Professional Documents
Culture Documents
Procurement of
INFRASTRUCTURE
PROJECTS
CONSTRUCTION OF DOUBLE TRACK
FROM SUCAT TO ALABANG SECTION
OF THE PHILIPPINE NATIONAL
RAILWAYS [RE-BID]
1
2
TABLE OF CONTENTS
3
Section I. Invitation to Bid
4
Republic of the Philippines
DEPARTMENT OF TRANSPORTATION AND COMMUNICATIONS
The Department of Transportation and Communications (DOTC), through its Bids and Awards
Committee (BAC), invites contractors registered with and classified by the Philippine
Contractors Accreditation Board (PCAB) to join in the procurement of the herein project:
5
One (1)-Motorized Skates Trucks
One (1)-One Bagger Concrete Mixer Two (2)-Rail Mounted Hauling
Equipment
Two (2)-Smooth Drums
Pre-Bidding Conference 24 July 2015, 2:00 PM, at Unit 167, 16th Floor,
The Columbia Tower, Ortigas Ave.,
Mandaluyong City.
Submission and Receipt of Bids The deadline for submission and receipt of bids
is 07 August 2015, 2:00 PM, only at Unit 153,
15th Floor, The Columbia Tower, Ortigas Ave.,
Mandaluyong City.
Prospective bidders must have an experience of having completed at least one (1) contract that
is similar to the contract to be bid, and whose value, adjusted to current prices using NSO
consumer price indices, must be at least fifty percent (50%) of the Approved Budget for the
Contract (ABC) and have key personnel and equipment available for the prosecution of the
contract.
Bidding will be conducted through open competitive bidding procedures using non-
discretionary pass/fail criteria as specified in the Revised Implementing Rules and Regulations
(RIRR) of Republic Act No. 9184 (RA 9184), otherwise known as the “Government
Procurement Reform Act”.
Interested bidders may obtain further information from DOTC and inspect the Bidding
Documents at the address given below from 8:00 AM – 5:00 PM.
The Bid Documents/Forms will be available at Unit 22, The Columbia Tower Bldg., Ortigas
Avenue, Mandaluyong City, upon payment of a non-refundable amount of Fifty Thousand
Pesos (Php 50,000.00) to the DOTC cashier. It may also be downloaded free of charge from the
website of the Philippine Government Electronic Procurement System (PhilGEPS)
(philgeps.gov.ph) and the DOTC website at www.dotc.gov.ph provided that the bidders shall
pay the fee of the Bidding Documents not later than the submission of bids. The pre-bid
conference is open to all interested parties.
All bids must be accompanied by the bid security in any of the acceptable forms and in the
amount stated in the Instructions to Bidders Clause 18.
Bids will be opened in the presence of the bidders‟ representatives who choose to attend at the
address as stated above. Late bids shall not be accepted.
6
The DOTC reserves the right to reject any or all bids, and accept the offer most advantageous
to the Government. The DOTC assumes no responsibility whatsoever to compensate or
indemnify bidders for any expenses incurred in the preparation of the bid.
~~
ATTY.~SEt !.~RPETUOM. LOTILLA
Chairman, Bids and Awards Committee
and Undersecretary for Legal Affairs
n
7
Section II. Instructions to Bidders
8
TABLE OF CONTENTS
A. GENERAL..................................................................................................... 11
1. SCOPE OF BID .....................................................................................................11
2. SOURCE OF FUNDS ...........................................................................................11
3. CORRUPT, FRAUDULENT, COLLUSIVE, AND COERCIVE
PRACTICES ..........................................................................................................11
4. CONFLICT OF INTEREST ................................................................................13
5. ELIGIBLE BIDDERS ..........................................................................................14
6. BIDDER’S RESPONSIBILITIES .......................................................................15
7. ORIGIN OF GOODS AND SERVICES .............................................................17
8. SUBCONTRACTS ................................................................................................17
B. CONTENTS OF BIDDING DOCUMENTS ...................................................... 17
9. PRE-BID CONFERENCE ...................................................................................17
10. CLARIFICATION AND AMENDMENT OF BIDDING
DOCUMENTS .......................................................................................................18
C. PREPARATION OF BIDS .............................................................................. 18
11. LANGUAGE OF BIDS .........................................................................................18
12. DOCUMENTS COMPRISING THE BID: ELIGIBILITY AND
TECHNICAL COMPONENTS ...........................................................................19
13. DOCUMENTS COMPRISING THE BID: FINANCIAL
COMPONENT ......................................................................................................21
14. ALTERNATIVE BIDS .........................................................................................22
15. BID PRICES ..........................................................................................................22
16. BID CURRENCIES ..............................................................................................23
17. BID VALIDITY.....................................................................................................23
18. BID SECURITY ....................................................................................................23
19. FORMAT AND SIGNING OF BIDS ..................................................................25
20. SEALING AND MARKING OF BIDS ...............................................................26
D. SUBMISSION AND OPENING OF BIDS ......................................................... 27
21. DEADLINE FOR SUBMISSION OF BIDS .......................................................27
22. LATE BIDS ...........................................................................................................27
23. MODIFICATION AND WITHDRAWAL OF BIDS ........................................27
24. OPENING AND PRELIMINARY EXAMINATION OF BIDS .......................27
E. EVALUATION AND COMPARISON OF BIDS ............................................... 29
9
25. PROCESS TO BE CONFIDENTIAL .................................................................29
26. CLARIFICATION OF BIDS ...............................................................................29
27. DETAILED EVALUATION AND COMPARISON OF BIDS ........................29
28. POST QUALIFICATION ....................................................................................29
29. RESERVATION CLAUSE ..................................................................................31
F. AWARD OF CONTRACT .............................................................................. 32
30. CONTRACT AWARD .........................................................................................32
31. SIGNING OF THE CONTRACT .......................................................................33
32. PERFORMANCE SECURITY............................................................................34
33. NOTICE TO PROCEED......................................................................................34
10
A. General
1. Scope of Bid
1.1. The Procuring Entity as defined in the BDS, invites bids for the construction
of Works, as described in Section VI. Specifications. The name and
identification number of the Contract is provided in the BDS.
1.2. The successful bidder will be expected to complete the Works by the intended
completion date specified in SCC Clause 0.
2. Source of Funds
The Procuring Entity has a budget or has applied for or received funds from the
Funding Source named in the BDS, and in the amount indicated in the BDS. It
intends to apply part of the funds received for the Project, as defined in the BDS, to
cover eligible payments under the Contract for the Works.
(a) defines, for purposes of this provision, the terms set forth below as
follows:
11
Procuring Entity, designed to establish bid prices at artificial,
non-competitive levels; and
(b) will reject a proposal for award if it determines that the bidder
recommended for award has engaged in corrupt or fraudulent practices
in competing for the Contract; and
(c) will declare a firm ineligible, either indefinitely or for a stated period
of time, to be awarded Contract funded by the Funding Source if it at
any time determines that the firm has engaged in corrupt or fraudulent
practices in competing or, or in executing, a Contract funded by the
Funding Source.
3.2. Further, the Procuring Entity will seek to impose the maximum civil,
administrative, and/or criminal penalties available under the applicable laws
on individuals and organizations deemed to be involved in any of the practices
mentioned in the Instructions to Bidders (ITB) Clause 3.10.
3.3. Furthermore, the Funding Source and the Procuring Entity reserve the right to
inspect and audit records and accounts of a contractor in the bidding for and
performance of a contract themselves or through independent auditors as
reflected in the GCC Clause 0.
12
4. Conflict of Interest
4.1. All bidders found to have conflicting interests shall be disqualified to
participate in the procurement at hand, without prejudice to the imposition of
appropriate administrative, civil, and criminal sanctions. A Bidder may be
considered to have conflicting interests with another Bidder in any of the
events described in paragraphs (a) through (c) and a general conflict of interest
in any of the circumstances set out in paragraphs (d) through (g) below:
(b) A Bidder receives or has received any direct or indirect subsidy from
any other Bidder;
(c) A Bidder has the same legal representative as that of another Bidder
for purposes of this Bid;
(d) A Bidder has a relationship, directly or through third parties, that puts
them in a position to have access to information about or influence on
the bid of another Bidder or influence the decisions of the Procuring
Entity regarding this bidding process. This will include a firm or an
organization who lends, or temporarily seconds, its personnel to firms
or organizations which are engaged in consulting services for the
preparation related to procurement for or implementation of the project
if the personnel would be involved in any capacity on the same project;
(e) A Bidder submits more than one bid in this bidding process. However,
this does not limit the participation of subcontractors in more than one
bid;
4.2. In accordance with Section 47 of the IRR of RA 9184, all Bidding Documents
shall be accompanied by a sworn affidavit of the Bidder that it is not related to
the Head of the Procuring Entity members of the Bids and Awards Committee
(BAC), members of the Technical Working Group (TWG), members of the
BAC Secretariat, the head of the Project Management Office (PMO) or the
end-user unit, and the project consultants, by consanguinity or affinity up to
the third civil degree. On the part of the bidder, this Clause shall apply to the
following persons:
13
(b) If the Bidder is a partnership, to all its officers and members;
(d) If the Bidder is a joint venture (JV), the provisions of items (a), (b), or
(c) of this Clause shall correspondingly apply to each of the members
of the said JV, as may be appropriate.
5. Eligible Bidders
5.1. Unless otherwise indicated in the BDS, the following persons shall be eligible
to participate in this Bidding:
(b) Partnerships duly organized under the laws of the Philippines and of
which at least seventy five percent (75%) of the interest belongs to
citizens of the Philippines;
(c) Corporations duly organized under the laws of the Philippines, and of
which at least seventy five percent (75%) of the outstanding capital
stock belongs to citizens of the Philippines;
(d) Cooperatives duly organized under the laws of the Philippines, and of
which at least seventy five percent (75%) of the interest belongs to
citizens of the Philippines; and
(e) Persons/entities forming themselves into a JV, i.e., a group of two (2)
or more persons/entities that intend to be jointly and severally
responsible or liable for a particular contract: Provided, however, that,
in accordance with Letter of Instructions No. 630, Filipino ownership
or interest of the joint venture concerned shall be at least seventy five
percent (75%): Provided, further, that joint ventures in which Filipino
ownership or interest is less than seventy five percent (75%) may be
eligible where the structures to be built require the application of
techniques and/or technologies which are not adequately possessed by
a person/entity meeting the seventy five percent (75%) Filipino
ownership requirement: Provided, finally, that in the latter case,
Filipino ownership or interest shall not be less than twenty five percent
(25%). For this purpose Filipino ownership or interest shall be based
on the contributions of each of the members of the joint venture as
specified in their JVA.
5.2. The Procuring Entity may also invite foreign bidders when provided for under
any Treaty or International or Executive Agreement as specified in the BDS.
14
5.3. Government Corporate Entities may be eligible to participate only if they can
establish that they (a) are legally and financially autonomous, (b) operate
under commercial law, and (c) are not dependent agencies of the GOP or the
Procuring Entity.
5.4. (a) Unless otherwise provided in the BDS, the Bidder must have completed a
single contract that is similar to this, equivalent to at least fifty percent (50%)
of the ABC adjusted to current prices using the National Statistics Office
consumer price index. However, contractors under Small A and Small B
categories without similar experience on the contract to be bid may be allowed
to bid if the cost of such contract is not more than fifty percent (50%) of the
Allowable Range on Contract Cost of their registration based on the
guidelines as prescribed by the PCAB.
(b) For Foreign-funded Procurement, the Procuring Entity and the foreign
government/foreign or international financing institution may agree on another
track record requirement, as specified in the BDS.
For this purpose, contracts similar to the Project shall be those described in the
BDS, and completed within the period stated in the Invitation to Bid and ITB
Clause 0.
5.5. The Bidder must submit a computation of its Net Financial Contracting
Capacity (NFCC) which must be at least equal to the ABC to be bid,
calculated as follows:
NFCC = [(Current assets minus current liabilities) (K)] minus the value of
all outstanding or uncompleted portions of the projects under ongoing
contracts, including awarded contracts yet to be started coinciding with the
contract for this Project.
Where:
The values of the bidder‟s current assets and liabilities shall be based on the
data submitted to the BIR, through its Electronic Filing and Payment System
(EFPS).
6. Bidder’s Responsibilities
6.1. The Bidder or its duly authorized representative shall submit a sworn
statement in the form prescribed in Section IX. Bidding Forms as required in
ITB Clause 0.
15
(b) Having acknowledged all conditions, local or otherwise, affecting the
implementation of the contract;
(c) Having made an estimate of the facilities available and needed for the
contract to be bid, if any;
(e) Ensuring that it is not “blacklisted” or barred from bidding by the GOP
or any of its agencies, offices, corporations, or LGUs, including
foreign government/foreign or international financing institution whose
blacklisting rules have been recognized by the GPPB;
(g) Authorizing the Head of the Procuring Entity or its duly authorized
representative/s to verify all the documents submitted;
(h) Ensuring that the signatory is the duly authorized representative of the
Bidder, and granted full power and authority to do, execute and
perform any and all acts necessary and/or to represent the Bidder in the
bidding, with the duly notarized Secretary‟s Certificate attesting to
such fact, if the Bidder is a corporation, partnership, cooperative, or
joint venture;
(i) Complying with the disclosure provision under Section 47 of the Act
in relation to other provisions of Republic Act 3019; and
Failure to observe any of the above responsibilities shall be at the risk of the
Bidder concerned.
6.3. The Bidder, by the act of submitting its bid, shall be deemed to have inspected
the site, determined the general characteristics of the contract works and the
conditions for this Project and examine all instructions, forms, terms, and
project requirements in the Bidding Documents.
6.4. It shall be the sole responsibility of the prospective bidder to determine and to
satisfy itself by such means as it considers necessary or desirable as to all
matters pertaining to this Project, including: (a) the location and the nature of
the contract, project, or work; (b) climatic conditions; (c) transportation
facilities; (c) nature and condition of the terrain, geological conditions at the
site communication facilities, requirements, location and availability of
construction aggregates and other materials, labor, water, electric power and
access roads; and (d) other factors that may affect the cost, duration and
execution or implementation of the contract, project, or work.
16
6.5. The Procuring Entity shall not assume any responsibility regarding erroneous
interpretations or conclusions by the prospective or eligible bidder out of the
data furnished by the procuring entity.
6.6. Before submitting their bids, the Bidders are deemed to have become familiar
with all existing laws, decrees, ordinances, acts and regulations of the
Philippines which may affect the contract in any way.
6.7. The Bidder shall bear all costs associated with the preparation and submission
of his bid, and the Procuring Entity will in no case be responsible or liable for
those costs, regardless of the conduct or outcome of the bidding process.
6.8. Bidders should note that the Procuring Entity will only accept bids only from
those that have paid the nonrefundable fee for the Bidding Documents at the
office indicated in the Invitation to Bid.
8. Subcontracts
8.1. Unless otherwise specified in the BDS, the Bidder may subcontract portions of
the Works to an extent as may be approved by the Procuring Entity and stated
in the BDS. However, subcontracting of any portion shall not relieve the
Bidder from any liability or obligation that may arise from the contract for this
Project.
8.2. Subcontractors must submit the documentary requirements under ITB Clause
0 and comply with the eligibility criteria specified in the BDS. In the event
that any subcontractor is found by the Procuring Entity to be ineligible, the
subcontracting of such portion of the Works shall be disallowed.
8.3. The Bidder may identify the subcontractor to whom a portion of the Works
will be subcontracted at any stage of the bidding process or during contract
implementation. If the Bidder opts to disclose the name of the subcontractor
during bid submission, the Bidder shall include the required documents as part
of the technical component of its bid.
(b) The pre-bid conference shall be held at least twelve (12) calendar days
before the deadline for the submission of and receipt of bids. If the Procuring
17
Entity determines that, by reason of the method, nature, or complexity of the
contract to be bid, or when international participation will be more
advantageous to the GOP, a longer period for the preparation of bids is
necessary, the pre-bid conference shall be held at least thirty (30) calendar
days before the deadline for the submission and receipt of bids, as specified in
the BDS.
9.2. Bidders are encouraged to attend the pre-bid conference to ensure that they
fully understand the Procuring Entity‟s requirements. Non-attendance of the
Bidder will in no way prejudice its bid; however, the Bidder is expected to
know the changes and/or amendments to the Bidding Documents as recorded
in the minutes of the pre-bid conference and the Supplemental/Bid Bulletin.
9.3. Any statement made at the pre-bid conference shall not modify the terms of
the bidding documents unless such statement is specifically identified in
writing as an amendment thereto and issued as a Supplemental/Bid Bulletin.
10.3. Any Supplemental/Bid Bulletin issued by the BAC shall also be posted on the
Philippine Government Electronic Procurement System (PhilGEPS) and the
website of the Procuring Entity concerned, if available. Unless, otherwise
provided in the BDS, it shall be the responsibility of all Bidders who secure
the Bidding Documents to inquire and secure Supplemental/Bid Bulletins that
may be issued by the BAC. However, bidders who have submitted bids before
the issuance of the Supplemental/Bid Bulletin must be informed and allowed
to modify or withdraw their bids in accordance with ITB Clause 0.
C. Preparation of Bids
18
12. Documents Comprising the Bid: Eligibility and Technical
Components
12.1. Unless otherwise indicated in the BDS, the first envelope shall contain the
following eligibility and technical documents:
19
(iii.11) value of outstanding works, if applicable;
20
(ii.2) List of contractor‟s personnel (viz, project Manager,
Project Engineers, Materials Engineers, and Foremen),
to be assigned to the contract to be bid, with their
complete qualification and experience data; and
(a) Financial Bid Form in accordance with the form prescribed in Section
IX. Bidding Forms, and
(b) Any other document related to the financial component of the bid as
stated in the BDS.
13.2. (a) Unless indicated in the BDS, all Bids that exceed the ABC shall not be
accepted.
(ii) The procuring entity has procedures in place to ensure that the
ABC is based on recent estimates made by the engineer or the
responsible unit of the procuring entity and that the estimates are
based on adequate detailed engineering (in the case of works) and
reflect the quality, supervision and risk and inflationary factors,
as well as prevailing market prices, associated with the types of
works or goods to be procured.
21
(iv) The procuring entity has established a system to monitor and
report bid prices relative to ABC and engineer‟s/procuring
entity‟s estimate.
14.2. Bidders shall submit offers that comply with the requirements of the Bidding
Documents, including the basic technical design as indicated in the drawings
and specifications. Unless there is a value engineering clause in the BDS,
alternative bids shall not be accepted.
14.3. Each Bidder shall submit only one Bid, either individually or as a partner in a
JV. A Bidder who submits or participates in more than one bid (other than as
a subcontractor if a subcontractor is permitted to participate in more than one
bid) will cause all the proposals with the Bidder‟s participation to be
disqualified. This shall be without prejudice to any applicable criminal, civil
and administrative penalties that may be imposed upon the persons and
entities concerned.
15.2. The Bidder shall fill in rates and prices for all items of the Works described in
the Bill of Quantities. Bids not addressing or providing all of the required
items in the Bidding Documents including, where applicable, bill of quantities,
shall be considered non-responsive and, thus, automatically disqualified. In
this regard, where a required item is provided, but no price is indicated, the
same shall be considered as non-responsive, but specifying a "0" (zero) for the
said item would mean that it is being offered for free to the Government.
15.3. All duties, taxes, and other levies payable by the Contractor under the
Contract, or for any other cause, prior to the deadline for submission of bids,
shall be included in the rates, prices, and total bid price submitted by the
Bidder.
15.4. All bid prices for the given scope of work in the contract as awarded shall be
considered as fixed prices, and therefore not subject to price escalation during
contract implementation, except under extraordinary circumstances as
22
specified in GCC Clause 0.Price escalation may be allowed in extraordinary
circumstances as may be determined by the National Economic and
Development Authority in accordance with the Civil Code of the Philippines,
and upon the recommendation of the Procuring Entity. Furthermore, in cases
where the cost of the awarded contract is affected by any applicable new laws,
ordinances, regulations, or other acts of the GOP, promulgated after the date
16.2. If so allowed in accordance with ITB Clause 0, the Procuring Entity for
purposes of bid evaluation and comparing the bid prices will convert the
amounts in various currencies in which the bid price is expressed to Philippine
Pesos at the exchange rate as published in the BSP reference rate bulletin on
the day of the bid opening.
16.3. Unless otherwise specified in the BDS, payment of the contract price shall be
made in Philippine Pesos.
17.2. In exceptional circumstances, prior to the expiration of the bid validity period,
the Procuring Entity may request Bidders to extend the period of validity of
their bids. The request and the responses shall be made in writing. The bid
security described in ITB Clause 0 should also be extended corresponding
tothe extension of the bid validity period at the least. A Bidder may refuse the
request without forfeiting its bid security, but his bid shall no longer be
considered for further evaluation and award. A Bidder granting the request
shall not be required or permitted to modify its bid.
23
(b) Bank draft/guarantee or irrevocable
letter of credit issued by a Universal or
Commercial Bank: Provided, however,
that it shall be confirmed or
authenticated by a Universal or
Commercial Bank, if issued by a
foreign bank.
(c) Surety bond callable upon demand
issued by a surety or insurance
company duly certified by the Five percent (5%)
Insurance Commission as authorized to
issue such security; and/or
(d) Any combination of the foregoing. Proportionate to share of form
with respect to total amount of
security
For biddings conducted by local government units, the Bidder may also submit
bid securities in the form of cashier‟s/manager‟s check, bank draft/guarantee,
or irrevocable letter of credit from other banks certified by the BSP as
authorized to issue such financial statement.
18.2. The bid security should be valid for the period specified in the BDS. Any bid
not accompanied by an acceptable bid security shall be rejected by the
Procuring Entity as non-responsive.
18.3. No bid securities shall be returned to bidders after the opening of bids and
before contract signing, except to those that failed or declared as post-
disqualified, upon submission of a written waiver of their right to file a motion
for reconsideration and/or protest. Without prejudice on its forfeiture, Bid
Securities shall be returned only after the bidder with the Lowest Calculated
Responsive Bid has signed the contract and furnished the Performance
Security, but in no case later than the expiration of the Bid Security validity
period indicated in ITB Clause 0.
18.4. Upon signing and execution of the contract, pursuant to ITB Clause 0, and the
posting of the performance security, pursuant to ITB Clause 0, the successful
Bidder‟s Bid security will be discharged, but in no case later than the Bid
security validity period as indicated in ITB Clause 0.
(a) if a Bidder:
(i) withdraws its bid during the period of bid validity specified in
ITB Clause 17;
(ii) does not accept the correction of errors pursuant to ITB Clause
0;
24
(iv) submission of eligibility requirements containing false
information or falsified documents;
(vi) allowing the use of one‟s name, or using the name of another
for purposes of public bidding;
(xi) failure of the potential joint venture partners to enter into the
joint venture after the bid is declared successful; or
(xii) all other acts that tend to defeat the purpose of the competitive
bidding, such as habitually withdrawing from bidding,
submitting late Bids or patently insufficient bid, for at least
three (3) times within a year, except for valid reasons.
25
19.2. Forms as mentioned in ITB Clause 0 must be completed without any
alterations to their format, and no substitute form shall be accepted. All blank
spaces shall be filled in with the information requested.
19.3. The Bidder shall prepare an original of the first and second envelopes as
described in ITB Clauses 0 and 0. In addition, the Bidder shall submit copies
of the first and second envelopes. In the event of any discrepancy between the
original and the copies, the original shall prevail.
19.4. The bid, except for unamended printed literature, shall be signed, and each and
every page thereof shall be initialed, by the duly authorized representative/s of
the Bidder.
19.5. Any interlineations, erasures, or overwriting shall be valid only if they are
signed or initialed by the duly authorized representative/s of the Bidder.
20.2. Each copy of the first and second envelopes shall be similarly sealed duly
marking the inner envelopes as “COPY NO. ___ - TECHNICAL
COMPONENT” and “COPY NO. ___ – FINANCIAL COMPONENT” and
the outer envelope as “COPY NO. ___”, respectively. These envelopes
containing the original and the copies shall then be enclosed in one single
envelope.
20.3. The original and the number of copies of the Bid as indicated in the BDS shall
be typed or written in indelible ink and shall be signed by the bidder or its duly
authorized representative/s.
(b) bear the name and address of the Bidder in capital letters;
(d) bear the specific identification of this bidding process indicated in the
Invitation to Bid; and
(e) bear a warning “DO NOT OPEN BEFORE…” the date and time for
the opening of bids, in accordance with ITB Clause 0.
26
20.5. If bids are not sealed and marked as required, the Procuring Entity will assume
no responsibility for the misplacement or premature opening of the bid.
23.2. A Bidder may, through a letter of withdrawal, withdraw its bid after it has
been submitted, for valid and justifiable reason; provided that the letter of
withdrawal is received by the Procuring Entity prior to the deadline prescribed
for submission and receipt of bids.
23.4. No bid may be modified after the deadline for submission of bids. No bid may
be withdrawn in the interval between the deadline for submission of bids and
the expiration of the period of bid validity specified by the Bidder on the
Financial Bid Form. Withdrawal of a bid during this interval shall result in the
forfeiture of the Bidder‟s bid security, pursuant to ITB Clause 0, and the
imposition of administrative, civil, and criminal sanctions as prescribed by RA
9184 and its IRR.
27
prescribed in ITB Clause 0. For this purpose, the BAC shall check the
submitted documents of each bidder against a checklist of required documents
to ascertain if they are all present, using a non-discretionary “pass/fail”
criterion. If a bidder submits the required document, it shall be rated “passed”
for that particular requirement. In this regard, bids that fail to include any
requirement or are incomplete or patently insufficient shall be considered as
“failed”. Otherwise, the BAC shall rate the said first bid envelope as “passed”.
24.3. Letters of withdrawal shall be read out and recorded during bid opening, and
the envelope containing the corresponding withdrawn bid shall be returned to
the Bidder unopened. If the withdrawing Bidder‟s representative is in
attendance, the original bid and all copies thereof shall be returned to the
representative during the bid opening. If the representative is not in
attendance, the Bid shall be returned unopened by registered mail. The Bidder
may withdraw its bid prior to the deadline for the submission and receipt of
bids, provided that the corresponding letter of withdrawal contains a valid
authorization requesting for such withdrawal, subject to appropriate
administrative sanctions.
24.4. If a Bidder has previously secured a certification from the Procuring Entity to
the effect that it has previously submitted the above-enumerated Class “A”
Documents, the said certification may be submitted in lieu of the requirements
enumerated in ITB Clause 0, items (i) to (vi).
24.5. In the case of an eligible foreign Bidder as described in ITB Clause 0, the
Class “A” Documents enumerated in ITB Clause 0may be substituted with the
appropriate equivalent documents, if any, issued by the country of the foreign
Bidder concerned.
24.6. Each partner of a joint venture agreement shall likewise submit the documents
required in ITB Clauses 0 and 0. Submission of documents required under
ITB Clauses 0 to 0by any of the joint venture partners constitutes compliance.
24.7. A Bidder determined as “failed” has three (3) calendar days upon written
notice or, if present at the time of bid opening, upon verbal notification within
which to file a request for reconsideration with the BAC: Provided, however,
that the request for reconsideration shall not be granted if it is established that
the finding of failure is due to the fault of the Bidder concerned: Provided,
further, that the BAC shall decide on the request for reconsideration within
28
seven (7) calendar days from receipt thereof. If a failed Bidder signifies his
intent to file a request for reconsideration, the BAC shall keep the bid
envelopes of the said failed Bidder unopened and/or duly sealed until such
time that the request for reconsideration or protest has been resolved.
25.2. Any effort by a bidder to influence the Procuring Entity in the Procuring
Entity‟s decision in respect of Bid evaluation, Bid comparison or contract
award will result in the rejection of the Bidder‟s Bid.
27.2. In evaluating the Bids to get the Lowest Calculated Bid, the Procuring Entity
shall undertake the following:
(b) The ranking of the total bid prices as so calculated from the lowest to
highest. The bid with the lowest price shall be identified as the Lowest
Calculated Bid.
