Professional Documents
Culture Documents
PLANNING
TECHNIQUES
EXAMPLES:
Hardware Design
Project
Parviz F. Rad
Vittal Anantatmula
Unit of Supply Cost
Resources: Measure Limit ($US)
1. Personnel
1.1. Design Engineers
1.1.1. Design Manager
1.1.1.1. Senior level Yr 1 275,000
1.1.2. Circuit Design Engineers
1.1.2.1. Analog
1.1.2.1.1. Principle level Yr 1 255,000
1.1.2.1.2. Staff level Yr 2 225,000
1.1.2.1.3. Sr. level Yr 1 200,000
1.1.2.1.4. Intermediate level Yr 3 167,500
1.1.2.1.5. Engineer level Yr 1 145,000
1.1.2.2. Digital
1.1.2.2.1. Staff level Yr 1 200,000
1.1.2.2.2. Sr. level Yr 1 185,000
1.1.2.2.3. Intermediate level Yr 2 160,000
1.1.3. Mask Design Engineers
1.1.3.1. Sr. level Yr 1 130,000
1.1.3.2. Intermediate level Yr 1 115,000
1.1.3.3. Engineer level Yr 1 97,500
1.2. CAE Engineers (Computer Automated Engineering)
1.2.1. Staff level Yr 1 200,000
1.2.2. Sr. Level Yr 1 185,000
1.3. ESD Engineers (Electro-Static Discharge)
1.3.1. Principle level Yr 1 210,000
1.3.2. Staff level Yr 2 182,500
1.4. Applications Engineers
1.4.1. Principle level Yr 1 165,000
1.4.2. Intermediate level Yr 1 125,500
1.4.3. Engineer level Yr 1 105,000
1.5. Product Engineers
1.5.1. Staff level Yr 1 150,000
1.5.2. Sr. level Yr 1 135,500
1.6. FA Engineers (Failure Analysis)
1.6.1. Principle level Yr 1 160,000
1.6.2. Sr. level Yr 1 130,000
1.6.3. Intermediate level Yr 1 115,500
1.7. Project Management
1.7.1. Staff level Yr 3 140,000
1.8. System Administration
1.8.1. Staff level Yr 1 130,000
1.8.2. Intermediate level Yr 2 155,500
2. Tools
2.1. Computers
2.1.1. Unix 5 payments, yearly 17 4,000
2.1.2. PC 5 payments, yearly 15 500
2.2. LCD projector 5 payments, yearly 3 850
2.3. Plotter 5 payments, yearly 1 2000
2.4. Printer
2.4.1. Color 5 payments, yearly 1 1,100
2.4.2. B/W 5 payments, yearly 1 625
2.5. Test boards
2.5.1. AC board fab run each Unlimited 5,000
2.5.2. DC board fab run each Unlimited 4,000
2.5.3. Jitter board fab run each Unlimited 5,000
2.5.4. Sockets each Unlimited 1,500
2.5.5. Application board each Unlimited 2,000
2.6. Test equipment
2.6.1. AC setup 5 payments, yearly 2 60,000
2.6.2. DC setup 5 payments, yearly 1 45,000
3. Licenses
3.1. Software
3.1.1. Cadence yearly 25 20,000
3.1.2. Microsoft project yearly 3 500
All personnel (Section 1.0) available in this project environment are salaried employees.
A small amount of the fringe benefit may vary year to year, but for this assignment it is
considered constant. Depending on the software utilized in creating the project schedule
in later assignments, care must be given to make sure that an overtime rate is assigned as
$0.00. The personnel resources are not able to receive overtime pay. In order to indicate
this, all personnel rates are as given as cost/year. The personnel are first grouped by
function. The lowest function level is then grouped by job title.
Most of the tools available in this project environment (Section 2.0, excluding section
2.5) are capitalized purchases. The tools are depreciated in a straight-line manner over
five years. The depreciation value per year is included in the RBS for cost purposes. In
order to allocate cost for the RBS it is assumed that the tools have been recently
purchased, therefore current book value is equal to purchase price. The tools are grouped
by logical segments. Some segments are then further grouped by type.
The test boards and sockets (Section 2.5) are generated and charged on a per - project basis
if needed. The boards are purchased from a vendor and processed as a sheet. The vendor
can yield up to six boards but guarantees a yield of four. If the yield is higher than four,
the charge does not change.
Work Breakdown Structure
* - Daily rates area calculated from the rates given in the RBS. The costs for the resources utilized in the WBS are given as yearly in
the RBS. The yearly costs were divided by 260 (52 weeks/yr, 5 days/week) to arrive at daily costs then divided by 8 to arrive at
hourly costs if necessary. Since all the human resources are paid on a salary basis, they are not eligible for overtime. This will be
taken into account when developing the schedule. The daily costs are rounded up to the next whole dollar.
Project Cost Comparison by Resource
(Expressed as a percentage of the total cost at given level of the WBS)
Integrated Circuit Mask
Circuit Design Design Docu-
Database Schematics Cells mentation
Resource: Level 0.0 % Level 1.0 % Level 2.0 % Level 3.0 %
Sr. Design Manager 4.32 1.27 3.22 15.16
Principle Analog Design Engineer 31.32 36.23 11.95 31.95
Sr. Analog Design Engineer 13.16 17.60 3.51 7.01
Interm. Analog Design Engineer 18.76 26.64 1.96 7.55
Analog Design Engineer 0.86 0.90 0.00 1.45
Interm. Digital Design Engineer 5.51 6.18 0.00 8.03
Sr. Mask Design Engineer 4.74 0.00 27.46 0.65
Mask Design Engineer 6.44 0.00 32.07 5.39
Staff CAE Engineer 1.96 0.93 7.03 1.00
Principle Applications Engineer 0.65 0.00 0.00 3.31
Interm. Applications Engineer 0.37 0.00 0.00 1.89
Applications Engineer 0.62 0.00 0.00 3.16
Principle Marketing Engineer 0.18 0.00 0.00 0.91
Staff Project Manager 2.14 0.00 0.00 10.91
Unix Workstation 1.63 1.72 2.15 0.91
PC 0.01 0.00 0.00 0.06
LCD projector 0.00 0.00 0.00 0.00
B/W Printer 0.00 0.00 0.00 0.02
Plotter 0.01 0.00 0.05 0.03
Cadence Software 7.32 8.53 10.60 0.60
MSProject Software 0.00 0.00 0.00 0.00
Totals 100.00 100.00 100.00 100.00
The distribution of resources shown in the above two tables are fairly consistent with
previous similar projects that have been completed within the department. Level 3.0 is
usually slightly lower and Level 1.0 slightly higher, as some of the reviews are accounted
for in the Level 1.0 deliverables. This WBS captures the reviews in the documentation
portion, therefore the differences are justified.
The total cost for the design project is in line with the cost of similarly scoped projects.
The use of the lead designer, principle analog design engineer, is slightly heavier in this
project due to the incorporation of technology that other engineers do not have much
experience with.
