Demolition & Dismantling Works (Non-Heritage Block)

Bracing of Heritage Block (Peripheral Wall)


Al Shafi Enterprises Commencement Date: December 15, 2017
Daily Construction Report
Site Info:
Site Name Silk Bank Tower
Owner JCL Reporting Date DATE: 11-01-2018

Subcontractor No. Contractor Al-Shafi Enterprises


Daily Job Report # 28 Day of Week Thursday

Weather
Weather type (Sunny/Cloudy/Rainy) Time Temperature C
Sunny 1200PM Max. 28`

Site Visitor
Name Organization Time In Time Out

ASE Site Staff:


Designation No. Work Hours Designation No. Work Hours
Project Manager 01

Project Engineer 01
Site Supervisor 01
Guard 02

Total 05
Demolition & Dismantling Works (Non-Heritage Block)
Bracing of Heritage Block (Peripheral Wall)
Al Shafi Enterprises Commencement Date: December 15, 2017

Daily Construction Report

Description of Works:
Current Week Targets:
Target Work Done Labor Details
Activity Job Today

Skilled Un-Skilled

Fencing (General Labors from ASE) Folder 02


1. State Bank (Office + Mech. room) Side
Fencing is in progress (95% completed) Labor 03

Dismantling Contractor Labor 08


Dismantling work started at 1st floor of
NHB
Support Bracing work for Heritage Building Welders 06
Bracing work in progress
Pipes erected = 40 /1080 = 3.7% of total
Props of GF =360,
For three floor = 1080
Prop frame in process = 40
1 prop frame avg = 37.12 kg
Total work done till now = 1491kg erected
Frame work prepared at ground = 1491 kg
Total = 2982 kg

Total 08 11
(Skilled + Unskilled)
Total Manpower 20 NOS.

Back Log Activities


Back Log:
Activity Target Work Done Total Achieved Labor Details
Quantum Today

-
-