You are on page 1of 151

Transmission of Power

Transmission Lines
Introduction

3/30
Transmission of Power
What is Power Transmission ?

 Power transmission is the movement of energy from its


place of generation to a location where it is applied to
performing useful work.
 Electric power is normally generated at 11-33 kV in a power
station. To transmit over long distances, it is then stepped-
up to 400kV, 220kV or 110 kV as necessary.
 Power is carried through a transmission network of high
voltage lines. Usually, these lines run into hundreds of
kilometers and deliver the power into a power grid.
Transmission of Power
What is Power Transmission ?

 The grid is connected to load centres (cities) through a


sub-transmission network of normally 33kV (or
sometimes 66kV) lines.
 These lines terminate into a 33kV (or 66kV) substation,
where the voltage is stepped-down to 11kV for power
distribution to load points through a distribution
network of lines at 11kV and lower.
Transmission of Power
Efficiency of transmission Line

 Whatever may be the category of transmission line, the


main aim is to transmit power from one end to another.
 Like other electrical system, the transmission network
also will have some power loss and voltage drop during
transmitting power from sending end to receiving end.
 Hence, performance of transmission line can be
determined by its efficiency and voltage regulation.
Transmission of Power
Efficiency of transmission Line
 Every transmission line will have three basic
electrical parameters.
 The conductors of the line will have electrical
resistance, inductance, and capacitance.
 As the transmission line is a set of conductors
being run from one place to another supported
by transmission towers, the parameters are
distributed uniformly along the line.
Transmission of Power
Efficiency of transmission Line
Power sent from sending end - line losses
=
Power delivered at receiving end.
Transmission of Power
The transmission lines are categorized as three types:

1) Short transmission Line – the line length is up to 80 km.


2) Medium Transmission Line – the line length is between
80km to 160 km.
3) Long Transmission Line – the line length is more than
160 km.
Transmission Lines

 Extra High Voltage


 110 kV, 132 kV, 220 kV, 400 kV

 Ultra High Voltage


 765kV

 High Voltage Direct Current


 ±500kV
Transmission Line Execution

Survey
&
Profile Plotting
Transmission Line Survey

 A transmission line is one of essential infrastructures of


the power supply system.
 In the site evaluation process for those facilities, it is
necessary to carefully consider not only technical issues,
but also the impact on natural environment, the influence
on local communities, and various regulations.
 To achieve optimum line length, minimise rocky and
water terrains, reduced tower angle cut points, ROW
issues etc; it is necessary to have detailed survey, profile
of transmission line route.
Transmission Line Survey

Why Surveying Is Important ?


 To optimize cost of transmission line
 Line length, number of locations, deviations.
 Minimum river crossings.
 Minimum forest areas.
 Accessibility, right of way considerations.
 To assess route constraints and do construction
planning.

 To ensure statutory clearances

 Ground clearance.
 Horizontal/Right of way clearance.
 Clearances from power lines, railway lines, road
crossings etc.
UHV Transmission Lines - 765 kV ,

Requiring Large ROW


Transmission Lines through Agricultural fields
Transmission Lines in Hilly areas
Transmission Line River Crossings
Multiple Transmission Lines
Through Same Corridor
Transmission Line Survey :
 Project Conceptualization / Project Feasibility Stage:

 Faster and accurate techniques required to evaluate


various line routes .

 Pre-Construction Stage:

 Route alignment, Detailed Mapping of right of way,


ground profiling, finalisation of tower locations.
 Detailed contouring of undulated terrain for estimation
of benching and revetment quantities

 Project Construction Stage

 Check Survey only


Detailed Survey – Modern Techniques
 Route Alignment using latest satellite imageries

superimposed on Survey of India Topographical Maps.

 Digital terrain modeling in hills using contouring data.

 Detailed Survey using GPS, Total stations or ALTM.

 Digitized contouring at undulated / hilly tower locations.

 Identification of Route constraints.

 Identification of infrastructure details .