27.3. The Procuring Entity's BAC shall immediately conduct a detailed evaluation
of all bids rated “passed,” using non-discretionary “pass/fail” criterion. The
BAC shall consider the following in the evaluation of bids:
(a) Completeness of the bid. Unless the ITB specifically allows partial
bids, bids not addressing or providing all of the required items in the
Schedule of Requirements including, where applicable, bill of
quantities, shall be considered non-responsive and, thus, automatically
disqualified. In this regard, where a required item is provided, but no
29
price is indicated, the same shall be considered as non-responsive, but
specifying a "0" (zero) for the said item would mean that it is being
offered for free to the Procuring Entity; and
27.4. Based on the detailed evaluation of bids, those that comply with the above-
mentioned requirements shall be ranked in the ascending order of their total
calculated bid prices, as evaluated and corrected for computational errors,
discounts and other modifications, to identify the Lowest Calculated Bid.
Total calculated bid prices, as evaluated and corrected for computational
errors, discounts and other modifications, which exceed the ABC shall not be
considered, unless otherwise indicated in the BDS.
27.5. The Procuring Entity‟s evaluation of bids shall only be based on the bid price
quoted in the Financial Bid Form
27.6. Bids shall be evaluated on an equal footing to ensure fair competition. For
this purpose, all bidders shall be required to include in their bids the cost of all
taxes, such as, but not limited to, value added tax (VAT), income tax, local
taxes, and other fiscal levies and duties which shall be itemized in the bid form
and reflected in the detailed estimates. Such bids, including said taxes, shall
be the basis for bid evaluation and comparison.
28.2. Within a non-extendible period of three (3) calendar days from receipt by the
Bidder of the notice from the BAC that it submitted the LCB, the Bidder shall
submit the following documentary requirements:
(a) Latest income and business tax return in the form specified in the BDS;
(c) Other appropriate licenses and permits required by law and stated in
the BDS.
Failure of the Bidder declared as LCB to duly submit the requirements under
this Clause or a finding against the veracity of such, shall be ground for
forfeiture of the bid security and disqualification of the Bidder for award.
30
28.3. The determination shall be based upon an examination of the documentary
evidence of the Bidder‟s qualifications submitted pursuant to ITB Clauses
0and 0, as well as other information as the Procuring Entity deems necessary
and appropriate, using a non-discretionary “pass/fail” criterion.
28.4. If the BAC determines that the Bidder with the Lowest Calculated Bid passes
all the criteria for post-qualification, it shall declare the said bid as the Lowest
Calculated Responsive Bid, and recommend to the Head of the Procuring
Entity the award of contract to the said Bidder at its submitted price or its
calculated bid price, whichever is lower, subject to ITB Clause 0.
28.5. A negative determination shall result in rejection of the Bidder‟s Bid, in which
event the Procuring Entity shall proceed to the next Lowest Calculated Bid to
make a similar determination of that Bidder‟s capabilities to perform
satisfactorily. If the second Bidder, however, fails the post qualification, the
procedure for post qualification shall be repeated for the Bidder with the next
Lowest Calculated Bid, and so on until the Lowest Calculated and Responsive
Bid is determined for contract award.
28.6. Within a period not exceeding seven (7) calendar days from the date of receipt
of the recommendation of the BAC, the Head of the Procuring Entity shall
approve or disapprove the said recommendation. In the case of government
owned and government-owned and/or -controlled corporations (GOCCs) and
government financial institutions (GFIs), the period provided herein shall be
fifteen (15) calendar days.
29.2. Based on the following grounds, the Procuring Entity reserves the right to
reject any and all Bids, declare a Failure of Bidding at any time prior to the
contract award, or not to award the contract, without thereby incurring any
liability, and make no assurance that a contract shall be entered into as a result
of the bidding:
31
which restricts, suppresses or nullifies or tends to restrict, suppress or
nullify competition;
(b) if the Procuring Entity‟s BAC is found to have failed in following the
prescribed bidding procedures; or
(c) for any justifiable and reasonable ground where the award of the
contract will not redound to the benefit of the Government as follows:
(iii) If the source of funds for the project has been withheld or
reduced through no fault of the Procuring Entity.
29.3. In addition, the Procuring Entity may likewise declare a failure of bidding
when:
(c) All bids fail to comply with all the bid requirements or fail post-
qualification; or
(d) The bidder with the Lowest Calculated Responsive Bid refuses,
without justifiable cause to accept the award of contract, and no award
is made.
F. Award of Contract
30. Contract Award
30.1. Subject to ITB Clause 0, the Procuring Entity shall award the contract to the
Bidder whose Bid has been determined to be the Lowest Calculated and
Responsive Bid (LCRB).
30.2. Prior to the expiration of the period of Bid validity, the Procuring Entity shall
notify the successful Bidder in writing that its Bid has been accepted, through
a Notice of Award received personally or sent by registered mail or
electronically, receipt of which must be confirmed in writing within two (2)
days by the LCRB and submitted personally or sent by registered mail or
electronically to the Procuring Entity.
30.3. Notwithstanding the issuance of the Notice of Award, award of contract shall
be subject to the following conditions:
32
(a) Submission of the following documents within the prescribed period
from receipt by the Bidder of the notice that it has the Lowest
Calculated and Responsive Bid:
(ii) Valid PCAB license and registration for the type and cost of the
contract to be bid for foreign bidders, within thirty (30)
calendar days, if allowed under a Treaty or International or
Executive Agreement mentioned in ITB Clause 0;
31.2. Within ten (10) calendar days from receipt of the Notice of Award, the
successful Bidder shall post the required performance security, sign and date
the contract and return it to the Procuring Entity.
31.3. The Procuring Entity shall enter into contract with the successful Bidder
within the same ten (10) calendar day period provided that all the documentary
requirements are complied with.
(c) Winning bidder‟s bid, including the Technical and Financial Proposals,
and all other documents/statements submitted;
(g) Other contract documents that may be required by existing laws and/or
specified in the BDS.
33
32. Performance Security
32.1. To guarantee the faithful performance by the winning Bidder of its obligations
under the contract, it shall post a performance security within a maximum
period of ten (10) calendar days from the receipt of the Notice of Award from
the Procuring Entity and in no case later than the signing of the contract.
32.2. The performance security shall be denominated in Philippine Pesos and posted
in favor of the Procuring Entity in an amount equal to the percentage of the
total contract price as stated in the BDS in accordance with the following
schedule:
34
33.2. The contract effectivity date shall be provided in the Notice to Proceed by the
Procuring Entity, which date shall not be later than seven (7) calendar days
from the issuance of the Notice to Proceed.
35
Section III. Bid Data Sheet
36
Bid Data Sheet
ITB Clause
1.1 The PROCURING ENTITY is the Department of Transportation and
Communications (DOTC).
5.4 The Bidder must have completed, within the period specified in the
Invitation to Bid and ITB Clause 12.1(a)(iii), at least one (1) contract that
5.4(a) is similar to this Project, equivalent to at least fifty percent (50%) of the
ABC.
9.1 DOTC will hold a pre-bid conference for this Project on 24 July 2015,
2:00 PM, at the 16th Floor, DOTC Multi-purpose Room, The Columbia
Tower Ortigas Avenue, Mandaluyong City
37
10.3 No further instructions.
No further instructions.
12.1 (a)(i)
For joint venture bidders, a Joint License issued by the PCAB pursuant to
Section 38 of RA4566, and not a PCAB license and registration individually
issued to each joint venture partner must be submitted. Failure of the joint
venture bidder, to submit a Joint License may be a ground for
disqualification despite the submission of the individual licenses of each
joint venture partner.
12.1(b) (ii)(ii.2) List of Contractor‟s Personnel to be assigned to the contract to be bid with
their respective curriculum vitae showing, among others, their educational
attainment, professional qualification and experiences (SF-INFR-48), as
follows:
1. Project Manager
2. Civil Engineer (licensed)
3. Materials Engineer (duly accredited by DPWH)
4. Safety Officer (with certificate of training in occupational safety and
health
Duly signed statement of Availability of Key Personnel and Equipment
(SF-INFR-18)
12.1(b) (ii)(ii.3) List of Contractor‟s Equipment OWNED/LEASED assigned to the
Proposed Contract (SF-INFR-49), as indicated in the Invitation to Bid:
38
One (1)-Generator
One (1)-Hauling dump truck
One (1)-Hauling Truck
One (1)-High Bed Trailer Truck
One (1)-Hydraulic Backhoe, Crawler-Mounted Excavator
One (1)-Job Mixed concrete 4-bagger
One(1)-Mechanized rail weld trimming machine
One (1)-Motorized Skates
One (1)-One Bagger Concrete Mixer
One (1)-Payloader
One (1)-Pnuematice Roller
One (1)-Rail grinding machine
One (1)-Railmounted Cargo Truck
One (1)-Railmounted Truck
One (1)-Tandem Roller
One (1)-Thermit Welding tools & equipment
One (1)-Truck Crane
One (1)-Truck Mounted Crane
One (1)-Truck w/ Mounted Lift
One (1)-Water truck
Two (2)-Dump truck
Two (2)-Rail Mounted Cargo Trucks
Two (2)-Rail Mounted Hauling Equipment
Two (2)-Smooth Drums
13.1 Checklist of Financial Components
13.1(b) The ABC is One Hundred Forty-Four Million Three Hundred Seventy-
Seven Thousand Six Hundred Twenty-Four Pesos and Sixty-Two
Centavos (Php 144,377,624.62). Any bid with a financial component
exceeding this amount shall not be accepted.
14.2 No further instructions.
17.1 Bids will be valid until One Hundred Twenty (120) calendar days from
the date of the opening of bids.
18.1 The bid security shall be in the following amount:
39
percent (2%) of the ABC if bid security is in cash, cashier‟s/manager‟s
check, bank draft/guarantee or irrevocable letter of credit;
18.2 The bid security shall be valid until One Hundred Twenty (120)
calendar days from the date of the opening of bids.
20.3 Each Bidder shall submit One (1) original and Two (2) copies of the first
and second components of its bid.
21 The address for submission of bids is:
24.1 The place of bid opening is DOTC, Unit 167, The Columbia Tower,
Ortigas Avenue, Mandaluyong City.
The date and time of bid opening is 07 August 2015, 2:00 PM.
28.2(a) Only tax returns filed and taxes paid through the BIR Electronic Filing and
Payment System (EFPS) shall be accepted.
NOTE: The latest income and business tax returns are those within the
last six months preceding the date of bid submission.
40
31.4(g) Construction schedule and S-curve, manpower schedule, construction
methods, equipment utilization schedule, construction safety and health
program approved by the Department of Labor and Employment, and
PERT/CPM.
41
Section IV. General Conditions of Contract
42
TABLE OF CONTENTS
1. DEFINITIONS ................................................................................................................45
2. INTERPRETATION ......................................................................................................47
3. GOVERNING LANGUAGE AND LAW .....................................................................47
4. COMMUNICATIONS ...................................................................................................47
5. POSSESSION OF SITE .................................................................................................48
6. THE CONTRACTOR’S OBLIGATIONS ...................................................................48
7. PERFORMANCE SECURITY .....................................................................................48
8. SUBCONTRACTING ....................................................................................................49
9. LIQUIDATED DAMAGES ...........................................................................................49
10. SITE INVESTIGATION REPORTS ............................................................................50
11. THE PROCURING ENTITY, LICENSES AND PERMITS .....................................50
12. CONTRACTOR’S RISK AND WARRANTY SECURITY .......................................50
13. LIABILITY OF THE CONTRACTOR .......................................................................52
14. PROCURING ENTITY’S RISK ...................................................................................52
15. INSURANCE...................................................................................................................53
16. TERMINATION FOR DEFAULT OF CONTRACTOR ...........................................54
17. TERMINATION FOR DEFAULT OF PROCURING ENTITY ...............................55
18. TERMINATION FOR OTHER CAUSES ...................................................................55
19. PROCEDURES FOR TERMINATION OF CONTRACTS ......................................57
20. FORCE MAJEURE, RELEASE FROM PERFORMANCE .....................................59
21. RESOLUTION OF DISPUTES.....................................................................................60
22. SUSPENSION OF LOAN, CREDIT, GRANT, OR APPROPRIATION .................60
23. PROCURING ENTITY’S REPRESENTATIVE’S DECISIONS..............................61
24. APPROVAL OF DRAWINGS AND TEMPORARY WORKS BY THE
PROCURING ENTITY’S REPRESENTATIVE ........................................................61
25. ACCELERATION AND DELAYS ORDERED BY THE PROCURING
ENTITY’S REPRESENTATIVE ..................................................................................61
26. EXTENSION OF THE INTENDED COMPLETION DATE ....................................61
27. RIGHT TO VARY ..........................................................................................................62
28. CONTRACTORS RIGHT TO CLAIM .......................................................................62
29. DAYWORKS ..................................................................................................................62
30. EARLY WARNING .......................................................................................................62
31. PROGRAM OF WORK.................................................................................................63
43
32. MANAGEMENT CONFERENCES .............................................................................63
33. BILL OF QUANTITIES ................................................................................................64
34. INSTRUCTIONS, INSPECTIONS AND AUDITS .....................................................64
35. IDENTIFYING DEFECTS ............................................................................................64
36. COST OF REPAIRS ......................................................................................................65
37. CORRECTION OF DEFECTS .....................................................................................65
38. UNCORRECTED DEFECTS........................................................................................65
39. ADVANCE PAYMENT .................................................................................................65
40. PROGRESS PAYMENTS .............................................................................................66
41. PAYMENT CERTIFICATES .......................................................................................66
42. RETENTION ..................................................................................................................67
43. VARIATION ORDERS .................................................................................................68
44. CONTRACT COMPLETION .......................................................................................69
45. SUSPENSION OF WORK.............................................................................................69
46. PAYMENT ON TERMINATION.................................................................................70
47. EXTENSION OF CONTRACT TIME .........................................................................71
48. PRICE ADJUSTMENT .................................................................................................72
49. COMPLETION...............................................................................................................72
50. TAKING OVER..............................................................................................................72
51. OPERATING AND MAINTENANCE MANUALS....................................................72
44
1. Definitions
For purposes of this Clause, boldface type is used to identify defined terms.
1.1. The Arbiter is the person appointed jointly by the Procuring Entity and the
Contractor to resolve disputes in the first instance, as provided for in GCC
Clause 0.
1.2. Bill of Quantities refers to a list of the specific items of the Work and their
corresponding unit prices, lump sums, and/or provisional sums.
1.3. The Completion Date is the date of completion of the Works as certified by
the Procuring Entity‟s Representative, in accordance with GCC Clause 0.
1.4. The Contract is the contract between the Procuring Entity and the Contractor
to execute, complete, and maintain the Works.
1.5. The Contract Price is the price stated in the Letter of Acceptance and
thereafter to be paid by the Procuring Entity to the Contractor for the
execution of the Works in accordance with this Contract.
1.6. Contract Time Extension is the allowable period for the Contractor to
complete the Works in addition to the original Completion Date stated in this
Contract.
1.7. The Contractor is the juridical entity whose proposal has been accepted by
the Procuring Entity and to whom the Contract to execute the Work was
awarded.
1.8. The Contractor’s Bid is the signed offer or proposal submitted by the
Contractor to the Procuring Entity in response to the Bidding Documents.
1.10. Dayworks are varied work inputs subject to payment on a time basis for the
Contractor‟s employees and Equipment, in addition to payments for associated
Materials and Plant.
1.11. A Defect is any part of the Works not completed in accordance with the
Contract.
1.13. The Defects Liability Period is the one year period between contract
completion and final acceptance within which the Contractor assumes the
responsibility to undertake the repair of any damage to the Works at his own
expense.
1.14. Drawings are graphical presentations of the Works. They include all
supplementary details, shop drawings, calculations, and other information
provided or approved for the execution of this Contract.
45
1.15. Equipment refers to all facilities, supplies, appliances, materials or things
required for the execution and completion of the Work provided by the
Contractor and which shall not form or are not intended to form part of the
Permanent Works.
1.16. The Intended Completion Date refers to the date specified in the SCC when
the Contractor is expected to have completed the Works. The Intended
Completion Date may be revised only by the Procuring Entity‟s
Representative by issuing an extension of time or an acceleration order.
1.17. Materials are all supplies, including consumables, used by the Contractor for
incorporation in the Works.
1.18. The Notice to Proceed is a written notice issued by the Procuring Entity or the
Procuring Entity‟s Representative to the Contractor requiring the latter to
begin the commencement of the work not later than a specified or
determinable date.
1.19. Permanent Works all permanent structures and all other project features and
facilities required to be constructed and completed in accordance with this
Contract which shall be delivered to the Procuring Entity and which shall
remain at the Site after the removal of all Temporary Works.
1.20. Plant refers to the machinery, apparatus, and the like intended to form an
integral part of the Permanent Works.
1.21. The Procuring Entity is the party who employs the Contractor to carry out
the Works stated in the SCC.
1.22. The Procuring Entity’s Representative refers to the Head of the Procuring
Entity or his duly authorized representative, identified in the SCC, who shall
be responsible for supervising the execution of the Works and administering
this Contract.
1.23. The Site is the place provided by the Procuring Entity where the Works shall
be executed and any other place or places which may be designated in the
SCC, or notified to the Contractor by the Procuring Entity‟s Representative as
forming part of the Site.
1.24. Site Investigation Reports are those that were included in the Bidding
Documents and are factual and interpretative reports about the surface and
subsurface conditions at the Site.
1.26. Specifications mean the description of Works to be done and the qualities of
materials to be used, the equipment to be installed and the mode of
construction.
46
1.27. The Start Date, as specified in the SCC, is the date when the Contractor is
obliged to commence execution of the Works. It does not necessarily coincide
with any of the Site Possession Dates.
1.29. Temporary Works are works designed, constructed, installed, and removed
by the Contractor that are needed for construction or installation of the
Permanent Works.
2. Interpretation
2.1. In interpreting the Conditions of Contract, singular also means plural, male
also means female or neuter, and the other way around. Headings have no
significance. Words have their normal meaning under the language of this
Contract unless specifically defined. The Procuring Entity‟s Representative
will provide instructions clarifying queries about the Conditions of Contract.
3.2. This Contract shall be interpreted in accordance with the laws of the Republic
of the Philippines.
4. Communications
Communications between parties that are referred to in the Conditions shall be
effective only when in writing. A notice shall be effective only when it is received by
the concerned party.
47
5. Possession of Site
5.1. On the date specified in the SCC, the Procuring Entity shall grant the
Contractor possession of so much of the Site as may be required to enable it to
proceed with the execution of the Works. If the Contractor suffers delay or
incurs cost from failure on the part of the Procuring Entity to give possession
in accordance with the terms of this clause, the Procuring Entity‟s
Representative shall give the Contractor a Contract Time Extension and certify
such sum as fair to cover the cost incurred, which sum shall be paid by
Procuring Entity.
5.2. If possession of a portion is not given by the date stated in the SCC Clause 0,
the Procuring Entity will be deemed to have delayed the start of the relevant
activities. The resulting adjustments in contact time to address such delay
shall be in accordance with GCC Clause 0.
5.3. The Contractor shall bear all costs and charges for special or temporary right-
of-way required by it in connection with access to the Site. The Contractor
shall also provide at his own cost any additional facilities outside the Site
required by it for purposes of the Works.
5.4. The Contractor shall allow the Procuring Entity‟s Representative and any
person authorized by the Procuring Entity‟s Representative access to the Site
and to any place where work in connection with this Contract is being carried
out or is intended to be carried out.
6.2. The Contractor shall commence execution of the Works on the Start Date and
shall carry out the Works in accordance with the Program of Work submitted
by the Contractor, as updated with the approval of the ProcuringEntity‟s
Representative, and complete them by the Intended Completion Date.
6.3. The Contractor shall be responsible for the safety of all activities on the Site.
6.4. The Contractor shall carry out all instructions of the Procuring Entity‟s
Representative that comply with the applicable laws where the Site is located.
6.5. The Contractor shall employ the key personnel named in the Schedule of Key
Personnel, as referred to in the SCC, to carry out the supervision of the
Works. The Procuring Entity will approve any proposed replacement of key
personnel only if their relevant qualifications and abilities are equal to or
better than those of the personnel listed in the Schedule.
48
Contractor shall ensure that the person leaves the Site within seven (7) days
and has no further connection with the Work in this Contract.
6.7. During Contract implementation, the Contractor and his subcontractors shall
abide at all times by all labor laws, including child labor related enactments,
and other relevant rules.
6.8. The Contractor shall submit to the Procuring Entity for consent the name and
particulars of the person authorized to receive instructions on behalf of the
Contractor.
6.9. The Contractor shall cooperate and share the Site with other contractors,
public authorities, utilities, and the Procuring Entity between the dates given
in the schedule of other contractors particularly when they shall require access
to the Site. The Contractor shall also provide facilities and services for them
during this period. The Procuring Entity may modify the schedule of other
contractors, and shall notify the Contractor of any such modification thereto.
7. Performance Security
7.1. Within ten (10) calendar days from receipt of the Notice of Award from the
Procuring Entity but in no case later than the signing of the contract by both
parties, the Contractor shall furnish the performance security in any the forms
prescribed in ITB Clause 0.
7.2. The performance security posted in favor of the Procuring Entity shall be
forfeited in the event it is established that the Contractor is in default in any of
its obligations under the Contract.
7.3. The performance security shall remain valid until issuance by the Procuring
Entity of the Certificate of Final Acceptance.
7.4. The performance security may be released by the Procuring Entity and
returned to the Contractor after the issuance of the Certificate of Final
Acceptance subject to the following conditions:
(a) There are no pending claims against the Contractor or the surety
company filed by the Procuring Entity;
(b) The Contractor has no pending claims for labor and materials filed
against it; and
7.5. The Contractor shall post an additional performance security following the
amount and form specified in ITB Clause 0 to cover any cumulative increase
49
of more than ten percent (10%) over the original value of the contract as a
result of amendments to order or change orders, extra work orders and
supplemental agreements, as the case may be. The Contractor shall cause the
extension of the validity of the performance security to cover approved
contract time extensions.
7.6. In case of a reduction in the contract value or for partially completed Works
under the contract which are usable and accepted by the Procuring Entity the
use of which, in the judgment of the implementing agency or the Procuring
Entity, will not affect the structural integrity of the entire project, the
Procuring Entity shall allow a proportional reduction in the original
performance security, provided that any such reduction is more than ten
percent (10%) and that the aggregate of such reductions is not more than fifty
percent (50%) of the original performance security.
7.7. Unless otherwise indicated in the SCC, the Contractor, by entering into the
Contract with the Procuring Entity, acknowledges the right of the Procuring
Entity to institute action pursuant to Act 3688 against any subcontractor be
they an individual, firm, partnership, corporation, or association supplying the
Contractor with labor, materials and/or equipment for the performance of this
Contract.
8. Subcontracting
8.1. Unless otherwise indicated in the SCC, the Contractor cannot subcontract
Works more than the percentage specified in ITB Clause 0.
8.2. Subcontracting of any portion of the Works does not relieve the Contractor of
any liability or obligation under this Contract. The Contractor will be
responsible for the acts, defaults, and negligence of any subcontractor, its
agents, servants or workmen as fully as if these were the Contractor‟s own
acts, defaults, or negligence, or those of its agents, servants or workmen.
8.3. Subcontractors disclosed and identified during the bidding may be changed
during the implementation of this Contract, subject to compliance with the
required qualifications and the approval of the Procuring Entity.
9. Liquidated Damages
9.1. The Contractor shall pay liquidated damages to the Procuring Entity for each
day that the Completion Date is later than the Intended Completion Date. The
applicable liquidated damages is at least one-tenth (1/10) of a percent of the
cost of the unperformed portion for every day of delay. The total amount of
liquidated damages shall not exceed ten percent (10%) of the amount of the
contract. The Procuring Entity may deduct liquidated damages from payments
due to the Contractor. Payment of liquidated damages shall not affect the
Contractor. Once the cumulative amount of liquidated damages reaches ten
percent (10%) of the amount of this Contract, the Procuring Entity shall
rescind this Contract, without prejudice to other courses of action and
remedies open to it.
50
9.2. If the Intended Completion Date is extended after liquidated damages have
been paid, the Engineer of the Procuring Entity shall correct any overpayment
of liquidated damages by the Contractor by adjusting the next payment
certificate. The Contractor shall be paid interest on the overpayment,
calculated from the date of payment to the date of repayment, at the rates
specified in GCC Clause 0.
12.2. The defects liability period for infrastructure projects shall be one year from
contract completion up to final acceptance by the Procuring Entity. During
this period, the Contractor shall undertake the repair works, at his own
expense, of any damage to the Works on account of the use of materials of
inferior quality within ninety (90) days from the time the Head of the
Procuring Entity has issued an order to undertake repair. In case of failure or
refusal to comply with this mandate, the Procuring Entity shall undertake such
repair works and shall be entitled to full reimbursement of expenses incurred
therein upon demand.
12.3. Unless otherwise indicated in the SCC, in case the Contractor fails to comply
with the preceding paragraph, the Procuring Entity shall forfeit its
performance security, subject its property (ies) to attachment or garnishment
proceedings, and perpetually disqualify it from participating in any public
bidding. All payables of the GOP in his favor shall be offset to recover the
costs.
12.4. After final acceptance of the Works by the Procuring Entity, the Contractor
shall be held responsible for “Structural Defects”, i.e., major
faults/flaws/deficiencies in one or more key structural elements of the project
which may lead to structural failure of the completed elements or structure, or
“Structural Failures”, i.e., where one or more key structural elements in an
infrastructure facility fails or collapses, thereby rendering the facility or part
51
thereof incapable of withstanding the design loads, and/or endangering the
safety of the users or the general public:
(d) Third Parties - Third Parties shall be held liable in cases where
Structural Defects/Failures are caused by work undertaken by them
such as leaking pipes, diggings or excavations, underground cables and
electrical wires, underground tunnel, mining shaft and the like, in
which case the applicable warranty to such structure should be levied
to third parties for their construction or restoration works.
12.6. The Contractor shall be required to put up a warranty security in the form of
cash, bank guarantee, letter of credit, GSIS or surety bond callable on demand,
in accordance with the following schedule:
Minimum Amount in
Form of Warranty Percentage (%) of Total
Contract Price
(a) Cash or letter of credit issued by Universal
or Commercial bank: provided, however,
that the letter of credit shall be confirmed
Five Percent (5%)
or authenticated by a Universal or
Commercial bank, if issued by a foreign
bank
52
(b) Bank guarantee confirmed by Universal or
Commercial bank: provided, however, that
the letter of credit shall be confirmed or
Ten Percent (10%)
authenticated by a Universal or
Commercial bank, if issued by a foreign
bank
(c) Surety bond callable upon demand issued
by GSIS or any surety or insurance
Thirty Percent (30%)
company duly certified by the Insurance
Commission
12.7. The warranty security shall be stated in Philippine Pesos and shall remain
effective for one year from the date of issuance of the Certificate of Final
Acceptance by the Procuring Entity, and returned only after the lapse of said
one year period.
(b) The risk of damage to the Works, Plant, Materials, and Equipment to
the extent that it is due to a fault of the Procuring Entity or in the
Procuring Entity‟s design, or due to war or radioactive contamination
directly affecting the country where the Works are to be executed.
53
15. Insurance
15.1. The Contractor shall, under his name and at his own expense, obtain and
maintain, for the duration of this Contract, the following insurance coverage:
15.3. The Contractor shall notify the insurers of changes in the nature, extent, or
program for the execution of the Works and ensure the adequacy of the
insurances at all times in accordance with the terms of this Contract and shall
produce to the Procuring Entity‟s Representative the insurance policies in
force including the receipts for payment of the current premiums.
The above insurance policies shall be obtained from any reputable insurance
company approved by the Procuring Entity‟s Representative.
15.4. If the Contractor fails to obtain and keep in force the insurances referred to
herein or any other insurance which he may be required to obtain under the
terms of this Contract, the Procuring Entity may obtain and keep in force any
such insurances and pay such premiums as may be necessary for the purpose.
From time to time, the Procuring Entity may deduct the amount it shall pay for
said premiums including twenty five percent (25%) therein from any monies
due, or which may become due, to the Contractor, without prejudice to the
Procuring Entity exercising its right to impose other sanctions against the
Contractor pursuant to the provisions of this Contract.