Precedence Table
Order of
Exectution Lowest level Elements Predecessors Successors
1 Product Requirement Specification Design Database Start Design FMEA
Base-level Schematic: Multiplexer1
Base-level Schematic: Multiplexer2
Base-level Schematic: Counter1
Base-level Schematic: Counter2
CAD and Design Library Development Plan
Project Risk Analysis
2 Design FMEA Product Requirement Specification DFT analysis
Base-level Schematic: Multiplexer1 Product Requirement Specification Base-level Cell: Multiplexer1
Block-level Schematic: Decoder
Base-level Schematic: Multiplexer2 Product Requirement Specification Base-level Cell: Multiplexer2
S S
Interm. Design SS + 5d
Review
Equalizer Top-level Top Level LVS/DRC Design
3.2.1.1 Floorplan Review Cell Report Database
Complete
3.2.2.5 2.3 3.1.8 5.0
3.1.7
Interm. Design
Review
Transmitter PLL
3.2.1.3
Project Risk
Analysis
3.1.4
uary February March April May June
ID WBS Task Name Duration Float Start Finish Predecessors Successors Resource Names 1/5 1/19 2/2 2/16 3/2 3/16 3/30 4/13 4/27 5/11 5/25
0 0 ABC123 Integrated Circuit Database 104 days 0 days Mon 1/6/03 Thu 5/29/03 0
1 1 Circuit Design Schematics 83 days 0 days Wed 1/8/03 Fri 5/2/03 1
2 1.1 Base-level Schematics 25 days 5 days Wed 1/8/03 Tue 2/11/03 1.1
3 1.1.1 Multiplexer 1 2 days 0 days Wed 1/8/03 Thu 1/9/03 39 15,21
5 1.1.3 Rotational Frequency Detector 10 days 0 days Wed 1/15/03 Tue 1/28/03 88 12,23 1.1.3
6 1.1.4 Variable Controlled Oscillator 6 days 0 days Wed 1/15/03 Wed 1/22/03 88 12,24 1.1.4
7 1.1.5 Digital/Analog Converter 20 days 0 days Wed 1/15/03 Tue 2/11/03 88 12,25 1.1.5
8 1.1.6 Counter 1 4 days 0 days Wed 1/8/03 Mon 1/13/03 39 15,26 1.1
9 1.1.7 Counter 2 5 days 0 days Wed 1/8/03 Tue 1/14/03 39 16,27 1.1.
10 1.2 Block-level Schematics 60 days 2 days Wed 1/8/03 Tue 4/1/03 1.2
11 1.2.1 Equalizer 30 days 0 days Wed 1/15/03 Tue 2/25/03 88 29,51 1.2.1
12 1.2.2 CDR PLL 35 days 0 days Wed 2/12/03 Tue 4/1/03 5,6,7 30,52 1.2.2
13 1.2.3 Transmitter PLL 40 days 0 days Wed 1/15/03 Tue 3/11/03 88 31,53 1.2.3
14 1.2.4 LVDS Driver 5 days 0 days Wed 1/8/03 Tue 1/14/03 39 32,54 1.2.
15 1.2.5 Decoder 8 days 0 days Tue 1/14/03 Thu 1/23/03 3,8 33,55 1.2.5
16 1.2.6 Encoder 8 days 0 days Wed 1/15/03 Fri 1/24/03 4,9 34,56 1.2.6
17 1.2.7 Cable Driver 12 days 0 days Wed 1/15/03 Thu 1/30/03 88 35,57 1.2.7
18 1.3 Top-level Schematic 20 days 0 days Mon 4/7/03 Fri 5/2/03 41,51,52,53,54,55,56,57,42 40SS,63SS+5 days,87,48,44,47 1.3
19 2 Mask Design Cells 97 days 0 days Fri 1/10/03 Mon 5/26/03 2
20 2.1 Base-level Cells 35 days 48 days Fri 1/10/03 Thu 2/27/03 2.1
21 2.1.1 Multiplexer 1 4 days 6 days Fri 1/10/03 Wed 1/15/03 3 33 2.1
22 2.1.2 Multiplexer 2 4 days 7 days Fri 1/10/03 Wed 1/15/03 4 34 2.1
23 2.1.3 Rotational Frequency Detector 7 days 38 days Wed 1/29/03 Thu 2/6/03 5 30 2.1.3
24 2.1.4 Variable Controlled Oscillator 8 days 41 days Thu 1/23/03 Mon 2/3/03 6 30 2.1.4
25 2.1.5 Digital/Analog Converter 12 days 23 days Wed 2/12/03 Thu 2/27/03 7 30 2.1.5
26 2.1.6 Counter 1 3 days 5 days Tue 1/14/03 Thu 1/16/03 8 33 2
27 2.1.7 Counter 2 3 days 5 days Wed 1/15/03 Fri 1/17/03 9 34
28 2.2 Block-level Cells 66 days 16 days Wed 1/15/03 Wed 4/16/03 2.2
29 2.2.1 Equalizer 8 days 0 days Wed 2/26/03 Fri 3/7/03 11 62 2.2.1
30 2.2.2 CDR PLL 11 days 0 days Wed 4/2/03 Wed 4/16/03 12,23,24,25 59 2.2.2
31 2.2.3 Transmitter PLL 7 days 0 days Wed 3/12/03 Thu 3/20/03 13 60 2.2.3
32 2.2.4 LVDS Driver 3 days 79 days Wed 1/15/03 Fri 1/17/03 14 36
35 2.2.7 Cable Driver 6 days 0 days Fri 1/31/03 Fri 2/7/03 17 61 2.2.7
36 2.3 Top-level Cell 12 days 0 days Fri 5/9/03 Mon 5/26/03 32,33,34,63,48,59,60,61,62 46,45SS+5 days 2.3
37 3 Documentation 104 days 0 days Mon 1/6/03 Thu 5/29/03 3
38 3.1 NPPRS deliverables 104 days 0 days Mon 1/6/03 Thu 5/29/03 3.1
39 3.1.1 Product Requirement Specification 2 days 0 days Mon 1/6/03 Tue 1/7/03 89 3,4,8,9,43,41,14,42
40 3.1.2 Intellectual Property Plan 2 days 18 days Mon 4/7/03 Tue 4/8/03 18SS 48
41 3.1.3 CAD and Design Library Development Plan 2 days 61 days Wed 1/8/03 Thu 1/9/03 39 18
42 3.1.4 Project Risk Analysis 2 days 61 days Wed 1/8/03 Thu 1/9/03 39 18
45 3.1.7 Buildsheet 1 day 9 days Fri 5/16/03 Fri 5/16/03 36SS+5 days 90
48 3.1.10 Final Design Review 4 days 0 days Mon 5/5/03 Thu 5/8/03 18,40 36 3.
49 3.2 Supplemental Design Documents 68 days 14 days Wed 1/15/03 Fri 4/18/03 3.2
50 3.2.1 Intermediate Design Reviews 58 days 0 days Wed 1/15/03 Fri 4/4/03 3.2.1
51 3.2.1.1 Equalizer 2 days 26 days Wed 2/26/03 Thu 2/27/03 11 18
63 3.2.2.5 Top-level Floorplan Review 2 days 17 days Mon 4/14/03 Tue 4/15/03 18SS+5 days 36
64 3.3 Miscellaneous Documents 101.5 days 1.5 days Tue 1/7/03 Wed 5/28/03 3.3
65 3.3.1 Weekly Project Reviews 101.5 days 1.5 days Tue 1/7/03 Wed 5/28/03 89 90
87 3.3.2 HSPICE Model 6 days 13 days Mon 5/5/03 Mon 5/12/03 18 90 3.3.2
88 3.3.3 DFT analysis 3 days 0 days Fri 1/10/03 Tue 1/14/03 43 5,6,7,11,13,17 3.