 Tower spotting & optimization of locations using
commercial software like PLS CADD.
 Estimation of BOQ & Preparation Of Survey reports.
 Soil Investigation.
Detailed Survey – Modern Techniques

 Global Positioning System

 Total Station

 PLS CADD
Detailed Survey – Modern Techniques
Global Positioning System

 The Global Positioning System


(GPS) is a space-based satellite
navigation system that provides
location and time information in
all weather, anywhere on or
near the Earth, where there is
an unobstructed line of sight
GPS satellite.
 It is a modern technology that
improves survey engineering to
Global orientation.
Detailed Survey – Modern Techniques
Total Station
 A Total Station is a modern
surveying instrument that
integrates an electronic
theodolite with an electronic
distance meter.
 A theodolite uses a movable
telescope to measure angles in
both the horizontal and vertical
planes.
 Coordinates of an unknown point
relative to a known coordinate
can be determined using the
total station.
Detailed Survey – Modern Techniques
PLS CADD Power Line Systems –
Computer Aided Design and Drafting
 PLS-CADD is the most powerful overhead power line
design program.
 PLS-CADD is a sophisticated three-dimensional
engineering model.
 The model can be viewed in a number of different
ways: profile views, plan views, plan & profile sheets,
3-D view etc.
 PLS-CADD supports both automatic and manual
spotting.
Detailed Survey – Modern Techniques
PLS – CADD software - Some views
Transmission Line
Sample route Profile through Google Earth
Transmission Line
Sample route Profile
Transmission Line
Sample route Profile
Topo Map

Sending end
SS
AP
1
AP
2
AP
3

Bee Line

Receiving end
AP SS
4
Digitized Toposheet

Survey of India Topo Sheet Corresponding Digitized Map


indicating relevant information
Computerized Route Optimization by Study of
Alternative Routes

Alternative
3

Bee
Line Alternative
2

Existing Line Alternative 1


Digital Terrain Model –
Computerized Three Dimensional Image
Plan & Profile Drawing
Transmission Line Survey:

The detailed survey is taken up on the line route


approved by the concerned Electricity board.
Detailed survey should cover:
 Fixing of Alignment
 Fixing of Line Points
 Fixing of Angles of deviation
 Fixing of Angle Points
 Fixing of Direction Points
 Measuring of distance between Angle Points
 Levels at every 10 M interval or where there is level
difference of 30 Cm
Transmission Line Survey:

Detailed survey should include:


 Details of Roads
 Details of Villages
 P & T Lines Crossings
 All Power Lines Crossings – LT to 765 kV
 Railway Crossings
 River Crossings
 Agricultural wells, Field bunds & Earth bunds etc.
 Measuring Soil resistivity at 1 Km interval
 Trial Pits
 Crop & Tree enumeration
Transmission Line Survey:

Detailed survey Obligatory Points

AVOID:

 Reserve Forest Area


 Military Firing Ranges
 Aerodromes
 Inhabited and thickly populated areas
 Hilly terrain
 Marshy, Low lying & Submersible areas
 Higher & 90 degrees angle turnings
 Oil & Gas storage areas
Transmission Line Profile:

Detailed Profile should be


 From the details of route survey, route plan and ‘Profile’, is
prepared. Profile is also termed as Longitudinal profile or
route profile.
 The profile is prepared and plotted paper rolls of graphed
tracing paper.
 The profile shall progress from left to right.
 A typical profile is enclosed.
Transmission Line Profile
Transmission Line Profile
Transmission Line Profile
Transmission Line Profile:

Detailed Route Profile should be

 Graphical representation
 Preferably be in the Scale of
X-axis 1 Cm = 20 M
Y-axis 1 Cm = 2M
 Plot Plan of Alignment of Line from AP to AP
 Plot Distances
 Plot Levels with respect to distance
Transmission Line Profile:

Detailed Profile should include & indicate


 All Power Lines crossings: LT to 765 kV
 All P & T Lines crossings
 All Railway crossings
 All River crossings
 All Roads: Cart Tracks to National Highways
 All Villages
 All Agricultural wells
 All Field bunds & Earth bunds
 All Ponds & Lakes
 Type of Soil
 Crops & Trees
Transmission Line Profile
Transmission Line Profile:

Tower Spotting

 Identify the position of Terminal Tower.