15.5. In the event the Contractor fails to observe the above safeguards, the
Procuring Entity may, at the Contractor‟s expense, take whatever measure is
deemed necessary for its protection and that of the Contractor‟s personnel and
third parties, and/or order the interruption of dangerous Works. In addition,
the Procuring Entity may refuse to make the payments under GCC Clause 0
until the Contractor complies with this Clause.
15.6. The Contractor shall immediately replace the insurance policy obtained as
required in this Contract, without need of the Procuring Entity‟s demand, with
54
a new policy issued by a new insurance company acceptable to the Procuring
Entity for any of the following grounds:
(v) Where reasonable grounds exist that the insurer may not be
able, fully and promptly, to fulfill its obligation under the
insurance policy.
16.2. Due to the Contractor‟s fault and while the project is on-going, it has incurred
negative slippage of fifteen percent (15%) or more in accordance with
Presidential Decree 1870, regardless of whether or not previous warnings and
notices have been issued for the Contractor to improve his performance;
16.3. Due to its own fault and after this Contract time has expired, the Contractor
incurs delay in the completion of the Work after this Contract has expired; or
(a) abandons the contract Works, refuses or fails to comply with a valid
instruction of the Procuring Entity or fails to proceed expeditiously and
without delay despite a written notice by the Procuring Entity;
(b) does not actually have on the project Site the minimum essential
equipment listed on the Bid necessary to prosecute the Works in
accordance with the approved Program of Work and equipment
deployment schedule as required for the project;
(c) does not execute the Works in accordance with this Contract or
persistently or flagrantly neglects to carry out its obligations under this
Contract;
55
(e) sub-lets any part of this Contract without approval by the Procuring
Entity.
16.5. All materials on the Site, Plant, Equipment, and Works shall be deemed to be
the property of the Procuring Entity if this Contract is rescinded because of the
Contractor‟s default.
(a) Failure of the Procuring Entity to deliver, within a reasonable time, supplies,
materials, right-of-way, or other items it is obligated to furnish under the terms
of this Contract; or
(b) The prosecution of the Work is disrupted by the adverse peace and order
situation, as certified by the Armed Forces of the Philippines Provincial
Commander and approved by the Secretary of National Defense.
18.2. The Procuring Entity or the Contractor may terminate this Contract if the other
party causes a fundamental breach of this Contract.
18.3. Fundamental breaches of Contract shall include, but shall not be limited to, the
following:
(a) The Contractor stops work for twenty eight (28) days when no
stoppage of work is shown on the current Program of Work and the
stoppage has not been authorized by the Procuring Entity‟s
Representative;
(c) The Procuring Entity shall terminate this Contract if the Contractor is
declared bankrupt or insolvent as determined with finality by a court of
competent jurisdiction. In this event, termination will be without
compensation to the Contractor, provided that such termination will
not prejudice or affect any right of action or remedy which has accrued
56
or will accrue thereafter to the Procuring Entity and/or the Contractor.
In the case of the Contractor's insolvency, any Contractor's Equipment
which the Procuring Entity instructs in the notice is to be used until the
completion of the Works;
(g) The Contractor has delayed the completion of the Works by the
number of days for which the maximum amount of liquidated damages
can be paid, as defined in the GCC Clause 0; and
(h) In case it is determined prima facie by the Procuring Entity that the
Contractor has engaged, before or during the implementation of the
contract, in unlawful deeds and behaviors relative to contract
acquisition and implementation, such as, but not limited to, the
following:
18.4. The Funding Source or the Procuring Entity, as appropriate, will seek to
impose the maximum civil, administrative and/or criminal penalties available
under the applicable law on individuals and organizations deemed to be
involved with corrupt, fraudulent, or coercive practices.
18.5. When persons from either party to this Contract gives notice of a fundamental
breach to the Procuring Entity‟s Representative in order to terminate the
existing contract for a cause other than those listed under GCC Clause 0, the
Procuring Entity‟s Representative shall decide whether the breach is
fundamental or not.
18.6. If this Contract is terminated, the Contractor shall stop work immediately,
make the Site safe and secure, and leave the Site as soon as reasonably
possible.
57
19. Procedures for Termination of Contracts
19.1. The following provisions shall govern the procedures for the termination of
this Contract:
(a) Upon receipt of a written report of acts or causes which may constitute
ground(s) for termination as aforementioned, or upon its own initiative,
the Procuring Entity shall, within a period of seven (7) calendar days,
verify the existence of such ground(s) and cause the execution of a
Verified Report, with all relevant evidence attached;
(i) that this Contract is being terminated for any of the ground(s)
afore-mentioned, and a statement of the acts that constitute the
ground(s) constituting the same;
(c) Within a period of seven (7) calendar days from receipt of the Notice
of Termination, the Contractor shall submit to the Head of the
Procuring Entity a verified position paper stating why the contract
should not be terminated. If the Contractor fails to show cause after
the lapse of the seven (7) day period, either by inaction or by default,
the Head of the Procuring Entity shall issue an order terminating the
contract;
(d) The Procuring Entity may, at anytime before receipt of the Bidder‟s
verified position paper described in item (c) above withdraw the Notice
to Terminate if it is determined that certain items or works subject of
the notice had been completed, delivered, or performed before the
Contractor‟s receipt of the notice;
(e) Within a non-extendible period of ten (10) calendar days from receipt
of the verified position paper, the Head of the Procuring Entity shall
decide whether or not to terminate this Contract. It shall serve a
written notice to the Contractor of its decision and, unless otherwise
provided in the said notice, this Contract is deemed terminated from
receipt of the Contractor of the notice of decision. The termination
58
shall only be based on the ground(s) stated in the Notice to Terminate;
and
(f) The Head of the Procuring Entity may create a Contract Termination
Review Committee (CTRC) to assist him in the discharge of this
function. All decisions recommended by the CTRC shall be subject to
the approval of the Head of the Procuring Entity.
19.2. Pursuant to Section 69(f) of RA 9184 and without prejudice to the imposition
of additional administrative sanctions as the internal rules of the agency may
provide and/or further criminal prosecution as provided by applicable laws,
the procuring entity shall impose on contractors after the termination of the
contract the penalty of suspension for one (1) year for the first offense,
suspension for two (2) years for the second offense from participating in the
public bidding process, for violations committed during the contract
implementation stage, which include but not limited to the following:
(b) Failure by the contractor to fully and faithfully comply with its
contractual obligations without valid cause, or failure by the contractor
to comply with any written lawful instruction of the procuring entity or
its representative(s) pursuant to the implementation of the contract.
For the procurement of infrastructure projects or consultancy contracts,
lawful instructions include but are not limited to the following:
59
(d) Poor performance by the contractor or unsatisfactory quality and/or
progress of work arising from his fault or negligence as reflected in the
Constructor's Performance Evaluation System (“CPES”) rating sheet.
In the absence of the CPES rating sheet, the existing performance
monitoring system of the procuring entity shall be applied. Any of the
following acts by the Contractor shall be construed as poor
performance:
(i) Negative slippage of 15% and above within the critical path of
the project due entirely to the fault or negligence of the
contractor; and
20.3. If the event continues for a period of eighty four (84) days, either party may
then give notice of termination, which shall take effect twenty eight (28) days
after the giving of the notice.
20.4. After termination, the Contractor shall be entitled to payment of the unpaid
balance of the value of the Works executed and of the materials and Plant
reasonably delivered to the Site, adjusted by the following:
(a) any sum to which the Contractor is entitled under GCC Clause 0;
60
(b) the cost of his suspension and demobilization;
20.5. The net balance due shall be paid or repaid within a reasonable time period
from the time of the notice of termination.
21.3. Any and all disputes arising from the implementation of this Contract covered
by the R.A. 9184 and its IRR shall be submitted to arbitration in the
Philippines according to the provisions of Republic Act No. 876, otherwise
known as the “ Arbitration Law” and Republic Act 9285, otherwise known as
the “Alternative Dispute Resolution Act of 2004”: Provided, however, That,
disputes that are within the competence of the Construction Industry
Arbitration Commission to resolve shall be referred thereto. The process of
arbitration shall be incorporated as a provision in this Contract that will be
executed pursuant to the provisions of the Act and its IRR: Provided, further,
That, by mutual agreement, the parties may agree in writing to resort to other
alternative modes of dispute resolution.
(a) The Procuring Entity is obligated to notify the Contractor of such suspension
within seven (7) days of having received the suspension notice.
If the Contractor has not received sums due it for work already done within forty five
(45) days from the time the Contractor‟s claim for payment has been certified
by the Procuring Entity‟s Representative, the Contractor may immediately
issue a suspension of work notice in accordance with GCC Clause 0.(b)
61
23.1. Except where otherwise specifically stated, the Procuring Entity‟s
Representative will decide contractual matters between the Procuring Entity
and the Contractor in the role representing the Procuring Entity.
23.2. The Procuring Entity‟s Representative may delegate any of his duties and
responsibilities to other people, except to the Arbiter, after notifying the
Contractor, and may cancel any delegation after notifying the Contractor.
24.3. The Procuring Entity‟s Representative‟s approval shall not alter the
Contractor‟s responsibility for design of the Temporary Works.
24.4. The Contractor shall obtain approval of third parties to the design of the
Temporary Works, when required by the Procuring Entity.
25.2. If the Contractor‟s Financial Proposals for an acceleration are accepted by the
Procuring Entity, they are incorporated in the Contract Price and treated as a
Variation.
26.2. The Procuring Entity‟s Representative shall decide whether and by how much
to extend the Intended Completion Date within twenty one (21) days of the
Contractor asking the Procuring Entity‟s Representative for a decision thereto
after fully submitting all supporting information. If the Contractor has failed
to give early warning of a delay or has failed to cooperate in dealing with a
62
delay, the delay by this failure shall not be considered in assessing the new
Intended Completion Date.
(c) in the absence of appropriate rates, the rates in this Contract shall be
used as the basis for valuation; or failing which
(d) at appropriate new rates, equal to or lower than current industry rates
and to be agreed upon by both parties and approved by the Head of the
Procuring Entity.
29. Dayworks
29.1. Subject to GCC Clause 0 on Variation Order, and if applicable as indicated in
the SCC, the Dayworks rates in the Contractor‟s Bid shall be used for small
additional amounts of work only when the Procuring Entity‟s Representative
has given written instructions in advance for additional work to be paid for in
that way.
29.2. All work to be paid for as Dayworks shall be recorded by the Contractor on
forms approved by the Procuring Entity‟s Representative. Each completed
form shall be verified and signed by the Procuring Entity‟s Representative
within two days of the work being done.
29.3. The Contractor shall be paid for Dayworks subject to obtaining signed
Dayworks forms.
63
future event or circumstance on the Contract Price and Completion Date. The
estimate shall be provided by the Contractor as soon as reasonably possible.
30.2. The Contractor shall cooperate with the Procuring Entity‟s Representative in
making and considering proposals for how the effect of such an event or
circumstance can be avoided or reduced by anyone involved in the work and
in carrying out any resulting instruction of the Procuring Entity‟s
Representative.
31.2. An update of the Program of Work shall the show the actual progress achieved
on each activity and the effect of the progress achieved on the timing of the
remaining work, including any changes to the sequence of the activities.
31.3. The Contractor shall submit to the Procuring Entity‟s Representative for
approval an updated Program of Work at intervals no longer than the period
stated in the SCC. If the Contractor does not submit an updated Program of
Work within this period, the PROCURING ENTITY‟s Representative may
withhold the amount stated in the SCC from the next payment certificate and
continue to withhold this amount until the next payment after the date on
which the overdue Program of Work has been submitted.
31.5. When the Program of Work is updated, the Contractor shall provide the
Procuring Entity‟s Representative with an updated cash flow forecast. The
cash flow forecast shall include different currencies, as defined in the
Contract, converted as necessary using the Contract exchange rates.
31.6. All Variations shall be included in updated Program of Work produced by the
Contractor.
64
the Conference and to the Procuring Entity . The responsibility of the parties
for actions to be taken shall be decided by the PROCURING ENTITY‟s
Representative either at the Management Conference or after the Management
Conference and stated in writing to all who attended the Conference.
33.2. The Bill of Quantities is used to calculate the Contract Price. The Contractor
is paid for the quantity of the work done at the rate in the Bill of Quantities for
each item.
33.3. If the final quantity of any work done differs from the quantity in the Bill of
Quantities for the particular item and is not more than twenty five percent
(25%) of the original quantity, provided the aggregate changes for all items do
not exceed ten percent (10%) of the Contract price, the Procuring Entity‟s
Representative shall make the necessary adjustments to allow for the changes
subject to applicable laws, rules, and regulations.
34.2. If the Procuring Entity‟s Representative instructs the Contractor to carry out a
test not specified in the Specification to check whether any work has a defect
and the test shows that it does, the Contractor shall pay for the test and any
samples. If there is no defect, the test shall be a Compensation Event.
34.3. The Contractor shall permit the Funding Source named in the SCC to inspect
the Contractor‟s accounts and records relating to the performance of the
Contractor and to have them audited by auditors appointed by the Funding
Source, if so required by the Funding Source.
65
Loss or damage to the Works or Materials to be incorporated in the Works between
the Start Date and the end of the Defects Liability Periods shall be remedied by the
Contractor at the Contractor‟s cost if the loss or damage arises from the Contractor‟s
acts or omissions.
37.2. Every time notice of a defect is given, the Contractor shall correct the notified
defect within the length of time specified in the Procuring Entity‟s
Representative‟s notice.
37.3. The Contractor shall correct the defects which he notices himself before the
end of the Defects Liability Period.
37.4. The Procuring Entity shall certify that all defects have been corrected. If the
Procuring Entity considers that correction of a defect is not essential, he can
request the Contractor to submit a quotation for the corresponding reduction in
the Contract Price. If the Procuring Entity accepts the quotation, the
corresponding change in the SCC is a Variation.
38.2. The use of a third party to correct defects that are uncorrected by the
Contractor will in no way relieve the Contractor of its liabilities and warranties
under the Contract.
39.2. The advance payment shall be made only upon the submission to and
acceptance by the Procuring Entity of an irrevocable standby letter of credit of
equivalent value from a commercial bank, a bank guarantee or a surety bond
callable upon demand, issued by a surety or insurance company duly licensed
by the Insurance Commission and confirmed by the Procuring Entity.
66
39.3. The advance payment shall be repaid by the Contractor by an amount equal to
the percentage of the total contract price used for the advance payment.
39.4. The contractor may reduce his standby letter of credit or guarantee instrument
by the amounts refunded by the Monthly Certificates in the advance payment.
39.5. The Procuring Entity will provide an Advance Payment on the Contract Price
as stipulated in the Conditions of Contract, subject to the maximum amount
stated in SCC Clause 0.
40.2. The Procuring Entity shall deduct the following from the certified gross
amounts to be paid to the contractor as progress payment:
(a) Cumulative value of the work previously certified and paid for.
40.3. Payments shall be adjusted by deducting therefrom the amounts for advance
payments and retention. The Procuring Entity shall pay the Contractor the
amounts certified by the Procuring Entity‟s Representative within twenty eight
(28) days from the date each certificate was issued. No payment of interest for
delayed payments and adjustments shall be made by the Procuring Entity.
40.4. The first progress payment may be paid by the Procuring Entity to the
Contractor provided that at least twenty percent (20%) of the work has been
accomplished as certified by the Procuring Entity‟s Representative.
40.5. Items of the Works for which a price of “0” (zero) has been entered will not be
paid for by the Procuring Entity and shall be deemed covered by other rates
and prices in the Contract.
67
41.2. The Procuring Entity‟s Representative shall check the Contractor‟s monthly
statement and certify the amount to be paid to the Contractor.
(b) comprise the value of the quantities of the items in the Bill of
Quantities completed; and
41.4. The Procuring Entity‟s Representative may exclude any item certified in a
previous certificate or reduce the proportion of any item previously certified in
any certificate in the light of later information.
42. Retention
42.1. The Procuring Entity shall retain from each payment due to the Contractor an
amount equal to a percentage thereof using the rate as specified in ITB Sub-
Clause 0.
42.2. Progress payments are subject to retention of ten percent (10%), referred to as
the “retention money.” Such retention shall be based on the total amount due
to the Contractor prior to any deduction and shall be retained from every
progress payment until fifty percent (50%) of the value of Works, as
determined by the Procuring Entity, are completed. If, after fifty percent
(50%) completion, the Work is satisfactorily done and on schedule, no
additional retention shall be made; otherwise, the ten percent (10%) retention
shall again be imposed using the rate specified therefor.
42.3. The total “retention money” shall be due for release upon final acceptance of
the Works. The Contractor may, however, request the substitution of the
retention money for each progress billing with irrevocable standby letters of
credit from a commercial bank, bank guarantees or surety bonds callable on
demand, of amounts equivalent to the retention money substituted for and
acceptable to the Procuring Entity, provided that the project is on schedule and
is satisfactorily undertaken. Otherwise, the ten (10%) percent retention shall
be made. Said irrevocable standby letters of credit, bank guarantees and/or
surety bonds, to be posted in favor of the Government shall be valid for a
duration to be determined by the concerned implementing office/agency or
Procuring Entity and will answer for the purpose for which the ten (10%)
percent retention is intended, i.e., to cover uncorrected discovered defects and
third party liabilities.
42.4. On completion of the whole Works, the Contractor may substitute retention
money with an “on demand” Bank guarantee in a form acceptable to the
Procuring Entity.
68
43.1. Variation Orders may be issued by the Procuring Entity to cover any
increase/decrease in quantities, including the introduction of new work items
that are not included in the original contract or reclassification of work items
that are either due to change of plans, design or alignment to suit actual field
conditions resulting in disparity between the preconstruction plans used for
purposes of bidding and the “as staked plans” or construction drawings
prepared after a joint survey by the Contractor and the Procuring Entity after
award of the contract, provided that the cumulative amount of the Variation
Order does not exceed ten percent (10%) of the original project cost. The
addition/deletion of Works should be within the general scope of the project as
bid and awarded. The scope of works shall not be reduced so as to
accommodate a positive Variation Order. A Variation Order may either be in
the form of a Change Order or Extra Work Order.
43.2. A Change Order may be issued by the Procuring Entity to cover any
increase/decrease in quantities of original Work items in the contract.
43.3. An Extra Work Order may be issued by the Procuring Entity to cover the
introduction of new work necessary for the completion, improvement or
protection of the project which were not included as items of Work in the
original contract, such as, where there are subsurface or latent physical
conditions at the site differing materially from those indicated in the contract,
or where there are duly unknown physical conditions at the site of an unusual
nature differing materially from those ordinarily encountered and generally
recognized as inherent in the Work or character provided for in the contract.
43.4. Any cumulative Variation Order beyond ten percent (10%) shall be subject of
another contract to be bid out if the works are separable from the original
contract. In exceptional cases where it is urgently necessary to complete the
original scope of work, the Head of the Procuring Entity may authorize a
positive Variation Order go beyond ten percent (10%) but not more than
twenty percent (20%) of the original contract price, subject to the guidelines to
be determined by the GPPB: Provided, however, That appropriate sanctions
shall be imposed on the designer, consultant or official responsible for the
original detailed engineering design which failed to consider the Variation
Order beyond ten percent (10%).
43.5. In claiming for any Variation Order, the Contractor shall, within seven (7)
calendar days after such work has been commenced or after the circumstances
leading to such condition(s) leading to the extra cost, and within twenty-eight
(28) calendar days deliver a written communication giving full and detailed
particulars of any extra cost in order that it may be investigated at that time.
Failure to provide either of such notices in the time stipulated shall constitute a
waiver by the contractor for any claim. The preparation and submission of
Variation Orders are as follows:
69
where such works are needed, the date of his inspections and
investigations thereon, and the log book thereof, and a detailed
estimate of the unit cost of such items of work, together with his
justifications for the need of such Change Order or Extra Work Order,
and shall submit the same to the Head of the Procuring Entity for
approval.
(b) The Head of the Procuring Entity or his duly authorized representative,
upon receipt of the proposed Change Order or Extra Work Order shall
immediately instruct the technical staff of the Procuring Entity‟s to
conduct an on-the-spot investigation to verify the need for the Work to
be prosecuted. A report of such verification shall be submitted directly
to the Head of the Procuring Entity or his duly authorized
representative.
(d) If, after review of the plans, quantities and estimated unit cost of the
items of work involved, the proper office of the procuring entity
empowered to review and evaluate Change Orders or Extra Work
Orders recommends approval thereof, Head of the Procuring Entity or
his duly authorized representative, believing the Change Order or Extra
Work Order to be in order, shall approve the same.
(e) The timeframe for the processing of Variation Orders from the
preparation up to the approval by the Head of the Procuring Entity
concerned shall not exceed thirty (30) calendar days.
70
field conditions as found necessary during construction. The Contractor shall
immediately comply with such order to suspend the work wholly or partly.
45.2. The Contractor or its duly authorized representative shall have the right to
suspend work operation on any or all projects/activities along the critical path
of activities after fifteen (15) calendar days from date of receipt of written
notice from the Contractor to the district engineer/regional director/consultant
or equivalent official, as the case may be, due to the following:
(a) There exist right-of-way problems which prohibit the Contractor from
performing work in accordance with the approved construction
schedule.
(e) Delay in the payment of Contractor‟s claim for progress billing beyond
forty-five (45) calendar days from the time the Contractor‟s claim has
been certified to by the procuring entity‟s authorized representative
that the documents are complete unless there are justifiable reasons
thereof which shall be communicated in writing to the Contractor.
45.3. In case of total suspension, or suspension of activities along the critical path,
which is not due to any fault of the Contractor, the elapsed time between the
effective order of suspending operation and the order to resume work shall be
allowed the Contractor by adjusting the contract time accordingly.
46.2. If the Contract is terminated for the Procuring Entity‟s convenience or because
of a fundamental breach of Contract by the Procuring Entity, the Procuring
Entity‟s Representative shall issue a certificate for the value of the work done,
71
Materials ordered, the reasonable cost of removal of Equipment, repatriation
of the Contractor‟s personnel employed solely on the Works, and the
Contractor‟s costs of protecting and securing the Works, and less advance
payments received up to the date of the certificate.
46.3. The net balance due shall be paid or repaid within twenty eight (28) days from
the notice of termination.
46.4. If the Contractor has terminated the Contract under GCC Clauses 0 or 0, the
Procuring Entity shall promptly return the Performance Security to the
Contractor.
47.2. No extension of contract time shall be granted the Contractor due to (a)
ordinary unfavorable weather conditions and (b) inexcusable failure or
negligence of Contractor to provide the required equipment, supplies or
materials.
47.3. Extension of contract time may be granted only when the affected activities
fall within the critical path of the PERT/CPM network.
47.4. No extension of contract time shall be granted when the reason given to
support the request for extension was already considered in the determination
of the original contract time during the conduct of detailed engineering and in
the preparation of the contract documents as agreed upon by the parties before
contract perfection.
72
and epidemics, and for causes such as non-delivery on time of materials,
working drawings, or written information to be furnished by the Procuring
Entity, non-acquisition of permit to enter private properties within the right-of-
way resulting in complete paralyzation of construction activities, and other
meritorious causes as determined by the Procuring Entity‟s Representative and
approved by the Head of the Procuring Entity. Shortage of construction
materials, general labor strikes, and peace and order problems that disrupt
construction operations through no fault of the Contractor may be considered
as additional grounds for extension of contract time provided they are publicly
felt and certified by appropriate government agencies such as DTI, DOLE,
DILG, and DND, among others. The written consent of bondsmen must be
attached to any request of the Contractor for extension of contract time and
submitted to the Procuring Entity for consideration and the validity of the
Performance Security shall be correspondingly extended.
49. Completion
The Contractor shall request the Procuring Entity‟s Representative to issue a
certificate of Completion of the Works, and the Procuring Entity‟s Representative will
do so upon deciding that the work is completed.
51.2. If the Contractor does not supply the Drawings and/or manuals by the dates
stated in the SCC, or they do not receive the Procuring Entity‟s
Representative‟s approval, the Procuring Entity‟s Representative shall
withhold the amount stated in the SCC from payments due to the Contractor.
73
Section V. Special Conditions of Contract
74
Special Conditions of Contract
GCC Clause
0 The Intended Completion Date is 200 Calendar Days (including
unworkable days).
0 The Procuring Entity is Department of Transportation and Communications
(DOTC), The Columbia Tower, Ortigas Avenue, Mandaluyong City
0 The Procuring Entity‟s Representative is the Undersecretary for Project
Implementation or his representative, The Columbia Tower, Ortigas
Avenue, Mandaluyong City
0 The Site is located at along the PNR Railway Line from Sucat to Alabang,
Muntinlupa City and is defined in the drawings.
0 The Start Date is the 7thcalendar day after the date of the receipt of the
Notice to Proceed.
0 The Works consist of Construction of Double Track from Sucat to Alabang
which includes but not limited to the supply of labor, equipment, and
materials in the formation of embankment, laying/installation of Prestressed
Concrete Sleepers and wood joint ties, installation of rails, ballasting works,
bridge works, drainage and slope protection, construction of Level Crossings
with provisions of stop crossing pavement painting, crossing barriers and
cabins, fencing of PNR Right of Way and other works necessary for the
completion of the project .
a. Project Manager
d. Safety Officer
0 No further instructions.
0 No further instructions.
0 No further instructions.
75
0 In case of permanent structures, such as buildings of types 4 and 5 as
classified under the National Building Code of the Philippines and other
structures made of steel, iron, or concrete which comply with relevant
structural codes (e.g. DPWH Standard Specifications), such as, but not
limited to steel/concrete bridges, flyovers, aircraft movement area, ports,
dams, tunnels, filtration and treatment plants, sewerage system, power
plants, transmission and communication towers, railway system, and other
similar permanent structures: Fifteen (15) years.
0 The Contractor shall submit the Program of Work to the Procuring Entity‟s
Representative (DOTC Project Manager concerned) within 10 days of
delivery of the Letter of Acceptance.
0 The period between Program of Work updates is 7 to 15 days.
The date of which “as-built” drawings are required is 15 days after project
completion.
0 The amount to be withheld for failing to produce “as built” drawings and/or
operating and maintenance manuals by the date required is 5% of the
contract amount.
76
Section VI. Specifications
77
TABLE OF CONTENTS
I. BACKGROUND ........................................................................................................ 80
II. THE PROJECT ......................................................................................................... 80
PART 1 GENERAL REQUIREMENTS ............................................................................. 83
1.1 GENERAL ...................................................................................................................... 83
1.2 OBLIGATIONS OF THE CONTRACTOR ........................................................................... 86
1.3 SURVEY LAYOUT AND INSTALLATION OF MARKERS, ETC. .......................................... 87
1.4 MATERIALS AND WORKMANSHIP ................................................................................ 88
1.5 PROGRAM OF WORK ..................................................................................................... 90
1.6 TEMPORARY WORKS .................................................................................................... 91
1.7 TEST AND INSPECTIONS ............................................................................................... 96
1.8 SUBMITTALS ................................................................................................................. 98
1.9 QUALITY CONTROL REQUIREMENTS.......................................................................... 102
1.10 MOBILIZATION AND DEMOBILIZATION .................................................................. 108
1.11 OPERATIONS AND MAINTENANCE OF OFFICE AND SERVICE VEHICLE .................. 110
78
5.12 TRIAL TRAIN OPERATION ON NEWLY CONSTRUCTED AND REHABILITATED TRACKS
220
5.13 ADJUSTMENT FOLLOWING RELAYING OF PERMANENT WAYS .............................. 221
5.14 MEASUREMENT AND PAYMENT ............................................................................. 222
79
I. BACKGROUND
The Philippine National Railways Metro Manila Commuter Line has an existing line from
Tutuban/Caloocan to Calamba which consist of a double railway track alignment from
Tutuban/Caloocan to Sucat and a single railway track alignment from Sucat to Calamba. At
present PNR is operating its commuter trains here from Tutuban to Calamba City.
