You are on page 1of 23

 not enough that there was non-performance or delay,

ART 170 (CONTRAVENTION OF TENOR) it should be imputable to the debtor


 Those who are in the performance of the following
obligations are liable for damages Excuse for non-performance
o guilty of  failure of performance due to fortuitous event
o cannot be held liable for damages
 fraud, o UNLESS there is an express agreement to the
 negligence, or contrary or the law so provides
 delay
o and those who in any manner contravene the Payment of money
tenor thereof  Damages may be recovered under this article when
the obligation is to do something other than the
Non-performance by fraud payment of money
 Fraud o If it is for the payment of money, it is
o voluntary execution of a wrongful act governed by ART 2209 of CC
 Fraud referred in this article
o Deliberate and intentional evasion of the ART 1167 (CONTRAVENTION OF TENOR)
normal fulfillment of obligations
 If a person obliged to do something fails to do it
 Fraud differs from negligence because the latter
lacks intent o Shall be executed at his cost
 Fraud as ground for damages  If he does it in contravention of the tenor of the
o Implies some kind of malice or dishonesty obligation
 The element of intent, not the degree of actual o Same rule shall be observed
harm done is the test o It may be decreed, that what has been poorly
By fault or negligence done be undone
 Omission of diligence required by nature of
obligation and corresponds with the circumstances Performance at debtor’s cost
of the person, time, and place
 Creditor entitled to have the thing done in the
 Culpa contractual proper manner
o incident in the fulfillment of an existing o By himself or by a 3rd person
obligation  At the expense of debtor
 Culpa aquiliana
o Independent source of obligation between Indemnification for damages
parties not previously bound  Article presupposes that the act be done by persons
 Whether contractual or non-contractual, the other than the debtor
negligence of the defendant should be the proximate o If the debtor is the only one who can do it,
cause of the damage to the plaintiff in order for the only remedy is to recover damages
liability to attach
In any manner contravene the tenor thereof
 Any illicit act which impairs the strict and ARRIETA v NARIC
faithful fulfillment of the obligation
 Every kind of defective performance TOPIC:
Under this provision, not only debtors guilty of
By delay and other violations fraud, negligence or default in the performance of
obligations a decreed liable; in general, every debtor
who fails in performance of his obligations is bound
to indemnify for the losses and damages caused As a result of the delay, the allocation of appellee's
thereby. The phrase "any manner contravene the tenor" supplier in Rangoon was cancelled and the 5% deposit,
of the obligation includes any illicit act which amounting to 524,000 kyats or approximately
impairs the strict and faithful fulfillment of the P200,000.00 was forfeited.
obligation or every kind or defective performance.  In this connection, it must be made of record that
although the Burmese authorities had set August 4,
FACTS 1952, as the deadline for the remittance of the
required letter of credit, the cancellation of the
Plaintiff-appellee participated in the public bidding allocation and the confiscation of the 5% deposit
called by the NARIC for the supply of 20,000 metric were not effected until August 20, 1952, or, a full
tons of Burmese rice. She was awarded the contract for half month after the expiration of the deadline.
the same. And yet, even with the 15-day grace, appellant
corporation was unable to make good its commitment
Plaintiff-appellee Paz P. Arrieta and the appellant to open the disputed letter of credit.
corporation entered into a Contract of Sale of Rice,
under the terms of which The appellee endeavored, but failed, to restore the
 the petitioner obligated herself to deliver to the cancelled Burmese rice allocation.
latter 20,000 metric tons of Burmess Rice at  She offered to substitute Thailand rice instead to
$203.00 per metric ton the defendant NARIC however, was rejected.
 the defendant corporation committed itself to pay On the foregoing, the appellee sent a letter to the
for the imported rice "by means of an irrevocable, appellant, demanding compensation for the damages
confirmed and assignable letter of credit in U.S. caused her in the sum of $286,000.00, U.S. currency,
currency in favor of the plaintiff-appellee and/or representing unrealized profit. The demand having been
supplier in Burma, immediately." rejected she instituted this case now on appeal.
A full month from the execution of the contract, the ISSUE
defendant corporation, thru its general manager, took whether appellant's failure to open immediately the
the first to open a letter of credit by forwarding to letter of credit in dispute amounted to a breach of
the Philippine National Bank its Application for the contract for which it may be held liable in
Commercial Letter Credit. damages. – YES

The Philippine National Bank informed the appellant RATIO


corporation that its application, "for a letter of Appellant corporation disclaims responsibility for the
credit for $3,614,000.00 in favor of Thiri Setkya has delay in the opening of the letter of credit.
been approved by the Board of Directors with the  Insists that the fault lies with the appellee
condition that: o appellee failed to seasonably furnish data
 marginal cash deposit be paid and that drafts are necessary and required for opening the same
to be paid upon presentment.  the amount of the letter of credit
 the Bank represented that it "will hold your  the person, company or corporation in
application in abeyance pending compliance with the whose favor it is to be opened
above stated requirement."  the place and bank where it may be
negotiated
As it turned out, however, the appellant corporation
was not in any financial position to meet the Appellant's explanation has neither force nor merit.
condition.  In the first place, the explanation reaches into an
area of the proceedings into which We are not at
Consequently, the credit instrument applied for was liberty to encroach.
opened only on September 8, 1952(which is more than o The explanation refers to a question of fact.
two months from the execution of the contract)
 Nothing in the record suggests any fulfillment of the obligation or every kind
arbitrary or abusive conduct on the or defective performance.
part of the trial judge in the
formulation of the ruling. The NARIC would also have this Court hold that the
 Disputed facts were known to defendant subsequent offer to substitute Thailand rice for the
even before the contract was executed originally contracted Burmese rice amounted to a
because these facts were necessarily waiver by the appellee of whatever rights she might
revealed to the defendant before she have derived from the breach of the contract
could qualify as a bidder.  Waivers are not presumed, but must be clearly and
convincingly shown, either by express stipulation
 Secondly, it is clear that what singularly delayed or acts admitting no other reasonable explanation.
the opening of the stipulated letter of credit and
which, in turn, caused the cancellation of the Lastly, herein appellant filed a counterclaim
allocation in Burma, was the inability of the asserting that it has suffered, likewise by way of
appellant corporation to meet the condition unrealized profit damages in the total sum of
importation by the Bank for granting the same. $406,000.00 from the failure of the projected contract
o The liability of the appellant, however, to materialize.
stems not alone from this failure or  supported by a cost study made and submitted by the
inability to satisfy the requirements of the appellant itself and wherein it was illustrated how
bank. Its culpability arises from its willful indeed had the importation pushed thru, NARIC would
and deliberate assumption of contractual have realized in profit the amount asserted in the
obligations even as it was well aware of its counterclaim.
financial incapacity to undertake the  And yet, the said amount of P406,000.00 was
prestation. realizable by appellant despite a number of
o despite the financial incompetence to open a expenses which the appellee under the contract, did
letter of credit immediately, appellant not have to incur. Thus, under the cost study
agreed in paragraph 8 of the contract to pay submitted by the appellant, banking and unloading
immediately "by means of an irrevocable, charges were to be shouldered by it, including an
confirm and assignable letter of credit," it Import License Fee of 2% and superintendence fee of
must be similarly held to have bound itself $0.25 per metric ton. If the NARIC stood to profit
to answer for all and every consequences that over P400 000.00 from the disputed transaction
would result from the representation inspite of the extra expenditures from which the
herein appellee was exempt, we are convicted of the
 In relation to the aforequoted observation of the fairness of the judgment presently under appeal.
trial court, We would like to make reference also
to Article 11 of the Civil Code which provides: In the premises, however, a minor modification must be
Those who in the performance of their obligation effected in the dispositive portion of the decision
are guilty of fraud, negligence, or delay, and appeal from insofar as it expresses the amount of
those who in any manner contravene the tenor damages in U.S. currency and not in Philippine Peso.
thereof, are liable in damages.  Republic Act 529 specifically requires the
 Under this provision, not only debtors guilty of discharge of obligations only "in any coin or
fraud, negligence or default in the performance of currency which at the time of payment is legal
obligations a decreed liable; in general, every tender for public and private debts." In view of
debtor who fails in performance of his obligations that law, therefore, the award should be converted
is bound to indemnify for the losses and damages into and expressed in Philippine Peso.
caused thereby.  UPON ALL THE FOREGOING, the decision appealed from
o The phrase "any manner contravene the tenor" is hereby affirmed, with the sole modification that
of the obligation includes any illicit act the award should be converted into the Philippine
which impairs the strict and faithful peso at the rate of exchange prevailing at the time
the obligation was incurred or on July 1, 1952 when
the contract was executed. The appellee insurance the missing parts, the interior cover and the P6.00.
company, in the light of this judgment, is relieved
of any liability under this suit. The plaintiff had his typewriter repaired by Freixas
Business Machines, and the repair job cost him a total
CHAVEZ v GONZALES of P89.85, including labor and materials.