89 4 Design Database Start 0 days 0 days Mon 1/6/03 Mon 1/6/03 39,65 1/6
90 5 Design Database Complete 0 days 0 days Thu 5/29/03 Thu 5/29/03 44,46,47,65,45,87 5/29
ABC123 Integrated Circuit Databas
ID Resource Name Initials Group Max. Units Std. Rate Ovt. Rate Cost/Use Accrue At Base Calendar
1 Sr. Design Manager S 100% $275,000.00/yr $0.00/hr $0.00 Prorated Standard
2 Principle Analog Design Engineer P 100% $255,000.00/yr $0.00/hr $0.00 Prorated Standard
3 Staff Analog Design Engineer S 200% $225,000.00/yr $0.00/hr $0.00 Prorated Standard
4 Sr. Analog Design Engineer S 100% $200,000.00/yr $0.00/hr $0.00 Prorated Standard
5 Intermediate Analog Design Engineer I 300% $167,500.00/yr $0.00/hr $0.00 Prorated Standard
6 Analog Design Engineer A 100% $145,000.00/yr $0.00/hr $0.00 Prorated Standard
7 Staff Digital Design Engineer S 100% $200,000.00/yr $0.00/hr $0.00 Prorated Standard
8 Sr. Digital Design Engineer S 100% $185,000.00/yr $0.00/hr $0.00 Prorated Standard
9 Intermediate Digital Design Enginee I 200% $160,000.00/yr $0.00/hr $0.00 Prorated Standard
10 Sr. Mask Design Engineer S 100% $130,000.00/yr $0.00/hr $0.00 Prorated Standard
11 Intermediate Mask Design Engineer I 100% $115,000.00/yr $0.00/hr $0.00 Prorated Standard
12 Mask Design Engineer M 100% $97,500.00/yr $0.00/hr $0.00 Prorated Standard
13 Staff CAE Engineer S 100% $200,000.00/yr $0.00/hr $0.00 Prorated Standard
14 Sr. CAE Engineer S 100% $185,000.00/yr $0.00/hr $0.00 Prorated Standard
15 Principle ESD Engineer P 100% $210,000.00/yr $0.00/hr $0.00 Prorated Standard
16 Staff ESD Engineer S 200% $182,500.00/yr $0.00/hr $0.00 Prorated Standard
17 Principle Applications Engineer P 100% $165,000.00/yr $0.00/hr $0.00 Prorated Standard
18 Intermediate Applications Engineer I 100% $125,500.00/yr $0.00/hr $0.00 Prorated Standard
19 Applications Engineer A 100% $105,000.00/yr $0.00/hr $0.00 Prorated Standard
20 Staff Product Engineer S 100% $150,000.00/yr $0.00/hr $0.00 Prorated Standard
21 Sr. Product Engineer S 100% $135,500.00/yr $0.00/hr $0.00 Prorated Standard
22 Principle FA Engineer P 100% $160,000.00/yr $0.00/hr $0.00 Prorated Standard
23 Sr. FA Engineer S 100% $130,000.00/yr $0.00/hr $0.00 Prorated Standard
24 Intermediate FA Engineer I 100% $115,500.00/yr $0.00/hr $0.00 Prorated Standard
25 Principle Marketing Engineer P 100% $180,000.00/yr $0.00/hr $0.00 Prorated Standard
26 Staff Project Manager S 300% $140,000.00/yr $0.00/hr $0.00 Prorated Standard
27 Staff System Administrator S 100% $155,500.00/yr $0.00/hr $0.00 Prorated Standard
28 Intermediate System Administrator I 200% $130,000.00/yr $0.00/hr $0.00 Prorated Standard
29 Unix Computer U 1,700% $4,000.00/yr $0.00/hr $0.00 Prorated Standard
30 PC P 1,500% $500.00/yr $0.00/hr $0.00 Prorated Standard
31 LCD Projector L 300% $850.00/yr $0.00/hr $0.00 Prorated Standard
32 Plotter P 100% $2,000.00/yr $0.00/hr $0.00 Prorated Standard
33 Color Printer C 100% $1,100.00/yr $0.00/hr $0.00 Prorated Standard
34 B/W Printer B 100% $625.00/yr $0.00/hr $0.00 Prorated Standard
35 AC Test Boards A 100% $0.00/hr $0.00/hr $5,000.00 Prorated Standard
36 DC Test Boards D 100% $0.00/hr $0.00/hr $4,000.00 Prorated Standard
37 Jitter Test Boards J 100% $0.00/hr $0.00/hr $5,000.00 Prorated Standard
38 Sockets S 100% $0.00/hr $0.00/hr $1,500.00 Prorated Standard
39 Applications Test Boards A 100% $0.00/hr $0.00/hr $2,000.00 Prorated Standard
40 AC Test Equipment Setup A 200% $60,000.00/yr $0.00/hr $0.00 Prorated Standard
41 DC Test Equipment Setup D 100% $45,000.00/yr $0.00/hr $0.00 Prorated Standard
42 Cadence Software License C 2,500% $20,000.00/yr $0.00/hr $0.00 Prorated Standard
43 MSProject 98 Software License M 300% $500.00/yr $0.00/hr $0.00 Prorated Standard
Resource Expenditure Bar Chart
Five Most-used Resource for the Entire Project
400
350
300
250
Usage (hours)
200
150
100
50
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Unix Computer Cadence Software License Principle Analog Design Engineer Mask Design Engineer PC
Resource Expenditure Bar Chart
Five Most-used Resource for the Entire Project
(Unix Computer - only)
400
350
300
250
Usage (hours)
200
150
100
50
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the Entire Project
(Cadence Software License - only)
400
350
300
250
Usage (hours)
200
150
100
50
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the Entire Project
(Principle Analog Design Engineer - only)
120
100
80
Usage (hours)
60
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the Entire Project
(Mask Design Engineer - only)
120
100
80
Usage (hours)
60
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the Entire Project
(PC - only)
70
60
50
Usage (hours)
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 1.0: Circuit Design Schematics
350
300
250
Usage (hours)
200
150
100
50
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
300
250
Usage (hours)
200
150
100
50
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 1.0: Circuit Design Schematics
(Cadence Software - only)
350
300
250
Usage (hours)
200
150
100
50
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 1.0: Circuit Design Schematics
(Principle Analog Design Engineer - only)
120
100
80
Usage (hours)
60
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 1.0: Circuit Design Schematics
(Intermediate Analog Design Engineer - only)
140
120
100
Usage (hours)
80
60
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
50
40
Usage (hours)
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 2.0: Mask Design Cells
120
100
80
Usage (hours)
60
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Unix Computer Cadence Software License Mask Design Engineer Sr. Mask Design Engineer Plotter
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 2.0: Mask Design Cells
(Unix Computer - only)
120
100
80
Usage (hours)
60
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 2.0: Mask Design Cells
(Cadence Software License - only)
120
100
80
Usage (hours)
60
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 2.0: Mask Design Cells
(Mask Design Engineer - only)
120
100
80
Usage (hours)
60
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 2.0: Mask Design Cells
(Sr. Mask Design Engineer - only)
70
60
50
Usage (hours)
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 2.0: Mask Design Cells
(Plotter - only)
45
40
35
30
Usage (hours)
25
20
15
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 3.0: Documentation
70
60
50
Usage (hours)
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
PC Staff Project Manager Unix Computer Principle Analog Design Engineer MSProject 98 Software License
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 3.0: Documentation
(PC - only)
70
60
50
Usage (hours)
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 3.0: Documentation
(Staff Project Manager - only)
70
60
50
Usage (hours)
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 3.0: Documentation
(Unix Computer - only)
60
50
40
Usage (hours)
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 3.0: Documentation
(Principle Analog Design Engineer - only)
60
50
40
Usage (hours)
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Resource Expenditure Bar Chart
Five Most-used Resource for the WBS Level - 1 Elements
Task 3.0: Documentation
(MSProject 98 Software License - only)
6
4
Usage (hours)
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Weekly Cost ($K US)
$0
$5
$10
$15
$20
$25
$30
$35
$40
$45
$2
1
0.