In view of the demands for a cheap, safe, fast and reliable mass transport, the Philippine
National Railways is embarking on a project named Double Tracking of Sucat to Alabang
section. The project will redound to the reduction of travel time and increase train operation‟s
capacity.
2. Drainage and Slope Protections – Supply and install concrete lined ditch, U-type ditch
and catch basin on locations to be designated by the Engineer.
3. Trackworks – Supply and install track ballast, 20meter-37kg rails including trackbolts
and angle bars, #10 x 37kg Turnouts and switch ties, pre-stressed concrete sleepers
with rail fastening, wood joint ties with trackspikes and thermit weldings and all other
necessary works.
4. Bridge - Design of One (1) Bridge Slab Deck using E35 Cooper Loading at Alabang
including construction of this Superstructure consisting of the supply/delivery of 2
each pre-stressed concrete girders AASHTO Type IVB, L=21.7m., 4000psi
concreting works on slab with reinforcement(Vol=17.95cu.m., RSB 4,343.84kgs.),
bearing pad & accessories (4 ea. elastomeric bearing pads, 200mm x 600mm x
50mm), 0.08 cu.m. Non-shrink mortar, 2.4mts 75mm dia. PVC Pipe, 3.2sq.m.
premolded expansion joint filler, scaffolding and other works and materials to
complete.
5. Fencing – Supply and install solid fence and see thru fence including survey works
and all coordination on the PNR Right of Way on both sides of the tracks (South and
North bound).
80
7. Demolition of Old Alabang Station – Demolition of Old Station, clearing & grubbing,
hauling and disposal of demolished materials, preparation of embankment for
earthworks and trackworks, turn-over of reusable materials to PNR and other works to
complete the project.
8. Construction drawings shall first be prepared by the Contractor and submitted as draft
for review and approval of the Project Engineer and Project Manager. If approved it
will be submitted in a standard size tracing paper for GFC Stamping and signature of
Project Engineer and Project Manager prior to any actual constructions.
9. All measurement for payment shall be referred to in the Bill of Quantities, thus all
other works not specified herein shall be deemed incidental for payment and have
been considered by the contractor in his unit cost estimate for the completion of the
project.
10. Site Investigation information -The Contractor shall be deemed to have acquired and
considered the information critical during the preparation of his bid and have carried
out such further tests as he may consider necessary. No claims for additional payment
will be considered from the Contractor on the grounds that the information acquired
from the Engineer is incorrect or misleading.
11. No work that will in any way adversely affect train operations shall be started until
adequate provision, satisfactory to the Engineer, has been made to allow trains to
operate safely and punctually. No train operations shall be hampered by the
Contractor except by written permission from the Engineer. This condition is further
explained under the General Obligations of the Contractor.
12. The contractor shall ensure that the line is clear from any obstructions that might
cause accidents/derailments. The contractor will be liable for any untoward incidents
that might occur during the project implementation caused by these obstructions
during his daytime and/or nighttime works.
13. As soon as an award has been made for the project, the contractor shall post a
tarpaulin signboard suitably framed for outdoor display at the project location. The
location will be as instructed by the Engineer. The design and format of the tarpaulin
shown below shall have the following specifications: (as per COA Circular No. 2013-
004).
81
PHILIPPINE NATIONAL RAILWAYS
PNR Executive Bldg., Mayhaligue St., Tutuban,Tondo, Manila, Philippines
Project Details :
For particulars or complaints about this project, please contact the Regional Office or Cluster
which has audit jurisdiction on this project:
COA Regional Office No./Cluster ______________________
Address : _________________________________________
Contact No. : __________or Text COA Citizen‟s Desk at 0915-5391957
Note:
1. The above form shall be filled-up by the Contractor in coordination with the PNR‟s
Representative. It shall be maintained as current as possible and updated as instructed by the
Engineer.
2. No additional payment will be measured for this works since the cost related herein
are included in the Contractor‟s detailed estimate for contingencies.
82
PART 1
GENERAL REQUIREMENTS
1.1 GENERAL
The Specifications define the general requirements for the quality and control
of materials and workmanship for the satisfactory completion of the work
herein described in the following Sections.
1.1.5 TESTING
The testing methods and procedures shall be in accordance with ASTM unless
otherwise specified in the particular Section of this Specification or as shown
on the Drawings and as may be directed by the Engineer in writing. When
samples of materials are to be taken for testing, the methods to be utilized are
fully described in the ASTM and shall be followed unless described in this
Specification or referred to in this Specification to other standards or as
directed in writing by the Engineer.
83
Any material which does not conform to the requirements of these
Specifications will be rejected whether in place or not. Such material shall be
removed immediately from the Site at the Contractor‟s expense.
1.1.6 STANDARDS
PS - Philippine Standard
The Contractor shall submit proof that, when a standard other than that
specified is proposed, it is in fact equal to or better than the specified standard.
Such reference shall in every case be considered to be made to the latest
edition of the said references.
1.1.8 ABBREVIATIONS
84
In these Technical Specifications, the following abbreviations are used:
(p) Pascal Pa
1.1.9 DRAWINGS
85
1.2 OBLIGATIONS OF THE CONTRACTOR
The Contractor shall be responsible in undertaking all the tests required by the
Engineer and conduct the testing of materials from a legitimate testing laboratory in
compliance with the requirements of the Contract.
The Contractor shall prepare all requisite working and shop drawings and submit to
the Engineer for approval.
The Contractor shall, without extra payment, re-establish railway facilities, etc.,
where these have been broken up by him during the execution of the Contract. Power
supply cables, telephone cables, water supply pipes, drain pipes, etc., affected during
the works shall be kept in working condition.
The Contractor shall not disrupt nor interfere with the continuous daily train operation
plying the route where the Contractor proposes his construction operation until the
Contractor‟s proposals have been approved by the Engineer. It shall be the
Contractor‟s responsibility to coordinate and obtain from PNR the daily train
operation schedule prior to commencing the works. The Contractor shall also
coordinate with PNR about the unscheduled train movements or change in train
schedule during the works.
No work that will in any way adversely affect train operation shall be started until
adequate provision, satisfactory to the Engineer, has been made to allow trains to
operate safely and punctually.
When the train route under repair/construction is being used by the traveling public,
special attention shall be paid to such conditions that the train can travel in comfort
and safety without undue delay.
The Contractor shall submit his proposed method of construction for approval and
coordinate with the Engineer prior to commencement of the actual construction
operation.
Materials stored along the railway tracks shall be so placed and the work at all time
shall be conducted as to cause as little obstruction to the train operation as possible.
The Contractor shall bear all expenses that will be incurred for the purpose
particularly over the section of railway undergoing improvement/construction and
maintaining such structures and other features as may be necessary without direct
compensation except otherwise provided and accepted by the Engineer.
86
1.3 SURVEY LAYOUT AND INSTALLATION OF MARKERS, ETC.
1.3.1 SCOPE
All survey work specified in this Section shall be carried out by licensed
Surveyors. The Contractor shall submit in advance for the Engineer‟s
approval, true copy of licenses and qualifications of the surveyors to be
employed for the works.
The Contractor shall, when required by the Engineer, carry out the
topographic survey of the job-site by means of traversing, and leveling. The
survey works shall be done in accordance with the site requirements prior to
commencing the works.
The Contractor shall layout the Works and shall be solely responsible for the
accuracy of such laying out. The Contractor shall provide, fix and maintain all
stakes, marks or the like which are necessary for the accurate laying out of the
works, and shall take all necessary precautions to prevent their removal or
disturbance, all as approved by the Engineer
Laying out of Work shall include the verification of position of all markers
and the supply and installation of any and all other markers which the
Contractor may require for the proper execution and completion of the Works,
and shall also include the repositioning of the Employer‟s marker if such
repositioning is deemed necessary by the Contractor and approved by the
Engineer.
Field notes, calculation sheets and all other documents shall be prepared in the
English language and in a manner acceptable to the Engineer. The Contractor
shall submit such notes and other documents on completion of the respective
works or, if so required, during the progress of works for the Engineer‟s
inspection thereof.
Contractor shall determine the sites for soil investigations based on the
Engineer‟s maps, drawings and instructions. The Contractor shall also
establish the levels of the ground and the various levels of investigation to
which he shall be solely responsible for the accuracy of such location and
elevations.
87
1.4 MATERIALS AND WORKMANSHIP
1.4.1 GENERAL
1.4.2 MATERIALS
All materials used in the Works shall be of the best quality of their respective
kinds as specified herein and or described in the Drawings and Bill of
Quantities, obtained from sources and suppliers approved by the Engineer and
shall comply strictly with the current issue of the appropriate standards
published by the American Society for Testing Materials (ASTM), Japanese
Industrial Standard (J.I.S.) or other equivalent national or international
standard approved by the Engineer. Reference to American or Japanese
Standards in the Specifications or Bill of Quantities does not imply any bias in
favor of equipment, fittings, finishing, etc. The Contractor may relate his offer
to other National Standards or Codes of Practice but shall explain the system
used and provide the Engineer with all the necessary information and
comparisons in English showing that his proposed standards are equivalent to
the specified ASTM or JIS Standards. Three copies of such alternative
standards in English are to be supplied by the Contractor to the Engineer when
required. Any material not fully specified herein shall be the best of their kind
and be specifically approved by the Engineer.
Articles or Materials Prepared Off Site. The Contractor shall supply to the
Engineer detailed drawings of pre-constructed units or parts thereof when such
are to be prepared or manufactured at a place not on the Site. The approval of
the Engineer of such drawings shall be obtained in writing by the Contractor
before preparation or manufacture commences.
The contractor shall give to the Engineer a written notice of the articles or
materials to be prepared or manufactured off-site, stating the place and time of
the preparation or manufacture, in sufficient time for the Engineer to make
88
inspection at all stages of the work and not only when any such article or
material is completed.
1.4.4 WORKMANSHIP
89
1.5 PROGRAM OF WORK
1.5.1 DESCRIPTION
The Contractor shall within seven (7)) calendar days from the date of the
Letter of Acceptance, submit to the Employer thru the Engineer a detailed
working program including among others, Gantt Chart/S-Curve and PERT-
CPM schedule. The program shall, in every respect, comply with the
stipulations regarding the sequence of work stated in the Contract Documents.
All works shall be completed within the Contract Period stated in the Contract
and by elaborating the program, due attention shall be made to all measures
which reasonably can be taken in the order to diminish the inconvenience (for
the common railway traffic) and to coordinate, when required, concurrent
labor operation. The work program shall be approved by the Engineer before
the work starts.
90
1.6 TEMPORARY WORKS
The Contractor shall select, arrange for, and if necessary pay for the use of
sites for detours, for all central mixing plants for concrete and for the storage
of equipment, for office buildings, housing, or other uses necessary to the
prosecution of the work:
If any utility for water, electricity, drainage, etc., passing through the site will
be affected by the Works, the contractor shall provide a satisfactory alternative
utility in full working order to the satisfaction of the owner of the utility and
the Engineer, before the cutting of the existing utility.
Temporary Works shall be adequate for intended uses and for all loads
imposed without excessive settlement, deflection or deformation. All parts
and members shall be properly supported, wedged, braced and secured to
prevent displacement or failure.
Temporary and permanent utilities used for construction shall be adequate for
intended uses and not to be overloaded or otherwise used or arranged in any
manner which will endanger persons, properties and premises of the Works.
Connections shall be properly made, lines and wirings securely anchored in
place, and protected against accidents.
1.6.2 RIGHT-OF-WAY
The right-of-way is the strip of land acquired for and devoted to the railway.
The right-of-way widths shown on the drawings are approximate only; the
effective widths will be established by the Engineer.
Water: The Contractor shall provide and maintain the necessary pumps,
valves, motors, storage tanks or reservoir and distribution lines to adequately
supply water for the Project.
91
a) Drinking Water: Provide and maintain canister, coolers or connected
drinking fountains, of sufficient number to reasonable serve the Project.
d) The Contractor shall undertake or arrange for the regular daily clean-
up and removal of trash, waste, construction debris, etc., from the Site and
Temporary Work Yard to disposal areas designated by the Engineer or in
accordance with local Codes and Regulations.
Fire Protection
92
Trenches intersecting thoroughfares shall be provided with bridges or other
crossing with railings, as necessary, suitable for safely carrying the type of
traffic involved.
Open shafts, ramps, platforms and other such conditions shall be protected by
sturdy barricades or railings.
1.6.6 ACCESS
The Contractor shall provide and maintain adequate access to the Project Site
and all areas related to the Works.
(2) Before constructing temporary road works, the Contractor shall make
all necessary arrangements, including payment if required, with the public
authorities or landowners concerned, for the use of the land, and he shall
obtain the approval of the Engineer. Such approval will not, however, relieve
the contractor of his responsibility. Upon completion of the Works, the
contractor shall clean up and restore the land to the satisfaction of the
Engineer or the landowner concerned. If existing roads will be used for access
to the Site, the Contractor shall maintain such road for the duration of its use.
The Contractor shall make all arrangements necessary to permit the passage
along the railway section relating to this Contract of the Constructional Plants,
materials and employees belonging to other Contractors engaged in the
construction of contiguous stretches of railway (if any). For this purpose the
Contractor and the Contractors concerned in the construction of the
stretches contiguous to those through which they pass shall, when necessary
and with at least 15 days notice, request the Engineer for permission to pass
and submit a schedule for passage. After the Engineer has granted such
permission and approved the schedule submitted, both the Contractors
permitting the passage and those requesting it shall undertake to observe the
schedule approved by the Engineer for the passage along the site without any
right to extra payment in consequence of the restrictions on passage or the
necessary temporary suspension of works due to the aforesaid schedule.(3)
93
1.6.7 TEMPORARY TRAFFIC RAMPS
(c) In addition to the requirements of (1) and (2) above, the Contractor
shall furnish and erect, within or in the vicinity of the project area, such
warning and guide signs as may be ordered by the Engineer.
2) The Contractor shall assume all cost of constructing any and all
temporary bridges and accessory features, and the removal of the same after
the completion of the project.
94
The Contractor is responsible for carrying out any necessary investigations
and the obtaining of approvals, licenses, escorts and any other necessary
facilities in order to enable extraordinary traffic to be moved on the roads in
the project area. Any expenses arising out of this requirement shall be deemed
to have been included in other item of works.
The Contractor shall keep the existing road open to traffic during the
performance of the works, provided that when approved by the Engineer the
Contractor may bypass traffic over a detour.
The contractor shall take necessary care at all times during the execution of
the works to ensure the existing convenience and safety of residents along and
adjacent to the road, and any public highway that may be affected by the
Works. Any failure of the Contractor to meet this requirement will entitle the
Engineer to carry out such work as he deems to be necessary and to charge the
Contractor with the full cost thereof plus ten percent of such cost, which sum
will be deducted from any money due or which may become due to the
Contractor under the Contract. The Engineer shall indicate the number and
type of road crossings involve in this Project.
1.6.12 PARKING
The parking space if any for use of vehicles for the project shall be maintained
by the Contractor.
1.6.13 PROTECTION
95
1.7 TEST AND INSPECTIONS
1.7.1 GENERAL
This Section sets forth general provisions regarding tests and inspections
required under this Contract.
The Contractor shall provide all the necessary testing of materials from
legitimate testing laboratory as approved by the Engineer and where
laboratory tests specified under various sections of the Specifications shall be
carried out, all at the Contractor‟s expense.
1.7.3 TESTS
The Contractor shall carry out all tests required under the various Sections of
the Specifications in the presence and under the supervision of the Engineer.
All tests shall generally be carried out in accordance with the requirements and
procedures of the referred standards for the Engineer‟s approval.
2) Where the tests are specified to be carried out in a manner directed by the
Engineer, the requirements of the above mentioned standards for similar tests
shall be taken into account for estimation purpose and the tests shall be
considered also as specified.
Unless otherwise expressly stated, all tests and the works in connection
therewith shall be considered as incidental to the Permanent Works which
require such tests and all costs thereof shall be deemed to be included in and
covered by Pay Items as shown in the Bill of Quantities.
1) All such examinations and tests shall be carried out by the Contractor at his
cost in the presence of the Engineer in accordance with the normal practice in
respect of such examinations and tests if the same may be carried out by the
Contractor with his staff and equipment available at the Site.
96
The Engineer shall be at liberty to reject any materials which do not comply
with the requirements of the Contract notwithstanding any previous approval
thereof.
The Contractor shall not be entitled to any extra payments or extension of time
for completion of the Works on account of the rejection of materials due to
their non-compliance with the requirements of the Contract or of the waiting
time reasonably required for carrying out the examinations and tests.
The Contractor shall furnish test samples as instructed and shall provide
reasonable assistance and cooperation as necessary to permit tests to be
performed on materials or work in place including reasonable stoppage of
Work during testing.
Unless otherwise expressly stated, all tests and the works in connection
therewith shall be considered as incidental to the Permanent Works which
required such tests and all costs thereof shall be deemed to be included in and
covered by the Pay Items as shown in the Bill of Quantities.
97
1.8 SUBMITTALS
1.8.1 GENERAL
This Section sets forth general provisions regarding submittals required of the
Contractor.
Schedules, data, field drawings and shop drawings shall be originally prepared
by Contractor, Sub-Contractor, Supplier or Distributor which shall illustrate
appropriate portions of work. The work items shall be described in relation to
responsibility, fabrication, layout, setting or erection details as specified in
appropriate Sections.
98
Construct field samples or mock-ups at locations acceptable to Engineer.
Verify:
1) Field Measurements
2) Field Construction Criteria
3) Catalogue Numbers and Similar Data
Coordinate each submittal with the Project requirements and Contract
Documents.
The Contractor shall submit one (1) reproducible transparency and one opaque
print of schedules, survey data and shop drawings, and number of copies of
project data which Contractor requires for distribution plus four (4) copies
which will be retained by Engineer.
1) Date
2) Project title and number
3) Contractor‟s name and address
4) Number of each shop drawing, product data and sample
5) Other pertinent data
Submittals shall include:
1) Data and revision dates
2) Project title and number
99
3) Name of - Contractor
- Sub-Contractor
- Supplier
- Manufacturer
- Separate retailer when pertinent
4) Identification of product or material
5) Relation to adjacent structure or material
6) Field dimensions, clearly identified as such
7) Specifications Section Number
8) Applicable standards, such as ASTM, JIS numbers
9) Contractor‟s stamp, initialed or signed, certifying review of submittal,
verification of field measurements and compliance with Contract Documents
Distribute copies of shop drawings and product data which carry Engineer‟s
stamp, to:
1) Job-site file
2) Record documents file
3) Sub-Contractors
4) Suppliers
5) Fabricators
As appropriate in each case.
Provide record progress photographs taken at a fixed point and angle as when
and where directed by the Engineer as intervals of not more than twenty eight
(28) calendar days.
The photographs shall be sufficient in number and location to record the exact
progress of works. Provide one (1) proof print of each photograph taken and
the negative and five (5) colored copies, 245 x 203 mm of any of the
photographs selected by the Engineer. Two (2) copies are to be signed by the
Contractor and the Engineer. Albums to accommodate the selected
photographs shall be supplied by Contractor.
The Contractor shall maintain a daily log describing the important events
pertaining to the works, the working hours, the number of laborers employed,
effective operation time of equipment, overtime hours, delays due to
meteorological conditions, the lack of labor, materials or equipment, progress
made and instructions, notifications and recommendations made by the
Engineer.
The Contractor shall furnish to the Engineer ten (10) copies of the monthly
progress reports within seven (7) days after the end of every month, indicating
progress made, construction activities, inventories of material used and stored
on jobsite numbers of labors, equipment available and hours utilized, number
100
of working days, the summary of the daily log of the month and all important
events in relation to the Works.
Within twenty eight (28) calendar days after the issuance of the Taking Over
Certificate, the Contractor shall prepare and submit two (2) sets of As-Built
Drawings and final construction report as draft. And within fourteen (14) days
after the issuance of the last Taking Over Certificate, the Contractor shall
submit five (5) sets of final construction report and final As-Built Drawings.
As built Drawings of the works consist of one (1) set of original size copy, one
(1) set of original size reproducible, two (2) sets of reduced size copy, one (1)
set of reduced size reproducible and one (1) set of electronic file, which shall
be subject to approval of the Engineer.
101
1.9 QUALITY CONTROL REQUIREMENTS
1.9.1 GENERAL
102
c) The Contractor shall maintain a complete file of all submittals which
he has certified and all submittals which have also been approved by the
Engineer. Upon the completion of the work under this Contract, the Contract
shall furnish one complete set of prints of all shop drawings as finally certified
in addition to those furnished in accordance with the Specification
requirements for shop drawings. These drawings shall show changes and
revisions made up to the time the Project is completed and accepted.
e) The Contractor shall perform on the site, and with his own
organization, work equivalent to at least fifty (50) percent of the total amount
of work to be performed under the Contract. If during the progress of the
work hereunder, the Contractor shall request a reduction in such percentage to
the Employer through the Engineer, and the Engineer determines that it would
be to the Employer‟s advantage, the percentage of the work required to be
performed by the Contractor may be reduced, provided, written approval of
such reduction is obtained by the Contractor from the Engineer. If the above
percentage is less than 100%, the successful bidder must furnish to the
engineer within fifteen (15) days after award a description of the items of
work which he will perform with his own forces, the estimated cost of those
items, and the percentage of total work those items represent.
The Employer will furnish to the Contractor some rails available as listed on
the drawings to be incorporated or installed in the work or used in its
performance. Such property will be furnished at the place shown on the
drawings, and the Contractor will be required to accept delivery when made,
paying any demurrage or detention charges incurred, and loading and
transporting the property to the job site at his own expense. All such property
will be installed or incorporated into the work at the expense of the Contractor,
unless otherwise indicated herein. The Contractor shall verify the quantity and
condition of such Government furnished property when delivered to him,
acknowledge receipt thereof in writing to the Engineer, and in case of damage
to or shortage of such property, he shall within 24 hours report in writing such
damage or shortage to the Engineer.
103
1) The Contractor shall establish a quality control system to review all
submittals made to the Engineer in accordance with the above submission
requirements, and to perform sufficient inspection and/or tests of all items of
work, including that of his subcontractors, to ensure conformance to
applicable specifications and drawings with respect to the materials,
workmanship, construction, with emphasis on the surveillance tests and
submittals required in the technical provisions of the contract specification
including in plant inspection. The Contractor‟s quality control system will be
established to include all construction, except where the technical provisions
of the contract provide for specific Government control by inspections, tests,
or other means. The Contractor‟s quality control system will be keyed to the
proposed construction deficiencies. The Employer reserves the right to direct
the location of the required test. Any of the test that, when performed, do not
indicate compliance with contract requirements will be reported but will not
be considered as a test to satisfy the required number of tests.
104
7) The Contractor shall provide and maintain all measuring and testing
devices, laboratory equipment, instruments, transportation, and supplies
necessary to accomplish the required testing and inspection. All measuring
and testing devices shall be calibrated at established intervals against certified
standards which have known valid relationships to national standards. The
Contractor‟s measuring and testing equipment shall be made available for use
by the Engineer for verification of their accuracy and condition as well as for
any inspection or test desired.
b) The Contractor‟s quality control system at the job site shall follow a
three-step procedure.
105
Contractor and approved by the Engineer. Additional check lists and forms for
specific operations may be required to supplement the daily inspection form.
The report shall include all inspections and tests made. It shall provide factual
evidence that the required inspections or tests have been performed, including
type and number of inspections or rejection and the corrective action taken.
The daily report shall cover both conforming and defective items. It shall
include a statement that all materials and equipment incorporated in the work
are in full compliance with the terms of the contract except as noted. The
report will cover all items and specifically include the items listed in the
quality control paragraphs of the technical provisions. The report will be
verified and signed by the prime Contractor‟s designated quality control
representative. The daily reports will be furnished in two copies (Original and
one duplicate) to the Engineer at the job site. The report will be legibly
handwritten in ink or typewritten. Reports shall be submitted not later than the
close of business on the first working day following the date of the report.
Reports shall have all supporting documents (such as concrete placement
checklists, laboratory reports of compaction tests, sieve analysis, etc.)
attached. Incomplete reports will not be accepted. The Contractor is
responsible for insuring that test reports are prepared and attached to the daily
report for the day that the test was performed. Negative reports are required
for days during which there is no activity on the project site to include a brief
statement as to why there was no activity during a normal workday or
schedule.
106
(4) Proposed methods of performing quality control inspections, including
those for his subcontractors‟ work.
(6) Procedures for reviewing all shop drawings, samples, certificates, etc.,
for contract compliance and certifying them.
(8) Each copy of the complete plan will be assembled in a folder in the
order listed above. Four (4) copies will be submitted for approval. Revisions
to the plan will be submitted in four (4) copies.
The requirements under this Section are incidental to other items of work and
will not be measured for payment, unless otherwise specified in the Bill of
Quantities.
107
1.10 MOBILIZATION AND DEMOBILIZATION
1.10.1 SCOPE
This Section refers to the mobilization in preparation for the execution of the
Works, and demobilization after completion of the Works.
1.10.2 MOBILIZATION
c) Unload and install, ready for use, all plant and equipment and whatever
else required for the execution of the Works.
4) Survey layout and installation of fixed points for the setting out of the
works.
1.10.3 DEMOBILIZATION
Transportation of all the above plant, equipment and materials of the site to the
home station or somewhere else outside the Site.2)
108
5) The clean-up of the Site and Work area, and the removal of material,
debris, waste, etc., and making good damage or temporary alterations.
The requirements under this Section are incidental to other items of work and
will not be measured for payment.
109
1.11 OPERATIONS AND MAINTENANCE OF OFFICE AND SERVICE VEHICLE
This covers the provisions office supplies on a day to day operating expenses
of the existing PNR‟s Engineer‟s office at Tutuban Manila such as common
stationeries, printer‟s refillable inks and a monthly (Php1,200.00) prepaid cell
cards for the period of two hundred (200) calendar days.
This covers the provision of service vehicle of at least 2009 model pick-up,
air-con, in good running condition and updated registration on owned / lease
basis including driver and twenty (20) liters of fuel per day for the exclusive
use of the PNR Project Engineer supervising the project for the period of two
hundred (200) calendar days. Maintenance and fuel cost for the service
vehicle shall be included under this item.
110
PART 2
EARTHWORKS
2.1.1 SCOPE
The clearing and grubbing shall consist of clearing of all trees, down timber,
snags, brush, other vegetation, rubbish, and all other objectionable material,
including grubbing stumps, roots, and disposing of all spoil material resulting
from the clearing and grubbing in accordance with these Specifications or as
directed by the Engineer. It shall also include the removal and disposal of
structures that obtrude, encroach upon, or otherwise obstruct the works except
where otherwise provided for in these Specifications or ordered by the
Engineer.
2.1.2CONSTRUCTION REQUIREMENTS
2.1.2.1 General
The Engineer will establish the limits of work and designate all trees,
shrubs, plants and other things to be cleared. The contractor shall
preserve all objects designated to remain.
All surface objects and trees, stumps, roots and other protruding
obstructions, not designated to remain, shall be cleared and/or grubbed,
including mowing as required, except as provided below:
111
If perishable material is burned, it shall be burned under the constant
care of competent watchmen at such times and in such a manner that
the surrounding vegetation, other adjacent property, or anything
designated to remain on the right of way will not be jeopardized. If
permitted, burning shall be done in accordance with applicable laws,
ordinances, and regulations.
In the event that the Contractor is directed by the Engineer not to start
burning operations or to suspend such operations because of hazardous
weather conditions, material to be burned which interferes with
subsequent construction operations shall be moved by the contractor to
temporary locations clear of construction operations and later if
directed by the Engineer, shall be placed on a designated spot and
burned.
All merchantable timber in the clearing area which has not been
removed from the right of way prior to the beginning of
112
construction, shall become the property of the Employer, unless
otherwise provided.
Timber cut inside the area staked for clearing shall be felled within the
area to be cleared.
The area occupied by the existing railway is excluded from the strip
considered, and the clearing and grubbing is limited to the surface area
directed by the Engineer.
In cut areas, all stumps and roots shall be removed to a depth of not
less than 50 cm below the finished subgrade level.
113
This removal of topsoil shall not be paid for separately as it is a
subsidiary obligation of the Contractor in carrying out the clearing and
grubbing operations.