 Start from Terminal Tower.
 Match the tower footing curve with the position of TT.
 Adjust the position of template.
 Ensure Ground Clearance.
 Identify the position of next tower.
 Move the template to the next tower.
 Repeat the procedure.
Transmission Line Profile:
Tower Spotting
NORMAL SPAN:
It is the design span
ACTUAL SPAN:
It is the actual distance between two adjacent towers
NULL POINT:
It is a point in a span where the position of the conductor is
lowest (or) It is a point in a span where the sag is maximum
WEIGHT SPAN:
The distance between two adjacent null points
WIND SPAN:
It is the distance between two centre points of adjacent spans.
Transmission Line Profile – SAG TEMPLATE
Transmission Line Profile – Span Limitations

SPAN 110 / 220 kV 400 kV


132 kV
NORMAL SPAN 320 M 350M 400 M

WIND SPAN

Both 320 M 350 M 400 M

Single 192 M 210 M 240 M

WEIGHT SPAN

Both 400 M 450 M 600/800 M

Single 240 M 270 M 300/400 M


Transmission Line Profile – Clearances

110/
Details 220 kV 400 kV
132 kV

Ground Clearance 6.1 M 8.5 M 9.0 M

LT to 132 kV and
P& T Lines
3.1 M 4.6 M 5.5 M

220 kV 4.6 M 4.6 M 5.5 M

400 kV 5.5 M 5.5 M 5.5 M


Transmission Line Profile – Clearances

110 /
Details 220 kV 400 kV
132 kV

Highway Crossing 9M 9M 9M

Railway Crossing 14.6 M 15.4 M 17.9 M

Railway Crossing
2/3 of NS 2/3 of NS 2/3 of NS
Span (Max)

Distance between
Tower & Railway TH+6 M TH+6 M TH+6 M
Track (Min)
Transmission Line – Tower Schedule

Left
Type Angle of Span Right Wt.
Location Wt. Total Wt. Remarks
of Deviation (M) Span
No. Span Span (M)
Tower (degrees) (M)
(M)
Boom at sending
SS Boom - - - -
end SS

70

Terminal tower at
1 TT S 35 L - 75 -
sending end SS

210

2 P - 135 150 285

300

3 R 22 R 150 130 280 Near village

280

4 P+3 - 150 125 255 33 kV Line crossing

250
Transmission Line Profile:

Check Survey

 Marking of Tower Location

 Forward & Backward Line Points

 Pit Marking

 Excavation
Transmission
Line
Foundation
Transmission Tower Foundation
Type of loads on foundation :

The foundation of towers are normally subjected to three


types of forces. These are:

a) The compression or downward thrust.


b) The tension or uplift.
c) The lateral forces of side thrusts in both transverse
and longitudinal directions.
Transmission Tower Foundation
Depending on the type of soil and the presence of surface
water table , four types of foundation will be used for each
type of tower location.

 Normal dry type :


To be used for location in normal day cohesive or non-
cohesive soils.
 Partially sub-merged type :
To be used at locations where sub soil water table is
met between 0.75 metre below the ground line.
Transmission Tower Foundation
 Fully sub-merged type :
To be used at locations where sub-soil water table is met
at less than 0.75 metre below the ground line.
 Wet type :
To used for locations:
1. Where sub-soil water is met at 1.5 m or more below
the ground line.
2. Which are in surface water for long periods with water
penetration not exceeding one metre below the ground
3. In black cotton soils.
Transmission Tower Foundation

In addition, depending on the site conditions, other types of


foundations may be introduced suitable for:

 Intermediate conditions under the above classification to


effect more economy, or

- For locations in hilly and rocky areas.