TOPIC Plaintiff commenced this action before the City Court


It is clear that the defendant-appellee contravened of Manila, demanding from the defendant the payment of
the tenor of his obligation because he not only did P90.00 as actual and compensatory damages, P100.00 for
not repair the typewriter but returned it "in temperate damages, P500.00 for moral damages, and
shambles", according to the appealed decision. For P500.00 as attorney’s fees.
such contravention, as appellant contends, he is
liable under Article 1167 of the Civil Code. The cost In his answer as well as in his testimony given before
of the execution of the obligation in this case should this court, the defendant made no denials of the facts
be the cost of the labor or service expended in the narrated above, except the claim of the plaintiff that
repair of the typewriter, which is in the amount of the typewriter was delivered to the defendant through
P58.75 because the obligation or contract was to a certain Julio Bocalin, which the defendant denied
repair it. allegedly because the typewriter was delivered to him
personally by the plaintiff.
In addition, the defendant-appellee is likewise
liable, under Article 1170 of the Code, for the cost RATIO
of the missing parts, in the amount of P31.10, for in According to City Court of Manila:
his obligation to repair the typewriter he was bound, The repair done on the typewriter by Freixas Business
but failed or neglected, to return it in the same Machines with the total cost of P89.85 should not,
condition it was when he received it. however, be fully chargeable against the defendant.
The repair invoice, shows that the missing parts had a
FACTS total value of only P31.10. and the costs of suit.
The plaintiff delivered to the defendant, who is a
typewriter repairer, a portable typewriter for routine The error of the court a quo, according to the
cleaning and servicing. plaintiff-appellant, Rosendo O. Chaves, is that it
awarded only the value of the missing parts of the
The defendant was not able to finish the job after typewriter, instead of the whole cost of labor and
some time despite repeated reminders made by the materials that went into the repair of the machine, as
plaintiff. The defendant merely gave assurances, but provided for in Article 1167 of the Civil Code,
failed to comply with the same. reading as follows:jgc:chanrobles.com.ph
 The defendant asked from the plaintiff the sum of
P6.00 for the purchase of spare parts, which amount "ART. 1167. If a person obliged to do something fails
the plaintiff gave to the defendant. to do it, the same shall be executed at his cost.
 After getting exasperated with the delay of the
repair of the typewriter, the plaintiff went to the This same rule shall be observed if he does it in
house of the defendant and asked for the return of contravention of the tenor of the obligation.
the typewriter. Furthermore it may be decreed that what has been
poorly done he undone."cralaw virtua1aw library
o The defendant and found out that the same was
in shambles, with the interior cover and some On the other hand, the position of the defendant-
parts and screws missing.
appellee, Fructuoso Gonzales, is that he is not liable
The plaintiff sent a letter to the defendant formally at all, not even for the sum of P31.10, because his
demanding the return of the missing parts, the contract with plaintiff-appellant did not contain a
interior cover and the sum of P6.00. The following period, so that plaintiff-appellant should have first
day, the defendant returned to the plaintiff some of filed a petition for the court to fix the period,
under Article 1197 of the Civil Code, within which the
defendant appellee was to comply with the contract the amount of P58.75. because the obligation or
before said defendant-appellee could be held liable contract was to repair it.
for breach of contract.
In addition, the defendant-appellee is likewise
The inferences derivable from these findings of fact liable, under Article 1170 of the Code, for the cost
are that the appellant and the appellee had a of the missing parts, in the amount of P31.10, for in
perfected contract for cleaning and servicing a his obligation to repair the typewriter he was bound,
typewriter; that they intended that the defendant was but failed or neglected, to return it in the same
to finish it at some future time although such time condition it was when he received it.
was not specified; and that such time had passed
without the work having been accomplished, far the Appellant’s claims for moral and temperate damages and
defendant returned the typewriter cannibalized and attorney’s fees were, however, correctly rejected by
unrepaired, which in itself is a breach of his the trial court, for these were not alleged in his
obligation, without demanding that he should be given complaint
more time to finish the job, or compensation for the  Claims for damages and attorney’s fees must be
work he had already done. pleaded, and the existence of the actual basis
 The time for compliance having evidently expired, thereof must be proved.
and there being a breach of contract by non-  The appealed judgment thus made no findings on
these claims, nor on the fraud or malice charged to
ART 1175 (EFFECT OF FORTUITOUS EVENT) the appellee. As no findings of fact were made on
the claims for damages and attorney’s fees, there
 No person shall be responsible is no factual basis upon which to make an award
o events which could not be foreseen therefor.
o though foreseen, were inevitable
 EXCEPT Hereby ordered to pay, the plaintiff-appellant the sum
of P89.85, with interest at the legal rate from the
o Specified by law filing of the complaint. Costs in all instances
o Declared by stipulation against appellee Fructuoso Gonzales.
o Nature of obligation requires assumption of risk
Fortuitous event
performance, it was academic for the plaintiff to  An event which takes place by accident and could
have first petitioned the court to fix a period for not have been foreseen
the performance of the contract before filing his o Also includes unavoidable accidents, even if
complaint in this case. Defendant cannot invoke there has been an intervention of human
Article 1197 of the Civil Code for he virtually element
admitted non-performance by returning the
typewriter that he was obliged to repair in a non-  Debtor is also relieved from liability if the non-
working condition, with essential parts missing. performance was because of the act of the creditor
The fixing of a period would thus be a mere himself
formality and would serve no purpose than to delay  2 general causes
o Natural
It is clear that the defendant-appellee contravened o Act of man
the tenor of his obligation because he not only did  Act of man
not repair the typewriter but returned it in shambles. o Should have the force of imposition which the
For such contravention, as appellant contends, he is debtor could not have resisted
liable under Article 1167 of the Civil Code, for the  Characteristics of fortuitous event
cost of executing the obligation in a proper manner.
The cost of the execution of the obligation in this o Cause  independent of human will
case should be the cost of the labor or service o Impossible to foresee
expended in the repair of the typewriter, which is in
 OR if it can be foreseen, it must be
impossible to avoid
o Occurrence renders it impossible for debtor
to fulfill his obligation
o Obligor must be free from participation in TANGUILIG v CA
the aggravation of the injury resulting to
the creditor TOPIC
This Court has consistently held that in order for a
Express stipulation party to claim exemption from liability by reason of
 Stipulation must be expressly stated in the fortuitous event under Art. 1174 of the Civil Code the
contract event should be the sole and proximate cause of the
loss or destruction of the object of the
Assumption of risk contract. In Nakpil vs. Court of Appeals, four (4)
 Principle was based on social justice requisites must concur:
o Injustices which industrialization created  the cause of the breach of the obligation must be
o Owners who benefit from the risk must also be independent of the will of the debtor;
liable  the event must be either unforeseeable or
o Applies to all kinds of public service unavoidable;
 the event must be such as to render it impossible
ART 1165 (EFFECT OF FORTUITOUS EVENT) for the debtor to fulfill his obligation in a
normal manner; and,
 the debtor must be free from any participation in
 What is to be delivered is a determinate thing or aggravation of the injury to the creditor.
o Creditor may compel the debtor to make the
delivery FACTS
 Apart from the rights granted to him by Petitioner Jacinto M. Tanguilig doing business under
ART 1170 the name and style J. M. T. Engineering and General
 If indeterminate Merchandising proposed to respondent Vicente Herce Jr.
o Obligation be complied with at the expense of to construct a windmill system for him.
the debtor After some negotiations they agreed on the
 If obligor delays or has promised to deliver the same construction of the windmill for a consideration
thing to two or more persons who do not have the same of P60,000.00 with a one-year guaranty from the date of
interest completion and acceptance by respondent Herce Jr. of
o Responsible for any fortuitous event until he has the project. Pursuant to the agreement respondent paid
petitioner a down payment of P30,000.00 and an
effected the delivery
installment payment of P15,000.00, leaving a balance
of P15,000.00.
Remedies of creditor
Due to the refusal and failure of respondent to pay
 Ask for performance the balance, petitioner filed a complaint to collect
 Rescind or resolve obligation the amount.
 Action for damages
In his Answer before the trial court respondent denied
the claim saying that he had already paid this amount
to the San Pedro General Merchandising Inc. which
constructed the deep well to which the windmill system  Respondent's payment of P15,000.00 to SPGMI should
was to be connected. be applied to his remaining balance with petitioner
thus effectively extinguishing his contractual
 According to respondent, since the deep well formed obligation.
part of the system the payment he tendered to SPGMI  Rejected petitioner's claim of force majeure and
should be credited to his account by ordered the latter to reconstruct the windmill in
petitioner. Moreover, assuming that he owed accordance with the stipulated one-year guaranty.
petitioner a balance of P15,000.00, this should be
offset by the defects in the windmill system which His motion for reconsideration having been denied by
caused the structure to collapse after a strong the Court of Appeals, petitioner now seeks relief from
wind hit their place. this Court.
Petitioner denied that the construction of a deep well ISSUES
was included in the agreement to build the windmill
1. whether the agreement to construct the windmill
system, for the contract price of P60,000.00 was system included the installation of a deep well
solely for the windmill assembly and its installation, – NO
exclusive of other incidental materials needed for the
project. He also disowned any obligation to repair or The preponderance of evidence supports the finding of
reconstruct the system and insisted that he delivered the trial court that the installation of a deep well
it in good and working condition to respondent who was not included in the proposals of petitioner to
accepted the same without protest. Besides, its construct a windmill system for respondent. There were
collapse was attributable to a typhoon, in fact two (2) proposals: one dated 19 May 1987 which
a force majeure, which relieved him of any liability. pegged the contract price at P87,000.00. This was
Trial court held: rejected by respondent. The other was submitted three
days later which contained more specifications but
 The construction of the
proposed a lower contract price of P60,000.00. The
deep well was not part of the windmill project as evidenc latter proposal was accepted by respondent and the
ed clearly by the letter proposals submitted by construction immediately followed.
petitioner to respondent.
 In the absence of such an agreement, it could be Notably, nowhere in either proposal is the
safely concluded that the construction of the deep installation of a deep well mentioned, even
well is not a part of the project undertaken by the remotely. Neither is there an itemization or
plaintiff. description of the materials to be used in
 With respect to the repair of the windmill, the constructing the deep well.
trial court found that "there is no clear and  While the words "deep well" and "deep well pump" are
convincing proof that the windmill system fell down mentioned in both, these do not indicate that a
due to the defect of the construction." deep well is part of the windmill system. They
merely describe the type of deep well pump for
The Court of Appeals reversed the trial court. which the proposed windmill would be suitable.
 construction of the deep well was included in the  words "deep well" preceded by the
agreement of the parties because the term "deep
well" was mentioned in both proposals. prepositions "for" and "suitable for" were meant only
to convey the idea that the proposed windmill would
 gave credence to the testimony of respondent's be appropriate for a deep well pump
witness Guillermo Pili, the proprietor of SPGMI o if the real intent of petitioner was to
which installed the deep well, that petitioner include a deep well in the agreement to
Tanguilig told him that the cost of constructing construct a windmill, he would have used
the deep well would be deducted from the contract
instead the conjunctions "and" or "with.
price of P60,000.00.
Respondent insists that petitioner verbally agreed that does not appear from the record that Pili and/or
the contract price of P60,000.00 covered the SPGMI was so authorized.
installation of a deep well pump. He contends that since  Respondent cannot claim the benefit of the law
petitioner did not have the capacity to install the concerning "payments made by a third person." The
pump the latter agreed to have a third party do the Civil Code provisions do not apply in the instant
work the cost of which was to be deducted from the case because no creditor-debtor relationship
contract price. To prove his point, he presented between petitioner and Guillermo Pili and/or SPGMI
Guillermo Pili of SPGMI who declared that petitioner has been established regarding the construction of
Tanguilig approached him with a letter from respondent the deep well.
Herce Jr. asking him to build a deep well pump as "part
of the price/contract which Engineer (Herce) had with 2. Whether petitioner is under obligation to
Mr. Tanguilig. reconstruct the windmill after it collapsed. –
 Court is disinclined to accept the version of YES
respondent. The claim of Pili that Herce Jr. wrote This Court has consistently held that in order for
him a letter is unsubstantiated. The alleged letter a party to claim exemption from liability by reason
was never presented in court by private respondent of fortuitous event under Art. 1174 of the Civil Code
for reasons known only to him. the event should be the sole and proximate cause of
 But granting that this written communication the loss or destruction of the object of the
existed, it could not have simply contained a request contract.
for Pili to install a deep well; it would have also In Nakpil vs. Court of Appeals, four (4) requisites
mentioned the party who would pay for the must concur: (a) the cause of the breach of the
undertaking. obligation must be independent of the will of the
 unusual that Pili would readily consent to build a debtor; (b) the event must be either unforeseeable
deep well the payment for which would come supposedly or unavoidable; (c) the event must be such as to
from the windmill contract price on the mere render it impossible for the debtor to fulfill his
representation of petitioner, whom he had never met obligation in a normal manner; and, (d) the debtor
before, without a written commitment at least from must be free from any participation in or aggravation
the former. For if indeed the deep well were part of of the injury to the creditor.
the windmill project, the contract for its
installation would have been strictly a matter Petitioner failed to show that the collapse of the
between petitioner and Pili himself with the former windmill was due solely to a fortuitous event.
assuming the obligation to pay the price.  evidence does not disclose that there was actually
 It was respondent Herce Jr. himself who paid for the a typhoon on the day the windmill collapsed.
deep well by handing over to Pili the amount  Petitioner merely stated that there was a "strong
of P15,000.00 clearly indicates that the contract for wind."
the deep well was not part of the windmill project o But a strong wind in this case cannot be
but a separate agreement between respondent and fortuitous - unforeseeable nor unavoidable. On
Pili. the contrary, a strong wind should be present
in places where windmills are constructed,
Can respondent claim that Pili accepted his payment on otherwise the windmills will not turn.
behalf of petitioner? No. The appellate court correctly observed that "given
 While the law is clear that "payment shall be made the newly-constructed windmill system, the same
would not have collapsed had there been no inherent
to the person in whose favor defect in it which could only be attributable to
the obligation has been constituted, or his successor the appellee.
in interest, or any person authorized to receive it," it  It emphasized that respondent had in his favor the
presumption"things have happened according to the ord
inary course of nature and the ordinary habits of The principle embodied in the act of God doctrine
life." strictly requires that the act must be one occasioned
o This presumption has not been rebutted by exclusively by the violence of nature and all human
petitioner. agencies are to be excluded from creating or entering
into the cause of the mischief. When the effect, the
Finally, petitioner's argument that private cause of which is to be considered, is found to be in
respondent was already in default in the payment of part the result of the participation of man, whether
his outstanding balance of P15,000.00 and hence it be from active intervention or neglect, or failure
should bear his own loss, is untenable. to act, the whole occurrence is thereby humanized, as
it were, and removed from the rules applicable to the
 In reciprocal obligations, neither party incurs in acts of God.
delay if the other does not comply or is not ready
to comply in a proper manner with what is incumbent FACTS
upon him.
The plaintiff, Philippine Bar Association decided to
 When the windmill failed to function properly it construct an office building on its 840 square meters
became incumbent upon petitioner to institute the lot located at the comer of Aduana and Arzobispo
proper repairs in accordance with the guaranty Streets, Intramuros, Manila.
stated in the contract. Thus, respondent cannot be  The construction was undertaken by the United
said to have incurred in delay; instead, it is Construction, Inc. on an "administration" basis, on
petitioner who should bear the expenses for the the suggestion of Juan J. Carlos, the president and
reconstruction of the windmill. Article 1167 of the general manager of said corporation. The proposal
Civil Code is explicit on this point that if a was approved by plaintiff's board of directors and
person obliged to do something fails to do it, the signed by its president Roman Ozaeta, a third-party
same shall be executed at his cost. defendant in this case. The plans and
specifications for the building were prepared by
NAKPIL & SONS v CA the other third-party defendants Juan F. Nakpil &
Sons. The building was completed in June, 1966.
TOPIC In the early morning of August 2, 1968 an unusually
strong earthquake hit Manila and its environs and the
There is no dispute that the earthquake of August 2, building in question sustained major damage.
1968 is a fortuitous event or an act of God.  As a temporary remedial measure, the building was
shored up by United Construction, Inc. at the cost
To exempt the obligor from liability under Article of P13,661.28.
1174 of the Civil Code, for a breach of an obligation
