PROJECT MANAGEMENT TEAM Rev. 00


DOC. NUMBER: XXXXXX Date:

PROJECT TITLE: Construction of Cofferdam, Skirt Modules & Provision of Support Services
CLIENT: SNEPCo
JOB NUMBER: CPHN 16040
PROJECT DATE: July 2017 to November 2017

PART A: RECORD OF LESSONS


S/N PROBLEMS/CONCERNS CAUSE SOLUTIONS/RECOMMENDATIONS RECORDED
DESCRIPTION BY
1 Having less time to study the client’s Accepting to finish a project at a lesser Pre-auditing the manpower available
drawings so as to know what is needed time not considering the manpower for the job in all department
to be done capacity at hand
2 Production of shop drawings without Lack of proper communication from the Provide all required documents
knowing what the specifications and project department to the engineering specifications for the team of
procedures from the clients are department engineers before commencing the
project
3 Double handling of drawings and Accepting to start fabrication without Get all AFC drawings before fabrication to
travel packs in order to jump the gun AFC drawings. avoid changes in design affecting
engineering deliverables
4 Delay in travel pack production to meet More workers employed in the shop floor Either giving engineering more time to get
up with fabrication demand. without increasing the number of engineers deliverables ready or increase the number
producing the required deliverables of engineers to commensurate with the
number of workers in the shop floor
5 Fabrication without proper consideration Top management giving orders to proceed Proper communication and team building
of the job requirement with fabrication without the consent of the with the production manager and the
engineering team. project engineering team.
Page 2 of 2
PROJECT MANAGEMENT TEAM Rev. 00
DOC. NUMBER: XXXXXX Date:

PROJECT TITLE: Construction of Cofferdam, Skirt Modules & Provision of Support Services
CLIENT: SNEPCo
JOB NUMBER: CPHN 16040
PROJECT DATE: July 2017 to November 2017

PART B: REVIEW OF LESSONS


Participants:

Objectives Set After Review:  To uphold thorough review of all Client’s drawings
 To improve on internal shop drawing review process
 To improve on material tracking record keeping

Project Management Team


Signature/Date: