CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECT : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DEL SECTOR AGUILAYOC DEL DISTRITO DE SANTA ANA, PROVINCIA DE LA
O CONVENCION-CUSCO
UBICACIÓN : DISTRITO: SANTA ANA /PROVINCIA: LA CONVENCION /REGION: CUSCO
LUGAR : AGUILAYOC

ITEM DESCRIPCION PARCIAL MES 01 MES02 MES 03 MES 04 MES 05 MES 06

01 TOPOGRAFO 3,012.86 260.25 223.42 244.49 802.52 1,242.37 239.82


02 OPERARIO 55,500.91 4,794.14 4,115.66 4,503.77 14,783.46 22,886.05 4,417.83
03 OFICIAL 26,725.28 2,308.52 1,981.81 2,168.69 7,118.66 11,020.29 2,127.31
04 PEON 236,143.23 20,397.93 17,511.15 19,162.47 62,900.13 97,374.72 18,796.84
05 ACEITE PARA MOTOR SAE-30 234.10 20.22 17.36 19.00 62.36 96.53 18.63
06 ALAMBRE NEGRO RECOCIDO # 16 1,832.75 158.31 135.91 148.72 488.18 755.74 145.89
07 ALAMBRE NEGRO RECOCIDO # 8 1,732.23 149.63 128.45 140.57 461.40 714.29 137.88
08 CLAVOS PARA MADERA C/C 2 1/2" 1.38 0.12 0.10 0.11 0.37 0.57 0.11
09 CLAVOS PARA MADERA C/C 2" 365.15 31.54 27.08 29.63 97.26 150.57 29.07
10 CLAVOS PARA MADERA C/C 3 1/2" 45.64 3.94 3.38 3.70 12.16 18.82 3.63
11 CLAVOS PARA MADERA C/C 3" 473.84 40.93 35.14 38.45 126.21 195.39 37.72
12 CLAVOS PARA MADERA C/C 4" 723.80 62.52 53.67 58.73 192.79 298.46 57.61
13 CLAVOS PARA MADERA S/C 3/4" 1.38 0.12 0.10 0.11 0.37 0.57 0.11
14 GRAMPAS GALVANIZADAS 2"X5"X1/4" P/CABLE 709.38 61.28 52.60 57.56 188.95 292.52 56.47
15 CLAVOS PARA CALAMINA 1,584.40 136.86 117.49 128.57 422.03 653.33 126.12
16 PERNOS 1/2" X 4" 123.28 10.65 9.14 10.00 32.84 50.84 9.81
17 TUBO FIERRO SOLIDO P/ANCLAJE 320.00 27.64 23.73 25.97 85.24 131.95 25.47
18 ACERO DE REFUERZO FY=4200 GRADO 60 31,725.95 2,740.47 2,352.63 2,574.49 8,450.66 13,082.34 2,525.36
19 ARENA FINA (PUESTO EN OBRA) 10,007.59 864.45 742.11 812.09 2,665.66 4,126.67 796.60
20 ARENA GRUESA (PUESTO EN OBRA) 9,829.02 849.03 728.87 797.60 2,618.10 4,053.04 782.38
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECT : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DEL SECTOR AGUILAYOC DEL DISTRITO DE SANTA ANA, PROVINCIA DE LA
O CONVENCION-CUSCO
UBICACIÓN : DISTRITO: SANTA ANA /PROVINCIA: LA CONVENCION /REGION: CUSCO
LUGAR : AGUILAYOC

ITEM DESCRIPCION PARCIAL MES 01 MES02 MES 03 MES 04 MES 05 MES 06

21 ARENA DE ASENTAR (PUESTO EN OBRA) 3,837.88 331.51 284.60 311.43 1,022.27 1,582.57 305.49
22 PIEDRA MEDIANA (PUESTO EN OBRA) 6,839.84 590.82 507.21 555.04 1,821.89 2,820.44 544.45
23 PIEDRA GRANDE (PUESTO EN OBRA) 12,234.80 1,056.84 907.27 992.83 3,258.91 5,045.07 973.88
24 GRAVA ZARANDEADA 1 1/2" 333.88 28.84 24.76 27.09 88.93 137.68 26.58
25 GRAVA ZARANDEADA 1" - 1/2" 333.88 28.84 24.76 27.09 88.93 137.68 26.58
26 GRAVA ZARANDEADA 1/2" (PUESTO EN OBRA) 12,280.52 1,060.78 910.66 996.54 3,271.09 5,063.93 977.52
27 CONDUCTOR ELECTRICO DE COBRE TW N° 12 184.00 15.89 13.64 14.93 49.01 75.87 14.65
28 PENDOLAS DE 1/4" INCLY. GRAPAS Y ABRAZADERAS 2,160.00 186.58 160.17 175.28 575.35 890.69 171.93
29 TEMPLADORES DE CABLE 180.00 15.55 13.35 14.61 47.95 74.22 14.33
30 INODORO TQUE. BAJO NORMAL COLOR C/A. 18,200.00 1,572.11 1,349.62 1,476.89 4,847.83 7,504.85 1,448.71
31 LAVATORIO 16"x12" DE 1 LLAVE B C/A. 8,400.00 725.59 622.90 681.64 2,237.46 3,463.78 668.63
32 URINARIO PICO BLANCO 3,850.00 332.56 285.50 312.42 1,025.50 1,587.56 306.46
33 GRIFO DE BRONCE 1/2" 2,100.00 181.40 155.73 170.41 559.37 865.94 167.16
34 DUCHA CON BRAZO Y CABEZA 1,960.00 169.30 145.34 159.05 522.07 808.21 156.01
35 FOCOS 100 W INCLY. CANASTILLA PROTECCION 46.00 3.97 3.41 3.73 12.25 18.97 3.66
36 INTERRUPTOR TERMOMAGNETICO 2x16Ax220V 18.40 1.59 1.36 1.49 4.90 7.59 1.46
37 CAJA DE MADERA (HERRAMIENTAS) 60.00 5.18 4.45 4.87 15.98 24.74 4.78
38 BLOQUE DE CONCRETO HUECO DE 12X20X40 CM 25,166.40 2,173.86 1,866.21 2,042.19 6,703.43 10,377.48 2,003.23
39 CEMENTO PORTLAND TIPO I (42.5KG) 68,842.12 5,946.55 5,104.97 5,586.38 18,337.08 28,387.36 5,479.79
40 BISAGRA 4" 23.00 1.99 1.71 1.87 6.13 9.48 1.83
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECT : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DEL SECTOR AGUILAYOC DEL DISTRITO DE SANTA ANA, PROVINCIA DE LA
O CONVENCION-CUSCO
UBICACIÓN : DISTRITO: SANTA ANA /PROVINCIA: LA CONVENCION /REGION: CUSCO
LUGAR : AGUILAYOC

ITEM DESCRIPCION PARCIAL MES 01 MES02 MES 03 MES 04 MES 05 MES 06

41 TIZA 8.00 0.69 0.59 0.65 2.13 3.30 0.64


42 CINTA TEFLON 316.00 27.30 23.43 25.64 84.17 130.30 25.15
43 PIZARRA ACRILICA 1.20x2.40 210.00 18.14 15.57 17.04 55.94 86.59 16.72
44 VASOS DESCARTABLES 10.00 0.86 0.74 0.81 2.66 4.12 0.80
45 YESO DE 50 Kg 1,070.46 92.47 79.38 86.87 285.13 441.41 85.21
46 IMPERMEABILIZANTE 1,650.04 142.53 122.36 133.90 439.51 680.40 131.34
47 PASTA MURAL 27.78 2.40 2.06 2.25 7.40 11.46 2.21
48 CABLE DE ACERO DE 1/4" TIPO BOA 2,080.20 179.69 154.26 168.80 554.09 857.78 165.58
49 PEGAMENTO PARA PVC 2,853.10 246.45 211.57 231.52 759.96 1,176.49 227.10
50 GLOBOS MEDIANOS 12.00 1.04 0.89 0.97 3.20 4.95 0.96
51 OCRE ROJO 578.76 49.99 42.92 46.97 154.16 238.65 46.07
PASTILLAS DPD
52 12.00 1.04 0.89 0.97 3.20 4.95 0.96
PASTILLAS DPD
53 PAPEL KRAFF 72.00 6.22 5.34 5.84 19.18 29.69 5.73
54 PLUMONES GRUESOS 78.00 6.74 5.78 6.33 20.78 32.16 6.21
55 CARTULINA 96.00 8.29 7.12 7.79 25.57 39.59 7.64
56 MANUALES DE PROMOCION PARA LA COMUNIDAD 2.00 0.17 0.15 0.16 0.53 0.82 0.16
57 FIGURAS DE GENERO (X45 UND) 45.00 3.89 3.34 3.65 11.99 18.56 3.58
58 AFICHES (3XFAMILIAS) 300.00 25.91 22.25 24.34 79.91 123.71 23.88
59 COMPARADOR DE CLORO RESIDUAL 21.00 1.81 1.56 1.70 5.59 8.66 1.67
DADOS
60 4.00 0.35 0.30 0.32 1.07 1.65 0.32
DADOS
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECT : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DEL SECTOR AGUILAYOC DEL DISTRITO DE SANTA ANA, PROVINCIA DE LA
O CONVENCION-CUSCO
UBICACIÓN : DISTRITO: SANTA ANA /PROVINCIA: LA CONVENCION /REGION: CUSCO
LUGAR : AGUILAYOC