30
$3
2
5.
46
$3
3
9.
81
$3
4
2.
37
$2
5
5.
25
$1
6
9.
21
$2
7
2.
79
$1
8
7.
90
$2
9
0.
07
$1
0.
10
97
$2
4.
11
42
$8
.8
12
3
Entire Project
$6
.1
13
8
$6
.1
14
8
$1
3.
15
80
$1
4.
16
12
$8
17 .4
1
$6
.1
18
8
$1
.5
19
9
$0
.8
20
1
$0
.8
21
1
$0
$50
$100
$150
$200
$250
$300
$350
66
6.
$3
$180
$35
$160
$30
$140
26
5.
$25
$120
$20 $100
13
8.
$1
51
6.
$1
04
5.
$80
$1
$15
32
73
1.
$60
$1
0.
$1
$10
$40
0
.8
7
7
.3
.3
.3
.3
.3
$5
$5
$5
$5
$5
$5
$5
5
2
.4
.2
$20
$3
$3
$0 $0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Cash Flow Bar Chart
Level 1 - Task 2.0: Mask Design Cells
$14 $80
90
1.
$70
$1
$12
$60
$10
9
.7
$8
0
.2
$7
1
$40
.6
$6
1
.1
$6
1
$6
.6
$5
8
.0
.9
$30
$5
$4
0
.4
$4
$4
$20
6
6
.9
.9
.9
$2
$2
$2
4
.3
$2
$2
$10
3
.9
$0
$0 $0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Cash Flow Bar Chart
Level 1 - Task 3.0: Documentation
$20 $100
53
8.
$1
$18 $90
84
6.
$1
$16 $80
$14 $70
51
2.
$12 $60
58
0.
$1
$10 $50
$8 $40
3
$6 $30
.3
$5
1
.2
$4
$4 $20
1
.8
3
.5
$2
3
7
$2
.1
.0
1
$2
$2
9
.7
.5
$2 $10
$1
1
0
$1
.2
.2
.2
.2
1
1
$1
$1
$1
$1
.8
.8
.8
.8
.8
$0
$0
$0
$0
$0
$0 $0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project Duration (weeks)
Element Original Compressed Change in Original Modified Change in Increase in
Number Description Duration Duration Duration Resource Effort* Effort* Effort* Cost
1.1.5 Base level 20 days 12.5 days 7.5 days Sr. Analog Design Eng. 160 175 15 $1,442.30
Schematic Unix Computer 160 175 15 $28.85
DAC Cadence Software License 160 175 15 $144.23
Total 45 $1615.38
1.2.2 Block level 35 days 25 days 10 days Interm. Analog Design Eng. 560 600 40 $3,221.16
Schematic Sr. Analog Design Eng. 280 300 20 $1,923.07
CDR PLL Unix Computer 840 900 60 $115.39
Cadence Software License 840 900 60 $576.93
Total 180 $5836.55
1.3 Top Level 20 days 12 days 8 days Principle Analog Design Eng. 160 192 32 $3,923.08
Schematic Unix Computer 160 192 32 $61.54
Cadence Software License 160 192 32 $307.69
Total 96 $4292.31
Total Cost Increase $11,744.24
* - Units of effort are not shown in the table. The effort is resource x time where the resource is listed in the resource column and time
is in hours (e.g. Unix Computer-hours).
In the previous assignment, the total cost of the project was calculated to be approximately $335,000. Fifteen percent of the total cost
is approximately $50,000. The fifteen percent reduction in total duration was accomplished with a cost increase of under $12,000. In
each case, the increased effort is a result of the coordination and merging of work. The more complicated schematics (1.2.2, and 1.3)
required a larger coordination effort, thus proved more costly.
Design Database Product Design FMEA DFT analysis Base Level Base Level Cell
DesS
i gt na r D
t atabase RequP
i r reomd eu nc t Design FMEA DFT analysis Schematic R F D
Start SpR
e cei qf iuc i ar tei m
o ne n t R F D
4.0 Sp
3 e. 1c .i f1i c a t i o n 3.1.5 3.3.3 1.1.3 2.1.3
4.0 3.1.1 3.1.5 3.3.3
S S
Interm. Design SS + 5d
Review
Equalizer Top-level Top Level LVS/DRC Design
3.1.7
Interm. Design
Review
Tr a n s m i t t e r P L L
3.2.1.3
Project Risk
Analysis
3.1.4
Original Modified Change in
Original Modified Change in Effort Effort Effort
Scope Element Duration Duration Duration (resource- (resource- (resource- Original Modified Change in
H Number Adjust Number Description (days) (days) (days) hrs) hrs) hrs) Cost Cost Cost
1 inc. by 7% 3.1.1 Product Requirement Specification 4 4 0 96 102.72 6.72 $6,623.07 $6,623.13 $0.06
2 inc. by 7% 3.1.5 Design FMEA 3 3 0 112 119.84 7.84 $8,467.30 $8,468.79 $1.49
3 inc. 15% 1.1.1 Multiplexer 1 2 2 0 48 55.2 7.2 $1,300.00 $1,300.00 $0.00
4 dec. to 85% 1.1.6 Counter 1 4 3.4 0.6 96 81.6 -14.4 $2,830.77 $2,406.01 ($424.76)
5 inc. by 7% 1.1.2 Multiplexer 2 2 2 0 48 51.36 3.36 $1,300.00 $1,300.00 $0.00
6 inc. by 7% 1.1.7 Counter 2 5 5 0 120 128.4 8.4 $3,538.46 $3,538.46 $0.00
7 inc. to 135% 1.2.4 LVDS Driver 5 5 0 120 162 42 $3,682.69 $3,682.69 $0.00
8 inc. by 7% 3.1.3 CAD and Design Library Development Plan 2 2 0 48 51.36 3.36 $5,346.15 $5,346.15 $0.00
9 inc. by 7% 3.1.4 Project Risk Analysis 3 3 0 80 85.6 5.6 $4,813.46 $4,812.95 ($0.51)
10 inc. by 7% 3.3.3 DFT analysis 3 3 0 96 102.72 6.72 $7,834.61 $7,835.79 $1.18
11 inc. by 7% 2.1.1 Multiplexer 1 4 4 0 96 102.72 6.72 $1,869.23 $1,869.23 $0.00
12 inc. by 7% 1.2.5 Decoder 8 8 0 192 205.44 13.44 $5,661.54 $5,307.69 ($353.85)
13 inc. 15% 2.1.6 Counter 1 3 3 0 72 82.8 10.8 $1,401.92 $1,401.93 $0.01