- For locations where special foundations (well type or
piles) are necessitated.
Transmission Tower Foundation

Testing of soil

It is desirable to undertake testing of soil for all the tower


locations and report should be obtained about the sub-soil
water table, bearing capacity of soil, possibility of
submergence and other soil properties required for the correct
casting of casing of foundations.
Transmission Tower Foundation

Testing of soil

It is desirable to undertake testing of soil for all the tower


locations and report should be obtained about the sub-soil
water table, bearing capacity of soil, possibility of
submergence and other soil properties required for the correct
casting of casing of foundations.
Transmission Tower Foundation

Tower Foundation:

1. Excavation
2. PCC
3. Stub setting
4. Template Alignment
5. Concreting
6. Curing
7. De-shuttering & Template removal.
8. Back- Filling
Transmission Tower Foundation
Excavation
Transmission Tower Foundation
Excavated pit on hard rock
Transmission Tower Foundation
Water at Excavated pit Dewatering
Transmission Tower Foundation
Stub setting & Template Assembly
Transmission Tower Foundation
Stub setting & Template Assembly
Transmission Tower Foundation
Base levelling with sand filling
Transmission Tower Foundation
PCC
Transmission Tower Foundation
Raft Concrete
Transmission Tower Foundation

Stub Footing concrete Stub Concrete


Tower Erection

69/30
Transmission Tower Erection
Method of Tower Erection

There are four main methods of erection of steel


transmission towers which are described below:

1) Build-up method or Piecemeal method.


2) Section method.
3) Ground assembly method.
4) Helicopter method.
Transmission Tower Erection
Build Up Method of Tower Erection

This method is most commonly used in India for the erection


of 66kV, 132kV, 220kV and 400kV transmission line towers.

 This method consists of erecting the towers, member by


member. The tower members are kept on ground serially
according to erection sequence to avoid search or time loss.
 The erection progresses from the bottom upwards. The four
main corner leg members of the first section of the tower
are first erected and bolted with the stub.
Transmission Tower Erection
Build Up Method of Tower Erection

 The cross braces of the first section which are already


assembled on the ground are raised one by one as a unit
and bolted to the already erected corner leg angles.
 The cross braces of the first section which are already
assembled on the ground are raised one by one as a unit
and bolted to the already erected corner leg angles.
 The members / sections are hoisted either manually or by
winch machines operated from the ground.
 After the tower top is placed and all side lacing are bolted
up. Cross – Arms are erected as complete unit .
Transmission Tower Erection
Section Method of Transmission Tower Erection

In the section method, major sections of the tower are


assembled on the ground and the same are erected as units.
These Units are erected with the help of mobile cranes.

Ground Assembly Method of Tower Erection


This method consists of assembling the tower on ground, and
erecting it as a complete unit. The complete tower is
assembled in a horizontal position on even ground.
In India, this method is not generally adopted because of
prohibitive cost of mobile crane, and non-availability of good
approach roads to tower locations.
Transmission Tower Erection

Helicopter Method 1

• In the helicopter method, the


transmission tower is erected in
section. Sometimes a completely
assembled tower is raised with
the help of helicopter.
• This method is mostly used
where access to the tower
location is limited.
Transmission Tower Erection
Tower erection - Finishing Works

 All nuts shall be tightened with one to two threads shall be


projected outside the nuts.
 Punching after nut tightening and tack welding shall be
done along with bolt and nut together to ensure that the
nuts are not loosened in course of time.
 The joints shall be painted with zinc paint on all contact
surfaces during the course of erection to avoid rusting.
 The finally erected tower shall be truly vertical after
erection. Tolerance limit for vertical shall be one in 360 of
the tower height.

Transmission Tower Foundation
Tower Erection in progress
Electrical Transmission Tower types and design

 The main supporting unit of overhead transmission


line is transmission tower.
 Transmission towers have to carry the heavy
transmission conductor at a sufficient safe height
from ground. In addition to that all towers have to
sustain all kinds of natural calamities.
 So transmission tower designing is an important
engineering job where all three basic engineering
concepts, civil, mechanical and electrical engineering
concepts are equally applicable.
Tower Erection

78/30
Electrical Transmission Tower types and design

A transmission tower consists of the following parts.

