PANEL 29 PANEL 28 PIER HEAD 3. Weight panel
PILE CAP PILE CAP 25/26/27/28/29/30 is 282.3 kg
AREA AREA
STOCK PANEL
PANEL 21 PANEL 22
ZONE 6
Image 1. Top View
Page 11 of 12
No. Description
Cycle Times for panel
21/22/23/24:
1. Lifting time = 30 min
2. Hanging formwork = 15 min +
Total = 45 min
U-ditch 60 cm U-ditch 60 cm
25900
NOTE :
- Total window times for closing the road (temporary) not include preparation is 2310 min or 38,5 hours.
- Not include formwork slab at central area.
2500 3600 3600 3600 3350 3350 3600 3600 3600 2500
ROW ROW
SODDING BAHU LAJUR LAJUR LAJUR LAJUR LAJUR LAJUR LAJUR LAJUR BAHU SODDING
LUAR UTAMA UTAMA UTAMA WORKINGUTAMA
GROVE
UTAMA UTAMA UTAMA UTAMA LUAR
SPACE
Marka Marka Marka Marka
Guardrail Marka Marka Marka Marka Guardrail
U-ditch 60 cm U-ditch 60 cm
10000
Page 12 of 12