CALCULO DE CARGAS ELECTRICAS

PROYECTO: MEJ. DE AREAS DEPORTIVAS, AREAS DE ORNATO Y DE LOS ACCESOS AL ESTADIO


DANIEL ALCIDES CARRION DISTRITO CHAUPIMARCA, PROVINCIA PASCO - PASCO

TC-1

C-1
CANT. LUM. CARGA CARGA FACTOR MAXIMA LONGITUD

UNITARIA INSTALADA DEMANDA DEMANDA SUBTERRA AEREA


ALUMBRADO 13.00 80.00 1,040.00 100% 1,040.00 165.00

CARGAS MOVILES 500.00 30% 150.00

TOTALES 1,540.00 1,190.00 165.00 0.00

SOLUCION ADOPTADA

NYY BIPOLAR 0,6/1 KV 2x4MM2


CALCULO DE CARGAS ELECTRICAS
PROYECTO: MEJ. DE AREAS DEPORTIVAS, AREAS DE ORNATO Y DE LOS ACCESOS AL ESTADIO
DANIEL ALCIDES CARRION DISTRITO CHAUPIMARCA, PROVINCIA PASCO - PASCO

TC-1

C-2
CANT. LUM. CARGA CARGA FACTOR MAXIMA LONGITUD

UNITARIA INSTALADA DEMANDA DEMANDA SUBTERRA AEREA


ALUMBRADO 17.00 80.00 1,360.00 100% 1,360.00 165.00

CARGAS MOVILES 500.00 30% 150.00

TOTALES 1,860.00 1,510.00 165.00 0.00

SOLUCION ADOPTADA

NYY BIPOLAR 0,6/1 KV 2x4MM2


CALCULO DE CARGAS ELECTRICAS
PROYECTO: MEJ. DE AREAS DEPORTIVAS, AREAS DE ORNATO Y DE LOS ACCESOS AL ESTADIO
DANIEL ALCIDES CARRION DISTRITO CHAUPIMARCA, PROVINCIA PASCO - PASCO

RESUMEN CIRCUITO C.I. M.D. AMP.

C-1 1,540.00 1,190.00 3.47


C-2 1,860.00 1,510.00 4.40

TOTALES 3,400.00 2,700.00

SUMINISTRO PREVISTO : 2,700.00 W

IN= 13.64 AMP TW 450/750 V 1x10 AWG


Id= 15.68 AMP AMP. ELEGIDO : 20 AMP
CALCULO DE CARGAS ELECTRICAS
PROYECTO: MEJ. DE AREAS DEPORTIVAS, AREAS DE ORNATO Y DE LOS ACCESOS AL ESTADIO
DANIEL ALCIDES CARRION DISTRITO CHAUPIMARCA, PROVINCIA PASCO - PASCO

TC-2

C-1
CANT. LUM. CARGA CARGA FACTOR MAXIMA LONGITUD

UNITARIA INSTALADA DEMANDA DEMANDA SUBTERRA AEREA


ALUMBRADO 12.00 80.00 960.00 100% 960.00 200.00

CARGAS MOVILES 500.00 30% 150.00

TOTALES 1,460.00 1,110.00 200.00 0.00

SOLUCION ADOPTADA

NYY BIPOLAR 0,6/1 KV 2x4 MM2


CALCULO DE CARGAS ELECTRICAS
PROYECTO: MEJ. DE AREAS DEPORTIVAS, AREAS DE ORNATO Y DE LOS ACCESOS AL ESTADIO
DANIEL ALCIDES CARRION DISTRITO CHAUPIMARCA, PROVINCIA PASCO - PASCO

TC-2

C-2
CANT. LUM. CARGA CARGA FACTOR MAXIMA LONGITUD

UNITARIA INSTALADA DEMANDA DEMANDA SUBTERRA AEREA


ALUMBRADO 8.00 80.00 640.00 100% 640.00 90.00

CARGAS MOVILES 500.00 30% 150.00

TOTALES 1,140.00 790.00 90.00 0.00

SOLUCION ADOPTADA

NYY BIPOLAR 0,6/1 KV 2x4 MM2


CALCULO DE CARGAS ELECTRICAS
PROYECTO: MEJ. DE AREAS DEPORTIVAS, AREAS DE ORNATO Y DE LOS ACCESOS AL ESTADIO
DANIEL ALCIDES CARRION DISTRITO CHAUPIMARCA, PROVINCIA PASCO - PASCO

RESUMEN CIRCUITO C.I. M.D. AMP.

C-1 1,460.00 1,110.00 3.24


C-2 1,140.00 790.00 2.30

TOTALES 2,600.00 1,900.00

SUMINISTRO PREVISTO : 1,900.00 W

IN= 9.60 AMP TW 450/750 V 1x10 AWG


Id= 11.04 AMP AMP. ELEGIDO : 20 AMP
CALCULO DE CARGAS ELECTRICAS
PROYECTO: MEJ. DE AREAS DEPORTIVAS, AREAS DE ORNATO Y DE LOS ACCESOS AL ESTADIO
DANIEL ALCIDES CARRION DISTRITO CHAUPIMARCA, PROVINCIA PASCO - PASCO

TC-3

C-1
CANT. LUM. CARGA CARGA FACTOR MAXIMA LONGITUD

UNITARIA INSTALADA DEMANDA DEMANDA SUBTERRA AEREA


ALUMBRADO 8.00 80.00 640.00 100% 640.00 60.00

CARGAS MOVILES 500.00 30% 150.00

TOTALES 1,140.00 790.00 60.00 0.00

SOLUCION ADOPTADA

NYY BIPOLAR 0,6/1 KV 2x4 MM2


CALCULO DE CARGAS ELECTRICAS
PROYECTO: MEJ. DE AREAS DEPORTIVAS, AREAS DE ORNATO Y DE LOS ACCESOS AL ESTADIO
DANIEL ALCIDES CARRION DISTRITO CHAUPIMARCA, PROVINCIA PASCO - PASCO

TC-3

C-2
CANT. LUM. CARGA CARGA FACTOR MAXIMA LONGITUD

UNITARIA INSTALADA DEMANDA DEMANDA SUBTERRA AEREA


ALUMBRADO 14.00 80.00 1,120.00 100% 1,120.00 120.00

CARGAS MOVILES 500.00 30% 150.00

TOTALES 1,620.00 1,270.00 120.00 0.00

SOLUCION ADOPTADA

NYY BIPOLAR 0,6/1 KV 2x4 MM2


CALCULO DE CARGAS ELECTRICAS
PROYECTO: MEJ. DE AREAS DEPORTIVAS, AREAS DE ORNATO Y DE LOS ACCESOS AL ESTADIO
DANIEL ALCIDES CARRION DISTRITO CHAUPIMARCA, PROVINCIA PASCO - PASCO

RESUMEN CIRCUITO C.I. M.D. AMP.

C-1 1,140.00 790.00 2.30


C-2 1,620.00 1,270.00 3.70

TOTALES 2,760.00 2,060.00

SUMINISTRO PREVISTO : 2,060.00 W

IN= 10.40 AMP TW 450/750 V 1x10 AWG


Id= 11.96 AMP AMP. ELEGIDO : 20 AMP