ITEM DESCRIPCION PARCIAL MES 01 MES02 MES 03 MES 04 MES 05 MES 06

61 LUDO FAMILIAR 250.00 21.59 18.54 20.29 66.59 103.09 19.90


62 ROMPECABEZAS 500.00 43.19 37.08 40.57 133.18 206.18 39.80
63 AFICHES DE AUTOEVALUACION 300.00 25.91 22.25 24.34 79.91 123.71 23.88
64 GUIA METODOLOGICA 5.00 0.43 0.37 0.41 1.33 2.06 0.40
65 MANUAL ROTAFOLIO 50.00 4.32 3.71 4.06 13.32 20.62 3.98
66 BOLSAS DE POLISEDA 600.00 51.83 44.49 48.69 159.82 247.41 47.76
67 FORMATOS E INSTRUMENTOS DEL SID (COPIA Y ANILLADO) 10.00 0.86 0.74 0.81 2.66 4.12 0.80
68 MANUAL DE CAPACITACION N°01 25.00 2.16 1.85 2.03 6.66 10.31 1.99
69 MANUAL DE CAPACITACION N°02 25.00 2.16 1.85 2.03 6.66 10.31 1.99
70 MANUAL DE CAPACITACION N°03 25.00 2.16 1.85 2.03 6.66 10.31 1.99
71 MANUAL DE CAPACITACION N°04 25.00 2.16 1.85 2.03 6.66 10.31 1.99
72 MANUAL DE CAPACITACION N°05 25.00 2.16 1.85 2.03 6.66 10.31 1.99
73 MANUAL DE CAPACITACION N°06 25.00 2.16 1.85 2.03 6.66 10.31 1.99
74 MANUAL DE CAPACITACION N°07 25.00 2.16 1.85 2.03 6.66 10.31 1.99
75 MANUAL DE CAPACITACION N°08 25.00 2.16 1.85 2.03 6.66 10.31 1.99
76 MANUAL DE CAPACITACION N°09 25.00 2.16 1.85 2.03 6.66 10.31 1.99
77 MANUAL DE CAPACITACION N°10 PARTICIPACION CUIDADANA 25.00 2.16 1.85 2.03 6.66 10.31 1.99
78 MANUAL DE CAPACITACION N°11 PROTECCION MICROCUENCA GESTION DE RI 25.00 2.16 1.85 2.03 6.66 10.31 1.99
79 GORROS 300.00 25.91 22.25 24.34 79.91 123.71 23.88
80 POLOS 450.00 38.87 33.37 36.52 119.86 185.56 35.82
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECT : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DEL SECTOR AGUILAYOC DEL DISTRITO DE SANTA ANA, PROVINCIA DE LA
O CONVENCION-CUSCO
UBICACIÓN : DISTRITO: SANTA ANA /PROVINCIA: LA CONVENCION /REGION: CUSCO
LUGAR : AGUILAYOC