due to an "act of God," the following must concur: (a) On November 29, 1968, the plaintiff commenced this
the cause of the breach of the obligation must be action for the recovery of damages arising from the
independent of the will of the debtor; (b) the event partial collapse of the building against United
must be either unforseeable or unavoidable; (c) the Construction, Inc. and its President and General
event must be such as to render it impossible for the Manager Juan J. Carlos as defendants.
debtor to fulfill his obligation in a normal manner;
and (d) the debtor must be free from any participation Plaintiff alleges that the collapse of the building
in, or aggravation of the injury to the creditor. was accused by defects in the construction, the
failure of the contractors to follow plans and
specifications and violations by the defendants of the
Thus, if upon the happening of a fortuitous event or terms of the contract.
an act of God, there concurs a corresponding fraud, Defendants in turn filed a third-party complaint
negligence, delay or violation or contravention in any against the architects who prepared the plans and
manner of the tenor of the obligation as provided for specifications, alleging in essence that the collapse
in Article 1170 of the Civil Code, which results in
loss or damage, the obligor cannot escape liability.
of the building was due to the defects in the said  Philippine Bar Association claimed that the measure
plans and specifications. of damages should not be limited to P1,100,000.00
as estimated cost of repairs or to the period of
Upon the issues being joined, a pre-trial was six (6) months for loss of rentals while United
conducted during which among others, the parties Construction Co., Inc.
agreed to refer the technical issues involved in the  Nakpils claimed that it was an act of God that
case to a Commissioner. caused the failure of the building
Meanwhile, plaintiff moved twice for the demolition of  Both UCCI and the Nakpils object to the payment of
the building on the ground that it may topple down in the additional amount of P200,000.00 imposed by the
case of a strong earthquake. The motions were opposed Court of Appeals. UCCI also claimed that it should
by the defendants and the matter was referred to the be reimbursed the expenses of shoring the building
Commissioner. in the amount of P13,661.28 while the Nakpils
opposed the payment of damages jointly and
 The building was authorized to be demolished at the solidarity with UCCI.
expense of the plaintiff
 The actual demolition was undertaken by the buyer ISSUE
of the damaged building. whether or not an act of God-an unusually strong
earthquake-which caused the failure of the building,
After the protracted hearings, the Commissioner exempts from liability, parties who are otherwise
eventually submitted his report on September 25, 1970 liable because of their negligence.
with the findings that while the damage sustained by
the PBA building was caused directly by the August 2, RATIO
1968 earthquake whose magnitude was estimated at 7.3 The applicable law governing the rights and
they were also caused by the defects in the plans and liabilities of the parties herein is Article 1723 of
specifications prepared by the third-party defendants' the New Civil Code, which provides:
architects, deviations from said plans and Art. 1723. The engineer or architect who
specifications by the defendant contractors and drew up the plans and specifications for a
failure of the latter to observe the requisite building is liable for damages if within
workmanship in the construction of the building and of fifteen years from the completion of the
the contractors, architects and even the owners to structure the same should collapse by
exercise the requisite degree of supervision in the reason of a defect in those plans and
construction of subject building. specifications, or due to the defects in
the ground. The contractor is likewise
All the parties registered their objections to responsible for the damage if the edifice
aforesaid findings which in turn were answered by the fags within the same period on account of
Commissioner. defects in the construction or the use of
materials of inferior quality furnished by
The trial court agreed with the findings of the him, or due to any violation of the terms
Commissioner except as to the holding that the owner of the contract. If the engineer or
is charged with full supervision of the construction. architect supervises the construction, he
shall be solidarily liable with the
The lower court rendered the assailed decision which contractor.
was modified by the Intermediate Appellate Court Acceptance of the building, after
completion, does not imply waiver of any
All the parties herein appealed from the decision of of the causes of action by reason of any
the Intermediate Appellate Court. defect mentioned in the preceding
paragraph.
In their respective briefs petitioners, among others,
raised the following assignments of errors:
The action must be brought within ten that the immediate cause of the damage was the act of
years following the collapse of the God. To be exempt from liability for loss because of
building. an act of God, he must be free from any previous
negligence or misconduct by which that loss or damage
On the other hand, the general rule is that no person may have been occasioned.
shall be responsible for events which could not be
foreseen or which though foreseen, were inevitable The negligence of the defendant and the third-party
(Article 1174, New Civil Code). defendants petitioners was established beyond dispute
both in the lower court and in the Intermediate
An act of God has been defined as an accident, due Appellate Court.
directly and exclusively to natural causes without  United Construction Co., Inc. was found to have
human intervention, which by no amount of foresight, made substantial deviations from the plans and
pains or care, reasonably to have been expected, could specifications. and to have failed to observe the
have been prevented. requisite workmanship in the construction as well
as to exercise the requisite degree of supervision;
There is no dispute that the earthquake of August 2,  Third-party defendants were found to have
1968 is a fortuitous event or an act of God. inadequacies or defects in the plans and
specifications prepared by them.
To exempt the obligor from liability under Article
1174 of the Civil Code, for a breach of an obligation  The defects in the construction and in the plans
due to an "act of God," the following must concur: (a) and specifications were the proximate causes that
the cause of the breach of the obligation must be rendered the PBA building unable to withstand the
independent of the will of the debtor; (b) the event earthquake. For this reason the defendant and
must be either unforseeable or unavoidable; (c) the third-party defendants cannot claim exemption from
event must be such as to render it impossible for the liability.
debtor to fulfill his obligation in a normal manner;
and (d) the debtor must be free from any participation The relevant and logical observations of the trial
in, or aggravation of the injury to the creditor. court as affirmed by the Court of Appeals that "while
it is not possible to state with certainty that the
Thus, if upon the happening of a fortuitous event or building would not have collapsed were those defects
an act of God, there concurs a corresponding fraud, not present, the fact remains that several buildings
negligence, delay or violation or contravention in any in the same area withstood the earthquake to which the
manner of the tenor of the obligation as provided for building of the plaintiff was similarly subjected,"
in Article 1170 of the Civil Code, which results in cannot be ignored.
loss or damage, the obligor cannot escape liability.
The principle embodied in the act of God doctrine
strictly requires that the act must be one occasioned
exclusively by the violence of nature and all human DIOQUINO v LAURENIANO
agencies are to be excluded from creating or entering
into the cause of the mischief. When the effect, the TOPIC
cause of which is to be considered, is found to be in The very wording of the law dispels any doubt that
part the result of the participation of man, whether what is therein contemplated is the resulting
it be from active intervention or neglect, or failure liability even if caused by a fortuitous event where
to act, the whole occurrence is thereby humanized, as the party charged may be considered as having assumed
it were, and removed from the rules applicable to the the risk incident in the nature of the obligation to
acts of God. be performed.
Thus it has been held that when the negligence of a FACTS
person concurs with an act of God in producing a loss, Attorney Pedro Dioquino, a practicing lawyer of
such person is not exempt from liability by showing Masbate, is the owner of a car.
 He met the defendant Federico Laureano, a patrol by stipulation, or when the nature of the obligation
officer of the MVO office, who was waiting for a requires the assumption of risk, no person shall be
jeepney to take him to the office of the Provincial responsible for those events which could not be,
Commander, PC, Masbate. foreseen, or which, though foreseen were inevitable."
 Attorney Dioquino requested the defendant Federico
Laureano to introduce him to one of the clerks in Authorities of repute are in agreement, more
the MVO Office specifically concerning an obligation arising from
contract "that some extraordinary circumstance
 Defendant Laureano rode on the car of Atty. independent of the will of the obligor, or of his
Dioquino. While about to reach their destination,
the car was stoned by some 'mischievous boys,' and employees, is an essential element of a caso
its windshield was broken. fortuito."
 Defendant Federico Laureano chased the boys and he  If it could be shown that such indeed was the
was able to catch one of them. The boy was taken to case, liability is ruled out. There is no
Atty. Dioquino [and] admitted having thrown the requirement of "diligence beyond what human care
stone that broke the car's windshield. and foresight can provide."