14 dec. to 85% 2.1.2 Multiplexer 2 4 3.4 0.6 96 81.6 -14.4 $1,869.23 $1,588.85 ($280.38)
15 inc. by 7% 1.2.6 Encoder 8 8 0 192 205.44 13.44 $5,661.54 $5,661.53 ($0.01)
16 inc. by 7% 2.1.7 Counter 2 3 3 0 72 77.04 5.04 $1,401.92 $1,401.93 $0.01
17 inc. to 135% 2.2.4 LVDS Driver 3 3 0 72 97.2 25.2 $1,401.92 $1,401.94 $0.02
18 inc. by 7% 1.1.3 Rotational Frequency Detector 10 10 0 256 273.92 17.92 $8,903.85 $8,904.14 $0.29
19 inc. by 7% 1.1.4 Variable Controlled Oscillator 6 6 0 144 154.08 10.08 $4,419.23 $4,419.24 $0.01
20 inc. by 7% 1.1.5 Digital/Analog Converter 20 20 0 480 513.6 33.6 $17,230.77 $17,230.76 ($0.01)
21 inc. by 7% 1.2.1 Equalizer 30 30 0 720 770.4 50.4 $32,192.31 $32,192.32 $0.01
22 inc. by 7% 1.2.3 Transmitter PLL 40 40 0 960 1027.2 67.2 $42,923.07 $42,923.07 $0.00
23 inc. 15% 1.2.7 Cable Driver 12 12 0 304 349.6 45.6 $10,800.01 $10,800.01 $0.00
24 dec. to 85% 2.2.5 Decoder 2 1.7 0.3 48 40.8 -7.2 $934.62 $794.43 ($140.19)
25 inc. by 7% 2.2.6 Encoder 2 2 0 48 51.36 3.36 $934.62 $934.63 $0.01
26 inc. by 7% 3.2.1.4 LVDS Driver 1 1 0 17 18.19 1.19 $659.91 $659.51 ($0.40)
27 inc. to 135% 2.1.3 Rotational Frequency Detector 7 7 0 168 226.8 58.8 $4,146.15 $4,146.16 $0.01
28 inc. by 7% 2.1.4 Variable Controlled Oscillator 8 8 0 208 222.56 14.56 $5,026.92 $5,027.11 $0.19
29 inc. by 7% 2.1.5 Digital/Analog Converter 12 12 0 288 308.16 20.16 $7,107.70 $7,107.70 $0.00
30 inc. by 7% 1.2.2 CDR PLL 35 35 0 2520 2696.4 176.4 $81,711.53 $81,711.58 $0.05
31 inc. by 7% 2.2.1 Equalizer 8 8 0 208 222.56 14.56 $5,700.00 $5,700.20 $0.20
32 inc. by 7% 3.2.1.1 Equalizer 2 2 0 33 35.31 2.31 $1,992.61 $1,993.23 $0.62
33 inc. 15% 2.2.3 Transmitter PLL 7 7 0 192 220.8 28.8 $5,240.38 $5,240.38 $0.00
34 dec. to 85% 3.2.1.3 Transmitter PLL 3 2.54 0.46 49 41.65 -7.35 $2,988.76 $2,531.15 ($457.61)
35 inc. by 7% 2.2.7 Cable Driver 6 6 0 144 154.08 10.08 $3,553.85 $3,553.85 $0.00
36 inc. by 7% 3.2.1.7 Cable Driver 2 2 0 33 35.31 2.31 $1,319.53 $1,319.95 $0.42
37 inc. to 135% 3.2.1.5 Decoder 1 1 0 17 22.95 5.95 $631.06 $630.68 ($0.38)
Original Modified Change in
Original Modified Change in Effort Effort Effort
Scope Element Duration Duration Duration (resource- (resource- (resource- Original Modified Change in
H Number Adjust Number Description (days) (days) (days) hrs) hrs) hrs) Cost Cost Cost
38 inc. by 7% 3.2.1.6 Encoder 1 1 0 17 18.19 1.19 $631.06 $630.68 ($0.38)
39 inc. by 7% 2.2.2 CDR PLL 11 11 0 400 428 28 $11,215.38 $11,215.38 $0.00
40 inc. by 7% 3.2.1.2 CDR PLL 3 3 0 73 78.11 5.11 $4,286.83 $4,287.44 $0.61
41 inc. by 7% 3.2.2.4 Equalizer 1 1 0 20 21.4 1.4 $393.56 $393.75 $0.19
42 inc. by 7% 3.2.2.2 Transmitter PLL 1 1 0 20 21.4 1.4 $393.56 $393.75 $0.19
43 inc. 15% 3.2.2.3 Cable Driver 1 1 0 20 23 3 $393.56 $393.76 $0.20
44 dec. to 85% 3.2.2.1 CDR PLL 2 1.66 0.34 36 30.6 -5.4 $783.95 $652.20 ($131.75)
45 inc. by 7% 1.3 Top-level Schematic 20 20 0 512 547.84 35.84 $25,115.37 $25,114.94 ($0.43)
46 inc. by 7% 3.1.2 Intellectual Property Plan 3 3 0 112 119.84 7.84 $8,467.30 $8,468.29 $0.99
47 inc. to 135% 3.2.2.5 Top-level Floorplan Review 2 2 0 36 48.6 12.6 $783.95 $783.95 $0.00
48 inc. by 7% 3.3.2 HSPICE Model 6 6 0 160 171.2 11.2 $4,938.47 $4,937.53 ($0.94)
49 inc. by 7% 3.1.9 Patent Application 2 2 0 40 42.8 2.8 $3,050.00 $3,049.38 ($0.62)
50 inc. by 7% 3.1.6 Business Case 3 3 0 56 59.92 3.92 $2,313.46 $2,313.71 $0.25
51 inc. by 7% 3.1.10 Final Design Review 4 4 0 67 71.69 4.69 $3,985.52 $3,984.89 ($0.63)
52 inc. by 7% 2.3 Top-level Cell 12 12 0 528 564.96 36.96 $20,969.24 $20,969.40 $0.16
53 inc. by 7% 3.1.8 DRC/LVS Report 3 3 0 49 52.43 3.43 $1,171.45 $1,171.22 ($0.23)
54 inc. by 7% 3.1.7 Buildsheet 1 1 0 17 18.19 1.19 $390.68 $390.45 ($0.23)
55 inc. by 7% 3.3.1 Weekly Project Reviews 101.5 101.5 0 651 696.57 45.57 $17,064.39 $17,064.42 $0.03
457.5 455.2 2.3 11307 12193.51 886.51 409768.42 407982.31 -1786.11
ABC123 Integrated Circuit Database
ID Resource Name Initials Group Max. Units Std. Rate Ovt. Rate Cost/Use Accrue At Base Calendar Code
3 Staff Analog Design Engineer S 200% $225,000.00/yr $0.00/hr $0.00 Prorated Standard
7 Staff Digital Design Engineer S 100% $200,000.00/yr $0.00/hr $0.00 Prorated Standard
8 Sr. Digital Design Engineer S 100% $185,000.00/yr $0.00/hr $0.00 Prorated Standard
11 Intermediate Mask Design Engineer I 100% $115,000.00/yr $0.00/hr $0.00 Prorated Standard
14 Sr. CAE Engineer S 100% $185,000.00/yr $0.00/hr $0.00 Prorated Standard
15 Principle ESD Engineer P 100% $210,000.00/yr $0.00/hr $0.00 Prorated Standard