When the topsoil will be used for dressing of the slopes of the
embankment as directed by the Engineer or as indicated on the
drawings, this work will be considered as formation of embankment
and shall conform to the requirement of Section 2.5 of these
Specifications for construction, measurement and payment. In this
case the removal of topsoil will not be measured for direct payment,
but will be considered as a subsidiary obligation of the Contractor
covered by the Scheduled item “Embankment” with material from
Common or Selected Borrow.
114
115
2.2 STRIPPING
2.2.1 SCOPE
The areas from which stripping of topsoil may be required shall be indicated
on the Drawings. The Contractor shall remove topsoil from such portions of
these areas and to such depth as the Engineer may require. No stripping of
topsoil of any designated area shall be less than 150 mm in depth. The topsoil
removed shall be transported, deposited in stock piles at locations approved by
the Engineer, and/or spread and compacted with a light roller where indicated
on the drawings or where directed by the Engineer. The topsoil shall be kept
separate from other excavated materials and shall be completely removed to
the required depth from any designated area prior to the beginning of regular
excavation or embankment work in the area. No payment will be made for
stripping the topsoil carried out in areas other than those ordered.
116
2.3 EXCAVATION
2.3.1 SCOPE
Excavation shall consist of all work necessary for the excavation including
placing or disposal of earth or rock or other material from or to the railway or
adjacent thereto, for construction of waterways, ditches, levees and approaches
for the unclassified excavation, rock excavation or muck excavation, for the
removal of unsuitable material and topsoil, the removal of landslides, all in
accordance with these Specifications and in reasonably close conformity with
the lines, grades, shown on the drawings or as established by the Engineer.
2.3.2 GENERAL
Any information of the properties of the soil that may be shown on the
drawings or obtained by the Contractor as a result of discussions with
the Engineer or others shall be without prejudice and shall not be
considered as a valid basis for the Contractor‟s Tender Prices.
117
The Engineer will supply the Contractor with the locations of the
Points of Intersection of Tangents and Grade Lines. The drawings will
indicate the properties of horizontal and vertical curves. The
Contractor shall stake-out the work and obtain the Engineer‟s approval
of his stake-out before proceeding with construction. If, in the opinion
of the Engineer, any modification of the line or grade is advisable,
either before or after stake-out the Engineer will issue detailed
instructions to the Contractor for such modifications, and the
contractor shall revise the stake-out for further approval. These
requirements shall be met without additional payment and all costs
thereof shall be included in the Tender Prices for pay items under the
Contract.
2.3.2.3 Quantities
2.3.3.1 General
118
All excavations shall be finished to reasonably smooth and uniform
surfaces. No materials shall be wasted without authority of the
Engineer. Excavation operations shall be conducted so that material
outside of the limits of slopes will not be disturbed. Prior to
excavation, all necessary clearing and grubbing in that area shall have
been performed in accordance with Section 2.1 Clearing and Grubbing.
All suitable material removed from the excavations shall be used in the
formation of the embankment, subgrade, shoulders, slopes, bedding
and backfill for structures, and for other purposes shown on the
Drawings or as directed by the Engineer.
All excess material, including rock and boulders that cannot be used in
embankments shall be disposed off as directed.
Borrow materials shall not be placed until after the readily accessible
railway excavation has been placed in the fill, unless otherwise
permitted or directed by the Engineer. If the Contractor places more
borrow than is required and thereby causes a waste of excavation, the
amount of such waste will be deducted from the borrow volume.
2.3.3.4 Pre-watering
119
excavated shall be moistened to the full depth, from the surface to the
bottom of the excavation. The water shall be controlled so that the
excavated material will contain the proper moisture to permit
compaction to the specified density with the use of standard
compacting equipment. Pre-watering shall be supplemented where
necessary, by truck watering units, to assure that the embankment
material contains the proper moisture at the time of compaction.
Ditches shall conform to the slope, grade, and shape of the required
cross-section, with no projections of roots, stumps, rock or similar
matter. The Contractor shall maintain and keep open and free from
leaves, sticks, and other debris all ditches dug by him until final
acceptance of the work.
120
completion of the construction work and shall be a condition for final
approval and acceptance.
Where the Drawings show the top portion of the roadbed to be selected
topping, all unsuitable materials shall be excavated to the depth
necessary for replacement of the selected topping to the required
compacted thickness.
2.3.3.9 Conglomerate
121
When the material in cuts is conglomerate that, in the opinion of the
Engineer, is not so firmly consolidated as to require drilling, the
Contractor shall use an excavator with suitable steel tines, or other
appropriate equipment for its removal. Such work shall be considered
as Common Excavation.
The Tender Price for all classes of excavation shall include the cost of
removal of all material, regardless of its nature, encountered within the
approved limits for excavation including the removal and disposal, as
required by the Engineer, of existing brick, stone, concrete or masonry,
rock boulders or fragments encountered during excavation.
All suitable material excavated within the limits and scope of the
project shall, unless provision is expressly made to the contrary in
these Specifications, be used in the most effective manner for the
formation of the embankment or for backfill. Any material surplus to
these requirements, or any material declared in writing by the Engineer
to be unsuitable, shall be disposed of and leveled in thin layers by the
Contractor outside the right-of-way or as directed by the Engineer in
accordance with the provisions of these Specifications, and shall be
considered as Common Excavation and paid for at the unit price for
this item subject to the provisions herein, which payment shall include
the cost of obtaining the consent of the owner or tenant of land where
122
the disposal is made. The use of arable land for this purpose shall be
avoided far as possible.
Loose earth or rock shall be removed from slopes when required by the
Engineer. Payment for such removal shall be at the Unit Price as
shown in the Bill of Quantities and subject to the provisions of this
Section.
123
In order to perform this work, the existing railway track shall be
temporarily removed and relocated without disconnecting them, and
restoring the railway to its original alignment at the changed level.
The Contractor shall note that there may be insufficient material from
the excavation to complete the fills. All additive materials required
shall be supplied by the Contractor unless other arrangements have
been made. When the Contractor is required to supply fill
material from outside the railway right-of-way, he shall state in his
proposal the locations from which he intends to obtain materials so that
the Engineer can investigate the quality of materials.
Borrow areas shall not be excavated before they have been cross-
sectioned if required by the Engineer.
124
Profile and cross-sections, to be approved scale and showing the
required details, shall be drawn on transparent tracing paper by the
Contractor, reviewed and checked by the Engineer, and in accordance
with the specified requirements, approved by him. They shall then
become the basis of the quantities to be measured for payment.
The Contractor shall provide the Engineer with three copies of the
approved tracings and of the detailed quantity computation sheets.
a) When the material resulting from the excavation made for the
construction of the roadbed for railway is declared in writing by the
Engineer to be unsuitable for use in the embankment.
b) When the material resulting from the excavation made for the
construction of the embankment is surplus to the amount required for
the construction of the works, provided, however it is not material
rendered surplus by reason of the Contractor‟s having opened borrow
pits solely for his own convenience.
125
2.4 STRUCTURE EXCAVATION
2.4.1 SCOPE
This Section shall consist of the necessary excavation for foundations, wall
footings of structures for ROW fencing, ballast and embankment wall
protection, and drainages The backfilling of completed structures and the
disposal of all excavated materials, shall be in accordance with these
Specifications and in reasonably close conformity with the Drawings or as
established by the Engineer.
It shall also include the furnishing and placing of approved foundation fill
material to replace unsuitable material encountered below the foundation
elevation of structures.
2.4.2.2 Excavation
126
loose and disintegrated rocks and thin strata shall be removed. When
the footing is to rest on material other than rock, excavation to final
grade shall not be made until just before the footing is to be placed.
When the foundation material is soft or mucky or otherwise unsuitable,
as determined by the Engineer, the Contractor shall remove the
unsuitable material and backfill with approved granular material. This
foundation fill shall be placed and compacted in 150 mm (6 inches)
layers up to the foundation elevation.
127
2.5 EMBANKMENT
2.5.1 SCOPE
2.5.3.1 General
128
Embankments and backfills shall contain no muck, peat, sod, roots, or
other deleterious matter. Rocks, broken concrete or other solid, bulky
materials shall not be placed in embankment areas where piling is to be
placed or driven.
129
When shoulder excavation is specified, the railway shoulder shall be
excavated to the depth and width shown on the drawings. The
shoulder material shall be removed without disturbing the adjacent
existing base course material, and all excess excavated materials shall
be disposed off as provided in Subsection 2.3.3.3. If necessary, the
areas shall be compacted before being backfilled.
130
Dumping and rolling areas shall be kept separate, and no lift shall be
covered by another until compaction complies with the requirements of
Subsection 2.5.3.3.
2.5.3.3 Compaction
Compaction Trials
Earth
The Engineer shall during the progress of the Work, make density tests
of compacted material in accordance with AASHTO T 191, T205, or
other approved field density tests, including the use of properly
calibrated nuclear testing devices. A correction for coarse particles
may be made in accordance with AASHTO T224. If, by such tests,
the Engineer determines that the specified density and moisture
131
conditions have not been attained, the Contractor shall perform
additional work as may be necessary to attain the specified conditions.
At least one group of three in-site density tests shall be carried out for
each 500 sq. m. each compacted fill.
Rock
Rounding – Except in solid rock, the tops and bottoms of all slopes,
including the slopes of drainage ditches, shall be rounded as indicated
on the Drawings. A layer of earth overlaying rock shall be rounded
above the rock as done in earth slopes.
132
adjusted and warped to flow into each other or into the natural ground
surfaces without noticeable break.
After the roadbed has been substantially completed, the full width shall
be conditioned by removing any soft or other unstable material that
will not compact properly or serve the intended purpose. The resulting
areas and all other low sections, holes or depressions shall be brought
to grade with suitable selected material. Scarifying, blading, dragging,
rolling, or other methods of work shall be performed or used as
necessary to provide a thoroughly compacted roadbed shaped to the
grades and cross-sections shown on the Drawings or as staked by the
Engineer.
All earth slopes shall be left with roughened surfaces but shall be
reasonably uniform without any noticeable break and in reasonably
close conformity with the Drawings or other surfaces indicated on the
Drawings or as staked by the Engineer, with no variations therefrom
readily discernible as viewed from the road.
Cut slopes in rippable material (soft rock) having slope ratios between
0.75:1 and 2:1 shall be constructed so that final slope line shall consist
of a series of small horizontal steps. The step rise and tread
dimensions shall be shown on the Drawings. No scaling shall be
performed on the stepped slopes except for removal of large rocks
which will obviously be a safety hazard if they fail into the ditchline or
railway.
133
section of the finished compacted bermshall reasonably conform to the
typical cross-section shown on the Drawings.
2.5.3.11Uncompacted Berm
134
payment will be deemed to include the cost of excavating, hauling,
stockpiling and all other costs incidental to the work.
Material for Selected Borrow topping will be measured and paid for
under the same conditions specified in the preceding paragraph.
135
2.6 COMPACTION EQUIPMENT AND DENSITY CONTROL STRIPS
2.6.1 SCOPE
136
Upon completion of the compaction, the mean density of the control
strip will be determined by averaging the results of ten in place density
tests taken at randomly selected sites within the control strip. The
mean density of the control strip shall be the target density for the
remainder of the course which it represents.
If the mean density of the control strips is less than 95 percent of the
density of laboratory compacted specimens as determined by testing
procedures appropriate for the material being placed, the Engineer may
order the construction of another control strip.
137
PART 3
DRAINAGE AND SLOPE PROTECTION STRUCTURES
3.1.1 SCOPE
This Section shall consist of the construction of concrete lined ditch and U-
type ditches.
The Work shall also include the general items in connection with the
construction of ditches along the slope toes and cut sections, vertical ditches
along the slopes, median strip drains, relating ditches connecting to these
drains, catch basins, drainage pipes, inlet and outlet of drain, connection
between drains. All works shall be done in accordance with these
Specifications and in reasonably close conformity with the lines, levels, grades
and dimensions shown on the Drawings or as directed by the Engineer.
3.1.2 MATERIAL
Materials for any precast and cast-in-place concrete shall conform to the
requirements of Section 4.1, of these Specifications.
The shape and size of drainage structures shall be as shown on the Drawings.
Joint Mortar – Joint mortar for concrete pipes shall consist of 1 part, by
volume of Portland Cement, and two (2) parts of approved sand with water as
necessary to obtain the required consistency.
Portland cement and sand shall conform to the requirements of Section 4.1,
Concrete Works for Structures. Mortar shall be used within thirty (30)
minutes after its preparation.
When the location of manufacturing plants allows, the plants will be inspected
periodically for compliance with specified manufacturing methods, and
material samples will be obtained for laboratory testing for compliance with
materials quality requirements. This can be the basis for acceptance of
manufacturing lots as to quality.
Prior to and during incorporation of materials in the work, these materials will
be subject to the latest inspection and approval of the Engineer.
3.1.3.1 Excavation
138
Trenches shall be excavated in accordance with the requirements of
2.3, Excavation, to a width sufficient to allow for proper jointing of the
conduit and thorough compaction of the bedding and backfill material
under and around the conduit. When feasible, trench walls shall be
vertical.
The completed trench bottom shall be firm for its full length and width.
Where required, in the case of crop drains, the trench shall have a
longitudinal camber of the magnitude specified.
3.1.3.2 Bedding
For large diameter structural plate pipe the shaped bed to be used need
not exceed the width of bottom plate.
139
The conduit laying shall begin at the downstream end of the conduit
line. The lower segment of the conduits shall be in contact with the
shaped bedding throughout its full length.
Drainage ditches shall be laid out to the exact line and grade as shown
on the Drawings.
a) Jointing Conduit
The method of joining conduit sections shall be such that the ends are
fully entered and the inner surfaces are reasonably flush and even.
Joints shall be made with (a) Portland Cement mortar, (b) Portland
Cement grout, or any other type, as may be specified. Mortar joints
shall be made with an excess of mortar to form a continuous bead
around the outside of the conduit and finished smooth on the inside.
For grouted joints, molds or runners shall be used to retain the poured
grout.
When Portland Cement mixtures are used, the completed joints shall
be protected against rapid drying by any suitable covering material.
140
shall be as shown on the drawings or as approved by the Engineer. The
contractor shall place and attach to the structure all timber, metal or
other accessories necessary for the completion of drainage ditch as
shown on the Drawings.
3.1.3.5 Backfilling
Materials for backfill on each side of the conduit for the full trench
width and to an elevation of 300 mm above the top of the conduit shall
be fine, readily compactible soil or granular material selected from
excavation or from a source of the Contractor‟s choice, and shall not
contain stones that would be retained on a 50 mm sieve, chunks of
highly plastic clay, or other objectionable material. Granular backfill
material shall have not less than 95 percent passing a 12.5 mm sieve
and not less than 95 percent retained on a 4.75 mm sieve. Oversized
material, if present, shall be removed at the source of the material,
except as directed by the Engineer.
When the top of the conduit is flushed with or below the top of the
trench, backfill material shall be placed at or near optimum moisture
content and compacted in layers not exceeding 1500 mm (compacted)
on both sides of an elevation 300 mm above the 300 mm above the top
of the conduit. Care shall be exercised to thoroughly compact the
backfill under the haunches of the conduit. The backfill shall be
brought up evenly on both sides of the conduit for the full required
length. Except where negative projecting embankment-type
installation is specified, the backfill material shall be placed and
compacted for the full depth of the trench.
When the top of the conduit is above the top of the trench, backfill
shall be placed at or near optimum moisture content and compacted in
layers not exceeding 300 mm (compacted) and shall be brought up
openly on both sides of the conduit for its full length to an elevation
300 mm above the top of the conduit. The width of backfill on each
side of the conduit for the portion above the top of the trench shall be
equal to twice the diameter of the conduit or 3.5 m, whichever is less.
The backfill material used in the trench for a distance on each side of
the conduit equal to the horizontal inside diameter and to 300 mm
above the top of the conduit shall conform to the requirements for
backfill material in this Subsection. The remainder of the backfill shall
consist of material from excavation and borrow that is suitable for
embankment construction.
141
Backfill for ditches or inlets on the railway shall be carefully made so
as to obtain a bearing capacity equal to the adjacent subgrade. Backfill
for vertical ditches along the slopes shall be carefully constructed so as
to prevent erosion by overflow of drain water or rain.
142
3.2 RC PIPES
3.2.1 SCOPE
143
3.3 CLEANING AND REHABILITATION OF EXISTING DRAINAGE EARTH
AND CONCRETE DITCHES
3.3.1 SCOPE
This Section shall consist of cleaning and rehabilitation of existing earth and
concrete ditches, in reasonably close conformity with this Specification and as
shown on the Drawings.
Materials used for repair or replacement under the various Pay Items shall
conform to the requirements of the applicable Sections of this Specification.
The earth and concrete shall be carefully removed and cleaned of foreign
materials.
In such cases where the Contractor damaged the existing ditches, he shall
furnish all materials required to repair the ditches and perform all excavation
and backfill and restore the ditches all at the contract bid price for this Item.
All debris and left outs shall be properly disposed off by the Contractor at the
disposal area designated and approved by the Engineer at no additional cost to
the Employer.
Ditches cleaned in place will be measured along the flow line of the
center line acceptably cleaned as directed.
144
3.4 CONCRETE LINED DITCH
The work shall include the trimming of the foundation and the construction of
the canal lining with the necessary construction joints as specified herein.
Trimming foundation for concrete lining includes trimming and finishing the
ditch section upon which concrete lining is to be placed.
Where foundation material has been excavated beyond the neat lines of the
underside of the ditch lining, the excess excavation shall be filled with
selected material conforming to the requirements of a compacted
embankment. Where foundation material has been disturbed or loosened
during trimming operations or with selected material as directed by the
Engineer. Selected material placed on ditch side slopes shall be placed in
layers which parallel the foundation. Selected material placed in the invert
shall be placed in layers which parallel the foundation surface. Where the
thickness of the selected material is more than 150 mm, the material shall be
placed in layers not exceeding 150 mm thick before compaction. Selected
material shall be moisture conditioned for proper compaction and compacted
to not less than 90 percent compaction.
2. Canal Lining
Concrete for canal lining shall conform to the provisions of Section 4.1. The
surface of the lining shall be finished as specified for finish under Section 4.1
or as specified herein.
The Contractor may be permitted to over excavate the foundation and increase
the thickness of the lining at his expense to facilitate his construction
operations. However, no abrupt changes in the configuration of the
foundation will be permitted. Such changes shall be gradual and shall be
subject to approval by the Engineer.
When concrete lining operations are stopped for the day because of equipment
breakdown or delayed by other causes, the end of fresh concrete shall be
bulkheaded to a vertical surface and a construction joint be provided as
specified herein.
Construction joints in canal lining shall be provided at every four (4) meters.
145
3.4.3 CONCRETE FINISH FOR LINED DITCH
Finishing of concrete surfaces for concrete lined ditch shall be performed only
by skilled workmen. The Contractor shall advise the Engineer as to when
concrete will be finished. Unless inspection is waived in each specific case,
finishing of concrete shall be performed only in the presence of the Engineer.
Concrete surfaces will be tested by the Engineer to determine that surface
irregularities are within the limits hereinafter specified.
Exterior surfaces for concrete lined ditch will be sloped for drainage where
shown on the Drawings or as directed. The finished surface shall be
equivalent in evenness, smoothness and from freedom from rock pockets and
surface voids to that obtainable by effective use of a long-handled steel trowel.
Light surface fitting and light trowel marks will not be considered
objectionable. Surface irregularities measured as described above shall not
exceed 0.60 cm for bottom slabs and 1.20 cm for side slopes.
In warm, dry, or windy weather the moisture control measures specified herein
shall be taken to inhibit loss of moisture from the surface of the concrete.
Such surfaces shall be fog-sprayed, covered completely with white
polyethylene sheet, or otherwise treated as approved. The curing specified in
Section 4.1, shall be started as soon as the concrete hardens, however, the
surface of the concrete shall be kept wet during the change in curing methods.
Plastic shrinkage cracks which occur before the concrete hardens shall be
closed. Shrinkage cracks shall be closed by working; crack shall not be sealed
by troweling only.
146
3.4.4 MEASUREMENT AND PAYMENT
Payment of concrete for canal lining will be made on the contract unit
price per cubic meter, which price and payment shall constitute full
compensation for furnishing all materials, labor, supplies, tools,
equipment and incidentals necessary to complete the work and for
subsidiary work called for in the construction including construction
joints.
147
PART 4
BRIDGE CONSTRUCTION
4.1.1 SCOPE
4.1.1.1
4.1.2.1
4.1.2.2
148
Reinforcement
C 33 Concrete Aggregate
C 94 Ready-mixed Concrete
149
Official (AASHTO)
Sampling of fresh concrete T 141
4.1.2.3 Submittals
150
6. Concrete Curing Compound. Curing compound shall conform
to the requirements of AASHTO M 148 Liquid membrane-forming
compounds for curing concrete.
4.1.3.1.1 Cement
Type Specification
151
When Types IV and V (AASHTO M 85), P and PA (AASHTO
M 150) cements are used, proper recognition shall be given to
the effects of slower strength gain on concrete proportioning
and construction practices. Types S and SA cements will be
permitted only when blended with Portland Cement in
proportions approved by the Engineer.
4.1.3.2 Admixtures
a) Air-Entraining Admixtures
4.1.3.3 Aggregates
1) Coarse Aggregates
152
thereof, having hard, strong, durable pieces and free from any adherent
coatings.
It shall contain not more than one (1) mass percent of material passing
the 0.075 mm (No. 200) sieve, not more than 0.25 mass percent of clay
lumps, nor more than 3.5 mass percent of soft fragments.
If slag is used, its density shall not be less than 1120 kg/m3 (70 lb/cu.
Ft.). The gradation of the coarse aggregate shall conform to Table
4.1.3.4.
Only one grading specification shall be used from any one source.
2) Fine Aggregates
It shall not contain more than three (3) mass percent of material
passing the 0.075 mm (No. 200 sieve) by washing nor more than one
(1) mass percent each of clay lumps or shale. The use of beach sand
will not be allowed without the approval of the Engineer.
153
If the fine aggregate is subjected to five (5) cycles of the sodium
sulfate soundness test, the weighted loss shall not exceed 10 mass
percent.
The fine aggregate shall be well-graded from coarse to fine and shall
conform to Table 4.1.3.1.
4.1.3.4 Water
It is required that the mixing water shall be clear and apparently clean.
If it contains quantities or substances that discolor it or make it smell
or taste unusual or objectionable, or cause suspicion, it shall not be
used unless service records or concrete made with it (or other
information) indicate that it is not injurious to the quality, shall be
subject to the acceptance criteria as shown in Table 4.1.3.2 and Table
4.1.3.3 or as designated by the Engineer.
Limits
Compressive strength, min. %
154
control at 7 days 90
Time of Setting deviation from control from 1:00 earlier
Limits
Chemical Requirements, Minimum Concentration
Wash water reused as mixing water in concrete may exceed the listed
concentrations of sulfate if it can be shown that the concentration
calculated in the total mixing water, including mixing water on the
aggregate and other sources, does not exceed the stated limits.
Water will be tested in accordance with, and shall meet the suggested
requirements of AASHTO T 26.
155
Water known to be of potable quality may be used without test.
4.1.3.6
4.1.3.7
Reinforcement
4.1.3.8
The filler for its joint shall be furnished in a single piece for the depth
and width required for the joint unless otherwise authorized by the
Engineer. When the use of more than one piece is authorized for a
joint, the abutting ends shall be fastened securely, and held accurately
to shape, by stapling or other positive fastening satisfactory to the
Engineer.
4.1.3.9
156
2) Polyethylene sheeting shall be not less than 0.2 mm nominal
thickness.
4.1.4.1
1) Cement
Sampled either at the mill or at the site of the work and tested by an
approved independent commercial or national testing laboratory at no
additional cost to the Employer. Certified copies of laboratory test
reports shall be furnished for each lot of cement and shall include all
test data, results, land certificates that the sampling and testing
procedures are in conformity with the Specifications. No cement shall
be used until notice has been given by the Engineer that the test results
are satisfactory. Cement that has been stored, other than in bins at the
mills, for more than 4 months after delivery to the Site shall be
retreated before use. Cement delivered at the Site and later found
under test to be unsuitable shall not be incorporated into the permanent
works.
2) Aggregates
3) Reinforcement
4) Concrete Tests
For test purposes, three sets of test specimens shall be taken, under the
instruction of the Engineer, from each 50 cubic meter or fraction
thereof of each class of concrete placed. At least one set of test
specimen shall be provided for each class of concrete placed in each 8-
hour shift.
Each shall consist of two test specimens, and shall be made from a
separate batch. Samples shall be secured in conformity with ASTM C
172. Test specimens shall be made, cured, and packed for shipment in
accordance with ASTM C 31. Cylinders will be tested in accordance
with ASTM C 39 by and at the expense of the contractor. Test
specimens will be evaluated separately by the Engineer for meeting
strength requirements with CONCRETE QUALITY of ACI 318. The
standard age of test shall be 28 days, but 7-day test may be used, with
157
the permission of the Engineer, provided that the relation between the
7-day and 28-day strengths on the concrete is established by tests for
the materials and proportions used. When samples fail to conform to
the requirements for strength, the Engineer shall have the right to order
a change in the proportions of the concrete mix for the remaining
portions of the work at no additional cost to the Engineer.
When the result of the strength test of the control specimens indicates
the concrete as placed does not meet the requirements or where there is
other evidence that the quality of the concrete is below the
requirements, test on core of in-place concrete shall be made in
conformity with ASTM C 42.
6) Admixtures
All admixtures shall be tested and those that have been in storage at the
Project Site for longer than 6 months shall be retest and if found to be
satisfactory, it can be used.
a) Air-Entraining Admixtures
4.1.5 STORAGE
4.1.5.1
1) Cement
158
Immediately upon receipt at the Site, the cement shall be stored
separately in a dry weather tight, properly ventilated structure, with
adequate provisions for prevention or absorption of moisture. Cement
bags should not be stacked more than 13 bags high. The cement most
likely to have been exposed to moisture or stored in bags for more than
4 months shall not be used unless proven by tests to be in good
condition.
2) Aggregates
3) Reinforcement
2. The loading used on timber piles shall not exceed the bearing
value for the pile and shall in no case exceed 20 tons per pile.
3. Soil bearing values and soil condition (wet and dry) shall be
designated by the Contractor on the falsework drawings. Falsework
footings shall be designed to carry the loads imposed upon them
without exceeding estimated soil bearing values or allowable
settlements.
159
4. The maximum loadings and deflections used on jacks, brackets,
columns and other manufactured devices shall not exceed the
manufacturer‟s recommendations. If requested by the Engineer, the
Contractor shall furnish catalogue or other data verifying these
recommendations.
160
In addition to the above requirements, falsework for place pre-stressed
portion of structure shall not be released until after the pre-stressing
steel has been tensioned.
All debris and refuse resulting from work shall be removed and the site
left in a neat and presentable condition.
4.1.6.4
The Contractor shall prepare drawings and material data for the
formwork and shutters to be submitted to the Engineer for approval
unless otherwise directed.
4.1.6.5
Formwork Construction
The inside surfaces of forms shall be cleaned of all dirt, mortar and
foreign material. Forms which will later be removed shall be
thoroughly coated with form oil prior to use. The form oil shall be of
commercial quality form oil or other approved coating which will
permit the ready release of the forms and will not discolor the concrete.
161
The rate of depositing concrete in forms shall be such to prevent
bulging of the forms or form panels in excess of the deflections
permitted by the Specification.
Forms for all concrete surfaces which will not be completely enclosed
or hidden below the permanent ground surface shall conform to the
requirements herein for forms for exposed surfaces. Interior surfaces
of underground drainage structures shall be considered to be
completely enclosed surfaces.
Anchor devices may be cast into the concrete for later use in
supporting forms or for lifting pre-cast members.
162
Forms and falsework shall not be removed without the consent of the
Engineer. The Engineer‟s consent shall not relieve the Contractor of
responsibility for the safety of the work. Blocks and bracing shall be
removed at the time the forms are removed and in no case shall any
portion of the wood forms be left in the concrete.
a) Control Tests
When concrete strength tests are used for removal of forms and
supports, such removal should not begin until the concrete has attained
the percentage of the specified design strength shown in the table
below.