It was likewise noted in the decision now on appeal: The error committed by the lower court in holding
"The defendant Laureano refused to file any charges defendant Federico Laureano liable appears to be thus
against the boy and his parents because he thought obvious. Its own findings of fact repel the motion
that the stone-throwing was merely accidental and that that he should be made to respond in damages to the
plaintiff for the broken windshield. What happened was
it was due to force majeure. So he did not want to clearly unforeseen. It was a fortuitous event
take any action and after delaying the settlement, resulting in a loss which must be borne by the owner
after perhaps consulting a lawyer, the defendant of the car. An element of reasonableness in the law
Federico Laureano refused to pay the windshield would be manifestly lacking if, on the circumstances
himself and challenged that the case be brought to as thus disclosed, legal responsibility could be
court for judicial adjudication. imputed to an individual in the situation of defendant
Laureano. Art. 1174 of the Civil Code guards against
There is no question that the plaintiff tried to the possibility of its being visited with such a
convince the defendant Federico Laureano just to pay reproach.
the value of the windshield and he even came to the
extent of asking the wife to convince her husband to Unfortunately, the lower court was of a different mind
settle the matter amicably but the defendant Federico and thus failed to heed its command.
Laureano refused to make any settlement, clinging [to] It was misled, apparently, by the inclusion of the
the belief that he could not be held liable because a exemption from the operation of such a provision of a
minor child threw a stone accidentally on the party assuming the risk, considering the nature of the
windshield and therefore, the same was due to force obligation undertaken. The very wording of the law
majeure." dispels any doubt that what is therein contemplated is
the resulting liability even if caused by a fortuitous
ISSUE event where the party charged may be considered as
Whether the incident was a fortuitous event having assumed the risk incident in the nature of the
obligation to be performed. It would be an affront,
RATIO not only to the logic but to the realities of the
The law being what it is, such a belief on the part of situation, if in the light of what transpired, as
defendant Federico Laureano was justified. The express found by the lower court, defendant Federico Laureano
language of Art. 1174 of the present Civil Code which could be held as bound to assume a risk of this
is a restatement of Art. 1105 of the Old Civil Code, nature. There was no such obligation on his part.
except for the addition of the nature of an obligation
requiring the assumption of risk, compels such a Reference to the leading case of Republic v. Luzon
conclusion. It reads thus: "Except in cases expressly
specified by the law, or when it is otherwise declared Stevedoring Corp. will illustrate when the nature of
the obligation is such that the risk could be of First Instance of Manila an action against her and
considered as having been assumed. her husband for recovery of the pendant or of its
 For caso fortuito or force majeure (which in law are value, and damages.
identical in so far as they exempt an obligor from  Answering the allegations of the complaint,
liability) by definition, are extraordinary events defendants spouses set up the defense that the
not foreseeable or avoidable, 'events that could alleged robbery had extinguished their obligation.
not be foreseen, or which, though foreseen, were
inevitable' (Art. 1174, Civil Code of the After due hearing, the trial court rendered judgment
Philippines). for the plaintiff, and ordered defendants spouses,
 It is, therefore, not enough that the event should jointly and severally, to pay to the former the sum of
not have been foreseen or participated but it must P4,500.00, with legal interest thereon, plus the
be one impossible to foresee or to avoid. amount of P450.00 as reasonable attorneys' fees, and
the costs.
AUSTRIA v CA  Defendants failed to prove the fact of robbery, or,
if indeed it was committed, that defendant Maria
TOPIC Abad was guilty of negligence when she went home
without any companion, although it was already
It may be noted the reform that the emphasis of the getting dark and she was carrying a large amount of
provision is on the events, not on the agents or cash and valuables on the day in question, and such
factors responsible for them. To avail of the negligence did not free her from liability for
exemption granted in the law, it is not necessary that damages for the loss of the jewelry.
the persons responsible for the occurrence should be
found or punished; it would only be sufficient to Not satisfied with his decision, the defendants went
established that the enforceable event, the robbery in to the Court of Appeals, and there secured a reversal
this case did take place without any concurrent fault of the judgment.
on the debtor's part, and this can be done by  The appellate court overruling the finding of the
preponderant evidence. To require in the present trial court on the lack of credibility of the two
action for recovery the prior conviction of the defense witnesses who testified on the occurrence
culprits in the criminal case, in order to establish of the robbery, and holding that the facts of
the robbery as a fact, would be to demand proof beyond robbery and defendant Maria Abad's possesion of the
reasonable doubt to prove a fact in a civil case. pendant on that unfortunate day have been duly
published, declared respondents not responsible for
FACTS the loss of the jewelry on account of a fortuitous
event, and relieved them from liability for damages
In a receipt dated 30 January 1961, Maria G. Abad to the owner.
acknowledged having received from Guillermo Austria
one (1) pendant with diamonds valued at P4,500.00, to Plaintiff thereupon instituted the present proceeding.
be sold on commission basis or to be returned on ISSUE
demand. Whether Court of Appeals erred in finding that there
was robbery in the case, although nobody has been
found guilty of the supposed crime.
while walking home to her residence in Mandaluyong,
Rizal, Abad was said to have been accosted by two men, RATIO
one of whom hit her on the face, while the other It is petitioner's theory that for robbery to fall
snatched her purse containing jewelry and cash, and under the category of a fortuitous event and relieve
ran away. Among the pieces of jewelry allegedly taken the obligor from his obligation under a contract,
by the robbers was the consigned pendant. pursuant to Article 1174 of the new Civil Code, there
ought to be prior finding on the guilt of the persons
Abad failed to return the jewelry or pay for its value responsible therefor. In short, that the occurrence of
notwithstanding demands, Austria brought in the Court
the robbery should be proved by a final judgment of action for recovery the prior conviction of the
conviction in the criminal case. culprits in the criminal case, in order to establish
the robbery as a fact, would be to demand proof beyond
We find no merit in the contention of petitioner. reasonable doubt to prove a fact in a civil case.
It is recognized in this jurisdiction that to It is undeniable that in order to completely exonerate
constitute a caso fortuito that would exempt a person the debtor for reason of a fortutious event, such
from responsibility, it is necessary that (1) the debtor must, in addition to the cams itself, be free
event must be independent of the human will (or of any concurrent or contributory fault or
rather, of the debtor's or obligor's); (2) the negligence. This is apparent from Article 1170 of the
occurrence must render it impossible for the debtor to Civil Code of the Philippines, providing that:
fulfill the obligation in a normal manner; and that ART. 1170. Those who in the performance of
(3) the obligor must be free of participation in or their obligations are guilty of fraud,
aggravation of the injury to the creditor. A negligence, or delay, and those who in any
fortuitous event, therefore, can be produced by manner contravene the tenor thereof, are
nature, e.g., earthquakes, storms, floods, etc., or by liable for damages.
the act of man, such as war, attack by bandits,
robbery,etc., provided that the event has all the It is clear that under the circumstances prevailing at
characteristics enumerated above. present in the City of Manila and its suburbs, with
their high incidence of crimes against persons and
It is not here disputed that if respondent Maria Abad property that renders travel after nightfall a matter
were indeed the victim of robbery, and if it were to be sedulously avoided without suitable precaution
really true that the pendant, which she was obliged and protection, the conduct of respondent Maria G.
either to sell on commission or to return to Abad, in returning alone to her house in the evening,
petitioner, were taken during the robbery, then the carrying jewelry of considerable value would be
occurrence of that fortuitous event would have negligent per se and would not exempt her from
extinguished her liability. The point at issue in this responsibility in the case of a robbery.
proceeding is how the fact of robbery is to be  We are not persuaded, however, that the same rule
established in order that a person may avail of the should obtain ten years previously, in 1961, when
exempting provision of Article 1174 of the new Civil the robbery in question did take place, for at that
Code, which reads as follows: time criminality had not by far reached the levels
ART. 1174. Except in cases expressly attained in the present day.
specified by law, or when it is otherwise
declared by stipulation, or when the There is likewise no merit in petitioner's argument
nature of the obligation requires the that to allow the fact of robbery to be recognized in
assumption of risk, no person shall be the civil case before conviction is secured in the
responsible for those events which could criminal action, would prejudice the latter case, or
not be foreseen, or which, though would result in inconsistency should the accused
foreseen, were inevitable. obtain an acquittal or should the criminal case be
dismissed.
It may be noted the reform that the emphasis of the
provision is on the events, not on the agents or It must be realized that a court finding that a
factors responsible for them. To avail of the robbery has happened would not necessarily mean that
exemption granted in the law, it is not necessary that those accused in the criminal action should be found
the persons responsible for the occurrence should be guilty of the crime; nor would a ruling that those
found or punished; it would only be sufficient to actually accused did not commit the robbery be
established that the enforceable event, the robbery in inconsistent with a finding that a robbery did take
this case did take place without any concurrent fault place. The evidence to establish these facts would not
on the debtor's part, and this can be done by necessarily be the same.
preponderant evidence. To require in the present
WHEREFORE, finding no error in the decision of the Subsequently, Philcomsat installed and established the
Court of Appeals under review, the petition in this earth station at Cubi Point and the USDCA made use of
case is hereby dismissed with costs against the the same.
petitioner.
The Senate passed and adopted Senate Resolution No.
141, expressing its decision not to concur in the
ratification of the Treaty of Friendship, Cooperation
and Security and its Supplementary Agreements that was
supposed to extend the term of the use by the US of
Subic Naval Base, among others.

