CONTENTS
1.0 PURPOSE
1.1 Overview
The location of the 3 sets of produced water pre-separator tanks installation distribution in DS6 、DS7
and DS8,1 set produced water tank is located in the DS7.
Refer to the arrangement drawing below:
2 Warehouse 12m*3.6m*3m 2
3 Meeting Room 12m*3.6m*3m 1
Welding Rod
4 12m*3.6m*3m 1
Drying Room
5 Office 12m*3.6m*3m 2
6 Medical Room 12m*3.6m*3m 1
7 Dinner Room 12m*3.6m*3m 1
Pre-separator Tank 15
16
Generator
Material Storage
500KW
20m*30m
2
1
17 Prefabrication
20m*35m 1
Platform
18 Fence 2.5m 520m
19 T Wall 2.5m 160m
20 Bunker 2.5*2.5*6m 3
21 Gate 8*2.5m 2
22 Gate 5*2.5*6m 1
2 Warehouse 12m*3.6m*3m 2
3 Meeting Room 12m*3.6m*3m 1
Welding Rod
4 12m*3.6m*3m 1
Drying Room
5 Office 12m*3.6m*3m 2
6 Medical Room 12m*3.6m*3m 1
7 Dinner Room 12m*3.6m*3m 1
16 Generator 100KW 2
17 Material Storage 20m*30m 1
18 Prefabrication
20m*40m 1
Platform
19 Fence 2.5m 700m
20 T Wall 2.5m 160m
21 Bunker 2.5*2.5*6m 5
22 Gate 8*2.5m 3
23 Gate 5*2.5*6m 1
2 Warehouse 12m*3.6m*3m 2
3 Meeting Room 12m*3.6m*3m 1
Welding Rod
4 12m*3.6m*3m 1
Drying Room
5 Office 12m*3.6m*3m 2
6 Medical Room 12m*3.6m*3m 1
7 Dinner Room 12m*3.6m*3m 1
15 Generator 500KW 2
Prefabrication of bottom plates, roof plates and shell plates will be done in site. 55t mobile crane and
25t mobile crane will be used for the lifting works of the tank.
The purpose of this Method Statement is to describe lifting process and method using the crane and
lifting clamp the location of the crane when working safety controls.
Weight of steel plates to be calculated on the basis of the sizes of the existing.
Table 2.2-1 List of Main Work of Liftingproduced water pre-separator tank
Quantity/
NO. Describe Elevation /mm SIZE(L*W*H)/mm Weight/Kg
pieces
1 Bottom Plate(BP1) 0-64.2 10000*2000*10 1570 3
2 Shell Plate(S1/S2/S3) 0-11110 10000*2000*10 1884 12
3 Roof plate(R2) 11110-11472 6849*1745/264 384 84
4 Roof circle Structure (R1) 11110-11472 Φ1050 190 3
Table 2.2-2 List of Main Work of Liftingproduced water tank
Quantity/
NO. Describe Elevation /mm SIZE(L*W*H)/mm Weight/Kg
pieces
1 Bottom Plate(BP1) 0-302 10000*2000*10 1570 3
2 Shell Plate(S1/S2/S3) 0-11110 10000*2000*10 1884 12
3 Roof plate(R2/R3) 11110-13203 6429*1665/264 660 84
4 Roof circle Structure(R1) 11110-13203 Φ2100 190 3
Due to the difference with the size and weight of component, to select crane capacity basis of the biggest one.
Table2.3-1 List of Main Lifting Performance for produced water pre-separator tank
Chart Rate of
Weight of hook Total Boom
Weight of rigging Radius capacity in capacity
NO. Describe Net Weight/t block and lifting Selected crane length
accessories /t /m working max load of
dynamic rope /t lode /t /m
radius /t crane/%
GT550-E
0.75 2.37 20 38.1 3.6 65.8
55t mobile crane
Bottom Plate(BP1
1 1.57 0.05
location in center) KATO NK-250E-Ⅲ
0.25 1.87 16 26.2 2.45 76.4
25t mobile crane
Chart Rate of
Weight of hook Total Boom
Weight of rigging Radius capacity in capacity
NO. Describe Net Weight/t block and lifting Selected crane length
accessories /t /m working max load of
dynamic rope /t lode /t /m
radius /t crane/%
GT550-E
0.75 2.684 20 38.1 3.6 74.6
55t mobile crane
GT550-E
3 Roof plate(R2) 0.384 0.05 0.75 1.184 22 42 2.5 47.4
55t mobile crane
Roof circle GT550-E
4 0.19 0.05 0.75 0.99 22 42 2.5 40
Structure (R1) 55t mobile crane
NOTE:- Total lifting lode = Net Weight + Weight of rigging accessories + Weight of hook block and dynamic rope.
