Index
2 Salient Feature 3
4 Project Data 5
11 Revenue Projection 12
17 Areas of Concern 18
Residential Complex
Salient Features
Salient Features
Completed %
% of Completed
Total in the month Completed %
Trades Unit Contract Upto
Quantity of in Completed
Value 31/01/2010
31/01/2010 31/01/2010
Earthwork
L.S 1.05 - - - 0.830
Subcontract
Job Number/Code
Job Name
Client Name
Client Address
Scope of Work (Initial) Entire Civil work including finishing together with all
services like, electrical, firefighting plumbing &
landscaping.
Location of Project
PMC Client
PMC Representative Client
Structural Consultant
Services (Plumbing, Electrical, HVAC
etc)
Liaison
Project Management & Contact Number
Project Coordinator
Project Manager
Planning Engineer
Billing Engineer
Construction Manager
PMC Coordinator Mr.Sandeep & Ms Mayuri
Contractual Conditions / Obligations
Penalty
Electric & Power supply Free Client supply
Limit for Interim Bill No Limit
RMC = 2 %,
Permitted Extra Over Theoretical Reinforcement Steel = 5 %
(EOT)
Cement =3%
Project Data
Mobilization Amount Rs. 89,249,567/- and Rs 78728983/- Total Rs. 167978550/-
Received on June 24, 2008 and November 20,2009
Recovered Till 31/12/2009 Rs. 21,405,141/-
RA Bill Number 26th
Balance Mobilisation Recovery Amount Rs. 235,822,976.00 /-
Mobilization Amount (Yet not Received) Rs. 22455357/-
Type of Bank
Value Validity Issuing Bank
Guarantee
Mobilisation Standard
19,000,000 31.12.2009
Advance Chartered Bank
Mobilisation Standard
30,000,000 30.06.2010
Advance Chartered Bank
Mobilisation Standard
Bank Guarantee (Type – 30,000,000 30.06.2010
Advance Chartered Bank
Advance/Performance/Retention)
Mobilisation Standard
51,074,285 30.06.2010
Advance Chartered Bank
Mobilisation Standard
62,074,285 31.12.2010
Advance Chartered Bank
Mobilisation Standard
62,074,285 31.12.2010
Advance Chartered Bank
Total 254,222,855
Billing & Certification Detail Certified till RA Bill No.22 dt. 31/08/2009
Billed Till 31/12/2009 Rs. 679,892,626/-
Slide Number - 6 -
Claims Details
Decision on Claim from Client
Delays (Reasons, Period, cause & effect
Details shown in Areas of concern – From Client.
Analysis)
Basic Rate of Material supplied by Client
Material Base Rate
RMC-10 Rs. 3000 / cum
RMC-15 Rs. 3281 / cum
RMC-25 with high volume PFA Rs. 3200 / cum
M30 Rs. 3888 / cum
M40 Rs. 4280 / cum
Cement Rs. 250 / Bag
Steel Fe415 Rs. 38000 / Mton
Steel Fe500 Rs. 38500 / Mton
For other items sheet attached separately.
Note:- These rates were the basis for rate analysis for control estimate. Since the contract is not yet
finalised confirmation of the same is not on paper.
Carpenter 230,961
Fitter 66,793
Male coolie
98,895
Including Mason
Carpenter joinery
66,336
work
Note:
Task work for Carpenter (A pair of 1 skilled, 1 semiskilled and 1 helper) = Appr. 4 sqm
Task work for Fitter (A pair of 1 Fitter, 1 Helper) = Appr. 145 kg
Slide Number - 9 -
Labour Statement as on 31/01/2010
Carpenter 40,803,111
Fitter 15,027,120
Male Coolie
14,659,111
incl.Mason
Brickwork mason
10933215
incl.male coolie
Plaster mason
40,971,647
incl.male coolie
Carpenter joinery
13,604,989
work
A B A-B C B-C
Batching Plant 1 1 0 1 0 08.05.2010
Dumper 1 0 1 0 0
JCB 1 1 0 1 0 08.05.2010
15.11.2010(2nos)
Mini dumper 2 4 -2 3 1
29.04.2012
Pickup 1 1 0 1 0 31.05.2012
26.07.2010
Passenger lift 3 5 -2 5 0 14.09.2010 Two not in use
14.11.2010
Total Station 1 1 0 1 0 29.04.2012
2 nos are used
for Baching
plant which
are included in
installation
Pumps 10 6 4 14 -8
charges.1 is
being used by
client which
will be claimed
extra.