Centering under
Girders, beams
Frames or arches 14 days 80%
163
Floor slabs 14 days 70%
Walls 1 day 70%
Columns 2 days 70%
Sides of beams and
all other vertical
surfaces 1 day 70%
Forms and falsework shall not be released from under concrete without
first determining if the concrete has gained adequate strength without
regard to the time element. In the absence of strength determination,
the forms and falsework are to remain in place until removal is
permitted by the Engineer.
Form surfaces that will be in contact with concrete shall be sound, tight
lumber or other material producing equivalent finish.
4.1.6.9Form Ties
164
upon removal. Solid backing shall be provided for each tie. Ties shall
be fitted with devices that will leave holes in the concrete surface not
less than 9 mm nor more than 25 mm in diameter and of depth not less
than 25 mm.
4.1.6.10 Chamfering
4.1.6.11 Coating
Forms for exposed surfaces shall be coated with form oil or form-
release agent before reinforcement is placed. The coating shall be a
commercial formulation of satisfactory and proven performance that
will not bond with, stain, or adversely affect concrete surfaces, and will
not impair subsequent treatment of concrete surfaces depending upon
bond or adhesion nor impede the wetting of surfaces to be cured with
water or curing compounds. The coating shall be used as
recommended in the manufacturer‟s printed or written instructions.
Forms for unexposed surfaces may be wet with water in lieu of coating
immediately before placing of concrete. Surplus coating on form
surfaces and coating on reinforcement steel and construction joints
shall be removed before placing concrete.
4.1.7 REINFORCEMENT
Bars with kinks or bends not shown on the Drawings shall not be
placed. The use of heat to bend or straighten reinforcing steel shall not
be permitted. Bars shall be moved as necessary to avoid interference
with other reinforcing steel, conduits, or embedded items. If bars are
moved more than one bar diameter, the resulting arrangement of bars
including additional bars necessary to meet structural requirements
shall be approved by the Engineer before concrete is placed. In slabs,
beams, and girders, reinforcing steel shall not be spliced at points of
maximum stress unless otherwise indicated.
165
The nominal dimensions and unit weights of deformed bar designation
shall be in accordance with the following table.
Unit Weight
Bar No. Diameter (mm) Area (mm2)
(Kg/m)
2 6mm 28.27 0.222
3 10mm 78.54 0.616
4 12mm 113.10 0.888
5 16mm 201.10 1.579
6 20mm 314.20 2.466
8 25mm 491.90 3.854
9 28mm 615.75 4.833
10 32mm 804.25 6.313
11 36mm 1,017.90 7.991
Wire and wire mesh shall conform to AASHTO M 55. The type of
mesh shall be as indicated on the drawings and approved by the
Engineer. The wire shall conform to AASHTO M 32.
4.1.7.5 Tie-Bars
166
shall be rigidly held in place and supported during placing of the
concrete.
4.1.7.6 Supports
Supports shall be provided in conformity with ACI 315 and ACI 318
unless otherwise indicated or specified. Wire, ties, when used, shall be
rigidly held in place and supported during placing of the concrete.
Exposed reinforcement bars, dowels and plates intended for bonding with future extensions
shall be protected from corrosion.
167
less than 75 mm 6 mm
4.1.8 CLASSES OF CONCRETE AND USAGE
4.1.8.2 Usage
Class D – Thin reinforced sections, railings, and for filler in steel grid
floors.
4.1.8.3 Materials
168
50 2" 95-100
37.5 1 1/2" 100 95-100 100
25 1" 95-100 35-70 95-100 100
19.0 3/4" 35-70 90-100 100
12.5 1/2" 25-60 10-30 25-60 90-100
9.5 3/8" 10-30 20-55 40-70
4.75 No. 4 0-10+ 0-5 0-5 0-10+ 0-10* 0-15*
*The measured cement content shall be within plus (+) or minus (-) 2 mass percent of the
design cement content.
169
Compressive strength of molded
concrete cylinders T 22
4.1.9.2 Consistency
170
the difficulty in mixing and transporting. The quantity of mixing water
shall be determined by the Engineer and shall not be varied without his
consent. Concrete as dry as it is practical to place with the equipment
specified shall be used.
4.1.9.3 Batching
1. Portland Cement
2. Water
3. Aggregates
The batching plant shall include separate bins for bulk cement,
fine aggregate and for each size of coarse aggregate, a weighing
hopper, and scales capable of determining accurately the mass of each
component of the batch.
171
Scales shall be accurate to one half (0.5) percent throughout the range
used.
5. Batching
Batches shall be delivered to the mixer separate and intact. Each batch
shall be dumped cleanly into the mixer without loss, and, when more
than one batch is carried on the truck, without spilling of material from
one batch compartment into another.
6. Admixtures
172
For batch mixing in the site of construction or at a central point, a
batch mixer, or an approved type shall be used. Mixer having a rated
capacity of less than one bag batch shall not be used. The volume of
concrete mixed per batch shall not exceed the mixer‟s nominal
capacity as shown on the manufacturer‟s standard rating plate on the
mixer except that an overload up to ten percent above the mixer‟s
nominal capacity may be permitted, provided concrete test data from
strength, segregation and uniform consistency are satisfactory and
provided no spillage of concrete takes place. The batch shall be so
charge into the drum that a portion of water shall enter in advance of
the cement and aggregates. The flow of water shall be uniform and
shall be in the drum by the end of the first 15 seconds of the mixing
period. Mixing time shall be measured from the time all materials,
except water, are in the drum. Mixing time shall not be less than
60 seconds for mixers having a capacity of 1.5 m3 or less. For mixers
having a capacity greater than 1.5 m3, the mixing time shall not be less
than 90 seconds. If timing starts, the instant the skip reaches its
maximum raised position, 4 seconds shall be added to the specified
mixing time. Mixing time ends when the discharge chute opens.
173
concrete shall be sufficient to complete the casting of a section up to a
construction joint that will meet the approval of the Engineer.
When bulk cement is used and volume of the batch is 0.5m3 or more,
the scale and weigh hopper for Portland Cement shall be separate and
distinct from the aggregate hopper or hoppers. The discharge
mechanism of the bulk cement weigh hopper shall be interlocked
against opening before the full amount of cement is in the hopper.
The discharging mechanism shall also be interlocked against opening
when the amount of cement in the hopper is underweight by more than
3 mass percent of the amount specified.
When the aggregate contains more water than the quantity necessary to
produce a saturated surface-dry condition, representative samples shall
be taken and the moisture content determined for each kind of
aggregate.
174
The batch shall be so charged into the mixer that some water will enter
in advance of cement and aggregate. All water shall be in the drum by
the end of the first quarter of the specified mixing time.
Cement shall be batched and charged into the mixer so that it will not
result in loss of cement due to the effect of wind, or in accumulation of
cement on surfaces of conveyors or hoppers, or in other conditions
which reduce or vary the required quantity of cement in the concrete
mixture.
The entire content of a batch mixer shall be removed from the drum
before materials for a succeeding batch are placed therein. The
materials composing a batch except water shall be deposited
simultaneously into the mixer.
All concrete shall be mixed for a period of not less than 1 ½ minutes
after all materials, including water, are in the mixer. During the period
of mixing, the mixer shall operate at the speed for which it has been
designed.
The first batch of concrete materials placed in the mixer shall contain a
sufficient excess of cement, sand, and water to coat the inside of the
drum without reducing the required mortar content of the mix. When
mixing is to cease for a period of one hour or more, the mixer shall be
thoroughly cleaned.
175
The maximum size of batch in truck mixers shall not exceed the
minimum rated capacity of the mixer as stated by the manufacturer and
stamped in metal on the mixer. Truck mixing shall, unless otherwise
directed be continued for not less than 100 revolutions after all
ingredients, including water, are in the drum. The mixing speed shall
not be less than 4 rpm, nor more than 6 rpm.
Mixing shall begin within 30 minutes after the cement has been added
either to the water or aggregate, but when cement is charged into a
mixer drum containing water or surface-wet aggregate and when the
temperature is above 32 deg. C, this limit shall be reduced to 15
minutes. The limitation in time between the introduction of the
cement to the aggregate and the beginning of the mixing may be
waived when, in the judgment of the Engineer, the aggregate is
sufficiently free from moisture so that there will be no harmful effects
on the cement.
176
The Contractor shall have sufficient plant capacity and
transportation apparatus to insure continuous delivery at the rate
required. The rate of delivery of concrete during concreting operations
shall be such as to provide for the proper handling, placing and
finishing of the concrete. The rate shall be such that the interval
between batches shall not exceed 20 minutes. The methods of
delivering and handling the concrete shall be such as will facilitate
placing of the minimum handling.
Concrete shall not be placed until forms and reinforcing steel have
been checked and approved by the Engineer.
In preparation for the placing of concrete all sawdust, ships and other
construction debris and extraneous matter shall be remove from inside
the formwork, struts, stays and braces, serving temporarily to hold the
forms in correct shape and alignment, pending the placing of concrete
at their locations, shall be removed when the concrete placing has
reached an elevation rendering their service unnecessary. These
177
temporary members shall be entirely removed from the forms and not
buried in the concrete.
No concrete shall be used which does not reach its final position in the
forms within the time stipulated under “Time of Hauling and Placing
Mixed Concrete”.
Open troughs and chutes shall be of metal or metal lined; where steep
slopes are required, the chutes shall be equipped with baffles or be in
short lengths that reverse the direction of movement to avoid
segregation.
All chutes, troughs and pipes shall be kept clean and free from coatings
of hardened concrete by thoroughly flushing with water after each run.
Water used for flushing shall be discharged clear of the structure.
178
At the conclusion of placing the concrete, the entire equipment
shall be thoroughly cleaned.
179
be completely filled and slowly lowered to avoid backwash. It
shall not be dumped until it rests on the surface upon which the
concrete is to be deposited and when discharged shall be
withdrawn slowly until well above the concrete.
180
Joints in the concrete due to stopping work shall be avoided as much as
possible. Such joints, when necessary, shall be constructed to meet the
approval of the Engineer.
181
Concrete in T-beam or deck girder spans shall be placed in one
continuous operation unless otherwise directed. If it is permitted to
place the concrete in two separate operations, each of the operations,
shall be continuous: first, to the top of the girder stems, and second, to
completion. In the latter case, the bond between stem and slab shall be
secured by means of suitable shear keys which may be formed by the
use of timber blocks approximately 50 mm x 100 mm in cross-section
having a length of 100 mm less than the width of the girder stem.
These key blocks shall be placed along the girder stems as required,
but the spacing shall not be greater than 300 mm center to center. The
blocks shall be beveled and oiled in such a manner as to insure their
ready removal, and they shall be removed as soon as the concrete has
set sufficiently to retain its shape. If the Contractor wishes to place the
concrete in two separate operations, he shall, with his request for
permission to do so, submit plans and proposals shall be subject to the
approval of the Engineer.
In box girders, the concrete in the bottom slab shall be poured first, as
a separate operation.
The concrete in the webs and the top slab shall be placed in one
continuous operation unless otherwise specified. If it is permitted to
place the concrete in more than one operation, the requirements for T-
beam shall apply.
182
4.1.10.7 Concrete Surface Finishing
Excluded, however, are the tops and bottoms of floor slabs, and
sidewalks, bottoms of beams and girders, sides of interior beams and
girders, backwalls above bridge seats or the underside of the copings.
The surface exposed surfaces below the bridge seats to 20 cm below
low water elevation or 50 cm below finished ground level when such
ground level is above the water surface. Wingwalls shall be finished
from the top to 50 cm below the finished slope lines on the outside face
and shall be finished on top and for a depth of 20 cm below the top on
the back sides.
183
The resulting surface shall be true and uniform. All repaired surfaces,
the appearance of which is not satisfactory to the Engineer, shall be
“rubbed” as specified below.
After all concrete above the surface being created has been cast, the
final finish shall be obtained by rubbing with a fine carborundum stone
and water. This rubbing shall be continued until the entire surface is of
smooth texture and uniform color.
After the final rubbing is completed and the surface has dried, it should
be rubbed with burlap to remove loose powder and shallbe left free
from all unsound patches, paste, powder and objectionable marks.
184
produced equivalent result may be substituted for the above manual
method.
After the longitudinal floating has been completed and the excess
water removed, but while the concrete is still plastic, the slab surface
shall be tested for trueness with a straight-edge. For this purpose, the
Contractor shall furnish and use an accurate 3m straight-edge swung
handless 1m longer than one-half the width of the slab.
When the concrete has hardened sufficiently, the surface shall be given
a broom finish. The broom shall be an approved type. The strokes
shall be square across the slabs from edge to edge, with adjacent
strokes slightly overlapped, and shall be made by drawing the broom
without tearing the concrete, but so as to produce regular corrugations
not over 3 mm in depth. The surface as thus finished shall be free from
porous spots, irregularities, depressions and small pockets or rough
spots such as may be caused by accidental disturbing, during the final
brooming of particles of coarse aggregate embedded near the surface.
1. Water Method
185
sand blankets may be used to retain the moisture. At the expiration of
the curing period the concrete surface shall be cleared of the curing
medium.
2. Curing compound
186
container shall be labeled with a manufacturer‟s name, specification
number, batch number, capacity and date of manufacture, and shall
have label warning concerning flammability. The label shall also warn
that the curing compound shall be well-stirred before use. When the
curing compound is shipped in tanks or tank trunks, a shipping invoice
shall accompany each load. The invoice shall contain the same
information as that required herein for container labels.
4. Forms-in-Place Method
187
All newly placed concrete for cast-in-situ structures, other than
highway bridge deck, shall be cured by the water method, the forms-
in-place method, or as permitted herein, by the curing compound
method, all in accordance with the requirements of Subsection 4.1.10.8
Curing Concrete.
The top surface of highway bridge decks shall be cured by either the
curing compound method or the water method. The curing compound
method or the water method. The curing compound shall be applied
progressively during the deck finishing operations. The water cure
shall be applied not later than 4 hours after completion of the deck
finishing.
Pre-cast concrete members shall be cured for not less than 7 days by
the water method or by steam curing. Steam curing for pre-cast
members shall conform to the following provisions:
188
where temperature of the enclosure will be the same as that of the
concrete.
4.1.11.1 Scope
4.1.11.2 Materials
(4) Reinforcement:
189
4.1.11.3 Design Requirement:
(3) Loads
Loading for members and connections shall include all dead load, live
load, applicable lateral loads such as wind and earthquake, applicable
construction loads such as handling, erection loads, and other
applicable loads.
Perform the following testing to ensure the materials and method used
meet the requirements and will produce precast-prestressed concrete
members which are suitable for their intended use.
(2) Concrete
190
time of stress transfer and a minimum of two test cylinders, shall be
made for each mix design to verify the attainment of the specified
strength.
c. Cylinder Curing
d. Testing of Cylinders
4.1.11.5 Execution
(1) Inspection
191
Comply with requirements of ACI 301, Section 9 – Prestressed
Concrete.
(2) Preparation
(3) Placement
4.1 Sequence;
4.2 Tensioning multiple;
4.3 Prestressing force;
4.4 Prestress loss;
4.5 Formwork;
4.6 Prevention of damage to tendons, and
4.7 Trimming of tendons.
4.1.12.1 Measurement
Setting out of the work to be paid for shall not be measured separately,
the cost shall be deemed as part of and incidentals to the foundation
works.
192
4.1.12.2 Payment
193
4.2 PREFORMED JOINT FILLER AND JOINT SEALING FILLER
4.2.1 SCOPE
This work shall consist of furnishing and application of a resilient joint filler
and joint sealing material in connection with the construction of bridges in
accordance with these specifications and drawings or as directed by the
Engineer.
4.2.2 MATERIAL
Prior to resealing of joints, the existing joint material shall be removed to the
depth shown on the drawings. If joint sealer other than that originally used is
specified, all existing joint sealer shall be removed.
4.2.4
Hot Poured Sealants. The joint sealant shall be applied uniformly solid from
bottom to top and shall be filled without formation of entrapped air or voids.
A backing material shall be placed which shall be non-adhesive to the concrete
or the sealant material. The sealant shall not be heated to more than 11 deg. C
below the safe heating temperature. The safe heating temperature can be
obtained from the manufacturer‟s shipping container. A direct connecting
pressure type extruding device with nozzles shaped for insertion into the joint
shall be provided. Any sealant spilled on the surface of the concrete shall be
removed immediately.
Preformed Joint Fillers. Preformed joint filler shall be placed using equipment
capable of installing the filler in the upright position, without cutting, nicking,
distorting, or otherwise damaging the seal. Lubricant shall be applied to the
concrete or the preformed filler, or both, and the seal shall be installed in a
substantially compressed condition and at the depth below the surface of the
concrete. The joint filler shall be installed in the longest practicable length in
194
longitudinal joints and shall be cut at the joint intersections for continuous
installation in the transverse joint.
Payment for the joint sealing material shall be made at the contract unit
price per liter and square meter as shown in the Bill of Quantities. The
payment shall be full compensation for furnishing all materials, and for
all labor, equipment, tools, and incidentals necessary to complete the
work.
195
PART 5
TRACKWORKS
5.1 SCOPE
d. Track laying using new 37 kg ASCE rails with new fishplates or angle
bars, trackbolts, prestressed concrete sleepers, rail fastenings and ballasting
with crushed rocks on prepared sub-base/sub-ballast.
f. Installation of new turnout 4 sets of No. 10for new 37 kg rails for the
station yard (300meters third track each at Sucat and Alabang complete with
accessories and wood sleepers.
5.3.1 RAILS
a. Supply of Rails
The Contractor shall supply new 37 kg rails. The Contractor shall also use re-
conditioned 37 kg ASCE rail as directed by the Engineer.
The Contractor shall thoroughly inspect the existing rails, and those rails
having the following defects shall not be reconditioned.
(1) Breaks, cracks and wear more than 11mm at the top of rail
196
(3) Excessive corrosion.
(5) Length of less than 5m. In case of welding, 3.0m rails can be used.
c. The Contractor shall weld the rails in situ into a 60 m panel using the
Thermit Welding or gas pressure and flash but welding process.
Joint bars for 37kg ASCE and for 40 Kg N rails shall be supplied by the
Contractor. Compromise angle bars for 37kg ASCE rails and 32kg ASCE rails
shall also be supplied by the Contractor.
b. The materials for compromise angle bars for 37kg ASCE and 32kg
ASCE rails shall be manufactured from rolled steel or cutting in accordance
with the requirements of JIS E-1102 (Carbon Steel for Machine Structural
Use) S45C or equivalent standards (Refer to the attached drawing).
Rail clips shall be used for new pre-stressed concrete sleepers as shown in the
drawings. It shall conform to standards acceptable PNR and shall include all
parts and fittings for the various types of sleepers as shown in the drawings
and as instructed by the Engineer. The Contractor shall submit technical data
from the manufacturer for the Engineer‟s approval.
197
A. CONCRETE SLEEPERS
1. SCOPE
This specification covers all the requirements for the size, shape
and quality for the supply of Prestressed Concrete Sleepers including
Complete Sets of Rail Fastening Components.
1.1
1.2
The rail fastening system shall be the e type 2000 or the latest
equivalent with anti-vandal mechanism to thwart the
unauthorized removal of the clips. The Supplier shall provide
PNR with the drawings of the rail fastening components
indicating the detailed measurements.
2.
2.1 PERFORMANCE
2.2
Table 1
198
Lower Flange : Upper Flange
13.0 ton : 11.5 ton
Span : 700 mm
The shape and dimensions of the sleepers shall conform to the drawing
unless otherwise specified in this standard. However, dimensions
shown in the drawings shall be used as standard if the tolerance are not
specifically indicated.
4. QUALITY
4.1 Cement
4.2 Aggregate
4.3 Strength
Steel material for prestressed concrete shall be indented steel wire. The
steel wire for prestressed concrete shall conform to JIS G 3532
(Uncoated Stress – Relieved Steel Wire and Standard Wire for
Prestressed Concrete) or equivalent and this material shall be used after
being cold drawn, bluing in the final process for stress relieving. The
quality of the wire shall meet the requirements shown in Table 2. The
deformed steel standard wire for the prestressed concrete sleepers shall
be capable to provide sufficient bonding performance and fatigue
strength.
Table 2
199
3 – 2.90 36.61 Minimum Minimum Minimum Minimum
3,900 3,450 kg 3.5 3.5
6. STEEL WIRE
8. MANUFACTURING METHOD
200
8.5
Ends of strips of steel wire shall be cut – off to the same length
as the sleepers so as to prevent any projection of steel wire
beyond the ends of sleeper and shall be properly treated for
preventing corrosion.
9. TESTING
Table 3
201
9.2.3 Test for Guaranteed Pullout Strength and
Test for Pullout Breaking Strength of cast
shoulder.
10. INSPECTION
10.2 Acceptance
202
is found to be conforming to the test requirements for
guaranteed flexural strength and guaranteed pullout strength set
forth in Section 9.2, the specimen shall be deemed to have
successfully passed the test.
d. Marking
1.0 GENERAL
1.1
1.2
203
.
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
204
Spheroidal Graphite Iron Shoulder:
Carbon 3.1% – 4%
Silicon 1.8% – 3%
Phosphorus 0.05% maximum
Sulphides 0.02% maximum
Manganese 0.02% - 0.06%
Hardness 235 – 285 HB
Tensile Strength 650 – 850 mpa
Elongation 7% - 14.5%
Rail Clip:
Carbon 0.50% – 0.65%
Silicon 1.7% – 2.1%
Phosphorus 0.05% maximum
Sulphides 0.05% maximum
Manganese 0.70% - 1.0%
Hardness 44 – 48 HRC scale
Load Deflection 1250 kgf
Insulator:
Hardness ≥105 HRR
Shearing Test ≥4.5 kN
Resistivity ≥1 x 108 Ohms
Impact test 6 x without crack
Density Without air hole in section
Rail Pad:
Density ≥0.95gm per cu.m.
Hardness 45 – 70 SHORE D
Tensile Strength ≥ 25kN
Elongation at broken
point ≥180%
Melt flow index 5.2 – 2 dl/g
Volume resistivity ≥1x108 Ohms
1.11
1.12
The Supplier shall provide PNR with the drawings of the rail
fastening components indicating the detailed measurements.
1.13
205
be subject to return or disposal and replacement by the
Supplier.
2.0 TESTING
2.1
2.2
2.3
C. WOODEN SLEEPERS
1 QUALITY OF SLEEPERS
For specification for imported and local wooden sleepers see Drawings
206
c. Turnout laying shall comprise the installation of all components of the
turnout consisting of (frog), straight and curve leading portions,
movable portion including tongue rails, and guard rails assemblies.
Rail braces shall be either fixed or adjustable type or per standard
manufacture. Switch stand shall consist of switching assemblies with a
throwing lever, a connecting bar, a switch lock and a movable switch
sign, and shall be manually operated.
d. All tongue rails, frogs and guard rails shall be placed in accordance
with the drawings and track work plan approved by the Engineer.
G. THERMIT WELDING
207
5.4 PREPARATION AND HANDLING OF TRACK MATERIALS
5.4.1 PREPARATION
a. The Contractor shall obtain the approval of the Engineer on the track
work schedule including the force to be employed and the speed with
which the work will proceed. Prior to commencement of the work, the
Contractor shall notify the Engineer at least five working days in
advance so that adequate arrangements can be made by the Engineer
for the execution of the work.
c. No material shall be placed nor shall the track be laid on the subgrade
until the sub-grade has been constructed and finished true to the line
and planes according to the stakes set by the Contractor on the
completed subgrade as approved by the Engineer.
The Contractor shall take all precautions for the transport of track materials to
the site of work and shall coordinate fully with the Engineer in advance on the
locations and times of loading and unloading the track materials.
a. At the site, it is necessary to load or convey the rails by the rail carrier
with derrick crane. When handling rails by hand using rail tongs, no
attempt shall be made to throw the rails. Special care shall be taken in
handling the tongue rails of turnouts so as not to cause any damage
thereon.
b. Distribution of Rails
The Contractor shall distribute rails so that they can be laid without
unnecessary additional handling taking care of the following:
Place rails base down, parallel with the track and with sufficient bearing to
prevent bending or swinging.
To minimize the cutting of new full-length rails, short rails shall be distributed
in proper places to provide for proper spacing on the curved track and
locations for connections to switches.
208
c. Handling of Wooden Sleepers
(1) Any fabricating such as end trimming and, if required, adzing and
boring or application of anti-cracking devices shall be performed at
manufacturing plants of wood sleepers.
(2) As the turnout sleepers are not uniform in length, location of the switch
components cannot be predicted, and they shall not be adzed or bored in
advance.
e. Handling of Ballast
(1) The ballast shall be loaded and unloaded by the Contractor. Care shall
be taken not to destroy or disturb the grade stakes. The Contractor shall trim
the ballast to conform to the standard ballast cross section plans. Any surplus
ballast after trimming shall be disposed of as directed by the Engineer.
Care shall be taken in the transport, handling, placing, and tamping of ballast
beneath the sleepers so as to avoid chipping and cracking of the concrete
sleepers. Any sleeper which has been so damaged, and in the judgment of the
Engineer is unserviceable, shall be removed and replaced.
209
5.5 TRANSPORT AND STORAGE OF TRACK MATERIALS
a. The Contractor shall fully coordinate with the Engineer and obtain has
approval on locations, methods and times of storage of track materials.
c. Joint bars, track bolts, spring washers and track spikes and accessories of
turnouts shall be stored in the warehouses or sheds. If they are required to be
stored outdoors, appropriate protective measures shall be taken against
rainwater and other foreign matters that may cause any damage thereto.
f. Handling and transporting of concrete sleepers shall be done with utmost care
so as not to incur undue cracks and/or chipping at edges. Sleepers shall not be
unloaded by dropping or throwing unto rails, rocks or hard surfaces. Sleepers
shall be handled with tongs and not with bars or sharp tools to avoid any
damage. Any damaged sleeper resulting from mishandling shall be replaced.
g. In the case where the ballast is stored in the stockyard, the surface shall be
graded, and vegetation and rubbish shall be removed prior to the stacking of
ballast materials.
i. The Contractor shall be responsible for the security to prevent any Pilferage or
damage to the materials stored at the site.
210
5.6 USE OF TRACK MATERIALS
a. Use of Rails
Specified short rails on the ordinary fish plates joint should be used on the curved
track, in order to ensure even rail joints on both rails to connect with the turnouts.
Rails less than 5 meters in length shall not be used.
Rails to be used on sharp curves shall be bent prior to the laying work.
When short rails are used on the curved track, the arrangement of short rails shall be
approved by the Engineer in advance.
When available, the Contractor shall use a friction type rail saw for the cutting of
rails. The surface to be cut shall be square to the centerline of rail. No rail shall be cut
with gas torches under any circumstances.
When drilling a new bolt hole on the rail web as required to prepare the short rails, the
drilling shall be carried out in accordance with the standard drilling practices.
c. Laying of Sleepers
Concrete sleepers shall be laid only on track sections where specified or as directed by
the Engineer. Use of concrete sleepers under rail joints shall be avoided.
Sleepers shall be laid square to the rail on the straight track and concentrically on the
curved track in a uniform interval. Sleepers shall be laid at spacing as specified on the
drawings. The bottom of the rail, the rail pad and the rails seats shall be ensured that
all fastening components such as rail clips, ferrules, rail pads, etc. are complete and
properly installed.
The centerline of the sleeper length shall coincide with the centerline of track
alignment.
d. Laying of Rails
In laying the rails, the Contractor shall take the following precautions:
Use mechanical devices whenever possible and take utmost care to protect the
workers from possible hazards.
In laying second hand rails, care shall be exercised to prevent a gap of more than
2mm and to align the rail within allowable gauge tolerance.
211
Gauging of the track shall be carried out at least every third sleeper when the second
line of rails is laid against the requisite track gauge plus required slack on the curved
track.
