WHRB#1 COMPREHENSIVE SHUTDOWN PLANNING -MAY-2018

06 07 08 09 10 11 12 13 14 15 16
Sr. Responsible Location / Priority Plan
Activity May-18 May-18 May-18 May-18 May-18 May-18 May-18 May-18 May-18 May-18 May-18 Remark/Reason for delay
No. Department Area Level
Actual Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11
Power connections tightness , checking, blowing to be done from AC Drive & motor both Plan 1
1 Electrical WHRB#1 High
sides of ID FAN-3 of WHRB-1. Actual

Power connections tightness , checking, blowing to be done from AC Drive & motor both Plan 1
2 Electrical WHRB#1 High
sides of ID FAN-4 of WHRB-1. Actual

Visual Inspection to be carried out & to be changed if requires of Support Insulators of ESP Plan 1 2
3 Electrical WHRB#1 High
of WHRB-1. Actual

Power connection tightness , checking & blowing to be done of Rapper Panel ( CE & DE ) of Plan 1
4 Electrical WHRB#1 Medium
WHRB-1. Actual

Connection tightness , checking, Resistance value measurement & healthiness checking to Plan 1
5 Electrical WHRB#1 Medium
be done of Rappers( CE & DE ) of WHRB-1. Actual

Power connections tightness checking & cleaning to be done from Transformer and Panel Plan 1 2
6 Electrical WHRB#1 High
(ESP Trans. Panel) both sides of ESP Transformers (WHRB-1). Actual
Plan 1
7 Transformer Oil top-up to be carried out in ESP Transformers, if requires. Electrical WHRB#1 High
Actual
Plan 1
8 Silica gel to be changed if requires of ESP Transformers of WHRB-1. Electrical WHRB#1 High
Actual

Power , control & Limit Switch connections tightness , checking , blowing to be done from Plan 1
9 Electrical WHRB#1 Medium
starter & motor both sides of Soot blowers of WHRB-1. Actual
Plan 1
10 ESP Field # 1 to 4 TR. Air charge testing work has to be done. Electrical WHRB#1 Medium
Actual
Legend:
Note: Shut down period is taken from boiler MSSV Plan
Actual
closed to MSSV open. In progress
Delay