16 Staff ESD Engineer S 200% $182,500.00/yr $0.00/hr $0.00 Prorated Standard
20 Staff Product Engineer S 100% $150,000.00/yr $0.00/hr $0.00 Prorated Standard
21 Sr. Product Engineer S 100% $135,500.00/yr $0.00/hr $0.00 Prorated Standard
22 Principle FA Engineer P 100% $160,000.00/yr $0.00/hr $0.00 Prorated Standard
23 Sr. FA Engineer S 100% $130,000.00/yr $0.00/hr $0.00 Prorated Standard
24 Intermediate FA Engineer I 100% $115,500.00/yr $0.00/hr $0.00 Prorated Standard
27 Staff System Administrator S 100% $155,500.00/yr $0.00/hr $0.00 Prorated Standard
28 Intermediate System Administrator I 200% $130,000.00/yr $0.00/hr $0.00 Prorated Standard
33 Color Printer C 100% $1,100.00/yr $0.00/hr $0.00 Prorated Standard
35 AC Test Boards A 100% $0.00/hr $0.00/hr $5,000.00 Prorated Standard
36 DC Test Boards D 100% $0.00/hr $0.00/hr $4,000.00 Prorated Standard
37 Jitter Test Boards J 100% $0.00/hr $0.00/hr $5,000.00 Prorated Standard
38 Sockets S 100% $0.00/hr $0.00/hr $1,500.00 Prorated Standard
39 Applications Test Boards A 100% $0.00/hr $0.00/hr $2,000.00 Prorated Standard
40 AC Test Equipment Setup A 200% $60,000.00/yr $0.00/hr $0.00 Prorated Standard
41 DC Test Equipment Setup D 100% $45,000.00/yr $0.00/hr $0.00 Prorated Standard
1 Sr. Design Manager S 1 100% $275,000.00/yr $0.00/hr $0.00 Prorated Standard
2 Principle Analog Design Engineer P 2 100% $255,000.00/yr $0.00/hr $0.00 Prorated Standard
17 Principle Applications Engineer P 3 100% $165,000.00/yr $0.00/hr $0.00 Prorated Standard
30 PC P 4 1,500% $500.00/yr $0.00/hr $0.00 Prorated Standard
4 Sr. Analog Design Engineer S 5 100% $200,000.00/yr $0.00/hr $0.00 Prorated Standard
9 Intermediate Digital Design Enginee I 6 200% $160,000.00/yr $0.00/hr $0.00 Prorated Standard
26 Staff Project Manager S 7 300% $140,000.00/yr $0.00/hr $0.00 Prorated Standard
6 Analog Design Engineer A 8 100% $145,000.00/yr $0.00/hr $0.00 Prorated Standard
29 Unix Computer U 9 1,700% $4,000.00/yr $0.00/hr $0.00 Prorated Standard
42 Cadence Software License C 10 2,500% $20,000.00/yr $0.00/hr $0.00 Prorated Standard
5 Intermediate Analog Design Engineer I 11 300% $167,500.00/yr $0.00/hr $0.00 Prorated Standard
13 Staff CAE Engineer S 12 100% $200,000.00/yr $0.00/hr $0.00 Prorated Standard
10 Sr. Mask Design Engineer S 13 100% $130,000.00/yr $0.00/hr $0.00 Prorated Standard
18 Intermediate Applications Engineer I 14 100% $125,500.00/yr $0.00/hr $0.00 Prorated Standard
12 Mask Design Engineer M 15 100% $97,500.00/yr $0.00/hr $0.00 Prorated Standard
34 B/W Printer B 16 100% $625.00/yr $0.00/hr $0.00 Prorated Standard
32 Plotter P 17 100% $2,000.00/yr $0.00/hr $0.00 Prorated Standard
19 Applications Engineer A 18 100% $105,000.00/yr $0.00/hr $0.00 Prorated Standard
25 Principle Marketing Engineer P 19 100% $180,000.00/yr $0.00/hr $0.00 Prorated Standard
31 LCD Projector L 20 300% $850.00/yr $0.00/hr $0.00 Prorated Standard
43 MSProject 98 Software License M 21 300% $500.00/yr $0.00/hr $0.00 Prorated Standard
ABC123 Integrated Circuit Database
ID Resource Name Initials Group Max. Units Std. Rate Ovt. Rate Cost/Use Accrue At Base Calendar
3 Staff Analog Design Engineer S 200% $225,000.00/yr $0.00/hr $0.00 Prorated Standard
7 Staff Digital Design Engineer S 100% $200,000.00/yr $0.00/hr $0.00 Prorated Standard
8 Sr. Digital Design Engineer S 100% $185,000.00/yr $0.00/hr $0.00 Prorated Standard
11 Intermediate Mask Design Engineer I 100% $115,000.00/yr $0.00/hr $0.00 Prorated Standard
14 Sr. CAE Engineer S 100% $185,000.00/yr $0.00/hr $0.00 Prorated Standard
15 Principle ESD Engineer P 100% $210,000.00/yr $0.00/hr $0.00 Prorated Standard
16 Staff ESD Engineer S 200% $182,500.00/yr $0.00/hr $0.00 Prorated Standard
20 Staff Product Engineer S 100% $150,000.00/yr $0.00/hr $0.00 Prorated Standard
21 Sr. Product Engineer S 100% $135,500.00/yr $0.00/hr $0.00 Prorated Standard
22 Principle FA Engineer P 100% $160,000.00/yr $0.00/hr $0.00 Prorated Standard
23 Sr. FA Engineer S 100% $130,000.00/yr $0.00/hr $0.00 Prorated Standard
24 Intermediate FA Engineer I 100% $115,500.00/yr $0.00/hr $0.00 Prorated Standard
27 Staff System Administrator S 100% $155,500.00/yr $0.00/hr $0.00 Prorated Standard
28 Intermediate System Administrator I 200% $130,000.00/yr $0.00/hr $0.00 Prorated Standard
33 Color Printer C 100% $1,100.00/yr $0.00/hr $0.00 Prorated Standard
35 AC Test Boards A 100% $0.00/hr $0.00/hr $5,000.00 Prorated Standard
36 DC Test Boards D 100% $0.00/hr $0.00/hr $4,000.00 Prorated Standard