PH COMMUNICATIONS v GLOBE  The Philippine Government sent a Note Verbale to the


US Government through the US Embassy, notifying it
TOPIC of the Philippines termination of the RP-US Military
Bases Agreement.
 The withdrawal of all US military forces from Subic
FACTS Naval Base should be completed by said date.
For several years prior to 1991,Globe Telecom, Inc. Globe notified Philcomsat of its intention to
(Globe), had been engaged in the coordination of the discontinue the use of the earth station effective 08
provision of various communication facilities for the November 1992
military bases of the United States of America (US) in
Clark Air Base and Subic Naval Base in Cubi  invoked as basis for the letter of termination
Point. Globe, on the other hand, contracted with local Section 8 (Default) of the Agreement, which provides
service providers such as the Philippine Communications o Neither party shall be held liable or deemed
Satellite Corporation (Philcomsat) for the provision of to be in default for any failure to perform its
the communication facilities. obligation under this Agreement if such failure
results directly or indirectly from force
Philcomsat and Globe entered into an Agreement whereby majeure or fortuitous event. Either party is
Philcomsat obligated itself to establish, operate and thus precluded from performing its obligation
provide an IBS Standard B earth station (earth station) until such force majeure or fortuitous event
within Cubi Point for the exclusive use of the shall terminate. For the purpose of this
USDCA. The term of the contract was for five (5) paragraph, force majeure shall mean
years. In turn, Globe promised to pay Philcomsat monthly circumstances beyond the control of the party
rentals for each leased circuit involved. involved including, but not limited to, any
law, order, regulation, direction or request
At the time of the execution of the Agreement, both of the Government of the Philippines, strikes
parties knew that the Military Bases Agreement between or other labor difficulties, insurrection
the Republic of the Philippines and the US was to expire riots, national emergencies, war, acts of
in 1991. public enemies, fire, floods, typhoons or other
catastrophies or acts of God.
 Under Section 25, Article XVIII of the 1987
Constitution, foreign military bases, troops or Philcomsat sent a reply letter
facilities, which include those located at the US
Naval Facility in Cubi Point, shall not be allowed  we expect [Globe] to know its commitment to pay the
in the Philippines unless a new treaty is duly stipulated rentals for the remaining terms of the
concurred in by the Senate and ratified by a majority Agreement even after [Globe] shall have
of the votes cast by the people in a national discontinue[d] the use of the earth station after
referendum when the Congress so requires, and such November 08, 1992. Philcomsat referred to Section 7
new treaty is recognized as such by the US of the Agreement, stating as follows:
Government.
o Should [Globe] decide to discontinue with the The Court of Appeals promulgated its Decision dismissing
use of the earth station after it has been put Philcomsats appeal for lack of merit and affirming the
into operation, a written notice shall be trial courts
served to PHILCOMSAT at least sixty (60) days
prior to the expected date of Both parties filed their respective Petitions for
termination. Notwithstanding the non-use of the Review assailing the Decision of the Court of Appeals.
earth station, [Globe] shall continue to pay
PHILCOMSAT for the rental of the actual number ISSUE
of T1 circuits in use, but in no case shall be Whether the termination of the RP-US Military Bases
less than the first two (2) T1 circuits, for Agreement cannot be considered a fortuitous event – YES
the remaining life of the agreement. However,
should PHILCOMSAT make use or sell the earth RATIO
station subject to this agreement, the
obligation of [Globe] to pay the rental for the There is no merit is Philcomsats argument that Section
remaining life of the agreement shall be at 8 of the Agreement cannot be given effect because the
such monthly rate as may be agreed upon by the enumeration of events constituting force majeure therein
parties. unduly expands the concept of a fortuitous event under
Article 1174 of the Civil Code and is therefore invalid.
After the US military forces left Subic Naval Base,
Philcomsat sent Globe a letter demanding payment of its However, Article 1174, which exempts an obligor from
outstanding obligations plus interest and attorneys liability on account of fortuitous events or force
fees. However, Globe refused to heed Philcomsats demand. majeure, refers not only to events that are
unforeseeable, but also to those which are foreseeable,
Philcomsat filed with the Regional Trial Court of Makati but inevitable:
a Complaint against Globe
 Globe filed an Answer to the Complaint, insisting that Art. 1174. Except in cases specified by the law, or
it was constrained to end the Agreement. when it is otherwise declared by stipulation, or when
the nature of the obligation requires the assumption
 Globe explained that the occurrence of said events of risk, no person shall be responsible for those
exempted it from paying rentals for the remaining events which, could not be foreseen, or which, though
period of the Agreement. foreseen were inevitable.
The trial court rendered its Decision in favor of
petitioner. A fortuitous event under Article 1174 may either be an
act of God, or natural occurrences such as floods or
Both parties appealed the trial courts Decision to the typhoons, or an act of man, such as riots, strikes or
Court of Appeals. wars.
Philcomsat claimed that the trial court erred in ruling Clearly, the foregoing are either unforeseeable, or
that: (1) the non-ratification by the Senate of the foreseeable but beyond the control of the parties. There
Treaty constitutes force majeure which exempts Globe is nothing in the enumeration that runs contrary to, or
from complying with its obligations under the expands, the concept of a fortuitous event under Article
Agreement; (2) Globe is not liable to pay the rentals 1174.
for the remainder of the term of the Agreement; and (3)
Globe is not liable to Philcomsat for exemplary damages. Furthermore, under Article 1306 of the Civil Code,
parties to a contract may establish such stipulations,
Globe, on the other hand, contended that the RTC erred clauses, terms and conditions as they may deem fit, as
in holding it liable for payment of rent of the earth long as the same do not run counter to the law, morals,
station for December 1992 and of attorneys fees. good customs, public order or public policy.
Article 1159 of the Civil Code also provides that
[o]bligations arising from contracts have the force of ART 1177 (SUBSIDIARY REMEDIES OF CREDITOR)
law between the contracting parties and should be  The creditors, after having pursued the property of the
complied with in good faith. Courts cannot stipulate for debtor to satisfy their claims, may
the parties nor amend their agreement where the same
does not contravene law, morals, good customs, public o Exercise all the rights and bring all the actions of
order or public policy, for to do so would be to alter the latter for the same purpose
the real intent of the parties, and would run contrary
to the function of the courts to give force and effect  SAVE those which are inherent in his
thereto. persons
Not being contrary to law, morals, good customs, public o Impugn acts which the debtor may have done
order, or public policy, Section 8 of the Agreement to defraud them
which Philcomsat and Globe freely agreed upon has the
force of law between them.
Right of creditors
Philcomsat and Globe had no control over the non-renewal
of the term of the RP-US Military Bases Agreement when  exact fulfillment with the right to damages (DE
the same expired in 1991, because the prerogative to LEON)
ratify the treaty extending the life thereof belonged  Levy by attachment and execution upon all property
to the Senate. Neither did the parties have control of debtor EXCEPT such as are exempt by law
over the subsequent withdrawal of the US military forces o Attachment  court, at the request of
and personnel from Cubi Point in December 1992: creditor, designates specific property of
debtor to be transferred to creditor
The formal order from Cdr. Walter Corliss of the USN,  Exercise all the rights and actions of the debtor
the letter notification from ATT and the complete EXCEPT such as are inherently personal to him
withdrawal of all the military forces and personnel o All rights  example: right to redeem
from Cubi Point in the year-end 1992 are also acts and o Actions of debtor  example: right to
circumstances beyond the control of the defendant. collect from debtor of debtor
o EXCEPTION example: right to vote, right to
Considering the foregoing, the Court finds and so hold office, right for legal support
holds that the afore-narrated circumstances constitute  Ask for the rescission of the contracts made by the
force majeure or fortuitous event(s) as defined under debtor in fraud of their rights
paragraph 8 of the Agreement.
Liability of debtor’s property
The aforementioned events made impossible the  Subject to liability for his obligations
continuation of the Agreement until the end of its five- o Composed of his present and future property
year term without fault on the part of either party. The o Legal guaranty in favor of creditors
Court of Appeals was thus correct in ruling that the
happening of such fortuitous events rendered Globe Exercise of debtor’s rights
exempt from payment of rentals for the remainder of the  Requisites
term of the Agreement. o Creditor has an interest in the right or
action because of insolvency of debtor
o Malicious or negligent inaction of the debtor
as to endanger the claim of creditor
o Credit of debtor against 3rd person is clear,
demandable and liquidated
o Debtor’s right against 3rd person must be
patrimonial or susceptible of being
transformed to patrimonial value for benefit Thus, the following successive measures must be taken
of creditor by a creditor before he may bring an action for
 Not essential that creditor’s claim be prior to the rescission of an allegedly fraudulent sale:
acquisition of the right (1) exhaust the properties of the debtor through levying
by attachment and execution upon all the property of
Accion Subrogatoria the debtor, except such as are exempt by law from
 Action which creditor may exercise in the place of execution;
his negligent debtor (2) exercise all the rights and actions of the debtor,
o Preserve or recover for the patrimony of the save those personal to him (accion subrogatoria); and
debtor the product of such action (3) seek rescission of the contracts executed by the
o Obtain satisfaction of his own credit debtor in fraud of their rights (accion pauliana).
 Previous approval of court is not necessary
Without availing of the first and second
Personal rights of debtor remedies, i.e., exhausting the properties of the debtor
 Existence or subrogating themselves in Francisco Barengs
 Relations of a public character transmissible rights and actions, petitioners simply
undertook the third measure and filed an action for
 Honorary character
annulment of the sale. This cannot be done.
 Powers which have not been used
o Power to administer FACTS
o Power to carry out an agency or deposit Respondent Saturnino Bareng was the registered owner of
o Power to accept an offer for a contract two parcels of land, both of which are in San Fabian,
 Non-patrimonial rights Echague, Isabela. Petitioners were lessees of a portion
 Patrimonial rights not subject to execution of his lot.
 Patrimonial rights inherent in the person of the
debtor Saturnino Bareng and his son, private respondent
Francisco Bareng, obtained a loan from petitioners
Rescission of Fraudulent Act amounting to twenty six thousand pesos (P26,000), in
 Accrion pauliana consideration of which they promised to transfer the
o Action to revoke or rescind fraudulent possession and enjoyment of the fruits of Lot No. 661-
reductions of the properties of the debtor E.
which constitute guaranty for his debts Saturnino sold to his son Francisco 18,500 sq.m. of Lot
No. 661-D-5-A.
ADORABLE v CA  Francisco sold to private respondent Jose Ramos 3,000
sq.m. of the lot.
TOPIC  The portion of land being rented to petitioners was
included in the portion sold to Jose Ramos.
Art. 1177 of the Civil Code provides:
The creditors, after having pursued the property in  The deeds of sale evidencing the conveyances were
possession of the debtor to satisfy their claims, may not registered in the office of the register of
exercise all the rights and bring all the actions of deeds.
the latter for the same purpose, save those which are
inherent in his person; they may also impugn the As the Barengs failed to pay their loan, petitioners
actions which the debtor may have done to defraud complained to Police Captain Rodolfo Saet of the
Integrated National Police (INP) through whose
them. mediation a Compromise Agreement was executed between
Francisco Bareng and the Adorables whereby the former
acknowledged his indebtedness of P56,385.00 which he
promised to pay on or before July 15, 1987.
 When the maturity date arrived, however, Francisco the latter for the same purpose, save those which are
Bareng failed to pay. inherent in his person; they may also impugn the
actions which the debtor may have done to defraud
 A demand letter was sent to Francisco Bareng, but he
refused to pay. them.

