Professional Documents
Culture Documents
By
Superintending Engineer,
TVCC,
BBMP
1
BBMP Quality Control :
Several lakhs of rupees being spent for Infrastructure
and other Improvement works in BBMP.
In order to ensure quality of works a full fledged,
well equipped in house laboratory is necessary.
Presently the BBMP has a quality control wing
constituting EE’s , AEE’s & AE’s.
The quality control lab is equipped for testing
cement, sand, metal, bitumen, bituminous mix, etc.,
The field Engineers shall make use of BBMP quality
control lab to ensure good quality works.
2
Emplaned Laboratories in BBMP
3
Quality Control
Performed by Contractor
4
Quality Assurance
Performed by Owner
5
Quality Control vs. Quality Assurance
High Quality
QC + QA =
Finished Road
6
3 Phases of Contractor Quality Control
Preparatory
Phase Start-up
Phase Production
Phase
7
3 Phases of Contractor Quality Control
What is involved?
Production Phase
•Ensure Contract Compliance
•Conduct intermittent or continuous inspections to identify and correct
deficiencies
•Inspect completed phases before scheduled Government acceptance
•Ensure Testing reports are submitted
•Ensure rework is completed
8
CONSTRUCTION PHASE-Quality Control
9
Requirements
Ensure Quality
10
Advantages
Improved Quality
Uniformity
½ to 1% of Construction Cost
11
Pre
Pre--requisites
12
Quality Control In Road Construction
Control of Materials
Test Procedure
Frequency and Extent of Testing
Acceptance Criteria
Equipment Type & its Calibration
Recording of Test Results
Training for QC
13
Quality Control Test
Individual Materials
Soil, Gravel, Aggregate, Binder
Mixes
Gradation of Aggregates, Mix Proportion, Mixed Design
Properties
14
Quality Control Test
Test on Compacted Layer
Mixed Proportion (Unbound Layers)
Density
Mix proportion and Gradation (bound layers after extraction)
Finished Surface
Longitudinal Profile
Transverse Profile
Cross Slope
Texture
15
Tests On Borrow Materials Of embankment/subgrade
17
Compaction Requirements For Embankment
And Subgrade
Expansive Clays:
Subgrade and 500 mm Not Allowed
portion just below the
subgrade
Remaining Portion of Not Less than 90
Embankment
18
Frequency of Compaction Tests
Degree of compaction
(a) Body of embankment At least one test per 1,000 m2 for
each layer
(b) Subgrade and shoulders At least one test per 500 m2 for each
layer
19
Location Of Density Test Points For Earth
Work
20
Acceptance Criteria
Control should be based on the mean value of a
set of 5-
5-10 density measurement.
1.65
1.65 − (No. of samples)0.5 times the standard deviation
21
Granular Sub-
Sub-base
Gradation One test per 200 m3
CBR As Required
22
Lime/ Cement Stabilised Soil Sub-
Sub-base
Test Requirements
25
Wet Mix Macadam
27
Surface Dressing
Water Absorption of - do -
Aggregates
Grading of Aggregates One Test per 25 m3 of Aggregates
29
Physical Requirements Of Aggregates For
Bituminous Macadam
Test Requirement
Los Angeles Abrasion 40 % Max.
Value
FI and EI 30 % Max.
Coating and Stripping of 30 % Max.
Bitumen Aggregate
Mixtures
Soundness 12 % Max.
Water Absorption 2 % Max. 30
Bituminous Macadam
Water Absorption of - do -
Aggregates
Water Sensitivity of mix As Required for BC
34
Requirements Of Bituminous Concrete Mix
36
Aggregate Gradation
SAMPLING
• STOCK PILE
• COLD FEEDER BELT
• HOT BINS
• EXTRACTED ASPHALT MIXTURE (END
PRODUCT)
37
Trouble Shooting
Sampling stock pile
Check gradation of new material added
Segregation in feeder belt
Improper loading of cold bins
Improper setting of individual bins
38
Asphalt Content
39
Temperature
40
Temperature
41
Compaction
Commence From Edges And Progress Towards
Centre
Initial Breakdown Rolling – 8 To 10 T Smooth
Wheel Roller
Intermediate Rolling – 8-10 T Dead Wt. Or
Vibratory Roller.Pneumatic Tyred Roller –12
12--15 T
Wt. 5.6 Kg/Sq.Cm Pr.
Finished Rolling – 6-8 T Smooth Wheel Tandem
Roller
42
Compaction
43
Suggested Frequency And Amplitude For Vibratory
Compaction
Nature of Frequency Amplitude Thickness of
Soil/ (CPM) (mm) Compaction,
Materials mm
Rock 1800
1800--2500 1.2 – 1.5 750
Sandy/clay 1600--2000
1600 0.8 – 1.2 600
/clayey
Clay 2000
2000--2500 0.8 – 1.0 400
Asphalt 2500-
2500-3500 0.4 – 0.6 50 – 75
44
Effect Of Speed Of Roller In Density And
Finish Surface
ROUGH
SMOOTH
FINISH
FINISH
HIGHER SPEED
LOWER SPEED
LOW DENSITY
HIGH DENSITY
OPERATION
SPEED
45
Relationship Between Compactability &
Temperature
46
47
48
TACK COATING BY SPRAYER
49
Tack Coat Without Crack Sealing
50
Overlay Over Severely Cracked
Surface
51
Inadequate Compaction And Excess
Binding Material
52
WBM Surface Without Key Aggregates And Excess Binding
Material
53
Shoulders At Higher Elevation
54
Poorly Widened WBM Carriageway
55
POORLY WIDENED WBM CARRIAGEWAY
56
Depressed Carriageway
57
Tack Coat Surfaced WBM Layer
58
Modern Equipment For
Quality Control Tests In
Highways Construction
59
Asphalt Content Guage
60
Portable Pendulum Type Skid Resistance Tester
61
Dynamic Skid Resistance Tester
62
Portable Asphalt Core Cutter
63
Non Nuclear Density Gauge
64
Benkelmen Beam
65
Fifth Wheel Bump Integrator (Roughometer)
66
Nuclear Density Meter
67
Asphalt Content Guage
68
69
70
71
Falling Weight Deflectometer
72
73