SUBJECT: METHOD STATEMENT FOR ACC BLOCK
MASONRY WORK
METHOD STATEMENT
FOR
WORKS
Prepared by: Ashwini Kumar Checked by: Mr. A.K.Tripathi
PROJECT NAME: LOGIX BLOSSOM COUNTY, SEC137, DATE: 23.06.11
NOIDA
PAGE: 2 OF 6
SUBJECT: METHOD STATEMENT FOR ACC BLOCK
MASONRY WORK
INDEX OF CONTENTS
1. OBJECTIVE
2. SCOPE
3. RESOURCES USED
4. WORK METHODOLOGY
5. SAFETY MEASURES
Prepared by: Ashwini Kumar Checked by: Mr. A.K.Tripathi
PROJECT NAME: LOGIX BLOSSOM COUNTY, SEC137, DATE: 23.06.11
NOIDA
PAGE: 3 OF 6
SUBJECT: METHOD STATEMENT FOR ACC BLOCK
MASONRY WORK
WORK METHODOLOGY FOR REINFORCEMENT WORKS
Objective – The objective of this method statement is to describe in detail all the
operation concerned with the Logix Blossom County Project.
Scope of work – As per B.O.Q. Item number 4.03 & 4.04 to execute 6000 cum and
11500 Sqm (approx.) ACC block masonry works at all levels.
Resources used
1. Materials: Cement, Sand, flyash and Water
2. Machinery and Tools: Measuring box, mortar mixer, Curing pipes etc
3. Manpower : Engineer, Supervisors/Foremen, Mason Gang and Unskilled
workers
WORK METHODOLOGY
1. The jointing mortar shall be leaner like 1:6. the mortar shall not be spread so
much ahead of the actual laying of the unit that it tends to stiffen and lose it's
plasticity there by resulting poor bond.
2. Consistency of cement mortar as per requirement of site must be maintained at
the time of laying.
3. After obtaining the approval of the same and when the preparatory works of
concreting viz., shuttering and reinforcement are ready, checked and approved for
casting by client’s representative, concrete mixing will be done in batching plant in
accordance to pre – approved design mix.
4. Control of concrete quality is done both at batching plant and at pouring
points. Checking for workability, preparation of concrete cubes and testing
of cubes is as per manual/reports submitted and got approved / as per
Prepared by: Ashwini Kumar Checked by: Mr. A.K.Tripathi
PROJECT NAME: LOGIX BLOSSOM COUNTY, SEC137, DATE: 23.06.11
NOIDA
PAGE: 4 OF 6
SUBJECT: METHOD STATEMENT FOR ACC BLOCK
MASONRY WORK
contract requirements.
5. The concrete thus manufactured in batching plant is conveyed to site of
placing by transit mixers.
6. Placing of Concrete:
a) In Foundation Raft : Concrete pump, Boom placer, Gravity chute and
Direct pumping from Batching plant are the alternate modes proposed
to be adopted based upon the practical situation, location and
accessibility and with approval by client. Except for the method of
direct pumping, for all other methods transit mixers convey the
concrete and transfers to the mode adopted for concreting. If for
various reasons, construction joint is required to be provided then the
proposal of the same for positions and details in schematic sketch is
submitted to the client for approval. After obtaining approval of the
same, necessary steps are taken to provide construction joints with
approved material and casting is done continuously upto the joint. A
system of staging and gangways is done for laying pipe and movement
of workmen/ staff.
b) In columns and walls : Columns and walls are casted upto the
approved height in single lift with pump and pipelines, boom placer,
with tower crane bucket or manually as agreed by client. Necessary
staging for support of distributor manifold in case of pumping will be
provided. Expansion joints will be provided as shown in drawings and
as per details given. A system of staging and gangways is done for
laying pipe and movement of workmen/ staff.
c) In Slab and Beams : Concrete will be placed using either concrete
pump, Boom placer, tower crane bucket or by direct pumping as per the
Prepared by: Ashwini Kumar Checked by: Mr. A.K.Tripathi
PROJECT NAME: LOGIX BLOSSOM COUNTY, SEC137, DATE: 23.06.11
NOIDA
PAGE: 5 OF 6
SUBJECT: METHOD STATEMENT FOR ACC BLOCK
MASONRY WORK
ground situation and with approval by client. The method of provision
of construction joint if needed, is as explained above and the casting is
done at single stretch up to the approved construction joint if approved or the slab is
cast at once.
7. Simultaneously, with the placing of concrete, compaction is done using
high frequency vibrator needles for sufficient period and the extraction of
the same will slow and carefully done so that no loose pockets are formed.
8. After the casting and removal of formwork , the curing is done for the type
of structures as follows:
9. Raft foundation: By ponding in segments on top and by using wet jute on
vertical sides for adequate time.
10. Isolated Foundations: By spraying water or using wet jute.
11. For Columns and Beams: By spraying water using curing pumps and by
using wet jute.
12. For Slab and Beams: By ponding in segments.
SAFETY MEASURES:
1. Provisions for workmen: All persons working at the site shall be provided with
the safety equipments, protection means such as hand gloves, safety helmets
and other necessary kinds.
2. Provisions for Equipment, Machine:
a) All equipment will be ensured to operate safely, maintained and
repaired periodically.
b) All power equipment should be insulated and covered to all exposed
live parts.
Prepared by: Ashwini Kumar Checked by: Mr. A.K.Tripathi
PROJECT NAME: LOGIX BLOSSOM COUNTY, SEC137, DATE: 23.06.11
NOIDA
PAGE: 6 OF 6
SUBJECT: METHOD STATEMENT FOR ACC BLOCK
MASONRY WORK
c) A competent person shall inspect equipment during shift duty.
3. Provisions for Job Site:
a) Relevant Caution boards and sufficient lighting system shall be installed
at the working area to ensure safety for construction activities at night
time.
b) The working area shall be free from hazards before starting the work.
c) Unnecessary materials such as empty bags and rubbish shall be
removed periodically.
Prepared by: Ashwini Kumar Checked by: Mr. A.K.Tripathi