MEP PRODUCTIVITY RATES

Productivity norms
S.N0 Activity
Qty Units

ELECTRICAL/ELV
1 Conduit 16-20 Rm/man/day

2 Wiring 200 Rm/man/day


3 Cable tray 6 Rm/man/day
4 Trunking 10 sq.m/man/day

5 Cable Pulling 30 sq.m/man/day


6 DB Installation 2-4 Nos/man/day

7 DB Termination 2 Nos/man/day
8 Final Fix Accessories 10 - 14 Nos/man/day
9 Light points 10 - 14 Nos/man/day

PLUMBING

1 Water supply pipe installation 08 - 10 Rm/man/day

2 Drain pipe installation 06 - 08 Rm/man/day

DUCTING:
1 Duct 1.2 – 1.5 Sqm/man/day

2 Insulation 4-7 Sqm/man/day


3 1 No - VAV 3-5 Sqm/man/day

4 1 No - ECV 3-5 Sqm/ man/day


5 1 No – Joint Insulation 0.4 Sqm/man/day
6 1 No - Flexible Duct 2-4 Sqm/man/day

7 1 No - Plenum 2-4 Sqm/man/day


8 1 No - MSFD 3-5 Sqm/man/day

9 1 No - VCD 2-4 Sqm/man/day


10 Pressure Test per 25 Sqm ducting 4.5 Sqm/man/ day
11 Multipurpose Supports – 4 No 1.5 Sqm/man/day

12 Grills & Diffusers 6 No’s / Man/ day


13 Linear Slot Diffuser 6 Rm / Man / day
CHW PIPE:

1 1" – 2" dia 7.5 - 10 Rm/man/day


2 2" - 3"dia 5 Rm/man/day

3 4"dia 2.5 Rm/man/day


4 6"dia 1.5 Rm/man/day
5 8"dia 1.2 Rm/man/day

6 10"dia 1 Rm/man/day
7 CHW Pipe Insulation 15 Rm/man/day

8 Pressure Test for 100 Rm 3 man/day


9 Valve Package 1.5 Man / day / unit
Remarks

Kindly note that Piping


Installation is inclusive of
Support fixing

Kindly note that here


ducting is inclusive
Support fixing + Cleat
fixing + Sealant application
Kindly note that here
Chilled water piping is
inclusive of Support fixing