1) Peak of transmission tower


2) Cross arm of transmission tower
3) Boom of transmission tower
4) Cage of transmission tower
5) Transmission Tower Body
6) Leg of transmission tower
7) Stub/Anchor Bolt and Base plate assembly of
transmission tower.
Electrical Transmission Tower types and design

Peak of Transmission Tower

The portion above the top cross


arm is called peak of
transmission tower. Generally
earth shield wire connected to
the tip of this peak.
Electrical Transmission Tower types and design

Cage of Transmission Tower

The portion between tower body


and peak is known as cage of
transmission tower. This portion of
the tower holds the cross arms.
Electrical Transmission Tower types and design

Cage of Transmission Tower

The portion between tower body


and peak is known as cage of
transmission tower. This portion of
the tower holds the cross arms.
Electrical Transmission Tower types and design

Cross Arms of Transmission Tower

The portion from bottom cross arms


up to the ground level is called
transmission tower body.
This portion of the tower plays a vital
role for maintaining required ground
clearance of the bottom conductor of
the transmission line.
Electrical Transmission Tower types and design

Design of Transmission Tower


During Design of transmission tower the following points
to be considered in mind.
1. The minimum ground clearance of the lowest
conductor point above the ground level.
2. The length of the insulator string.
3. The minimum clearance to be maintained between
conductors & between conductor and tower.
4. The location of ground wire with respect to outer
most conductors.
Electrical Transmission Tower types and design

Transmission Tower
To determine the actual transmission
tower height by considering the above
points, we have divided the total height of
tower in four parts.
1. Minimum permissible ground clearance
(H1).
2. Maximum sag of the conductor (H2).
3. Vertical spacing between top and
bottom conductors (H3).
4. Vertical clearance between ground
wire and top conductor (H4).
Electrical Transmission Tower types and design

Types of Transmission Tower

According to different considerations, there are different


types of transmission towers.
The transmission line goes as per available corridors.
Due to unavailability of shortest distance straight
corridor transmission line has to deviate from its straight
way when obstruction comes.
In total length of a long transmission line there may be
several deviation points.
Electrical Transmission Tower types and design

Types of Transmission Tower

According to the angle of deviation there are four types


of transmission tower.

1) A – type tower – angle of deviation 0 to 2


2) B – type tower – angle of deviation 2 to 15
3) C – type tower – angle of deviation 15 to 30
4) D – type tower – angle of deviation 30 to 60
Electrical Transmission Tower types and design

Types of Transmission Tower

As per the force applied by the conductor on the cross


arms, the transmission towers can be categorized in
another way.
1. Tangent suspension tower and it is generally A - type
tower.
2. Angle tower or tension tower or sometime it is called
section tower. All B, C and D types of transmission
towers come under this category.
Electrical Transmission Tower types and design

Types of Transmission Tower

Apart from the above customized type of tower, the


tower is designed to meet special usages.

1. River crossing tower.


2. Railway/ Highway crossing tower.
3. Transposition tower.

These are called special type tower.


Electrical Transmission Tower types and design

Classification of Transmission Tower

Based on numbers of circuits carried by a transmission


tower, it can be classified as:

1. Single circuit tower


2. Double circuit tower
3. Multi circuit tower.
Transmission Tower Erection
Method of Tower Erection

There are four main methods of erection of steel


transmission towers which are described below:

1) Build-up method or Piecemeal method.


2) Section method.
3) Ground assembly method.
4) Helicopter method.
Transmission Tower Erection
Build Up Method of Tower Erection

This method is most commonly used in India for the erection


of 66kV, 132kV, 220kV and 400kV transmission line towers.
 This method consists of erecting the towers, member by
member. The tower members are kept on ground serially
according to erection sequence to avoid search or time loss.
 The erection progresses from the bottom upwards. The four
main corner leg members of the first section of the tower
are first erected and bolted with the stub.
 The members / sections are hoisted either manually or by
winch machines operated from the ground
Transmission Tower Erection
Build Up Method of Tower Erection
Transmission Tower Erection

Section Method of Transmission


Tower Erection

In the section method, major sections of the tower


are assembled on the ground and the same are
erected as units. Units are erected with the help of
mobile cranes.
Transmission Tower Erection
Ground Assembly Method of Tower Erection

