C/o 2 vent-900 mm dia NP3 Pipe culvert at 1/0 km on Road from Boinpalli to Vemulawada of Boinpalli Mand

Estimate cost : Rs. 3.75 Lakhs

The above work has been proposed for according adminisrative sanction for Rs 3.75 Lakhs.
2011 census The population of Boinpalli village is 4008 and Vemulawada viilage is 31363 The
surface of the road is BT surface. Total length of Road is 9 km and it is most important road for B
mandal People and Surrounding village people as Sri Raja Rajeswara Swamy Temple is Exi
Vemulawada, at 1/0 km 2vent 600 mm dia pipe culvert is Badly Damaged and Proprosed for Pipe
with 2 Vent-900 mm dia is as per site conditions.
The Line estimate is prepared with following provisions

The Pipe culvert work estimate is prepared with the following provisions.

1 Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including set
construction of shoring and bracing, removal of stumps and other deleterious material and disposal up to a lead
dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Spe
305 MORD / 304 MORTH ,including overhead charges & Contractors profit ,But excluding VAT & Seignarage charg

2 Sand Filling in foundation trenches as per drawing and technical specification Clause 305.3.9 MORD & 304
,including overhead '- charges & Contractors profit, But excluding VAT & Seignarage charges.

3 Providing concrete for plain concrete M15 ( Nominal mix) in open foundations using 40,20 & 10mm size Gra
stone aggregate, mechanically mixed, placed in foundation and compacted by vibration including curing for
complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700
MORTH ,including overhead charges & Contractors profit ,But excluding VAT & Seignarage charges. for Foundatio
4 Plain cement concrete M15grade (Nominal mix) using 40,20 & 10mm HBG metal mechanically mixed in sub
complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD a
1700 & 2200 MORTH ,including overhead charges & Contractors profit ,But excluding VAT & Seignarage char
Abutments, Piers, cut-off walls above Bed Level

5 Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as p
1300.1, no fragment weighing less than 25 / 40 kg laid dry complete as per drawing and technical specification
1301 MORD / 2503 MORTH ,including overhead charges and contractors profit ,But excluding VAT & Seignarage c

Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material
fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and mason
in head wall and parapets. Tech Specification Clause 1106 MORD ,including overhead charges & Contractors p
excluding VAT & Seignarage charges.

The estimate is prepared with the SSR for the year 2016-17 .

Early Administrative sanction of estimate is solicited.

Asst Executive Engineer Deputy Executive Engineer District Panchayatraj Engineer


PRSD/Vemulawada PRSD/Vemulawada Rajanna Siricilla District
ulawada of Boinpalli Mandal

ction for Rs 3.75 Lakhs. As per


da viilage is 31363 The existing
most important road for Boinpalli
Swamy Temple is Existing at
d and Proprosed for Pipe culvert

Clause 305.1 including setting out,


al and disposal up to a lead of 50 m,
aterial as per Technical Specification
ing VAT & Seignarage charges.

ause 305.3.9 MORD & 304 MORTH


harges.

g 40,20 & 10mm size Graded hard


bration including curing for 14 days
203 MORD and 1500, 1700 & 2100
rage charges. for Foundations
mechanically mixed in substructure
07, 1202 and 1204 MORD and 1500,
ing VAT & Seignarage charges. for

mum size and weight as per Table


g and technical specifications Clause
xcluding VAT & Seignarage charges.

edding of granular material including


kfilling, concrete and masonry works
ad charges & Contractors profit ,But

hayatraj Engineer
illa District
DETAILED AND ABSTRACT ESTIMATE FOR
C/o 2 vent-900 mm dia NP3 Pipe culvert at 1/0 km on Road from Boinpalli to Vemulawada of Boinpalli
Mandal
Const.of 2 Vent of 900mm Dia RCC NP3 Class Hume Pipe culvert Ch 1/0 km

Ch 1/0 km
Measurements
Sl no Description of work No.s Quantity Rate. Per Amount
L B D
1 2 3 4 5 6 7 8 9
1 Earthwork in excavation for structures as per drawing and technical
specifications Clause 305.1 including setting out, construction of
shoring and bracing, removal of stumps and other deleterious
material and disposal up to a lead of 50 m, dressing of sides and
bottom and backfilling in trenches with excavated suitable material
as per Technical Specification 305 MORD / 304 MORTH ,including
overhead charges & Contractors profit ,But excluding VAT &
Seignarage charges.

Body wall 1 x 2 6.90 1.40 1.20 23.184


Under Pipes 1 x 1 5.00 3.05 0.30 4.575

27.759 93.93 2,607.00


cum 1 cum
2 Sand Filling in foundation trenches as per drawing and technical
specification Clause 305.3.9 MORD & 304 MORTH ,including
overhead '- charges & Contractors profit, But excluding VAT &
Seignarage charges.
Body wall Foundation 1 x2 6.90 1.40 0.10 1.932
Under Pipes 1 x1 5.50 3.05 0.30 5.033

6.965 505.56 3,521.00


cum 1cum
3 Providing concrete for plain concrete M15 ( Nominal mix) in open
foundations using 40,20 & 10mm size Graded hard stone
aggregate, mechanically mixed, placed in foundation and
compacted by vibration including curing for 14 days complete as per
drawings and technical specifications Clause 802, 803, 1202 &
1203 MORD and 1500, 1700 & 2100 MORTH ,including overhead
charges & Contractors profit ,But excluding VAT & Seignarage
charges. for Foundations

Body wall Foundation 1 x 2 6.90 1.40 0.15 2.898


Body wall below GL 1 x 2 6.75 1.25+1.00/2 0.95 14.428
17.326 5202.02 90,131.00
cum 1cum
4 Plain cement concrete M15grade (Nominal mix) using 40,20 &
10mm HBG metal mechanically mixed in substructure complete as
per drawings and technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH
,including overhead charges & Contractors profit ,But excluding VAT
& Seignarage charges. for Abutments, Piers, cut-off walls above
Bed Level

Body wall above GL 1 x 2 6.75 1.00+0.45/2 1.70 16.639

P.P walls 1 x 2 6.75 0.45 0.45 2.734

Deduct Pipe Portion 22 x -4 1.10 1.10 1.00+0.60/2 -3.042


7 4
16.330 5502.05 89,850.00
1 2 3 4 5 6 7 8 9
cum 1cum

5 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 / 40 kg laid dry complete as per
drawing and technical specifications Clause 1301 MORD / 2503
MORTH ,including overhead charges and contractors profit ,But
excluding VAT & Seignarage charges.

Up stream Side 1 x 1 6.75 1.50 0.30 3.038

Down stream Side 1 x 1 6.75 3.00 0.30 6.075


( width equal to body wall length )
9.113 1404.02 12,794.00
cum 1cum
6 Providing and laying reinforced cement concrete pipe NP3 for
culverts on first class bedding of granular material including fixing
collar with cement mortar 1:2 but excluding excavation, protection
works, backfilling, concrete and masonry works in head wall and
parapets. Tech Specification Clause 1106 MORD ,including
overhead charges & Contractors profit ,But excluding VAT &
Seignarage charges.

- 900 mm dia Pipes 1 x 2 7.50 -- -- 15.000


15.000 8506.41 127,596.00
Rm Rm
326,499.00

TOTAL Rs.. 326,499.00

7 Add VAT 12% 39,180.00

8 Add 0.50% Q.C. Charges 1,632.00

9 Add 0.10% NAC . Charges 326.00

10 Add Seignorage Charges 4,741.00

11 LS For Roundoff 2,622.00


Total 375,000.00

Asst Executive Engineer Deputy Executive Engineer District Panchayatraj Engineer