ITEM DESCRIPCION PARCIAL MES 01 MES02 MES 03 MES 04 MES 05 MES 06

81 FORMATOS FOTOCOPIADOS 10.00 0.86 0.74 0.81 2.66 4.12 0.80


82 LIJA PARA FIERRO 79.20 6.84 5.87 6.43 21.10 32.66 6.30
RAFIA
83 72.00 6.22 5.34 5.84 19.18 29.69 5.73
RAFIA
84 CAJA DE CONCRETO 0.60X0.40X0.25 2,670.00 230.63 197.99 216.66 711.19 1,100.99 212.53
85 GASOLINA 84 OCTANOS 1,200.98 103.74 89.06 97.46 319.90 495.23 95.60
86 WAYPE 6.00 0.52 0.44 0.49 1.60 2.47 0.48
87 HORMIGON (PUESTO EN OBRA) 37,583.93 3,246.48 2,787.03 3,049.85 10,011.02 15,497.90 2,991.66
88 LIJA PARA CONCRETO 111.05 9.59 8.23 9.01 29.58 45.79 8.84
89 COLA SINTETICA 42.00 3.63 3.11 3.41 11.19 17.32 3.34
90 LIJA PARA MADERA 4.00 0.35 0.30 0.32 1.07 1.65 0.32
91 AGUA 296.91 25.65 22.02 24.09 79.09 122.43 23.63
92 HIPOCLORITO DE CALCIO AL 70% 4,806.96 415.22 356.46 390.07 1,280.40 1,982.17 382.63
93 HIPOCLORITO DE CALCIO AL 30% 80.00 6.91 5.93 6.49 21.31 32.99 6.37
94 TIJERA 35.00 3.02 2.60 2.84 9.32 14.43 2.79
95 CUADERNO DE ALMACEN 30.00 2.59 2.22 2.43 7.99 12.37 2.39
96 CINTA MASKINGTAPE 27.50 2.38 2.04 2.23 7.33 11.34 2.19
97 AGUJA GRANDE 2.00 0.17 0.15 0.16 0.53 0.82 0.16
98 CUTER 7.50 0.65 0.56 0.61 2.00 3.09 0.60
99 TAPA METALICA 0.60X0.60 C/PLNCHA ESTRIADA 6,435.00 555.85 477.19 522.19 1,714.05 2,653.50 512.22
100 TAPA METALICA 0.40X0.40 C/PLNCHA ESTRIADA 1,210.00 104.52 89.73 98.19 322.30 498.95 96.32
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECT : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DEL SECTOR AGUILAYOC DEL DISTRITO DE SANTA ANA, PROVINCIA DE LA
O CONVENCION-CUSCO
UBICACIÓN : DISTRITO: SANTA ANA /PROVINCIA: LA CONVENCION /REGION: CUSCO
LUGAR : AGUILAYOC

ITEM DESCRIPCION PARCIAL MES 01 MES02 MES 03 MES 04 MES 05 MES 06

101 REJILLA DE ALAMBRE GALV. P/TUB. VENTILACION 120.00 10.37 8.90 9.74 31.96 49.48 9.55
102 CARTEL DE OBRA GIGANTOGRAFIA 3.60X2.40 350.00 30.23 25.95 28.40 93.23 144.32 27.86
103 MADERA NACIONAL P/ENCOFRADOS 14,395.38 1,243.47 1,067.49 1,168.15 3,834.42 5,936.00 1,145.86
104 MADERA NACIONAL P/CARPINTERIA 210.00 18.14 15.57 17.04 55.94 86.59 16.72
105 PLANTON DE ARBUSTOS 1,050.00 90.70 77.86 85.21 279.68 432.97 83.58
106 ESTACAS MADERA 2"X2"X3' 1,140.80 98.54 84.60 92.57 303.87 470.41 90.81
107 MADERA PARA BALIZAS 669.56 57.84 49.65 54.33 178.35 276.10 53.30
108 MADERA 2" X 3" X 10' 7,606.48 657.04 564.06 617.25 2,026.09 3,136.57 605.47
109 MADERA 2" X 3" 700.00 60.47 51.91 56.80 186.46 288.65 55.72
110 LISTONES DE 2"X3"X3.0 M 4,508.00 389.40 334.29 365.81 1,200.77 1,858.89 358.83
111 ROLLIZO DE EUCALIPTO DE 5" 108.00 9.33 8.01 8.76 28.77 44.53 8.60
112 ROLLIZO DE EUCALIPTO DE 5"X5m. 846.40 73.11 62.76 68.68 225.45 349.02 67.37
113 TRIPLAY DE 6 MM 38.00 3.28 2.82 3.08 10.12 15.67 3.02
114 ALAMBRE DE PUAS 2,140.80 184.92 158.75 173.72 570.23 882.77 170.41
115 THINER STANDAR 504.20 43.55 37.39 40.91 134.30 207.91 40.13
116 PETROLEO 3,111.58 268.78 230.74 252.50 828.81 1,283.07 247.68
117 PINTURA LATEX 2,437.23 210.53 180.73 197.78 649.19 1,005.00 194.00
118 PINTURA ESMALTE SINTETICO 3,184.20 275.05 236.12 258.39 848.16 1,313.02 253.46
119 PINTURA ANTICORROSIVA 198.00 17.10 14.68 16.07 52.74 81.65 15.76
120 PINTURA IMPRIMANTE 794.05 68.59 58.88 64.44 211.51 327.43 63.21
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECT : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DEL SECTOR AGUILAYOC DEL DISTRITO DE SANTA ANA, PROVINCIA DE LA
O CONVENCION-CUSCO
UBICACIÓN : DISTRITO: SANTA ANA /PROVINCIA: LA CONVENCION /REGION: CUSCO
LUGAR : AGUILAYOC