-Rate of capacity load of crane = Total lifting lode÷Chart capacity in working max radius×100%.
Method of lifting bottom plates, roof plates and shell plates is “Single Crane Hoisting Method”, construction
flow chart as follow:
Crane in position
Sling connection
Joint inspection
Trial hoisting
Formal hoisting
Object in position
Sling release
Crane demobilization
Fig 3.1 Construction flow chart of the “Single Crane Hoisting Method”
The horizontal Plate lifting clamp be used to hoisting horizontal plate, sketch as follow:
For irregular shaped steel plate,will be lift using 2 or 3 lifting points according to the location of center of
gravity.
The Vertical Plate Lifting Clamp be used to hoisting vertical plate, sketch as follow:
Fig 3.2D The small size sheet plate upright lifting and turning over sketch
4¡ Á
5t 3m chain hoist
74¡ ã
8
2013
Using the hand chain hoist
shortening chain to adjust
53
¡ã
3635 3489
1432 1524 1554 1592 1607
1625 1661 1662 1675 1682 1688 1553
10¡ã
3820
19256
Fig 3.2F the roof sector steel structure lifting assembly sketch
- Light weight of the plate, in particular the plate distributed on the edge of foundation
- Using 25t mobile crane and 55t mobile crane placed at the edge of foundation, lifting the
plate
R16
000 5508
6800
2284,2
R2
95
6,
5
4438,8
0
2820
65
R3
R20000
5480
NK250E
25t crane
GT550-E
55t crane
25t Mobile
Crane
55t Mobile
Crane
Layout for Lifting Bottom Plate
Fig 3.3.1 Layout for lifting bottom plate
- A 25t mobile crane or 55t mobile crane will be used for lifting the shell plate
R1
40
00
5508
2284,2
R2
95
6800
6,
5
4438,8
0
2820
65
R3
NK250E
25t crane
R20000
5480
GT550-E
55t crane
25t Mobile
Crane
55t Mobile
Crane
Layout for Lifting Bottom Plate
6800
0
2820
65
R3
5480
R2200
0
GT550-E
55t crane
55t Mobile
Crane
Staff involved in lifting must be certificate,ensure that crane operators are qualified based on the
requirements set by local regulatory authorities.
Each mobile crane must be inspected by a competent person for mechanical defects upon its arrival, once
again before its use on the site, and monthly thereafter.
All lifting tackle must be certified.
The lift supervisor shall inspect all tackle prior to use.
Any damaged tackle item shall be marked ‘NOT FOR USE’ and returned to depot for disposal.
Nylon slings must be protected from sharp corners using suitable packing.
The safe working load (SWL) must be prominently displayed on the boom of anycrane and clearly marked
on other lifting devices.
Considering the total load to be lifted (including applicable crane component weights) and crane
configuration, the lift must not exceed 85 percent of the crane capacity for the greatest radius the load
achieves during pick, swing, or set. If the load exceeds 85%.the lift will be classified as a critical lift.
If changing the crane configuration within the manufacturer specifications provides greater gross capacity,
the modified configuration must be used to keep the lift below 85 percent capacity. If not, a larger capacity
crane must be used.
A lift is classified as critical, critical lifts must have a formal Critical Lift Plan/Rigging study before being
executed.
PROBABILITY
E. VERY LIKELY TO OCCUR NO CONTROLS IN PLACE
D. LIKELY TO OCCUR ONLY ONE PROCEDURAL CONTROL IS IN PLACE
C. COULD OCCUR MULTIPLE CONTROLS ARE IN PLACE BUT INCLUDE ONLY PROCEDURAL BARRIERS.
B. UNLIKELY TO OCCUR MULTIPLE CONTROLS ARE IN PLACE WHICH INCLUDE PROCEDURAL AND ACTIVE BARRIERS.
A. VERY UNLIKELY TO OCCUR MULTIPLE CONTROLS ARE IN PLACE WHICH INCLUDE AT LEAST ONE PASSIVE BARRIER, ACTIVE BARRIERS AND PROCEDURAL BARRIERS.
ATTACHMENTS