This method consists of assembling the tower on


ground, and erecting it as a complete unit. The
complete tower is assembled in a horizontal position
on even ground.
After the assembly is complete the tower is picked
up from the ground with the help of a crane and
carried to its location, and set on its foundation.
Transmission Tower Erection

Helicopter Method 1

• In the helicopter method, the


transmission tower is erected in
section. Sometimes a completely
assembled tower is raised with
the help of helicopter.
• This method is mostly used
where access to the tower
location is limited.
Transmission Tower Erection
Transmission Tower Erection
Transmission Tower Erection
Transmission Tower Foundation
Cross Arms assembled on ground for erection
Transmission Tower Foundation
Cross Arms Erected
Transmission Tower Erection
Tower erection - Finishing Works

 All nuts shall be tightened with one to two threads shall be


projected outside the nuts.
 Punching after nut tightening and tack welding shall be
done along with bolt and nut together to ensure that the
nuts are not loosened in course of time.
 The joints shall be painted with zinc paint on all contact
surfaces during the course of erection to avoid rusting.
 The finally erected tower shall be truly vertical after
erection. Tolerance limit for vertical shall be one in 360 of
the tower height.

Stringing

103/30
Transmission of Power
Stringing

 Stringing overhead conductors in transmission is a very


specialized type of construction requiring years of
experience, as well as equipment and tools that have
been designed, tried, and proven to do the work.
Transmission of Power
Medhods of installing

There are four methods that can be used to


install overhead transmission conductors:

 Slack stringing
 Semi-tension stringing
 Full-tension stringing
 Helicopter stringing
Transmission of Power
Slack stringing

 This type is normally limited to lower voltage lines and


smaller conductors.
 The conductors are normally placed on “Reels” or “Jack
Stand” and it is unreeled from the drum and dragged
along the ground by vehicle or pulling device.
 This method is typically used during construction of
new lines where Right Of Way is readily accessible.
Transmission of Power

Semi Tension method of stringing

Semi tension methods are merely an upgrading of slack


stringing, but do not necessarily keep the conductor
completely clear of the ground, or the lines used to pull
Transmission of Power
Full Tension method of stringing
 This is a method of installing the conductors in which
sufficient pulling capabilities on one end and tension
capabilities on the other, keep the wires clear of any
obstacles during the movement of the conductor from
the reel to its final sag position.
 This ensures that these current-carrying cables are
“clipped” into the support clamps in the best possible
condition, which is the ultimate goal of the work itself.
Transmission of Power
Stringing with helicopters

 This is much more expensive per hour of work, but can be much
less expensive when extremely arduous terrain exists along the
right-of-way and when proper pre-planning is utilized.
 Although pulling conductors themselves with a helicopter can be
done, it is limited and normally not practical.
 Maximum efficiency can be achieved when structures are set and
pilot lines are pulled with the helicopter, and then the conductor
stringing is done in a conventional manner.
Transmission Line
Component of Transmission Line
Transmission Line
Components of Transmission Line
Common Tools Required for Stringing
Common Tools Required for Stringing
Common Tools Required for Stringing
Common Tools Required for Stringing
Material Handling - Conductors
Handling, Loading /Unloading ,Transport & Storage
Material Handling - Conductors
Handling, Loading /Unloading ,Transport & Storage
1. Handling and transporting of the conductor and accessories shall
be carried out in such a manner as to minimize the possibility of
damages from abrasion through rough handling or dirt and grit.
2. The drums should always be transported in vertical position with
the cable ends fixed to prevent cable from slackening.
3. The drum should not be stored on its side under any
circumstances whatsoever.
4. The ends of the cable should be sealed to prevent water
penetration.
5. Loading and unloading are performed so that the drum remains
in vertical position and the sides of the drum are not damaged.
Material Handling - Conductors
Avoid storage like this
Transmission of Power
Stringing Procedure

The stringing procedure is broadly divided into the


following steps:

 Paying out & stringing of Conductor.