ITEM DESCRIPCION PARCIAL MES 01 MES02 MES 03 MES 04 MES 05 MES 06

121 PUERTA METALICA P/LETRINA 14,000.00 1,209.31 1,038.17 1,136.07 3,729.10 5,772.96 1,114.39
122 CALAMINA GALVANIZADA DE 1.83m x 0.83m x 0.27mm 48,720.00 4,208.41 3,612.82 3,953.51 12,977.27 20,089.91 3,878.08
123 CALAMINA GALVANIZADA DE 1.83m x 0.83m x 0.20mm 5,182.76 447.68 384.33 420.57 1,380.50 2,137.13 412.54
124 ARMELLA PARA MADERA 29.44 2.54 2.18 2.39 7.84 12.14 2.34
125 TUBO Fo.GALV. DE 3" 96.00 8.29 7.12 7.79 25.57 39.59 7.64
126 TUBERIA F°G° Ø 3/4"x6m. 544.00 46.99 40.34 44.14 144.90 224.32 43.30
127 CODO F° GALV. DE 3" 128.00 11.06 9.49 10.39 34.09 52.78 10.19
128 NIPLE DE F° GALV. DE 1" X 2" 256.00 22.11 18.98 20.77 68.19 105.56 20.38
129 NIPLE DE F° GALV. DE 1 1/2" X 4" 128.00 11.06 9.49 10.39 34.09 52.78 10.19
130 NIPLE DE F° GALV. DE 3" X 4" 128.00 11.06 9.49 10.39 34.09 52.78 10.19
131 CANASTILLA DE SUCCION 3" 112.00 9.67 8.31 9.09 29.83 46.18 8.92
132 UNION UNIVERSAL DE BRONCE 1 1/2" 768.00 66.34 56.95 62.32 204.57 316.69 61.13
133 UNION UNIVERSAL DE BRONCE 3" 944.00 81.54 70.00 76.60 251.45 389.26 75.14
134 UNION UNIVERSAL DE BRONCE 1" 1,536.00 132.68 113.90 124.64 409.14 633.38 122.26
135 UNION UNIVERSAL DE BRONCE 1/2" 6,230.00 538.14 461.98 505.55 1,659.45 2,568.97 495.90
136 SUMIDERO DE BRONCE DE 2" 2,100.00 181.40 155.73 170.41 559.37 865.94 167.16
137 CANASTILLA DE SUCCION 2" 280.00 24.19 20.76 22.72 74.58 115.46 22.29
138 TAPA DE CONCRETO 0.40X0.25M 1,068.00 92.25 79.20 86.67 284.48 440.39 85.01
139 TUB. PVC SAP PRESION C-10 EC DE 1/2" x5m 15,656.30 1,352.38 1,160.99 1,270.47 4,170.28 6,455.95 1,246.23
140 TUB. PVC SAP PRESION C-10 EC 1" x 5m 13,572.25 1,172.36 1,006.45 1,101.36 3,615.16 5,596.58 1,080.34
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECT : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DEL SECTOR AGUILAYOC DEL DISTRITO DE SANTA ANA, PROVINCIA DE LA
O CONVENCION-CUSCO
UBICACIÓN : DISTRITO: SANTA ANA /PROVINCIA: LA CONVENCION /REGION: CUSCO
LUGAR : AGUILAYOC

