ID Task Name Duration

Feb 11, '18 Feb 25, '18 Mar 11, '18 Mar 25, '18 Apr 8, '18 Apr 22, '18 May 6, '18 May 20, '18
19 23 27 3 7 11 15 19 23 27 31 4 8 12 16 20 24 28 2 6 10 14 18 22 26
1 1 Work Shop (Phase I ) 60 days
2 1.1 BUILDING RENOVATION 60 days
3 1.1.1 Renovation Approval from YCDC 3 days

4 1.1.2 Agreement with Construction company 1 day

5 1.1.3 Building Cleaning 1 day

6 1.1.4 Building Interior and exterior renovation 30 days

7 1.1.5 Tube Well and under ground septic Digging 15 days

8 1.1.6 Bath and Toilet Room 25 days

9 1.1.7 Electrical work 3 days

10 1.1.8 painting(Interior and outerior) 25 days

11 1.2 Purchasing 15 days


12 1.2.1 Hand tools and Equipment Sourcing (Local & oversea) 5 days

13 1.2.2 Hand tools and Equipment purchasing and delivery (Local 10 days
& oversea)
14 1.3 Recuirmentation 20 days

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: workshop set up Milestone Inactive Milestone Start-only


Date: Wed 2/28/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
ID Task Name Duration
Feb 11, '18 Feb 25, '18 Mar 11, '18 Mar 25, '18 Apr 8, '18 Apr 22, '18 May 6, '18 May 20, '18
19 23 27 3 7 11 15 19 23 27 31 4 8 12 16 20 24 28 2 6 10 14 18 22 26
15 1.3.1 Recuirmentation 20 days

16 1.4 Installation 14 days


17 1.4.1 Tools and Equipment Installation 7 days

18 1.4.2 water pump installation 3 days

19 1.5 <New Summary Task> 11 days


20 1.5.1 Warehouse Unloading from Hlaingtharyar 4 days

21 1.5.2 warehouse set up 7 days

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: workshop set up Milestone Inactive Milestone Start-only


Date: Wed 2/28/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2