partida EXCAVACION DE ZANJAS :CIMIENTOS

CIMIENTO CORRIDO CANTIDAD LARGO


EXCAVACION DE ZANJAS :CIMIENTOS
EJE VERTICALES
EJE AA, BB, CC Entre 11,22,33,44 3 10.25
EJE BB, B'B' ENTRE 22, 33 1 1.85
EJE HORIZONTALES
EJE 1-1,22,33,44 entre AA , CC 4 6.8
RELLENO COMPACTADO MATERIAL PROPIO
RELLENO POR DEBAJO DEL TNATURAL
EJE AA, BB, CC Entre 11,44 4 9.65
EJE B-B' ENTRE 22.33 1 1.85
E EJE HORIZONTALES
EJE 11,44 ENTRE AA,CC 2 6.8
EJE 22,33 entre AA ,CC 2 6.8
EJE 22 ,33 ENTRE AA ,CC 2 6.65
relleno debajo de ntn
ejes horizontales
eje 11,22,33,44 entre AA, BB 6 3.625
eje 22,33 entre BB, CC 2 14.200
ejes verticales
UNIDAD M3
ANCHO ALTO METRADO PARCIAL METRADO TOTAL

0.4 1.100 13.53


0.4 1.100 0.814 14.344

0.4 1.100 11.968

0.15 0.300 1.737


0.15 0.300 0.08325

0.25 0.300 1.02


0.15 0.300 0.612
0.15 0.300 0.5985 4.05075

0.25 0.3
0.25 0.3