Slide Number - 11 -
Staff Strength as on 31/01/2010
Budgeted Projected
Revised Variance Actual
Staff Category as per Variance Demobilization Remarks
Budget Deployed
Tender Date
A B A-B C B-C
Project Co-Ordinator 0 0 0 1 -1
General Manager
Project Manager 1 1 0 1 0 working as Project
Manager
General Manager 0 0 0 1 -1
Resource Co-Ordinator 1 0 1 0 0
Assistant Project Manager 0 2 -2 0 2
One working as a
Billing engineer, one
Junior Project Manager 0 0 0 3 -3
as Planning, one as
Quality incharge.
Planning Engineer 1 1 0 0 1
Two site engineers
Billing Engineer 2 4 -2 0 4 are working as
Billing Engineer.
One Senior engineer
is transferred to
Senior Engineer 5 8 -3 3 5
Lodha site in June
09
Site Engineer 13 11 2 6 5
Two Site Engineers
Quality Control Engineer 0 1 -1 0 1 are working as
Quality Engineer.
Assistant Quality Control
0 3 -3 0 3
Engineer
Quality Engineer 2 0 2 0 0
Assistant Engineer 0 0 0 2 -2
Junior Engineer 5 11 -6 8 3
Senior Civil Foreman 5 0 5 0 0
One working as
Foreman 1 16 -15 10 6
Surveyor.
Assistant Foreman 0 0 0 1 -1
Jr.Mechanical Engineer 1 1 0 1 0
Electrical Engineer 1 0 1 1 -1
Senior Supervisor 0 0 0 7 -7
Supervisor 7 40 -33 14 26
Assistant Supervisor 0 0 0 1 -1
Junior Supervisor 0 0 0 1 -1
Surveyor 1 2 -1 1 1
Electrician 3 7 -4 4 3
Helper 12 0 12 0 0
Mechanic 3 0 3 2 -2
Assistant Mechanic 0 0 0 1 -1
Technician 0 0 0 1 -1
Lab Technician 1 0 1 0 0
Fitter 0 0 0 2 -2
Cost Accountant 1 0 1 0 0
Store Keeper 2 2 0 2 0
Assistant Store Keeper 3 4 -1 3 1
Safety Officer 1 2 -1 2 0
Safety Steward 8 12 -4 2 10
Safety Supervisor 0 0 0 2 -2
Operator 21 21 0 10 11
Welder 0 3 -3 1 2
Driver 2 3 -1 3 0
Office Boy 4 3 1 0 3
Computer Operator 2 1 1 0 1
Slide Number - 12 -
Budgeted Projected
Revised Variance Actual
Staff Category as per Variance Demobilization Remarks
Budget Deployed
Tender Date
Mechanical Engineer 0 0 0 0 -1
Trainee 0 0 0 3 -3
Cumulative Cumulative
Planned Billed (In Variance Cumulative
Month Planned (In Billed (In Remark
(In Lacs) Lacs) (In Lacs) (In Lacs)
Lacs) Lacs)
A B A-B C D C–D
JAN 10
Slide Number - 13 -
Revenue Projection
Outstanding Dues
31 – 60 Days Rs.
60 – 90 days Rs.
Project To
Sr No. Description Staff Labour Total This Month
Date
1 Total Manpower
2 Worked
3 No. of Accidents
First Aid
Minor
Major
Near Miss
6 Trained Person
7 Defective Equipment
RMC
Cement
Utilized for
Total Work In Physical
Total Non Recovered Allowable
Received Progress Stock at EOT Remarks
Invoice Chargeable by client EOT (%)
(cement) ( Not Billed ) site
Activity
4 Co-ordination- 15%
3 Safety at site
4 Co-ordination
6 Resources utilization
Areas of Concern
From Client Site possession for Tower D & E was given 4.5 months after start of project.
