MAIN PUMPING STATION

1-Pump Guide bar auto coupling Arrangement foundation details is not clear, should be provided
after getting vendor datasheet.

2-Duck foot bend foundation detail is not clear should be provided after getting vendor datasheet.

3- Pump pedestal size is not clear, should be provided after getting vendor datasheet.

4-Dimention of Screen/Conveyor, details is not clear should be provided after getting vendor
datasheet.

5-Sluice gate foundation /Anchoring/Thimble fixing details is not clear should be provided after
getting vendor datasheet.

6-Exust Fan arrangement and fixing details is not clear should be provided after getting vendor
datasheet.

7-Motorise sluice valve details at pump delivery line is not clear should be provided after getting
vendor datasheet.

8- NRV Arrangement details at delivery site is not clear should be provided after getting vendor
datasheet.

9-Ultrasonic flow meter arrangement and chamber details are not clear should be provided after
getting vendor datasheet.

10- Pump Bottom clearance is not clear should be provided after getting vendor datasheet.