 Paying out & stringing of Earthwire.
 Final sagging of Earthwire and conductor.
 Clipping & Fixing accessories.
Transmission of Power
Steps of Stringing

 Proper Guying
 Insulator Hoisting.
 Paying out of pilot wire & Conductor.
 Rough sagging of conductor.
 Final sagging of conductor.
 Clipping & Spacering.
 Finishing activities.
 Jumpering.
 Final Checking.
Guying
Before commencing of stringing, the angle towers where the
stringing is to be started must be provided with guy supports.
Guying
Precautions which should be taken at the time of guying?

 The guys used generally are 20 mm steel wire rope. The guys are
attached to the tower at the tip of the cross arm , to the strain
plates with suitable D-shackles.
 The guys are anchored in the ground at an angle of 45 deg. or
less from the horizontal, attached to dead end anchors .
 The guy wire is attached to the dead end anchor wire with the
help of turn buckles of 10 tons capacity.
 Excessive tightening of guy should be avoided. It is advisable to
tighten the guy progressively at the time of rough sagging of the
conductor.
Guying – Anchoring on ground
Insulator Hoisting
Insulator Hoisting
 Single / Double suspension insulator strings are used on
suspension towers and single /double tension insulator strings are
used on angle and dead end towers. This is generally indicated in
the tower schedule.
 Double suspension insulator strings are used lines on Suspension
towers of Railway, River and Power Line Crossings only.
Suspension Type Insulators

Consist of a number of porcelain discs


connected in series by metal links in
the form of a string.
Suspension Type Insulators

 The conductor is suspended at the


bottom end of this string while the
other end of the string is secured
to the cross-arm of the tower.
 These insulators have a number of
interconnected porcelain discs,
with each unit designed to support
a particular voltage.
 Together, a system of these discs is
capable of effectively supporting
high voltages.
Strain Type Insulators

 When there is a dead end of the


line or there is corner or sharp
curve, the line is subjected to
greater tension. To relieve the line
of excessive tension, strain
insulators are used.
 However, for the high voltage
transmission lines, strain insulator
consists of an assembly of
suspension insulators as shown.
Strain Type Insulators

 Strain type insulators are


horizontally suspended suspension
insulators.
 When the tension in lines is
exceedingly high, at long river
spans, power line, railway & road
crossings, two or more strings are
used in parallel.
 Strain insulators are typically used
for high voltage transmissions.
Silicon Rubber Composite Insulators

Composite insulators with silicone

rubber sheds offer advantages over

traditional ceramics:

 Improved safety for personnel

and equipment.

 superior pollution performance

due to hydrophobic surface

condition.

 Excellent seismic performance.

 Low weight & Flexible design

 Short delivery times


Insulator fitted with Roller and Pulley
for conductor Payout
Insulator Prepared for Hoisting
Insulator Hoisting
Insulator Hoisting
Payout
 The paying out of conductor is done generally between two
tension towers. In between two tension towers, there could
be either zero or one or more suspension towers.
 A pilot wire is used to pull the conductor. The pilot wire is
initially laid through the centre wheel of the roller.
 The pilot wire can be laid and joined with pilot wire
connectors or it can be pulled from one side of the section.
 Scaffolding shall be provided for P&T and road crossing before
paying out of the pilot wire.
Stringing Procedure
Drum Scheduling - Basics
1. For effective utilization of the conductor and to prevent Wastage
of the conductor.
2. Details of Tower schedule, Receipt of drum details, Standard
length of each drum.
3. Knowledge of Usage of cut lengths for Jumpers and Short Spans.
4. All the joints or splices shall be made at least 30 metres away
from the tower structures.
5. No joints or splices shall be made in spans crossing over main
roads, railways and small river tension spans.
6. Not more than one joint per sub conductor per span shall be
allowed.
Transmission Line
Tower Schedule
Transmission Line
Sample Drum Scheduling
Paying out Earthwire

Earthwire drum on turn table& unreeling in


progress for payout.
Payout of Earthwire
Final tensioning of Earthwire
Precautions before conductor Payout
Precautions before conductor Payout
Conductor Payout through Suspension Towers
Conductor Passing through rough terrains
Conductor Payout for each Phase
Conductor Rough Sag in progress
Conductor tensioning using come along Clamp and
four sheave pulleys
Conductor Stringing Completed
Transmission Line Work Completion

You might also like