300 m - 0
300 – 175 m - 8 mm
<175 m - 15 mm
C = 8.40 V2/R
Cmax = 90 mm
Joints in the opposite rails shall be located evenly unless otherwise directed by the
Engineer. In laying the rails on curves, care shall be taken to place the short rails on
the location of inside rails so as to maintain even rail joints throughout the curves.
Rail joints on prestressed concrete sections shall be of the supported type and rail
joints on wooden sections shall be of the suspended type.
Rail joints shall be provided at locations remote from road crossings, at least 5 m
before crossing.
Provision of space allowance for expansion of rails shall follow the criteria to be
made by the Engineer. Approved expansion shims of metal or fibre shall be used to
provide for the proper space allowance between adjacent rail ends, and a rail
thermometer shall be used to determine the proper thickness of shims to be inserted in
accordance with rail temperature. After laying the rails and setting up rail joints, all
records of expansion spaces set up on the rack shall be submitted to the Engineers for
review and approval.
Contact surfaces between the rails and joint bars shall be greased, and those between
joint bars and track bolts and on the threads of track bolts shall be lubricated just
before laying the rails.
All rail joints shall be firmly bolted and fitted with approved spring washers. All bolts
shall be tightened to the following torque before track is turned over to train
operation:
212
2,000 kg-cm (73 lb. rails)
Bolts shall be tightened in the proper sequence to seat joints, beginning at the center
of the joint and working both ways to the ends of the joint. When bolts are tightened,
the surfaces of rail heads and gauge line of both rails shall be set coinciding with one
another.
f. Track Spikes
Two (2) track spikes shall be used for fastening the rail to the sleeper. The existing
sleepers of insufficient bearing for the track spikes shall be reworked and the holes
shall be plugged with wooden inserts. Track spikes shall be provided as shown in the
drawings.
g. Screw Spikes
Four (4) screw spikes shall be used for fastening rails to bridge sleepers.
213
5.7 WELDING OF RAILS
A field inspection shall be made on rails in service, and all rails containing severe
engine drive burns, anchor nicks, excessive wear on the rail base or other visible flaws
shall be rejected for welding. It is recommended that the rail selected for welding be
picked up in such a manner that the rail wear pattern in the continuous welded rail
(CWR) string will remain approximately the same as it was in original service. One
method to keep the rails in an orderly manner with respect to their wear pattern is to
mark the north or west rail 2-4-6 etc.
Remove jointed rail in sections 60 meter long, then the joint bars are removed. Joint
bars, bolts and washers may be salvaged as repair material or the rail may be cropped
as a unit. The rail is carefully inspected after cropping, and rail not suitable for
welding is removed. Some engine drive burns may be oxyacetylene welded to
upgrade the rail.
When the rail arrives at the welding site, a qualified rail inspector shall carefully
inspect the rail for head wear, corrosion, base wear, sweeps, kinks or any other defect
that may have escaped detection in the previous inspection. Rail for each CWR string
must be matched to have the same height and width within 1.6 mm (1/16 in.).
The Contractor has the option for any methodology to achieve efficient welding
operation while continuing to maintain rail traffic, subject however to the approval of
the Engineer. The Engineer will not allow the use of a Holland-in-Track flash butt
welder.
It is recommended that the rail be stored straight and level on a firm base and each tier
stripped in four places.
(2) Excess oils, grease, tars, etc., must be removed from the rail before welding.
(3) Maximum head flow should be 6.4mm (1/4 in.) on each side of the rail if
shears are used to remove the upset metal.
(4) Grade crossing rails must be free of corrosion or rejected for welding except
for yards or similar tracks.
(6) After cropping, both ends of the rail should be inspected for piped condition.
214
Main Line use – Very
Class 1
3.2 mm.(1/8 in.) 3.2 mm.(1/8 in.) minor engine burns and
37 kg, 65 Lb
corrugation
Branch Lines – Small
Class II
6.4 mm.(1/4 in.) 4.8 mm.(3/16 in.) engine burns and
37 kg, 65 Lb
corrugation
Light Branches Lines–
Class II Medium Engine burns and
6.4 mm.(1/4 in.) 4.8 mm.(3/16 in.)
37 kg, 65 Lb corrugations, may be pitted
and show some oxidation
Class IV Yards – Any burns not
9.5 mm.(3/8 in.) 9.5 mm(3/8 in.)
37 kg, 65 Lb mashed or fractured
b. Thermit Welding
(1) Moisture and all foreign substances as dirt, grease, loose oxide, slag, etc.,
should be removed from the weld area.
(2) Rail ends should be aligned properly. Proper joint gap and lateral and vertical
positioning of the ends is imperative.
(3) Mold should be applied in exact location over rail gap and properly sealed.
(4) Detailed manufacturer‟s instructions for the specific thermit process being
used should be followed without deviation.
(5) It is assumed that flotation of impurities in the crucible and the mold, and
proper gating and feeding, are provided for in the equipment and instruction supplied
with the thermit package.
(6) The luting or sealing of the molds to the rail should be performed with care so
that the luting material is not introduced into the weld chamber. It has been found
practical to use sand mixed with bentonite in proper proportions with a minimum of
moisture in the mixture as a luting material.
(7) Molds and charges for excessive lengths of time may absorb detrimental
moisture. Manufacturer should be consulted for maximum recommended shelf life
and charges stored beyond that time should not be used. Molds should be stored in
such a manner and environment as to prevent moisture contamination. Care should be
taken when transporting from storage to the work site to protect charges and molds
from the elements.
(8) The crucible or reaction chamber must be made and kept dry and clean at all
times.
(9) Partial welding portions should never be used because of the possibility of
material segregation and the need for proper metal supply to the weld. Two weld
charges should never be mixed.
215
(10) It is recommended that welding not be performed during precipitation of any
kind unless adequate precautions are taken to completely protect the crucible, mold,
and adjacent rail from moisture.
(11) If temperature conditions are such that rapid contraction or expansion of rail is
taking place, welding should be avoided unless a rail puller/expander is used to
maintain the gap spacing and hold the rails in position until the weld metal is below
371 deg. C (700 deg. F).
(12) If compromise welds are being made, only molds and charges designed for the
specific transition in rail size shall be used.
(13) In the case of the processes in which the filler material is tapped manually, the
metal shall not be tapped until the reaction is completed and the slag has separated
from the filler material.
(14) The period of time immediately following the pouring of the metal is critical
to production of a good weld. During the first three minutes the rail should not be
disturbed in any manner. After that, at a time recommended by the manufacturer of
the charge used, the slag basin and mold may be removed, and the excess Ballast shall
be well packed with metal removed. If chisel cutting is performed, the rail must be
adequately supported; however, it is recommended that excess metal be removed by
shearing. Finish grinding the contours should be performed only after weld metal has
cooled below 316 deg. C (600 deg. F).
(16) If strap bars are used on the joint after welding, only bars designed with proper
clearance of cast-on fins should be used.
216
5.8 TRACK LAYING
a. Once the formation is ready for track laying, ballast shall be unloaded and
spread to a design of 200 mm after which it shall be rolled.
c. Parts which shall be welded into 60 meter panels shall be laid on top of the
sleepers and later fastened to the sleeper with slips. Rails shall be fasten
temporarily together using fish plates and bolts.
d. More ballast shall be unloaded and evenly spread using a ballast regulator.
e. A tamping machine shall tamp the ballast and align and level the tracks.
f. More ballast shall be unloaded and spread by the ballast regulator where it is
needed.
g. The tamping machine shall make another pass over the track to further tamp,
align and level the tracks.
i. Final tamping, aligning and leveling of the tracks to the final grade shall be
undertaken after which ballast is trimmed to conform to the standard ballast
section in the drawings. The Contractor shall dispose of any surplus ballast
after trimming as directed by the Engineers.
j. The rails shall be welded into 120 m panelafter removing the fish plates.
Various track materials derived as the consequence of the work shall be properly
stored in the location as directed by the Engineer for which proper inventories shall be
made and kept until proper turnover of such materials has been made to PNR.
After track laying, the overall conditioning of the tracks shall be carried out to finish
the track construction by overall tamping and trimming of ballast in accordance with
the specified alignment, cross-sections, grade based on grade stakes, super elevation,
track gauge and slack.
217
5.11 TOLERANCE OF TRACK CONSTRUCTION WORK AND TRACK
REHABILITATION WORK
Excessive values are expressed with (+) sign, while values in shortage are
expressed with (-) sign.
The left hand side rail on the straight track and the inner rail on the curved
track are used as the base of leveling; a (+) sign expenses the higher and a (-)
sign expenses the lower irregularities of the opposite rail.
5.11.3 ALIGNMENT
5.11.5 MEASUREMENT
218
The tolerance of newly constructed tracks and rehabilitated tracks at the time
of inspection to be conducted prior to the actual operation are shown as
follows:
TRACK TOLERANCES
Allowable Track Tolerance
Wearing Items Main Track Side Track
Track Gauge +4 to -3 +2 to -4
Cross Level 4 5
Longitudinal Level 5 6
Alignment 4 5
Deviation of Sleeper
+20 to -20 -
Spacingfrom the Standards
Track Gauge at Frog Portion +2 to -2 -
219
5.12 TRIAL TRAIN OPERATION ON NEWLY CONSTRUCTED AND
REHABILITATED TRACKS
In the case where trial operation is carried out on the newly constructedtracks, the
operation shall be performed by assigning a person responsible for the operation
under the following guidelines:
a. Prior to the trial run, track irregularities under various items as specified
elsewhere shall be measured by the Contractor, and the records of the result
shall be submitted by the Contractor to the Engineer for review.
b. Prior to the trial run, instruments to measure the settlement of track thereof
shall be installed by the Contractor according to the instructions given by the
Engineer, and their installations shall be examined by the Engineer for
approval.
c. Upon the trial run, the Contractor shall measure the settlement of track by the
aforementioned instruments installed. The records of the result shall be
submitted to the Engineer again for review.
d. After the trial run has been conducted, the Contractor shall carry out the track
conditioning again only at such locations instructed by the engineer as the
results of the trial run, the second trial run shall be carried out and the records
of second measurements shall be submitted to the Engineer again for review.
220
5.13 ADJUSTMENT FOLLOWING RELAYING OF PERMANENT WAYS
a. Final adjustment of permanent ways will be performed after all the ballast has
been placed. Any loose sleepers or low spots which develop under traffic will
be tightened, and final re-alignment will be performed at this stage using the
on-track tamping machine. The track shall be left in a first class condition for
the PNR to take over.
The condition of the track shall be inspected using the Standard Values (See TS-5-
51), and the Contractor‟s record of his finished work turned over to PNR.b.
c. After the final inspection has been performed and there should the be any need
to make adjustments to the tracks, tighten any fastenings, or pack any loose
sleepers, etc., the Contractor shall be required to make the necessary
adjustments within thirty (30) days
d. The newly laid track shall be thoroughly inspected by the Contractor using
roving patrols, to insure that there is no pilferage of materials, and that the
track is in as good a condition as possible.
Allowable tolerance for final inspection stipulated herein, for deficiencies discovered
within 30 days after test runs have been made, are as follows:
221
5.14 MEASUREMENT AND PAYMENT
5.14.1.1
5.14.1.2
5.14.1.3
5.14.1.4
5.14.1.5
5.14.1.6
222
5.14.1.7 Basis of Payment
223
PART 6
MISCELLANEOUS WORKS
6.1 FENCING
6.1.1 SCOPE
This work shall consist of furnishing and constructing concrete pile and
concrete panel for fencing in accordance with the details, and at the locations,
shown on the Drawings or as required by the Engineer.
6.1.2.1 Concrete
Concrete pile and concrete panel shall be made of Class “B” Concrete,
in accordance with Section 4.1, Concrete Works. The concrete pile
posts shall be cast to the length shown on the detailed Drawings, and
shall have a smooth surface finish. Concrete panel shall be cast to the
sections or dimensions shown on the detailed Drawings and shall have
a smooth surface finish.
6.1.2.2
The contractor shall perform such clearing and grubbing as may be necessary
to construct the fence to the required grade and alignment. Fence shall
generally follow the contour of the ground. Grading shall be performed where
necessary to provide a neat appearance.
6.1.3.1
6.1.3.2
224
6.2 CEMENT MORTAR
6.2.1 SCOPE
a. General
This work shall consist of preparing and furnishing mortar in accordance with
these Specifications for masonry and for any other incidental work. The work
under this section shall also be in accordance with Section 4.1 – Concrete
Works for Structures.
b. Composition
6.2.2 MATERIALS
Hydrated lime shall meet the requirements for residue, popping and pitting,
and water retention shown for type N lime in ASTM C207.
All the materials except the water shall be mixed, either in a tight box or in an
approved mortar mixer, until the mixture assumes a uniform color, after which
the water shall be added and the mixing continued.
Mortar shall be mixed only in those quantities required for immediate use.
Mortar that is not used within 45 minutes after the water has been added shall
be discarded.
225
6.3 STONE MASONRY
6.3.1 SCOPE
This work shall consist of stone masonry in minor structures, slope protection
around the drainage structures, in the retaining walls, and in other places
where called for on the drawings or ordered in writing by the Engineer. The
masonry shall be constructed on the prepared foundation bed in accordance
with these Specifications and the specifications for other work items involved
and in conformity with the lines, grades, sections, and dimensions shown on
the drawings or required by the Engineer.
6.3.2 MATERIALS
a. Stone
The stone shall be clean, hard, and of a kind known to be durable, and shall be
subject to the Engineer‟s approval. Adobe blocks shall not be used unless
otherwise specified.
Unless other sizes are shown on the drawings, stones shall have thicknesses of
not less than 15 cm, widths of not less than one and one half times their
respective thicknesses, and lengths of not less than one and one half times
their respective widths.
Each stone shall be of good shape and free of depressions and projections that
might weaken or prevent it from being properly bedded.
The stone shall be dressed to remove any thin or weak portions. Face stones
shall be dressed to provide bed and joint lines that do not vary more than 2 cm
from true lines and to ensure the meeting of bed and joint lines without the
rounding of the corners of the stones in excess of 3 cm in radius. Bed surfaces
of face stones shall be approximately normal to the faces of the stones for
about 8 cm and from this point may depart from a normal plane not to exceed
5 cm in 30 cm.
Face stones shall be pitched to line along all beds and joints. The maximum
projections of rock faces beyond pitch lines shall not be more than 5 cm.
b. Mortar
When the masonry is to be placed on a prepared foundation bed, the bed shall
firm and normal to, or in steps normal to, the face of the wall, and shall have
been approved by the Engineer before any stone is placed.
226
Care shall be taken to prevent the bunching of small stones or stones of the
same size. Large stones shall be used in the corners.
All stones shall be cleaned thoroughly and wetted immediately before being
set, and the bed which is to receive them shall be cleaned and moistened
before the mortar is spread. They shall be laid with their longest faces
horizontal in full beds of mortar, and joints shall be flushed with mortar.
The exposed faces of individual stones shall be parallel to the faces of the
walls in which the stones are set.
The stones shall be so handled as not jar or displace the stones already set.
Suitable equipment shall be provided for setting stones larger than those that
can be handled by two men. The rolling or turning of stones on the walls will
not be permitted. If a stone is loosened after the mortar has taken initial set, it
shall be removed, the mortar cleaned off, and the stone relaid with fresh
mortar.
Bed for face stones may vary from 2 cm to 5 cm in thickness. They shall not
extend in an unbroken line through more than five stones. Joints may vary
from 2 cm to 5 cm in thickness. They shall not extend in an unbroken line
through more than two stones. They may be at angles with the vertical from 0
to 45. Face stone shall bond at least 15 cm longitudinally and 5 cm vertically.
At no place shall corners of four stones be adjacent to each other.
Cross beds for vertical faced walls shall be level, and for battered walls may
vary from level to normal to the batter line of the face of the wall.
c. Headers
d. Backing
e. Pointing
Both bed and vertical joints shall be finished as shown on the drawings or as
directed by the Engineer. The mortar in joints on top surfaces shall be
crowned slightly at the center of the masonry to provide drainage.
227
f. Coping
Copings, if called for, shall be as shown on the drawings. Where copings are
not called for, the top of the wall shall be finished with stones wide enough to
cover the top of the wall from 45 cm to 1 meter in length, and of random
heights, with a minimum height of 15 cm. Stone shall be laid in such a
manner that the top course is an integral part of the wall. The tops of the top
courses of stone shall be pitched to line in both vertical and horizontal planes.
g. Weep Holes
All walls and abutments shall be provided with weep holes. Unless otherwise
shown on the drawings or directed by the Engineer, the weep holes shall be
placed at the lowest points where free outlets can be obtained and shall be
spaced not more than 2 meters center to center.
Immediately after laid, and while the mortar is fresh, all fresh stones shall be
thoroughly cleaned of mortar stains and shall be kept clean until the work is
completed.
i. Curing
In hot or dry weather the masonry shall be satisfactorily protected from the
sun and shall be kept wet for a period of at least three days after completion.
228
6.4 DEMOLITION WORK
6.4.1 DESCRIPTION
This section shall be applied to the general demolition work of structures, such
as concrete, steel structure, timber and drainage and others to be executed
under the Contract
The demolition work shall be carried out by the approved method and
equipment such as concrete breaker, gascutter, hydraulic jack, compressed air
disconnector, or manpower but no blasting shall be used unless approved in
writing by the Engineer.
The Contractor shall demolish all the structural members above the formation
level, on which the subsequent and permanent works under this Contract will
be constructed. To this end, the temporary work such as excavation shall be
conducted by the Contractor.
The Contractor shall, prior to the dismantling work of any steel members
classified as reusable, submit his scheme or method of operation in
disconnecting any members of the steel structures for the approval of the
Engineer.
The Contractor shall not be allowed to cut the steel members by gas cutter but
to disconnect the bolts, or rivets with due care thereby avoiding any damage to
the steel parts. If any difficulty in disconnecting the steel members are
encountered, the Contractor shall coordinate with the Engineer about his
methodology before any dismantling activity is to be undertaken by him.
All the reusable steel structures, shall be after dismantling operation, sorted in
a proper manner, transported and unloaded with care to Caloocan stockyard
upon the instructions of the Engineer.
229
The Contractor shall be responsible for the dismantling of steel structures
classified as scrap and shall be removed from the site, transported and
unloaded at the Caloocan stockyard.
The Contractor will be allowed to cut the steel members considered as scrap,
to facilitate for the easy and convenient dismantling and transporting
operation.
Pavement and excessive earth in the area shown on the Drawing shall be
removed in a proper manner and method approved by the Engineer and
dumped at the disposal area designated by the Engineer.
The Contractor shall prior to the commencement of any work herein submit
his proposal of work method for the Engineer‟s approval, including temporary
works such as formwork, support, scaffolding, etc.
The Contractor shall perform the work described above, within and adjacent to
the railway, on the right-of-way as shown on the drawings or as directed by
the Engineer. All materials recovered from demolition shall remain the
property of the Employer unless specifically provided otherwise in the
Contract Documents except materials resulting from the demolition structures.
All designated salvageable material shall be removed, without unnecessary
damage, in sections or pieces which may be readily transported, and shall be
stored by the Contractor at specified places on the project as directed by the
Engineer. Basements or cavities left by structure removal shall be filled with
acceptable material to the level of the surrounding ground.
230
PART 7
TRACK MATERIALS
1. GENERAL REQUIREMENTS
Prepared ballast shall furnished by the Contractor, and shall be crushed stone
composed of hard stone and durable particles free from injurious amounts of
deleterious substances and conforming to the requirements of these specifications.
The type and sizes of prepared ballast shall be as shown in paragraph (3) below.
2. QUALITY REQUIREMENTS
3. GRADING REQUIREMENTS
The grading shall be determined by test with laboratory sieves having square openings
and conforming with the requirements as given below:
4. HANDLING OF BALLAST
In loading and unloading the ballast, the Contractor shall take precautions to prevent
intrusion of soil or dust into the ballast.
The ballast shall be unloaded by the Contractor. Care shall be taken not to destroy or
disturb the grade stakes. The contractor shall trim the ballast to conform to the
standard ballast cross section plans. Any surplus ballast after trimming shall be
disposed as directed by the Engineer.
231
SPECIFICATION FOR RAILS
(JISE 1101 or Equivalent)
1. SCOPE
This standard covers railway rails: 40 kg rail and 37 kg rails which are used for tracks
in general (hereinafter referred to as “the rail”).
2. CLASSIFICATION
Rails are classified into two classes according to their weights and existence or
absence of fish – bolt holes as shown in Table 1.
Table 1
3. MATERIAL
3.1 The chemical composition on the steel shall be with the limits in Table 2. It is
desired that the number of heats in which the carbon content exceeds the
average value shown in Table 2 will not be less than the half of the total
number of heats.
Table 2
Table 3
4. MANUFACTURING PROCESS
4.1 Steel ingot intended for the manufacturer of rails shall be produced either by a
pure oxygen converter or by a basic open hearth furnace.
232
4.2 The ingot shall not be solidified while it is tumbled or shall not be rolled
before its complete solidification.
4.3 The end of the steel ingot shall be discarded by sufficient lengths to ensure
freedom from interior defects.
4.4 The rail shall be treated properly so that no shatter crack may be present.
4.5 It is desired that the rail‟s camber after rolling and cooling will be as little as
possible and that at both ends the rail will not deviate downward.
4.6 When the rail‟s camber is straightened no such force as may possible have a
bad effect on the material shall be exerted.
4.7 The both ends of rail shall be cut at a right angle to the lengthwise direction
and the burrs made at the cut end shall be removed.
5. SECTION
5.1 The section and dimension of a rail shall conform to the attached drawing.
Table 4
233
6.1 The rail shall be of uniform shape through the entire length, shall be kept
straight without any unnatural deformation and shall be free from any harmful
twist.
6.2 The rail shall not have any such defects as harmful crack and flaw on its
surface.
6.3 In the cross-section of rail and in the inside surface of fish-bolt hole, there
shall not exist any internal defects such as the harmful pipe and the
segregation of impurities.
6.4 Fish-bolt holes shall be drilled accurately and smoothly in the web at both
ends of rail as shown in the attached drawing.
6.5 The rail with fish-bolt holes shall be chamfered around rail head and upper
fillet at the periphery of fish-bolt hole shown in the attached drawing.
7.1
The tools to be used to inspect the shape and dimensions shall be those designated or
approved by PNR.
7.2.2 The method of analysis shall conform to the following and the result of
analysis shall conform to the provisions specified in Table 2.
JIS G 1211 (General rules concerning the method of iron and steel analysis)
JIS G 1211 (Method of carbon analysis of iron and steel)
JIS G 1212 (Method of silicon analysis of iron and steel)
JIS G 1213 (Method of manganese analysis of iron and steel)
JIS G 1214 (Method of phosphor analysis of iron and steel)
JIS G 1215 (Method of sulphur analysis of iron and steel)
JIS G 1202 (General rules concerning the method of emission-spectroscopic
analysis of iron and steel)
JIS G 1252 (Method of emission-spectroscopic analysis of carbon steel and low
alloy steel)
JIS G 1203 (General rules concerning the method of emission-spectroscopic
analysis of photoelectric-photometric system of iron and steel)
JIS G 1253 (Method of the emission-spectroscopic analysis of photoelectric-
photometric system of iron and steel)
234
Ingots obtained from the same heat shall be made one group and one tensile
test piece shall be taken from the rear end of the top-end crop of the rail rolled
from an ingot selected at random out of the group, as illustrated below:
b. When the test specimen breaks at a point more than ¼ of the gauge
length farther from the center between the datum marks and the result does not
conform to the provisions of Table 3, the test shall be considered null and void
and further test shall be conducted with respect to the rail from which the test
piece was taken in the beginning.
c. In case the test result conforms to the provision of Table 3, all the rails
that were rolled from the ingots of the group which the test piece represents
shall be accepted. In case the test result is unsatisfactory, the portions
corresponding to 300 kg of metal from the top end of rails represented by the
test piece shall be rejected and the rest shall be retested with the test piece
taken from the rear end of the rejected portion.
d. In case the result of re-test meets the provision, all the test of rails
rolled from the ingots which the test piece represents shall be accepted. In case
the result of re-test does not meet the provision, further test may be conducted
in accordance with item (3) above.
Ingots from the sane heat shall be made one group and one drop test piece
shall be taken from the rear end of the top end crop of the rail rolled from an
ingot selected at random out of the group other than those from which the
tensile test piece was taken. The test and inspection shall be conducted as
specified below.
a. For the drop test, the testing machine specified in the appendix to JIS E
1101 or equivalent “Ordinary Rail” shall be used.
b. The test piece shall be a 1.5 meter long cut from rail.
c. The test piece shall rest on the supports with head downward and the
test shall be conducted as specified in Table 5.
Table 5
Unit : Meter
235
d. The test piece shall neither break by a single blow nor shall show any
signs of defective abnormality.
e. The result of the test shall be treated as prescribed in 7.3 (3) and (4).
Ingots from the same heat shall be made one group and sulfur print test piece
be taken from the rear end of the top end crop of the rail rolled at random
from an ingot selected at random out of the group other than those from which
the tensile test piece or drop test piece was taken. The test and inspection shall
be conducted as specified below:
a. The test piece shall be a piece cut from the rear of 10mm or more in
length.
b. The testing surface of the test piece shall be made smooth and the
photographic printing paper previously impregnated with a 3% solution of
sulphuric acid for 5-10 minutes shall be tightly stuck to the surface for more
than two minutes, thus taking a print, and then the printing paper shall be fixed
and dried.
c. The result of the print shall be inspected on the basis of the limit
sample specified in the appendix and shall be treated as prescribed in (3) and
(4) of 7.3.
a. The appearance of the base, head, web and sectional surface of rail
shall be examined visually as a rule; provided that when there is doubt of an
abnormality, detecting tests shall be conducted.
8. MARKING
8.1 An arrow mark indicating the direction of the top end of the steel ingot, a mark
showing the type of rail, the manufacturing process, the name or brand of the
manufacturer and the month and the year of manufacture shall be embossed on
one side of the rail‟s web, following the example given below, clearly and
permanently enough to remain legible as long as the rail is in use.
Example:
236
37 A OH 2000 1111
On the other side of rail web, the serial number showing the order in which the rail
was rolled from an ingot, the mark showing the order of pouring of melt into mold,
the heat number, working gang identification and carbon contents shall be stamped at
a place which is not covered by the fish-plate in accordance with the following
example:
Example:
9. SUPERVISION OF MANUFACTURE
The manufacture of the rail shall be supervised and inspected by the manufacture
supervisor.
The supplier shall present a statement of results specified in 7.2, 7.3, 7.4 and 7.5 in
duplicate at the time of delivery.
Related Specifications:
237
SPECIFICATION FOR FISHPLATE FOR ANGLE BARS FOR 37A KG RAIL
(JIS E 1102 or equivalent)
1. SCOPE
This standard specifies fishplates to be used for rails of JIS E 1101, JIS E 1120, JIS E
1122 and JRS N.
2. TYPE
Table 1
Remarks: Fishplates of Class 1 are rolled but not heat-treated, while those of
class 2 are heat-treated (quenched and tempered) after rolling.
3. QUALITY
Table 2
Chemical Composition, %
Types
C Si Mn P S
0.35
Fishplates for 30 kg and 37 kg Rail
0.50
Fishplates for 40 kg N 50 kg and 0.40 0.40- 0.55- 0.040 0.054
50 kg N Rails 0.55 max. 1.00 max. max.
238
Table 3
Types Tensile strength
Kg/sq. mm Elongation, %
3.2.2 The hardness, tensile strength and elongation of class 2 fishplates shall
be as shown in Table 4.
Table 4
Surface
Tensile Strength, kg/sq. mm Elongation, %
Hardness
HB 262 – 331 70 min. 12 min.
a. A steel ingot from which shall be rolled only after it has completely solidified;
it shall not be removed to a length sufficient to eliminate any interior defects.
b. The steel ingot shall be rolled only after it has completely solidified; it shall
not be allowed to solidify in a sidewise position.
c. The ends of the steel ingot shall be removed to a length sufficient to eliminate
any interior defects.