37 Jitter Test Boards J 100% $0.00/hr $0.00/hr $5,000.00 Prorated Standard
38 Sockets S 100% $0.00/hr $0.00/hr $1,500.00 Prorated Standard
39 Applications Test Boards A 100% $0.00/hr $0.00/hr $2,000.00 Prorated Standard
40 AC Test Equipment Setup A 200% $60,000.00/yr $0.00/hr $0.00 Prorated Standard
41 DC Test Equipment Setup D 100% $45,000.00/yr $0.00/hr $0.00 Prorated Standard
1 Sr. Design Manager S 1 100% $305,250.00/yr $0.00/hr $0.00 Prorated Standard
2 Principle Analog Design Engineer P 2 100% $283,050.00/yr $0.00/hr $0.00 Prorated Standard
17 Principle Applications Engineer P 3 100% $183,150.00/yr $0.00/hr $0.00 Prorated Standard
30 PC P 4 1,500% $555.00/yr $0.00/hr $0.00 Prorated Standard
4 Sr. Analog Design Engineer S 5 100% $222,000.00/yr $0.00/hr $0.00 Prorated Standard
9 Intermediate Digital Design Enginee I 6 200% $177,600.00/yr $0.00/hr $0.00 Prorated Standard
26 Staff Project Manager S 7 300% $155,400.00/yr $0.00/hr $0.00 Prorated Standard
6 Analog Design Engineer A 8 100% $160,950.00/yr $0.00/hr $0.00 Prorated Standard
29 Unix Computer U 9 1,700% $4,440.00/yr $0.00/hr $0.00 Prorated Standard
42 Cadence Software License C 10 2,500% $22,200.00/yr $0.00/hr $0.00 Prorated Standard
5 Intermediate Analog Design Engineer I 11 300% $179,225.00/yr $0.00/hr $0.00 Prorated Standard
13 Staff CAE Engineer S 12 100% $214,000.00/yr $0.00/hr $0.00 Prorated Standard
10 Sr. Mask Design Engineer S 13 100% $139,100.00/yr $0.00/hr $0.00 Prorated Standard
18 Intermediate Applications Engineer I 14 100% $134,285.00/yr $0.00/hr $0.00 Prorated Standard
12 Mask Design Engineer M 15 100% $104,325.00/yr $0.00/hr $0.00 Prorated Standard
34 B/W Printer B 16 100% $668.75/yr $0.00/hr $0.00 Prorated Standard
32 Plotter P 17 100% $2,140.00/yr $0.00/hr $0.00 Prorated Standard
19 Applications Engineer A 18 100% $112,350.00/yr $0.00/hr $0.00 Prorated Standard
25 Principle Marketing Engineer P 19 100% $192,600.00/yr $0.00/hr $0.00 Prorated Standard
31 LCD Projector L 20 300% $909.50/yr $0.00/hr $0.00 Prorated Standard
43 MSProject 98 Software License M 21 300% $495.00/yr $0.00/hr $0.00 Prorated Standard
ID WBS H numbers % Complete Task Name Duration Float Start Finish
0 0 0 40% ABC123 Integrated Circuit Database 102.34 days 0 days Mon 1/6/03 Wed 5/28/03
1 1 0 43% Circuit Design Schematics 79.48 days 0 days Thu 1/9/03 Thu 5/1/03
2 1.1 0 46% Base-level Schematics 23.75 days 4.8 days Thu 1/9/03 Wed 2/12/03
3 1.1.1 3 50% Multiplexer 1 1.88 days 0 days Thu 1/9/03 Mon 1/13/03
4 1.1.2 5 50% Multiplexer 2 1.88 days 0 days Thu 1/9/03 Mon 1/13/03
5 1.1.3 18 44% Rotational Frequency Detector 9.69 days 0 days Thu 1/16/03 Thu 1/30/03
6 1.1.4 19 45% Variable Controlled Oscillator 5.75 days 0 days Thu 1/16/03 Fri 1/24/03
7 1.1.5 20 46% Digital/Analog Converter 18.75 days 0 days Thu 1/16/03 Wed 2/12/03
8 1.1.6 4 50% Counter 1 3.75 days 0 days Thu 1/9/03 Wed 1/15/03
9 1.1.7 6 49% Counter 2 4.75 days 0 days Thu 1/9/03 Thu 1/16/03
10 1.2 0 43% Block-level Schematics 57.92 days 0.9 days Thu 1/9/03 Tue 4/1/03
11 1.2.1 21 43% Equalizer 28.13 days 0 days Thu 1/16/03 Tue 2/25/03
12 1.2.2 30 41% CDR PLL 34.17 days 0 days Wed 2/12/03 Tue 4/1/03
13 1.2.3 22 43% Transmitter PLL 37.63 days 0 days Thu 1/16/03 Tue 3/11/03
14 1.2.4 7 49% LVDS Driver 4.81 days 0 days Thu 1/9/03 Thu 1/16/03
15 1.2.5 12 46% Decoder 7.56 days 0 days Wed 1/15/03 Mon 1/27/03
16 1.2.6 15 46% Encoder 7.56 days 0 days Thu 1/16/03 Tue 1/28/03
17 1.2.7 23 42% Cable Driver 11.5 days 0 days Thu 1/16/03 Mon 2/3/03
18 1.3 45 32% Top-level Schematic 18.75 days 0 days Fri 4/4/03 Thu 5/1/03
19 2 0 38% Mask Design Cells 92.73 days 0 days Mon 1/13/03 Thu 5/22/03
20 2.1 0 43% Base-level Cells 33.31 days 26.07 days Mon 1/13/03 Thu 2/27/03
21 2.1.1 11 45% Multiplexer 1 3.81 days 5.63 days Mon 1/13/03 Fri 1/17/03
22 2.1.2 14 45% Multiplexer 2 3.85 days 6.59 days Mon 1/13/03 Fri 1/17/03
23 2.1.3 27 42% Rotational Frequency Detector 6.69 days 36.54 days Thu 1/30/03 Mon 2/10/03
24 2.1.4 28 42% Variable Controlled Oscillator 7.69 days 0 days Fri 1/24/03 Wed 2/5/03
25 2.1.5 29 42% Digital/Analog Converter 11.44 days 22.73 days Wed 2/12/03 Thu 2/27/03
26 2.1.6 13 45% Counter 1 2.88 days 4.69 days Wed 1/15/03 Mon 1/20/03
27 2.1.7 16 45% Counter 2 2.88 days 4.69 days Thu 1/16/03 Tue 1/21/03
28 2.2 0 34% Block-level Cells 63.54 days 18.52 days Thu 1/16/03 Wed 4/16/03
29 2.2.1 31 32% Equalizer 7.56 days 0 days Tue 2/25/03 Fri 3/7/03
30 2.2.2 39 32% CDR PLL 10.44 days 0 days Tue 4/1/03 Wed 4/16/03