ITEM DESCRIPCION PARCIAL MES 01 MES02 MES 03 MES 04 MES 05 MES 06

141 TUB. PVC SAP PRESION C-10 EC 1 1/2" x 5m 9,364.58 808.91 694.43 759.91 2,494.39 3,861.53 745.41
142 TUB. PVC SAP PRESION C-10 EC 2" x 5m 2,510.10 216.82 186.14 203.69 668.60 1,035.05 199.80
143 TUB. PVC SAP PRESION C-10 EC 3" x 5m 848.00 73.25 62.88 68.81 225.88 349.68 67.50
144 TUB. PVC SAP PRESION C-10 EC 3/4" x 5m 10,963.56 947.03 813.00 889.67 2,920.30 4,520.87 872.69
145 TUB. PVC SAL P/DESAGUE DE 2" 5,600.00 483.73 415.27 454.43 1,491.64 2,309.19 445.76
146 TUB. PVC SAL P/DESAGUE DE 4" 5,070.00 437.94 375.96 411.42 1,350.47 2,090.64 403.57
147 TEE PVC SAP 1" 48.00 4.15 3.56 3.90 12.79 19.79 3.82
148 TEE PVC SAP 1 1/2" 24.00 2.07 1.78 1.95 6.39 9.90 1.91
149 TEE PVC SAP 2" 90.00 7.77 6.67 7.30 23.97 37.11 7.16
150 TEE PVC SAP 1/2" 210.00 18.14 15.57 17.04 55.94 86.59 16.72
151 TEE PVC SAP 3" 24.00 2.07 1.78 1.95 6.39 9.90 1.91
152 CODO DE 90º PVC P/DESAGUE DE 2" 350.00 30.23 25.95 28.40 93.23 144.32 27.86
153 TRAMPA "P" PVC P/DESAGUE DE 2" 700.00 60.47 51.91 56.80 186.46 288.65 55.72
154 TAPON HEMBRA PVC SAL P/DESAGUE DE 4" 50.00 4.32 3.71 4.06 13.32 20.62 3.98
155 NIPLE PVC 1/2" C/ROSCA 534.00 46.13 39.60 43.33 142.24 220.20 42.51
156 YEE PVC P/DESAGUE C/REDUCC. 4" - 2" 980.00 84.65 72.67 79.52 261.04 404.11 78.01
157 CODO PVC SAP 1/2"X 90° 1,107.00 95.62 82.09 89.83 294.87 456.48 88.12
158 CODO PVC SAP 1/2" X 45º 534.00 46.13 39.60 43.33 142.24 220.20 42.51
159 CODO PVC SAP 2" X 90° 550.00 47.51 40.79 44.63 146.50 226.79 43.78
160 CODO PVC SAP 1/2" X 90° 700.00 60.47 51.91 56.80 186.46 288.65 55.72
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECT : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DEL SECTOR AGUILAYOC DEL DISTRITO DE SANTA ANA, PROVINCIA DE LA
O CONVENCION-CUSCO
UBICACIÓN : DISTRITO: SANTA ANA /PROVINCIA: LA CONVENCION /REGION: CUSCO
LUGAR : AGUILAYOC

ITEM DESCRIPCION PARCIAL MES 01 MES02 MES 03 MES 04 MES 05 MES 06

161 CODO PVC SAP 1" X 90° 201.00 17.36 14.91 16.31 53.54 82.88 16.00
162 CODO PVC SAP 3" X 90° 80.00 6.91 5.93 6.49 21.31 32.99 6.37
163 CONO DE REBOSE PVC DE 3" 490.00 42.33 36.34 39.76 130.52 202.05 39.00
164 CONO DE REBOSE PVC DE 4" 112.00 9.67 8.31 9.09 29.83 46.18 8.92
165 TRANSICION 1 1/2" C/ROSCA EXTERNA Y CAMPANA 80.00 6.91 5.93 6.49 21.31 32.99 6.37
166 TRANSICION 1" C/ROSCA EXTERNA Y CAMPANA 160.00 13.82 11.86 12.98 42.62 65.98 12.74
167 TRANSICION 1/2" C/ROSCA EXTERNA Y CAMPANA 890.00 76.88 66.00 72.22 237.06 367.00 70.84
168 TRANSICION 3" C/ROSCA EXTERNA Y CAMPANA 80.00 6.91 5.93 6.49 21.31 32.99 6.37
169 ABRAZADERA PVC DE 1/2" X 4" 712.00 61.50 52.80 57.78 189.65 293.60 56.67
170 LLAVE DE PASO DE 1/2" 1,260.00 108.84 93.44 102.25 335.62 519.57 100.30
171 VALVULA COMPUERTA DE BRONCE DE 1/2" 1,960.00 169.30 145.34 159.05 522.07 808.21 156.01
172 VALVULA COMPUERTA DE BRONCE DE 1" 608.00 52.52 45.09 49.34 161.95 250.71 48.40
173 VALVULA COMPUERTA DE BRONCE DE 1 1/2" 544.00 46.99 40.34 44.14 144.90 224.32 43.30
174 VALVULA COMPUERTA DE BRONCE DE 3" 760.00 65.65 56.36 61.67 202.44 313.39 60.50
175 VALVULA DE PASO DE BRONCE DE 1/2" 3,382.00 292.14 250.79 274.44 900.84 1,394.58 269.20
175 HERRAMIENTAS MANUALES 14,763.62 1,275.27 1,094.79 1,198.03 3,932.50 6,087.84 1,175.17
176 ZARANDA METALICA e=1" 142.60 12.32 10.57 11.57 37.98 58.80 11.35
177 BOTAS DE JEBE (PUNTA DE ACERO) 2,400.00 207.31 177.97 194.75 639.27 989.65 191.04
178 GUANTES DE CUERO 800.00 69.10 59.32 64.92 213.09 329.88 63.68
179 LINTERNA A PILAS 20.00 1.73 1.48 1.62 5.33 8.25 1.59
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECT : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DEL SECTOR AGUILAYOC DEL DISTRITO DE SANTA ANA, PROVINCIA DE LA
O CONVENCION-CUSCO
UBICACIÓN : DISTRITO: SANTA ANA /PROVINCIA: LA CONVENCION /REGION: CUSCO
LUGAR : AGUILAYOC