4.2 Work Process – The work process for the fishplates shall be as follows:
a. Both ends of the fishplates shall be cut at right angles to the lengthwise
direction and the burrs on the cut ends shall be removed.
b. Fishbolt holes shall be bored and chamfered accurately and holes of fishplates
for 40 kg N and 50 kg N rails shall be chamfered as shown in the attached
figure.
4.3 Heat Treatment – Heat Treatment for Class 2 fishplates shall be conducted by
the following method:
239
a. The shapes and dimensions of the fishplates shall be as shown in the attached
figure.
Table 5
Unit. mm
Measured Place Tolerance
Length ±3
Thickness ±0.5
±1.0+1.0
Hole Diameter
-0.5-0.1
Intervals between holes ±1.0
Dimension of notches ±1.0
Position of notches ±1.5
Intervals between holes and notches ±1.5
Center Upwards ±1.5
Center Downwards +1.0
Camber
Center Outwards to rail 1.5
Center Inwards to rail 1.5
Fishplates for 30 kg, 37 kf, 50 kg ±2
Clearance between fishplate rails 1
and rail template Fishplates for 40 kg N, 50 kg N rails ±1.5
±0.5
6. APPEARANCE
a. All fishplates shall be free from such defects as harmful flaws, cracks and
twists.
b. No internal defects such as pipe marks shall exist in the cross-section of the
fishplates and in the inside surface of the fishbolt hole.
240
SPECIFICATION FOR TRACKBOLTS (FISHPLATE BOLTS)
(JIS E 1107 or equivalent)
1. SCOPE
The specification covers the bolt use for fishplates for 37 kg A rails.
2. MATERIALS
Materials to be used for bolts and nut shall be as specified in JIS C 2101 (Rolled Steel
for General Structures) particularly SS 41 and SS 50 (Steel Plates, Stripe, flat bars,
bars and shapes).
Shape and size shall be as indicated in the plan with an allowable error in size of bolts
and nuts as follows:
Length + 2 mm
Diameter + 1 mm - 0.5 mm
Threaded Length + 8 mm
Nut None
4. TESTS
4.1 Ultimate tensile stress for bolts and nuts shall be 41 to 52 kg/sq. mm with 20%
elongation.
4.2 Bead Test – shall not show any sign of fraction when cold bent around the bar
equal to the diameter until the sides are parallel.
5. APPEARANCES
The bolts and nuts shall be round, well finished, clean and free from defects of any
kind.
241
SPECIFICATION FOR SPRING WASHERS
(JIS E 1115 or equivalent)
1. SCOPE
This standard prescribes spring washers for fishbolts (hereinafter called washers) to
be used for rail joints of railroads.
2. KINDS
As shown in Table 1 below, washers shall be of two kinds according to shape and
size.
Table 1
---------------------------------------------------------------------------------------------------
Kinds : Uses
---------------------------------------------------------------------------------------------------
No. 1 : For 30 kg, 37 kg, 40 kg N and 50 kg N Rail uses
---------------------------------------------------------------------------------------------------
No. 2 : For 50 kg rail use
---------------------------------------------------------------------------------------------------
3. MATERIALS
Materials to be used for washers shall, as a general rule be of four, five or six kinds
specified in JIS G 3506.
4. MANUFACTURING METHOD
4.1 After forming wire rod into washers of free height about double its diameter,
they are subjected to heat treatment such as hardening and tempering.
4.2 Setting of washers shall be carried out by applying contact load once or over.
Shape, size and an allowable error in size of washers shall be indicated in the attached
figure and Table 2 below.
242
5.2 Standard dimensions of spring washer for 37 kg ASCE rails.
243
SPECIFICATION FOR TRACK SPIKES
(PNR SPECS)
1. MANUFACTURE
The steel shall be made by the Bessemer or by the open-hearth process, or by both,
having a dimension of 16 mm square by 114 mm length pf grade of steel to be in
accordance with JIS SS 41.
Bessemer Open-Hearth
b. Tension Tests
(1) The manufacturer may, at his option, substitute tension test for the chemical
analysis specified in Sec. 2.1 (1), in which case the finished spikes shall
conform to the following minimum requirements as to tensile properties.
(2) When this option is exercised, one tension shall be made from each 10-ton lot
or fraction thereof.
3.1 The body of the full-size finished spike shall bend cold through 180 degrees
flat on itself without cracking on the outside of the bent portion.
3.2 The head of the full-size finished spike shall bend backward to the line of the
face of the spike, without showing evidence of forging laps on the surface of
the bent portion.
3.3 On bend test of each kind shall be made from each lot of five tons or fraction
thereof.
244
SPECIFICATION FOR TURNOUT SLEEPERS FOR TURNOUT NO. 10 37 Kg Rails
1. SCOPE
This specification shall apply to wooden turnout sleepers (ties) for turnout No. 8 and
10 and diamond crossing sleepers. If imported wooden turnout and diamond sleepers,
the specification to be used shall be for imported wooden ordinary sleeper, except the
dimension. If the wood is purchased locally, such as Yakal, the specification to be
used shall be for local wooden ordinary sleepers, except the dimensions.
3.1 The timber shall be free from spongy or brittle wood. The ties shall be straight,
square edged and with edges parallel, free from box heart, decay or rot, bark,
sapwood, splits, shakes, hollows, unsound or hallow knots or injurious holes,
or other defects as may be reduce its life, strength and durability.
3.2 All switch ties and diamond crossing ties shall be well sawn on all sides and
cut parallel and square. Dressing with axe shall not be permitted.
3.3 A tie shall be considered not well sawn when its surfaces are not even.
3.4 A tie is not considered, not cut parallel if any difference in the thickness or
breadth exceeds 12 mm.
The sizes of ties shall be exactly as called for and with the following tolerances
allowed:
Depth - + 10 mm
Width - + 10 mm
Length - + 10 mm
245
SPECIFICATION FOR TURNOUT NO.10 37 KG RAIL
(JIS E 1303)
1. SCOPE
This standard specifies turnout No. 10 for 37 kg rails to be used on the PNR track.
2. COMPOSITION
Turnout shall consist of switches, Mn-crossing, guard rails other necessary rails,
special tie plates, switch stand, etc.
3.3 Tongue rails for switch shall be made from 37 kg rail and be hinged type. The
heels ends of tongue rails shall be so shaped as to ensure smooth connection
with lead rail.
Drawings.
4. DESIGN CONDITION
5. MATERIALS
5.1 Rails shall be made in accordance with the requirements specified by PNR,
and JIS, or equivalents.
5.2 Mn – crossing shall be made from high manganese cast steel (SCMn113).
Conform to specified in JIS G5131 as below.
246
P : 0.050 (%) max.
S : 0.035 (%) max.
Bolts and nuts for turnout shall be made in accordance with the
requirements of specification for track bolt & nut.
Tie plate, clip, slide plate and spike to be used for turnout shall be
made from first class quality steel with tensile strength of 37-48
kg/mm² in accordance with JIS G3101 or equivalent.
6. MANUFACTURE
Turnout shall be manufactured by first-class method and free from such injuries
defects as to affect the practical performance. The switch stands shall be pre-
assembled in the factory prior to the shipment. The manufacturer shall submit design
drawings and detailed specs to be approved by the Engineer.
7. INSPECTION
247
STANDARD SPECIFICATION FOR FUSHION WELDING OF RAILS BY
ALUMINO – THERMIC PROCESS,SKV – F Process
1. INTRODUCTION
1.2 The quantity of the „Mixture‟ required for welding one rail joint shall be called
a „Portion‟.
1.4 It is necessary to ensure that the „Portions‟ are prepared under proper quality
control and the execution of the sample welds is in strict conformity with the
practice approved by the (the Purchaser) for site welding of rails. No changes
in the analysis of the mixture, its acceptance tests and the methods of welding
shall be made without the consent of the Purchaser.
2. SCOPE
a. The technical requirements for the supply of the ‟Mixture‟ for the full fushion
method of welding of rails, and
2.2 The acceptance tests specified here are meant for fushion welding of flat
bottom steel rails32 kg ASCE, 37 kg ASCE.
3.2 Every „Portion‟ shall be sealed in a moisture proof container in such a manner
that no changes can be made to the „Portion‟ without damaging the container
or breaking its seal. The container shall indicate the batch number, the date of
manufacture, the section rail for which it is meant and the insignia of the firm.
4.1 The following tests shall be conducted for assessing the quality of the
„Portion‟.
a. Reaction tests;
248
b. Physical tests on test welds.
5. REACTION TESTS.
5.1 The reaction shall be allowed to take place in standard crucibles similar to
those used in site-welding. The alumino-thermic steel shall be poured in
standard moulds so as to obtain bars having a diameter between 25.0 and
35.0mm.
5.2 During the course of the thermic reaction, observations in regard to the
characteristics of the reaction i.e. whether it is quiet normal, vigorous or
boiling shall be made and recorded. The reaction shall at be vigorous or
boiling. The duration of the reaction shall normally be 20 seconds. A deviation
of 5 seconds may be permitted either way at the discretion of the Inspecting
Officer.
5.3 The sample of alumino-thermic steel obtained from above reaction, when
fractured, shall not show a mirror like structure or accretions. The fractured
surfaces shall show a fine grained structure.
5.4 A transverse section shall be cut from the middle third portion of the bar of
alumino-thermic steel obtained from reaction test as laid down in clause 5.1
Aluminum content of the steel shall be determined spectroscopically at two
points located at eh mid-radius of the cross section. The aluminium content so
determined shall not be less than 0.30% and shall not exceed 0.70%.
6. NUMBER OF REACTIONS
6.1 Reaction tests shall not be carried out on one “Portion” for every 250
“Portions” or partthereof of a batch. The frequency of the tests may be
decreased, by the Inspecting Officer or the Purchaser to a maximum of one
„Portion‟ for every 500 „Portions‟ of abatch, based on the past performance of
individual contractors supplying the Portions‟.
Tests welds shall be made either on new rails or on old but usable rails of
similar section and conforming to same specification. Two pieces of length not
less than 750mm required for the test weld shall be cut from the same rail. The
rail pieces can be obtained from PNR.
7.2 Spattering
No spattering of the fused „Mixture‟ shall be taken during the test that the
mould surface is free from moisture.
The excess of weld metal above the rail table and sides shall be chipped off in
red-hot condition and shall not show any hot shortness (i.e. brittleness of the
249
metal under red-hot condition, indicated in this case in the process of
chipping). The weld surface perfectly flat along-with the top table of parent
rail and shall not show any porosity or slag inclusions and other casting defect.
7.4.1 The Brinell Hardness survey shall be carried out on the welded zone,
heat affected zone and the un-affected portion of the rail on the top and
sides of the head of the test-weld using 3000 kg load and 10 mm
diameter ball for 10 seconds. The average hardness numbers
determined for the welded and the heat affected zones shall be not less
than 210 and not more than 250. This stipulation is based on the
assumption that the average hardness of the rail offered for welding is
about 230BHN. In cases where the hardness of the parent rail departs
considerably from this figure the average hardness numbers
determined for the welded and the heat affected zones shall not be less
than 20 points below and 20 points above respectively the harness of
the parent metal of the rail.
7.5.2 Test welds shall show before rupture a deflection of not less than 10
mm measured at the fracture.
7.5.3 If the fracture occurs far outside the weld, a slice may be out
transversely at the weld and etched in boiling 1:1 Hydrochloric acid to
determine the casting defects.
250
8.1 The test welds shall be made from one out of every 250 „Portions‟ or part
thereof of a batch. The frequency of the test may be decreased by the Engineer
or the Purchaser to a maximum of one every 500 „Portions‟ of a batch, based
on the past performance of individual contractors supplying the “Portions‟.
9. RETESTS
9.2 If the results of both these tests are satisfactory, the batch represented by the
„Portion‟ from which these welds were prepared may be accepted. If either or
both the tests show any of the above defects, the batch shall be rejected.
10.1 In the event of any sample „Portion‟ from a batch failing to comply with the
requirement ofClause 5.4 the supplier, if he desired so, may be permitted to
resubmit the batch after necessary reprocessing once only. The reprocessed
„Portions‟ shall be resubmitted under a separate batch and serial numbers.
11. ACCEPTANCE
11.1 Acceptance shall be done batch wise. Every individual batch that satisfies the
conditions prescribed in the specification shall be accepted after an
identification mark has been put on it by the Inspecting Officer.
12.1 The supplier shall at his own expense supply all labor and appliances for such
testing as may be carried out in the presence of the purchaser or the Engineer
in his own premises or at any other pace acceptable to the Purchaser in
accordance with this Specification.
13.1 Fusion welding of rails by this process shall be executed in accordance with
the best practice approved by the Purchaser. Only approved „Portions‟ shall be
used for the work.
13.2 Rail joints welded by a supplier shall be guaranteed by him against failure for
a period of two years from the date of making the welds or from the date such
welded joints are inserted in the track, in case the welding is done outside the
track. Any such welded joint, which fails by cracking within this period of
guarantee, shall be re-welded free of cost by the supplier.
251
13.3 One out of every 100 welded joints shall be picked up at random and subjected
to hardness and transverse tests as laid down in Clauses 7.4 and 7.5 shall
comply with the provisions laid therein.
13.3.1 In the event of any welded joint failing in any one or more
requirements of this specification, the Railways will be at liberty to
suspend forthwith further welding of joints. The work will remain
suspended until the supplier has improved his welding technique and
the Joints welded by him can stand up to the above tests. Further, the
period of guarantee vide Clause 13.2 above of the Joint already welded
shall be extend for a further period of one year and any such welded
joint which fails within this extended period of guarantee or shows
signs of failure by cracking shall be re-welded free of cost by the
supplier.
13.3.2 The welded joints with the extended period of guarantee shall be
marked „X‟ on the outer side of the head of the rail near the Joint in
addition to the markings prescribed in Clause 14. Such marked joints
shall be kept under careful observation by the Railway.
14. MARKINGS
14.1 All the welded Joint shall be distinctly stamped by the supplier in the
following manner:
The markings shall be on the outer side of the rail head within 150 mm from the
welded joints.
252
SPECIFICATIONS FOR WOODEN JOINT TIES
1.1 SCOPE
This specification covers the requirement for size, shape, quality, physical properties,
inspection, testing, marking and acceptance of joint wood sleepers from acceptable
species.
1.2 GENERAL
All ties shall be cut from mature, healthy live trees and shall be of the following
species:
I. LOCAL WOOD
a. Basilan – Yakal (H. Basilanica Foxw.)
b. Yakal – Kaliot (H. Malibato Foxw.)
c. Yakal – Magasusu (H. Mindanensis Foxw.)
d. Yakal – Saplungan (H. Plagata (Bico) Vid)
e. Yakal – (S. Astylosa Foxw.)
f. Yakal – Gisok (S. Gisok Foxw.)
g. Yakal – Mabolo (S. Ciliata King)
h. Yakal – Malibato (S. Malibato Foxw.)
i. Yakal – Yambak (S. Faloefereides Foxw.)
All imported timbers are to be merbau, yellow be merbau, yellow Balau, Selangan
Batu No. 1 or Chengal or equivalent imported hard wood that will comply with the
ranges of the mechanical and related properties of Philippine woods as stated in the
tabulation in this Technical Specifications.
RANGE: 45 species in Shorea group of this genus from Ceylon and India to
Malaya, Borneo, the Philippines and Moluccas. Sul (S. robusta) in Indian, Guijo (S.
guiso) in Philippine and Bangkirai (Shorea sp. Including S. laevis) in Borneo best
known in this group.
Large amount imported to Japan from Sabah and Sarawak mixed with Meranti. Logs
quite similar to Meranti and careful classification needed.
BARK: Similar to Seraya. Usually fibrous inner bark left on logs when
imported.
253
GRAIN: Interlocked.
1.2.1 The timber shall be free from spongy or brittle wood. Except, as otherwise
permitted in this specification, sleepers shall be straight, square edged, and with edges
parallel, free from boxed heart, decay or rot, bark, sapwood, splits, shakes, hollows,
unsound or hollow knots or injurious holes, scars or any other defects as may reduce
its life, strength and durability.
1.2.2 All sleepers shall be well sawn on all sides and cut parallel and square.
Dressing with axe shall not be permitted.
1.2.2.1 A Sleeper shall be considered not cut parallel if any difference in the thickness
and breadth exceeds 12 mm.
1.2.2.2 A sleeper is considered not cut parallel if any difference in the thickness and
breadth exceeds 12 mm.
1.2.2.3 If the sleeper is longer than specified, it should be reduced to the proper length
before it is offered for inspection.
1.3.1
Center or Boxed Heart of Presence of Pith will not be permitted. Sleepers with center
or boxed heart may, however, be accepted but only on molave species if the heart is
sound and tight.
(1) End Splits – Provided a split does not seem likely to extend and is not in the
direction of the spike position and the sleeper is not freshly sawn, a sleeper with this
defect may be accepted if the split does not exceed 150 mm in length and not more
than 1.5 mm in width.
(2) Cross Breaks – Sleepers with cross breaks are not acceptable.
(3) Surface Cracks – Sleepers sawn from sound timber with this defect may be
accepted provided the cracks are light.
(4) Sun or Seasoning Cracks – This is not easy to define. It may be taken to mean
a sleeper which is in existence for at least three months from the date of conversion
from the log. The color of freshly sawn sleepers is usually white and this provides an
indication of probable age. In deciding the age of sleeper, inspecting officers can take
other factors into account such as the time taken to reach the railway depot, period
held in storage at depot from local inquiry, etc. These would be permitted if they are
light.
(5) Miscellaneous Cracks and Splits – Ordinary cracks and splits may be
permitted if they are light.
254
1.3.3 Crook, Cup, Twist and Bow
1.3.4 Decay
Sleepers containing decay or rot in any form of degree will not be accepted.
1.3.5 Heart Defects – Sleepers with deep heart crack and winding heart crack are
not acceptable.
(1) Hollows – Hollows not more than 12 mm in diameter and less than 25 mm
deep and not exceeding three hollows per 300 mm length of the sleeper may be
permissible. No hollow shall be permitted between 450 mm and 750 mm from the
center of the sleeper.
(2) Knots – No sleeper will be accepted with large knots within the section lying
between 450 mm and 750 mm from the center of its length. Large knots are those
with diameter exceeding one – half of the width of the surface on which it appears.
No loose, hollow or unsound knots shall be permitted.
(3) Scars – Any small scar away from the rail seat will be permissible.
1.3.7 Sapwood
Presence of sapwood is permissible along one narrow surface of the sleepers only but
shall not exceed 12 mm thick. Sapwood is not permissible in general on undersize
sleepers.
1.3.8 Shakes
(1) Cup Shakes – These will not be permitted under the rail seat. Elsewhere it
may be permitted if less than 50 mm in width and not more than 300 mm from the end
of the sleeper.
1.4 SIZE
1.5.1
Sleepers shall be delivered and supplied at PNR station yard to be designated by the
Engineer.
255
1.5.2
The inspection of all sleepers will be made by the Engineer‟s Inspection Team and
those that conform to this specification and accepted shall be branded/stamped by the
Inspectors.
1.5.3
All sleepers offered for inspection must bear the Contractor‟s property mark, a
facsimile of which should be furnished to the Engineer who may direct the Contractor
to change it if considered not necessary. This facsimile shall be sleeper for identity of
the Supplier/Contractor.
All sleepers intended for inspection shall be spread with their heart side up in long
lines parallel with one another and supported with at least one support. Sleepers
spread on the ground will not be inspected.
All sleepers must be cleaned of mud and dirt before inspection. The ends must be
plastered at the time of inspection. Previously rejected sleepers should not be spread
for inspection without prior advice unless they are the subject of a complaint to a
higher authority in which case it will have the rejection mark of the Engineer‟s
inspection Team who originally rejected them.
Sleepers of a longer length than actually required should first be cut to desired length
before final/stamped accordingly by the Engineer‟s inspection Team unless sleeper is
thus cut.
Sleepers will be inspected one by one, each sleeper being turned round for inspection,
all sides and ends receiving individual inspection.
Contractor shall furnish all necessary labor to turn over all sleepers one by one for
inspection and branding/tamping by the Engineer‟s inspection Team. All accepted
sleepers will be stamped with big marking hammer at the middle top and clear faces
of the sleepers. Accepted sleepers shall be completely marked with the following:
(1) “M” if Molave, “Y” if Yacal and first letter for named of imported wood.
All accepted sleepers after being completely marked shall immediately be stockpiled
again in the same required manner.
256
The Contractor shall afford at his own expense all reasonable facilities to satisfy the
Engineer‟s Inspection Team that the sleepers are in accordance with these
specifications.
(1) Any fabricating such as end trimming and, if required, adzing and boring or
application of anti – cracking devices shall be performed at manufacturing plants of
wood sleepers.
Wooden sleepers shall not be unloaded by dropping or throwing them onto rails, rock
or hard surfaces. Sleepers shall be handled with tongs and not with bars or sharp tools
to avoid any damage.
The Contractor shall fully coordinate with the Engineer and obtain his approval on
locations, methods and times of storage of the wooden sleepers.
Stacks of sleepers shall be appropriately supported and likewise protected from sparks
or other fire hazards and undue damage.
When tested, imported hard wood shall meet the minimum ranges of Mechanical and
Related Properties of Philippine Woods shown on Figure 1 .
257
PART 8
DPWH STANDARDS FOR ASPHALT PAVEMENT OVERLAY AND PAVEMENT
MARKINGS
306.1 Description
306.2.2 Aggregate
1. New Aggregate
2. Salvaged Aggregate
Where aggregate required for the road mix surface course is already in
place, the Contractor shall not be responsible for its grading or quality
except for removal of oversize pieces. In general, salvaged aggregate
to be used for road mix surface course will consist of materials meeting
the requirements given in Item 703, Aggregates, for new aggregate or
may consist of selected granular material for other grading. Any
particles of salvaged aggregate appearing in the surface at the time of
lay-down and finishing that will not pass 37.5 mm (1-1/2 inch) sieve
shall be removed by the Contractor as directed by the Engineer.
258
The proportion of bituminous material on the basis of total dry aggregate, shall
be from 4.5 to 7.0 mass percent when cut-back asphalt is used and from 6.0 to
10.0 mass percent when emulsified asphalt is used. The exact percentage to be
used shall be fixed by the Engineer in accordance with the job-mix formula
and the other quality control requirements.
During the mixing operation, one-half to one (0.5 to 1.0) mass percent of
hydrated lime, dry aggregate basis, shall be added to the mixture. The lower
percentage limit is applicable to aggregates which are predominantly
calcareous.
259
1. Case 1 (New Aggregate)
When new aggregate is to be used for the road mix surface course, the
existing base shall be scarified lightly and bladed to uniform grade and
to the cross-section shown on the Plans and shall then be rolled or
watered and rolled, as directed. If so ordered by the Engineer,
depressions shall first be filled and weak portions of the base
strengthened with new aggregate.
When material in the existing road surface is to be used for mixing, the
surface shall be scarified lightly and bladed to uniform grade and to the
cross-section shown on the Plans. The reshaped surface shall then be
scarified again to the depth ordered by the Engineer and in such
manner as to leave a foundation of undisturbed material parallel, both
in profile and cross-section, to the proposed finished surface. The
loosened materials shall be bladed aside into a windrow at the side of
the road and the undisturbed material rolled or watered and rolled, as
directed.
In lieu of aerating and drying the aggregate, the Contractor may use an
approved additive, except where emulsified asphalt is used, which
shall be satisfactorily blended with the bituminous material. The
additive shall permit suitable coating of the wet aggregate and shall
prevent the bituminous coating from stripping in the presence of water.
260
The bituminous material shall be uniformly distributed in successive
application, in such amounts and at such intervals as directed. The
mixing equipment shall follow immediately behind the distributor,
after each application of bituminous material, to partially mix the
aggregate and the bituminous material.
306.3.6 Mixing
After the last application of bituminous material and partial mixing, the
entire mass of bituminous material and aggregate shall be windrowed
on the road surface and then mixed, by blading the mixture from side
to side of the road, or by manipulation producing equivalent results,
until all aggregate particles are coated with bituminous material and
the whole mass has a uniform color and the mixture is free from fat or
lean spots, or balls of uncoated particles. During the mixing operations,
care shall be taken to avoid cutting into the underlying course or
contaminating the mixture with earth or other extraneous matter. When
directed, the mixing process shall be confined to part of the width or
area of the road so as to allow traffic to pass.
After the material is spread, the surface shall be rolled. Rolling shall be
parallel to the road center line and shall commence at the outer edges
of the road, overlapping the shoulders and progressing towards the
center, overlapping on successive passes by at least one-half the width
261
of the roller, except that on superelevated curves, rolling shall progress
from the lower to the upper edge.
While the surface is being compacted and finished, the Contractor shall
trim the edges neatly to line.
Bituminous material and aggregate for Bituminous Road Mix Surface Course
will be measured by the tonne (t). The quantity to be paid for shall be the
number of tonnes of bituminous material and aggregate used and accepted in
the completed work. The weight of all moisture in the aggregate will be
deducted from the pay quantity.
Due to possible variations in the specific gravity of the aggregates, the tonnage
used may vary from the proposed quantities. No adjustment in contract unit
price will be made because of such variation.
262
Number Measurement
Aggregate for
306 (1) Bituminous Road Mix
Surface Course ton
Bituminous Material
306 (2) for Bituminous Road
Mix Surface Course ton
263
ITEM 606 – PAVEMENT MARKINGS
606.1 Description
This item shall consist of placing markings on the finished pavement. The
work shall include the furnishing of premixed reflectorized traffic paint or
reflectorized pavement marking paint conforming to the requirements of
AASHTO M 248, whichever is called for in the Contract, sampling and
packing, preparing the surface, and applying the paint to the pavement surface,
all in accordance with this Specification.
The paint shall be applied to the size, shape and location of the markings
shown on the Plans, or as required by the Engineer.
Premixed reflectorized traffic paint is a paint in which the glass beads are
mixed in the paint during the process of manufacture, so that upon application
and drying, the paint line is capable of retroreflection of the light beams.
Premixed reflectorized traffic paints which are available in both white and
yellow are paints that provide reflective marking for concrete, bituminous,
bricks or stone surface of highways, bridges, tunnels, streets, parking lots and
airports.
606.2.1 Classification
Type I – Alkyd
264
Resistance to Water – The dried paint film shall not show
blistering, peeling, wrinkling and discoloration when immersed
in water for 18 hours.
Minimum Maximum
Minutes - 40
Consistency (Kreb 65 95
Units) at 20 C
Requirements
Paint Composition
Type I Type II
Extenders, Percent by
265
weight, 13.0 - 13.0
White - 17.0 - 17.0
Yellow
Non-volatile Content
(based on the vehicle) 40 - 41 -
percent by weight
Quantity: The amount of glass beads to be mixed with the paint shall
be 500 grams per liter of paint.
Beads Diameter: The percentage of beads that will pass through the US
266
The painting of lane markers and traffic strips shall include the
cleaning of the pavement surfaces, the application, protection and
drying of the paint coatings, the protection of pedestrians, vehicular or
other traffic, the protection of all parts of the road structure and its
appurtenances against disfigurement by spatters, splashes or smirches
of paints or of paint materials, and the supplying of all tools, labor and
traffic paint necessary for the entire work.
The paint shall not be applied during rain or wet weather or when the
air is misty, or when in the opinion of the Engineer, conditions are
unfavorable for thework. Paint shall not be applied upon damp
pavement surfaces, or upon pavement which has absorbed heat
sufficient to cause the paint to blister and produce a porous film of
paint.
Traffic paint shall be applied to the pavement at the rate of 0.33 L /m2
and shall dry sufficiently to be free from cracking in from 15 to 30
minutes.
606.2.4 Sampling
The quantity of pavement markings to be paid for shall either be the length as
shown on the Plans of painted traffic line of the stated width or the area as
shown on the plans of symbols, lettering, hatchings, and the like, completed
267
and accepted. Separate items shall be provided for premixed reflectorized
traffic paint and reflectorized thermoplastic pavement markings.
Pay
Unit of
Item Description
Measurement
Number
606 (1) Pavement markings Square Meter
(Premixed
Reflectorized)
606 (2) Square Meter
Pavement markings
(Reflectorized
Thermoplastic)
268