Petitioners, learning of the sale made by Francisco Thus, the following successive measures must be taken
Bareng to Jose Ramos, then filed a complaint with the by a creditor before he may bring an action for
Regional Trial Court for the annulment or rescission of rescission of an allegedly fraudulent sale:
the sale on the ground that the sale was fraudulently (1) exhaust the properties of the debtor through levying
prepared and executed. by attachment and execution upon all the property of
 trial court rendered judgment dismissing the the debtor, except such as are exempt by law from
complaint for lack of cause of action, declaring the execution;
contract of sale between Francisco Bareng and Jose (2) exercise all the rights and actions of the debtor,
Ramos valid and ordering Francisco Bareng to pay the save those personal to him (accion subrogatoria); and
amount he owed petitioners. (3) seek rescission of the contracts executed by the
debtor in fraud of their rights (accion pauliana).
On appeal, the Court of Appeals affirmed the decision
of the Regional Trial Court, with modification as to Without availing of the first and second
the amount of Francisco Barengs debt to petitioners. remedies, i.e., exhausting the properties of the debtor
or subrogating themselves in Francisco Barengs
ISSUE: transmissible rights and actions, petitioners simply
Whether sale was made in fraud of creditors – NO undertook the third measure and filed an action for
annulment of the sale. This cannot be done.
We hold that, as creditors, petitioners do not have
such material interest as to allow them to sue for Indeed, an action for rescission is a subsidiary remedy;
rescission of the contract of sale. At the outset, it cannot be instituted except when the party suffering
petitioners’ right against private respondents is only damage has no other legal means to obtain reparation
a personal right to receive payment for the loan; it is for the same.[6]Thus, Art. 1380 of the Civil Code
not a real right over the lot subject of the deed of provides:
sale. The following contracts are rescissible:
. . . .
A personal right is the power of one person to demand (3) Those undertaken in fraud of creditors when the
of another, as a definite passive subject, the latter cannot in any other manner collect the claims
fulfillment of a prestation to give, to do, or not to due them;
do. On the other hand, a real right is the power
belonging to a person over a specific thing, without a Petitioners have not shown that they have no other means
passive subject individually determined, against whom of enforcing their credit.
such right may be personally exercised.[5] In this case,
 Plaintiffs-appellants had not even tried to exhaust
while petitioners have an interest in securing payment the property of defendants-appellees
of the loan they extended, their right to seek payment
does not in any manner attach to a particular portion Bareng. Plaintiffs-appellants, in seeking for the
of the patrimony of their debtor, Francisco Bareng. rescission of the contracts of sale entered into
between defendants-appellees, failed to show and
Nor can we sustain petitioners claim that the sale was prove that defendants-appellees Bareng had no other
made in fraud of creditors. Art. 1177 of the Civil Code property, either at the time of the sale or at the
time this action was filed, out of which they could
provides: have collected this (sic) debts.
The creditors, after having pursued the property in
possession of the debtor to satisfy their claims, may CHENG v CA
exercise all the rights and bring all the actions of
 While the case was still pending, Khe Hong Cheng
TOPIC executed deeds of donations of parcels of land in
An accion pauliana accrues only when the creditor favor of his children, herein co-petitioners Sandra
discovers that he has no other legal remedy for the Joy and Ray Steven.
satisfaction of his claim against the debtor other
than an accion pauliana. The accion pauliana is an The trial court rendered judgment against petitioner
action of a last resort. For as long as the creditor Khe Hong Cheng four years after the donations were made
still has a remedy at law for the enforcement of his and the TCTs were registered in the donees names.
claim against the debtor, the creditor will not have After the said decision became final and executory, a
any cause of action against the creditor for writ of execution was forthwith issued however, was not
rescission of the contracts entered into by and
between the debtor and another person or served.
persons. Indeed, an accion pauliana presupposes a  sheriff found no property under the name of Butuan
judgment and the issuance by the trial court of a writ Shipping Lines and/or petitioner Khe Hong Cheng to
of execution for the satisfaction of the judgment and levy or garnish for the satisfaction of the trial
the failure of the Sheriff to enforce and satisfy the court's decision.
judgment of the court. It presupposes that the
 When the sheriff, accompanied by counsel of
creditor has exhausted the property of the debtor. The respondent Philam, went to Butuan City to enforce
date of the decision of the trial court against the the alias writ of execution, they discovered that
debtor is immaterial. What is important is that the petitioner Khe Hong Cheng no longer had any property
credit of the plaintiff antedates that of the and that he had conveyed the subject properties to
fraudulent alienation by the debtor of his his children.
property. After all, the decision of the trial court
against the debtor will retroact to the time when the Philam filed a complaint with the Regional Trial Court
debtor became indebted to the creditor. for the rescission of the deeds of donation executed by
petitioner Khe Hong Cheng in favor of his children and
FACTS for the nullification of their titles.
Petitioner Khe Hong Cheng, alias Felix Khe, is the owner Petitioners subsequently filed their answer to the
of Butuan Shipping Lines. It appears that on or about complaint a quo. They moved for its dismissal on the
October 4, 1985, the Philippine Agricultural Trading ground that the action had already prescribed. They
Corporation shipped on board the vessel M/V PRINCE ERIC, posited that the registration of the deeds of donation
owned by petitioner Khe Hong Cheng, 3,400 bags of copra on December 27, 1989 constituted constructive notice
at Masbate, Masbate, for delivery to Dipolog City, and since the complaint a quo was filed only on February
Zamboanga del Norte. The said shipment of copra was 25, 1997, or more than four (4) years after said
covered by a marine insurance policy issued by American registration, the action was already barred by
Home Insurance Company. prescription.
M/V PRINCE ERIC, however, sank somewhere between Negros The trial court denied the motion to dismiss. It held
Island and Northeastern Mindanao, resulting in the that respondent Philam's complaint had not yet
total loss of the shipment. Because of the loss, the prescribed. According to the trial court, the
insurer, American Home, paid the amount of P354,000.00 prescriptive period began to run only from December 29,
(the value of the copra) to the consignee. 1993, the date of the decision of the trial court in
Civil Case No. 13357.[4]
Having been subrogated into the rights of the consignee,
American Home filed a complaint in the Regional Trial The CA affirmed the trial court's decision in favor of
Court to recover the money paid to the consignee, based respondent Philam.
on breach of contract of carriage.
 Citing Articles 1381 and 1383 of the Civil Code, the the prescriptive period for the action.[7] Article 1383
CA basically ruled that the four year period to of the Civil Code provides as follows:
institute the action for rescission began to run only
in January 1997, and not when the decision in the Art. 1383. An action for rescission is subsidiary; it
civil case became final and executory on December cannot be instituted except when the party suffering
29, 1993. damage has no other legal means to obtain reparation
 accrual of respondent Philam's cause of action on for the same.
January 1997, the time when it first learned that
the judgment award could not be satisfied because It is thus apparent that an action to rescind or
the judgment creditor, petitioner Khe Hong Cheng,
an accion pauliana must be of last resort, availed of
had no more properties in his name.
only after all other legal remedies have been exhausted
 Prior thereto, respondent Philam had not yet and have been proven futile. For an accion pauliana to
exhausted all legal means for the satisfaction of accrue, the following requisites must concur:
