Weekly Progress Report

Project Name: Hlaine Tet Hotel Project Location: Kyaike Wine


Project Code: 6YG 039 00 Report Date : 2018.2.1 Thursday Report No. WPR-083
Proj Start Date 2016-6-22 Contract Period Calendar Day Period From
Estimate Completion Date Remain Period Calendar Day 2018.1.26 2018.2.1
Work Force Machine & Equipments onsite

Sr No Description 1 2 3 4 5 6 7 Total Sr No Description 1 2 3 4 5 6 7 Total

1 PM 1 Tank (4'x4'x4') 1 1 1 1 1 1 1 7
2 PE 1 1 - 1 1 1 1 6 2 165KVA Generator 1 1 1 1 1 1 1 7
3 SSE 3 Empty Drum 10 10 10 10 10 10 10 70
4 SE 1 1 1 1 1 1 1 7 4 High Speed Cutter(14") 1 1 1 1 1 1 1 7
5 QA/QC 5 7" Concrete Gun 1 1 1 1 1 1 1 7
6 QS 6 Air Blower 1 1 1 1 1 1 1 7
7 Admin 1 1 1 1 1 1 1 7 7 Submersible Pump 1 1 1 1 1 1 1 7
8 Safety 8 Air Compressor Gun 1 1 1 1 1 1 1 7
9 Site Store 1 1 1 1 1 1 1 7
10 Supervisor
11 M&E 1 1 1 1 1 1 1 7
12 Surveyer
13 Geotech
14 Mason 7 8 - 7 5 - 5 32
15 Carpenter 1 1 - 1 - - - 3
16 Smith 2 2 - - 2 2 2 10
Wateproof
17 7 11 5 6 8 6 5 48
workers
18 Welder 3 3 3 4 3 3 3 22
Alu; Curtain
19 32 34 23 27 34 26 23 199
Installer
Roofing
20
worker
Painter(Exter
21 8 7 - 6 5 6 9 41
&Stair)
22 Worker 18 15 9 11 13 8 10 84

Total 83 86 44 67 75 56 62 473 Total 17 17 17 17 17 17 17 119


Progress Detail
Description Previous This Wk Ccmmulative Description Previous This Wk Ccmmulative
Foundation % % % 4th Floor
Main Building 100 0 100 Brick Work 100 0 100
Plastering Work 99 0 99
Sub-structure Topping Work (Not include Bath & W/C) 85 0 85
Main Building 100 0 100
5th Floor
Super Structure Brick Work 99 1 100
Main Building Work 100 0 100 Plastering Work 99 0 99
Concrete Work ( Stairs 1 & 2) 100 0 100

Architectural work 6th Floor


Ground Floor Brick Work 100 0 100
Brick Work 99 0 99 Plastering Work 99 0 99
Plastering Work 91 2 93 Topping Work 90 0 90

Mezzanine Floor 7th Floor


Brick Work 97 0 97 Brick Work 100 0 100
Plastering Work 95 2 97 Plastering Work 99 0 99
Topping Work 90 0 90
1st Floor
Brick Work 100 0 100 Penthouse Floor
Plastering Work 99 0 99 Brick Work 97 2 99
Topping Work 85 0 85 Plastering Work 90 0 90

FO-PM-04 REV-01 Page: 1/2


2nd Floor
Brick Work 100 0 100 Lower Roof
Plastering Work 99 0 99 Brick Work 90 0 90
Plastering Work 80 10 90
3rd Floor
Brick Work 100 0 100
Plastering Work 99 0 99
Topping Work (Not include Bath & W/C) 85 0 85 Total Overall Progress 95.78%

This Week Activities


Trades Of Work Location Remark
1 Brick Laying Work & Plastring Work Penthouse & Lower Roof
2 Plastering Work between Door Frame Level-6,5
Aircon Outdoor, Main Entarance Installation & Additional Handrail Installation at Front
3 Mezzanine, Ground Floor & Level-1 to Lower Roof
Stair
4 Rebar Production & Installation for Stiffner Columns,Beams & Septic Tank Ground Floor
5 Topping Casting in Landing at Front Stair Level-5 to Level-2
Aluminium Curtain Panels, Flexy Board,Terracotta Panel & Glass Installation,Silicon
6 GF to Lower Roof Start Date-9.9.2017
Injection
7 Water Proofing Work Penthouse Floor Start Date-29.1.2018
8 External Putty Work Level-1 to Penthouse Start Date-12.12.2017
9 Excavation Work & Concrete Hacking for Septic Tank Ground Floor Start Date-12.1.2018
Plan For Next Week
Trades Of Work Location Remark
1 Excavation Work for Septic Tank Ground Floor
2 Plastering Work between Door Frame Level-5 to Level-2
3 Handrail Installation in Front Stair GF to Lower Roof
4 Rebar Production & Installation for Septic Tank Ground Floor
5 Topping Work for Front Stair & Remaining Rooms (Bath & W/C, M&E ) Leve-1 to Lower Roof
Aluminium Curtain Panels, Flexy Board, Louver Wall & Glass Installation & Silicon
6 GF to Lower Roof
Injection
7 Water Proofing Work & Water Testing in Top Roof Penthouse Floor
8 External Putty & Painting Work Level-1 to Penthouse
SI/VO/NCR
Status Status
No. of SI Issue for previous No of VO previous NCR previous
No. of SI Issue for this week No of VO this week NCR this week
Total SI up to this week No of VO up to this wk NCR up to this wk
Project Manager Project Engineer Prepare By: Site Engineer Sign
Name Sign Nyo Aung Sign Ohm Mar Htay
PROGRESS PHOTOS Preriod From: 2018.1.26 To: 2018.2.1

Photo 1 Photo 2
`

Steel Beam & Column Installation Work for Main Entrance at Ground Floor External Putty Work

Silicon Injection Work Water Proofing Work at Penthouse Floor

FO-PM-04 REV-01 Page: 2/2