31 2.2.3 33 32% Transmitter PLL 6.63 days 0 days Tue 3/11/03 Wed 3/19/03
32 2.2.4 17 45% LVDS Driver 2.88 days 75.54 days Thu 1/16/03 Tue 1/21/03
33 2.2.5 24 43% Decoder 1.88 days 70.04 days Mon 1/27/03 Tue 1/28/03
34 2.2.6 25 43% Encoder 1.88 days 69.04 days Tue 1/28/03 Wed 1/29/03
35 2.2.7 35 32% Cable Driver 5.69 days 0 days Mon 2/3/03 Mon 2/10/03
36 2.3 52 32% Top-level Cell 11.38 days 0 days Tue 5/6/03 Thu 5/22/03
38 3.1 0 41% NPPRS deliverables 101.23 days 1.11 days Mon 1/6/03 Tue 5/27/03
39 3.1.1 1 50% Product Requirement Specification 3.75 days 0 days Mon 1/6/03 Thu 1/9/03
40 3.1.2 46 42% Intellectual Property Plan 2.13 days 16.63 days Fri 4/4/03 Tue 4/8/03
41 3.1.3 8 50% CAD and Design Library Development Plan 1.88 days 58.85 days Thu 1/9/03 Mon 1/13/03
42 3.1.4 9 52% Project Risk Analysis 2.69 days 58.04 days Thu 1/9/03 Tue 1/14/03
43 3.1.5 2 56% Design FMEA 2.5 days 0 days Thu 1/9/03 Tue 1/14/03
44 3.1.6 50 32% Business Case 2.81 days 16.3 days Thu 5/1/03 Tue 5/6/03
45 3.1.7 54 32% Buildsheet 0.94 days 0 days Tue 5/13/03 Wed 5/14/03
46 3.1.8 53 31% DRC/LVS Report 2.88 days 0 days Thu 5/22/03 Tue 5/27/03
ID WBS H numbers % Complete Task Name Duration Float Start Finish
47 3.1.9 49 32% Patent Application 1.88 days 17.24 days Thu 5/1/03 Mon 5/5/03
48 3.1.10 51 32% Final Design Review 3.75 days 0 days Thu 5/1/03 Tue 5/6/03
49 3.2 0 32% Supplemental Design Documents 65.48 days 0 days Thu 1/16/03 Fri 4/18/03
50 3.2.1 0 33% Intermediate Design Reviews 55.92 days 6 days Thu 1/16/03 Fri 4/4/03
51 3.2.1.1 32 32% Equalizer 1.88 days 25.73 days Tue 2/25/03 Thu 2/27/03
52 3.2.1.2 40 32% CDR PLL 2.81 days 0 days Tue 4/1/03 Fri 4/4/03
53 3.2.1.3 34 32% Transmitter PLL 2.81 days 0 days Tue 3/11/03 Fri 3/14/03
54 3.2.1.4 26 43% LVDS Driver 0.94 days 0 days Thu 1/16/03 Fri 1/17/03
55 3.2.1.5 37 32% Decoder 0.94 days 0 days Mon 1/27/03 Mon 1/27/03
56 3.2.1.6 38 32% Encoder 0.94 days 0 days Tue 1/28/03 Tue 1/28/03
57 3.2.1.7 36 31% Cable Driver 1.94 days 0 days Mon 2/3/03 Wed 2/5/03
58 3.2.2 0 31% Mask Design Reviews 48.1 days 0 days Mon 2/10/03 Fri 4/18/03
59 3.2.2.1 44 31% CDR PLL 1.94 days 0 days Wed 4/16/03 Fri 4/18/03
60 3.2.2.2 42 31% Transmitter PLL 0.97 days 0 days Thu 3/20/03 Thu 3/20/03
61 3.2.2.3 43 31% Cable Driver 0.97 days 0 days Mon 2/10/03 Tue 2/11/03
62 3.2.2.4 41 31% Equalizer 0.97 days 0 days Fri 3/7/03 Mon 3/10/03
63 3.2.2.5 47 31% Top-level Floorplan Review 1.94 days 0 days Fri 4/11/03 Tue 4/15/03
64 3.3 0 34% Miscellaneous Documents 101.34 days 0 days Tue 1/7/03 Wed 5/28/03
65 3.3.1 55 32% Weekly Project Reviews 101.34 days 0 days Tue 1/7/03 Wed 5/28/03
66 3.3.1.1 0 100% Weekly Project Reviews 1 12 hrs 0 hrs Tue 1/7/03 Wed 1/8/03
67 3.3.1.2 0 100% Weekly Project Reviews 2 12 hrs 0 hrs Tue 1/14/03 Wed 1/15/03
68 3.3.1.3 0 100% Weekly Project Reviews 3 12 hrs 0 hrs Tue 1/21/03 Wed 1/22/03
69 3.3.1.4 0 100% Weekly Project Reviews 4 12 hrs 0 hrs Tue 1/28/03 Wed 1/29/03
70 3.3.1.5 0 100% Weekly Project Reviews 5 12 hrs 0 hrs Tue 2/4/03 Wed 2/5/03
71 3.3.1.6 0 100% Weekly Project Reviews 6 12 hrs 0 hrs Tue 2/11/03 Wed 2/12/03
72 3.3.1.7 0 30% Weekly Project Reviews 7 12 hrs 0 hrs Tue 2/18/03 Wed 2/19/03
73 3.3.1.8 0 0% Weekly Project Reviews 8 10.75 hrs 520 hrs Tue 2/25/03 Wed 2/26/03
74 3.3.1.9 0 0% Weekly Project Reviews 9 10.75 hrs 480 hrs Tue 3/4/03 Wed 3/5/03
75 3.3.1.10 0 0% Weekly Project Reviews 10 10.75 hrs 440 hrs Tue 3/11/03 Wed 3/12/03
76 3.3.1.11 0 0% Weekly Project Reviews 11 10.75 hrs 400 hrs Tue 3/18/03 Wed 3/19/03
77 3.3.1.12 0 0% Weekly Project Reviews 12 10.75 hrs 360 hrs Tue 3/25/03 Wed 3/26/03
78 3.3.1.13 0 0% Weekly Project Reviews 13 10.75 hrs 320 hrs Tue 4/1/03 Wed 4/2/03
79 3.3.1.14 0 0% Weekly Project Reviews 14 10.75 hrs 280 hrs Tue 4/8/03 Wed 4/9/03
80 3.3.1.15 0 0% Weekly Project Reviews 15 10.75 hrs 240 hrs Tue 4/15/03 Wed 4/16/03
81 3.3.1.16 0 0% Weekly Project Reviews 16 10.75 hrs 200 hrs Tue 4/22/03 Wed 4/23/03
82 3.3.1.17 0 0% Weekly Project Reviews 17 10.75 hrs 160 hrs Tue 4/29/03 Wed 4/30/03
83 3.3.1.18 0 0% Weekly Project Reviews 18 10.75 hrs 120 hrs Tue 5/6/03 Wed 5/7/03
84 3.3.1.19 0 0% Weekly Project Reviews 19 10.75 hrs 80 hrs Tue 5/13/03 Wed 5/14/03
85 3.3.1.20 0 0% Weekly Project Reviews 20 10.75 hrs 40 hrs Tue 5/20/03 Wed 5/21/03
86 3.3.1.21 0 0% Weekly Project Reviews 21 10.75 hrs 0 hrs Tue 5/27/03 Wed 5/28/03
87 3.3.2 48 33% HSPICE Model 5.5 days 13.61 days Thu 5/1/03 Thu 5/8/03
88 3.3.3 10 56% DFT analysis 2.5 days 0 days Tue 1/14/03 Thu 1/16/03
$46.33