Contents
1. Overview……………………………………………………………………………………1
2. Project Highlight…………………………………………………………………………....3
3. Project Master Plan………………………………………………………………………. 4
4. Customer Service Week…………………………………………………………………..5-6
5. Contact Points ……………………………………………………………………………..7
6. TDS Guideline…………………………………………………………………………....8-9
7. Project Milestone………………………………………………………………………….10
8. Construction status……………………………………………………………………..11-15
9. Upcoming Projects…………………………………………………………………………16
11. Thank You
2
PROJECT HIGHLIGHTS
3
PROJECT MASTERPLAN
4
Customer Feedback on Customer Service Week
5
Customer Service Week
Oct 3rd to 7th
• Overwhelming response on customers
visit ,
• Customer Raves & feedbacks received,
• Health check camps -Apollo Clinic
• Plantation drive,
• Pest control drive / Maintenance checks
for electrical / Plumbing / Carpentry,
• Site Visit
6
Contact Point
Project Title: Godrej Avenues
7
8
TDS
1. TDS is applicable for any property worth 50 lacs and above (Excluding the maintenance and corpus
fund).
2. For customers where TDS is applicable, the same should be paid on time to avoid penal charges and
interest levies.
3. Upon remitting the TDS please send us the scan copy of the Form 16B duly signed using a black
pen to credit the paid TDS in your account with immediate effect, if the Form 16B is unsigned the
TDS cannot be accounted in your account.
4. We have identified a chartered accountant to ensure the process of TDS is done and if required avail
their service at a cost. The person to contact is Mr. R. Sivakumar – Chartered Accountant
(28117075/28117475/94440-18283) / rrsk_chnn@yahoo.co.in
5. TDS should be done in the name of “Godrej Construction Projects LLP”, PAN No. AANFG9970A .
6. For more information, please log in to
https://www.tin-nsdl.com/downloads/TDS/eTutorial_TDS_on_property_etax-immediately.pdf
9
MILESTONE PROJECTION
Milestone Tower A Tower B Tower C Tower D Tower E Tower F Tower G Tower H Tower I Tower J
Excavation Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete
1st week of 1st week of 2nd week 2nd week 4th week
2nd floor
Dec Dec of Dec of Dec of Dec
*Milestone completion dates are tentative projection dates, based on our current construction schedule
10
11
PROGRESS UPDATE
12
PROGRESS UPDATE
14
PROGRESS UPDATE
7 Acres in