Clause Identification of risk Red Book Yellow Book Silver Book
4.7 Setting Out (of original E E C
points, lines and levels of reference) 4.12 Unforeseeable Physical S S C Conditions Time = E Time = E Costs = E Costs = E Overhead = E Overhead = E Profit = C Profit = C 4.24 Fossils S S S Time = E Time = E Time = E Costs = E Costs = E Costs = E Overhead = E Overhead = E Overhead = E Profit = C Profit = C Profit = C 7.4 Employer’s Delay in E E E Performing Tests 7.5 Rejection of Plant, C C C Material or Workmanship 7.6 Remedial Work C C C 8.4 Extension of Time for S S S Completion Time = E Time = E Time = E Costs = C Costs = C Costs = C Overhead = C Overhead = C Overhead = C Profit = C Profit = C Profit = C 8.4 Exceptionally Adverse S S C Climatic Conditions Time = E Time = E Costs = C Costs = C Overhead = C Overhead = C Profit = C Profit = C 8.5 Delays Caused by S S S Authorities Time = E Time = E Time = E Costs = C Costs = C Costs = C Overhead = C Overhead = C Overhead = C Profit = C Profit = C Profit = C 8.6 Insufficient Rate of C C C Progress 8.9 Consequences of S S S Suspension Time = E Time = E Time = E Costs = E Costs = E Costs = E Overhead = E Overhead = E Overhead = E Profit = C Profit = C Profit = C 9.4 Failure to Pass Tests on C C C Completion 10.2 Taking Over of Parts of E E E the Works 10.3 Interference with Tests E E E on Completion 11.4 Failure to Remedy C C C Defects 486 Appendix E: FIDIC Forms Risk Allocation Charts
Clause Identification of risk Red Book Yellow Book Silver Book
11.8 Contractor to Search S S S
for the Cause of any Time = C Time = C Time = C Defect Costs = E Costs = E Costs = E Overhead = E Overhead = E Overhead = E Profit = E Profit = E Profit = E 12.3 Evaluation E or C - - 12.4 Omission of any Work S - - Red Book according to Variation Time = C Costs = E Overhead = E Profit = C 12.4 Failure to Pass Tests - C C Yellow & after Completion Silver Book 13.3 Variation Procedure S S S Time = C Time = C Time = C Costs = E Costs = E Costs = E Overhead = E Overhead = E Overhead = E Profit = C Profit = E Profit = E 13.7 Adjustments for S S S Changes in Legislation Time = E Time = E Time = E Costs = E Costs = E Costs = E Overhead = E Overhead = E Overhead = E Profit = C Profit = C Profit = C 13.8 Adjustments for E or C E or C C Changes in Costs (Indexation) 14.8 Delayed Payment E E E 15.4 Payment after C C C Employer’s Termination 16.1 Contractor’s E E E Entitlement to Suspend Work 16.4 Payment after E E E Contractor’s Termination 17.1 Indemnities E or C E or C E or C 17.4 Consequences of E E E Employer’s Risks 19.4 Consequences of Force S S S Majeure Time = E Time = E Time = E Costs = E Costs = E Costs = E Overhead = E Overhead = E Overhead = E Profit = C Profit = C Profit = C