Introduction of Fire staircase has affected the work
Introduction of tie beams between stilt and first floor level has affected the work.
Introduction of break pressure tank at 13th floor level has affected the work.
Flyash bricks were supplied quite late by client.
All Nominated agencies are appointed very late which has delayed finishing work.
Final Drawings for finishing work were received late which has delayed finishing work.
Contract not yet finalized.
Decisions are made quite late which is affecting the progress of work.
Working space at Site is restricted due to construction of sales office, sample flat and
area reserved for Flyash Brick manufacturing yard.
Compound wall work on west and north side held up due to non-clearance by MLDL.
BOQ and G.C.C for Nominated agencies were finalized late.
Deletion of internal plaster has delayed the brick work.
Changes in the methodology of fixing of door frame have affected plastering work.
Site possession and details for podium work are being released quite late.
A frequent change in drawings is affecting work.
Rate for Podium work yet not finalized.
Payments against R.A bills are getting unduly delayed.
Work front for podium is not available fully.
Slide Number - 20 -
Tower A, B and C.
Tower D and E.
UG TANK
Slide Number - 22 -
General Information
Name of the Project
May 27, 2008 ( Valid till 3 years from date of Execution unless
Date of MOU
terminated)
Date of Letter of Intent Not received
Date of Commencement
Date of Completion
3 Years From Virtual Completion,
Defect Liability Period 17
10 Yrs For Waterproofing
When whole of the project works is substantially completed
CONTRACTOR to give notice to Technical Referee with copy
to Client accompanied by a written undertaking to finish
with due expedition any outstanding work during Defects
Liability Period.
Certificate of Virtual If there are no defects then, technical referee shall within
Completion (VCC) 28 days of the date of delivery of such notice issue VCC.
If there are defects affecting balance work then Technical
referee will notify this to CONTRACTOR & Client
Once defects are rectified then issue VCC within 15 days.
Before granting VCC to CONTRACTOR Technical referee
should also take Client’s review into account.
Contract Value Rs. 2,231,239,174/-
Employer
Architect
Structural Consultant
Priority of Documents
Date of Contract
-
Agreement
Entire Civil work including finishing together with all services
Scope of work
like electrical, fire fighting, plumbing and landscaping.
If Client appoints……… as Main Contractor for the project
Responsibility 2
which shall include responsibility of
Slide Number - 24 -
a. Construction Coordinator
b. Construction Manager
Architects & Consultants will be appointed by Client to
Architect’s duties and
prepare drawings, designs & lay specifications for the 2
authorities
project.
Guarantees and Deposits
Within 30 days of execution of the Construction Contract,
CONTRACOITR shall furnish a BG issued by Scheduled Bank
Performance Security of amount of 10 % of Contract Value which will remain in 11
force until 30 days after the date of Virtual Completion.
This will be then replaced by Retention money Guarantee.
Retention money Guarantee 2.5% of gross value of Final bill
Retention Money amount including extra items & claims & shall be valid until
11, 17
(Liability of Defects ) 30 days after the date of expiry of the Defects Liability
Period.
Advances
With LOI ……..will receive Advance of 4% of estimated value
of project works as in LOI against BG of equal amount from
scheduled Bank
Within 30 days of execution of the Construction Contract
Mobilisation Advance 4
between Client & CONTRACTR CONTRACTOR will receive an
advance equal to 8% of CV after deducting advances already
received by CONTRACTOR along with LOI.
Employer’s Risks
Insurance covers
Submission of Interim
Every month
Bills
Minimum amount of
Not specified
Interim Bill
Adhoc 50% of Value of RA bill within 7 working days of
receipt of bill & balance within 7 working days of the receipt
of Certificate of Payment.
Once bill amount reaches 90% no adhoc payment will be
Release of payments made. Total amount due will be paid on within 7 working 17
days of the receipt of Certificate of Payment.
Checking & verification of bills shall not take more than 14
working days for RA bills
Slide Number - 28 -
at least 1 year after they have left the service of the other
party.