the decision in its favor, as prescribed under
Article 1383 of the Civil Code.
1) That the plaintiff asking for rescission has a
The Court of Appeals thus denied the petition credit prior to the alienation, although demandable
for certiorari filed before it, and held that the trial later;
court did not commit any error in denying petitioners'
motion to dismiss. Their motion for reconsideration was 2) That the debtor has made a subsequent contract
likewise dismissed in the appellate court's resolution conveying a patrimonial benefit to a third person;
Petitioners now assail the aforesaid decision.
3) That the creditor has no other legal remedy to
ISSUE: satisfy his claim, but would benefit by rescission of
Whether the four (4) year prescriptive period as the conveyance to the third person;
provided for in Article 1389 of the Civil Code for
respondent Philam to file its action for rescission of 4) That the act being impugned is fraudulent;
the subject deeds of donation had already prescribed –
NO 5) That the third person who received the property
conveyed, if by onerous title, has been an accomplice
RATIO
in the fraud.[8] (Emphasis ours)
Article 1389 of the Civil Code simply provides that,
The action to claim rescission must be commenced within We quote with approval the following disquisition of
four years. Since this provision of law is silent as to the CA on the matter:
when the prescriptive period would commence, the
general rule, i.e, from the moment the cause of action
accrues, therefore, applies. Article 1150 of the Civil An accion pauliana accrues only when the creditor
Code is particularly instructive: discovers that he has no other legal remedy for the
satisfaction of his claim against the debtor other
Art. 1150. The time for prescription for all kinds of than an accion pauliana. The accion pauliana is an
actions, when there is no special provision which action of a last resort. For as long as the creditor
ordains otherwise, shall be counted from the day they still has a remedy at law for the enforcement of his
may be brought. claim against the debtor, the creditor will not have
any cause of action against the creditor for
rescission of the contracts entered into by and
Indeed, this Court enunciated the principle that it is
the legal possibility of bringing the action which between the debtor and another person or persons.
determines the starting point for the computation of
An accion pauliana presupposes a judgment and the 2) the issuance by the trial court of a writ of
issuance by the trial court of a writ of execution for execution for the satisfaction of the judgment, and
the satisfaction of the judgment and the failure of 3) the failure of the sheriff to enforce and satisfy
the Sheriff to enforce and satisfy the judgment of the the judgment of the court.
court. It presupposes that the creditor has exhausted
the property of the debtor. The date of the decision It requires that the creditor has exhausted the property
of the trial court against the debtor is of the debtor. The date of the decision of the trial
immaterial. What is important is that the credit of court is immaterial. What is important is that the
credit of the plaintiff antedates that of the fraudulent
the plaintiff antedates that of the fraudulent alienation by the debtor of his property. After all,
alienation by the debtor of his property. After all, the decision of the trial court against the debtor will
the decision of the trial court against the debtor retroact to the time when the debtor became indebted to
will retroact to the time when the debtor became the creditor.
indebted to the creditor.
While it is necessary that the credit of the plaintiff
Petitioners, however, maintain that the cause of action in the accion pauliana must be prior to the fraudulent
of respondent Philam against them for the rescission of alienation, the date of the judgment enforcing it is
the deeds of donation accrued as early as December 27, immaterial. Even if the judgment be subsequent to the
1989, when petitioner Khe Hong Cheng registered the alienation, it is merely declaratory with retroactive
subject conveyances with the Register of Deeds. effect to the date when the credit was constituted.
Respondent Philam allegedly had constructive knowledge
of the execution of said deeds under Section 52 of
Presidential Decree No. 1529, quoted infra, as follows: In the same case, the Court also quoted the rationale
of the CA when it upheld the dismissal of the accion
Section 52. Constructive knowledge upon registration. pauliana on the basis of lack of cause of action:
Every conveyance, mortgage, lease, lien, attachment,
order, judgment, instrument or entry affecting In this case, plaintiffs appellants had not even
registered land shall, if registered, filed or entered commenced an action against defendants-appellees
in the Office of the Register of Deeds for the Bareng for the collection of the alleged indebtedness.
province or city where the land to which it relates Plaintiffs-appellants had not even tried to exhaust
lies, be constructive notice to all persons from the the property of defendants-appellees Bareng.
time of such registering, filing, or entering. Plaintiffs-appellants, in seeking the rescission of
the contracts of sale entered into between defendants-
Petitioners argument that the Civil Code must yield to appellees, failed to show and prove that defendants-
the Mortgage and Registration Laws is misplaced, for in appellees Bareng had no other property, either at the
no way does this imply that the specific provisions of time of the sale or at the time this action was filed,
the former may be all together ignored. To count the out of which they could have collected this (sic)
four year prescriptive period to rescind an allegedly debts.
fraudulent contract from the date of registration of
the conveyance with the Register of Deeds, as alleged Even if respondent Philam was aware, as of December 27,
by the petitioners, would run counter to Article 1383 1989, that petitioner Khe Hong Cheng had executed the
of the Civil Code as well as settled jurisprudence. It deeds of donation in favor of his children, the
would likewise violate the third requisite to file an complaint against Butuan Shipping Lines and/or
action for rescission of an allegedly fraudulent petitioner Khe Hong Cheng was still pending before the
conveyance of property, i.e., the creditor has no other trial court. Respondent Philam had no inkling, at the
legal remedy to satisfy his claim. time, that the trial court's judgment would be in its
An accion pauliana thus presupposes the following: favor and further, that such judgment would not be
satisfied due to the deeds of donation executed by
1) A judgment; petitioner Khe Hong Cheng during the pendency of the
case. Had respondent Philam filed his complaint on
December 27, 1989, such complaint would have been
dismissed for being premature. Not only were all other
legal remedies for the enforcement of respondent
Philams claims not yet exhausted at the time the deeds
of donation were executed and registered. Respondent
Philam would also not have been able to prove then that
petitioner Khe Hong Chneg had no more property other
than those covered by the subject deeds to satisfy a
favorable judgment by the trial court.
It bears stressing that petitioner Khe Hong Cheng
even expressly declared and represented that he had
reserved to himself property sufficient to answer for
his debts contracted prior to this date:

That the DONOR further states, for the same purpose as


expressed in the next preceding paragraph, that this
donation is not made with the object of defrauding his
creditors having reserved to himself property
sufficient to answer his debts contracted prior to
this date.

As mentioned earlier, respondent Philam only learned


about the unlawful conveyances made by petitioner Khe
Hong Cheng in January 1997 when its counsel accompanied
the sheriff to Butuan City to attach the properties of
petitioner Khe Hong Cheng. There they found that he no
longer had any properties in his name. It was only then
that respondent Philam's action for rescission of the
deeds of donation accrued because then it could be said
that respondent Philam had exhausted all legal means to
satisfy the trial court's judgment in its favor. Since
respondent Philam filed its complaint for accion
pauliana against petitioners on February 25, 1997,
barely a month from its discovery that petitioner Khe
Hong Cheng had no other property to satisfy the judgment
award against him, its action for rescission of the
subject deeds clearly had not yet prescribed.

You might also like