ITEM DESCRIPCION PARCIAL MES 01 MES02 MES 03 MES 04 MES 05 MES 06

180 ALARMA AUDIBLE-COMPLETO 40.00 3.46 2.97 3.25 10.65 16.49 3.18
181 BALDE PRUEBA-TAPON -ABRAZ. Y ACCESORIOS 3,924.05 338.96 290.99 318.43 1,045.23 1,618.10 312.35
182 REGLA DE PERFIL METALICO DE 6m 6.14 0.53 0.46 0.50 1.64 2.53 0.49
183 PISON DE CONCRETO MANUAL 472.30 40.80 35.02 38.33 125.80 194.76 37.59
184 CASCO DE SEGURIDAD 1,600.00 138.21 118.65 129.84 426.18 659.77 127.36
185 PROTECTOR DE OIDOS 1,280.00 110.57 94.92 103.87 340.95 527.81 101.89
186 CHALECO REFLECTIVO 2,800.00 241.86 207.63 227.21 745.82 1,154.59 222.88
187 CINTA DE SEGURIDAD 160.00 13.82 11.86 12.98 42.62 65.98 12.74
188 BOTIQUIN DE MADERA-EQUIPADO 800.00 69.10 59.32 64.92 213.09 329.88 63.68
189 EXTINTOR DE FUEGO-MEDIANO 800.00 69.10 59.32 64.92 213.09 329.88 63.68
190 CAMILLA 200.00 17.28 14.83 16.23 53.27 82.47 15.92
191 CILINDRO PARA ARENA 80.00 6.91 5.93 6.49 21.31 32.99 6.37
192 LENTES DE PROTECCION 1,200.00 103.66 88.99 97.38 319.64 494.83 95.52
193 CAMION CISTERNA (AGUA) 2,000 GAL. 4,500.00 388.71 333.70 365.16 1,198.64 1,855.60 358.20
194 CONOS REFLECTIVOS 80.00 6.91 5.93 6.49 21.31 32.99 6.37
195 ANDAMIO METALICO 3,619.90 312.69 268.43 293.75 964.21 1,492.68 288.14
196 COMPRESOR Y PISTOLA AEROGRAFICA 480.00 41.46 35.59 38.95 127.85 197.93 38.21
197 COMPACTADOR VIBR. TIPO PLANCHA 4 HP 36.00 3.11 2.67 2.92 9.59 14.84 2.87
198 VIBRADOR DE CONCRETO 4 HP 2.40" 534.22 46.15 39.61 43.35 142.30 220.29 42.52
199 MOTONIVELADORA DE 125 HP 1,410.00 121.80 104.56 114.42 375.57 581.42 112.24
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECT : AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DEL SECTOR AGUILAYOC DEL DISTRITO DE SANTA ANA, PROVINCIA DE LA
O CONVENCION-CUSCO
UBICACIÓN : DISTRITO: SANTA ANA /PROVINCIA: LA CONVENCION /REGION: CUSCO
LUGAR : AGUILAYOC

ITEM DESCRIPCION PARCIAL MES 01 MES02 MES 03 MES 04 MES 05 MES 06

200 MEZCLADORA CONCRETO TROMPO 8 HP 9 P3 2,718.87 234.85 201.62 220.63 724.21 1,121.14 216.42
201 EQUIPO TOPOGRAFICO 3,710.90 320.55 275.18 301.13 988.45 1,530.21 295.39
202 HONORARIOS DEL PROMOTOR 24,500.00 2,116.30 1,816.79 1,988.12 6,525.93 10,102.68 1,950.18
203 HONORARIOS AL CAPACITADOR TALLER I ESTATUTOS Y REGLAMENTOS 110.00 9.50 8.16 8.93 29.30 45.36 8.76
204 HONORARIOS AL CAPACITADOR TALLER II ADMINISTRACION CONTABILIDAD Y 110.00 9.50 8.16 8.93 29.30 45.36 8.76
205 HONORARIOS AL CAPACITADOR TALLER III PARTES DEL SISTEMA 110.00 9.50 8.16 8.93 29.30 45.36 8.76
206 HONORARIOS AL CAPACITADOR TALLER IV GASFITERIA Y REPARACIONES 110.00 9.50 8.16 8.93 29.30 45.36 8.76
207 HONORARIOS AL CAPACITADOR TALLER V OPERACION Y MANTENIMIENTO 110.00 9.50 8.16 8.93 29.30 45.36 8.76
208 HONORARIOS AL CAPACITADOR TALLER VI CLORACION Y DESINFECCION 110.00 9.50 8.16 8.93 29.30 45.36 8.76
209 HONORARIOS AL CAPACITADOR TALLER VII HABITOS DE HIGIENE Y SID (DESPU 110.00 9.50 8.16 8.93 29.30 45.36 8.76
210 HONORARIOS AL CAPACITADOR TALLER VIII PARTICIPACION CIUDADANA 110.00 9.50 8.16 8.93 29.30 45.36 8.76
211 HONORARIOS AL CAPACITADOR TALLER IX MICROCUENCA Y GESTION DE DES 110.00 9.50 8.16 8.93 29.30 45.36 8.76
212 TRASLADOS 250.00 21.59 18.54 20.29 66.59 103.09 19.90
213 ALIMENTACION 200.00 17.28 14.83 16.23 53.27 82.47 15.92
214 ALOJAMIENTO 200.00 17.28 14.83 16.23 53.27 82.47 15.92
215 FLETE TERRESTRE 25 KM 26,569.46 2,295.06 1,970.25 2,156.05 7,077.16 10,956.04 2,114.91

TOTAL VALORIZADO POR MESES S/. 79,771.01 68,481.56 74,939.45 245,986.11 380,807.29 73,509.57
Informe de compatibilidad para SSBB AGUILAYOC_CRONOGRAMA ADQUISICION DE
INSUMOS.xls
Ejecutar el 24/01/2013 15:02

Las siguientes características de este libro no son compatibles con versiones anteriores de
Excel. Estas características podrían perderse o degradarse si abre el libro con una versión
anterior de Excel o si lo guarda con un formato de archivo anterior.

Pérdida menor de fidelidad Nº de apariciones

Algunas celdas o estilos de este libro contienen un formato no admitido en el formato de 3


archivo seleccionado. Estos formatos se convertirán al formato más cercano disponible.
Versión

Excel 97-2003
Informe de compatibilidad para SSBB AGUILAYOC_CRONOGRAMA ADQUISICION DE
INSUMOS.xls
Ejecutar el 24/01/2013 15:03

Las siguientes características de este libro no son compatibles con versiones anteriores de
Excel. Estas características podrían perderse o degradarse si abre el libro con una versión
anterior de Excel o si lo guarda con un formato de archivo anterior.

Pérdida menor de fidelidad Nº de apariciones

Algunas celdas o estilos de este libro contienen un formato no admitido en el formato de 3


archivo seleccionado. Estos formatos se convertirán al formato más cercano disponible.
Versión

Excel 97-2003
Informe de compatibilidad para SSBB AGUILAYOC_CRONOGRAMA ADQUISICION DE
INSUMOS.xls
Ejecutar el 24/01/2013 15:03

Las siguientes características de este libro no son compatibles con versiones anteriores de
Excel. Estas características podrían perderse o degradarse si abre el libro con una versión
anterior de Excel o si lo guarda con un formato de archivo anterior.

Pérdida menor de fidelidad Nº de apariciones

Algunas celdas o estilos de este libro contienen un formato no admitido en el formato de 3


archivo seleccionado. Estos formatos se convertirán al formato más cercano disponible.
Versión

Excel 97-2003

You might also like