INFORME LEVANTAMIENTO TOPOGRAFICO

PROYECTO:

“CONSTRUCCION DE CICLO VIA LA CA

Ç525

LLE BENJAMINVIZQUERRA, PJE. EL PARAISO, PROLONG. 1° DE MAYO, AV. RUSSVELT, ANTIGUA


CARRETERA PANAMERICANA NORTE DE CHANCAY DISTRITO CHANCAY - HUARAL - LIMA”.

CONSULTOR:

ING. ARTEAGA HERRERA, JANETT FRANCISCA


INGENIERO CIVIL
CIP. 111327

AGOSTO - 2016

ESTUDIOS DE INFRAESTRUCTURA SOCIAL


ÍNDICE

1. INTRODUCCIÓN ....................................................................................................................................... 3
2. NOMBRE DEL PROYECTO.......................................................................................................................... 3
3. UBICACIÓN DEL PROYECTO ...................................................................................................................... 3
4. DESCRIPCIÓN DEL PROYECTO .................................................................................................................. 4
5. OBJETIVOS DE LOS ESTUDIOS BÁSICOS ................................................................................................... 4
6. LEVANTAMIENTO TOPOGRÁFICO ............................................................................................................... 4
6.1 OBJETIVOS DEL LEVANTAMIENTO TOPOGRÁFICO ...................................................................................... 5
6.2 AREA DEL LEVANTAMIENTO Y ALCANCES .................................................................................................. 5
6.3 SISTEMA DE COORDENADAS ................................................................................................................... 6
6.4 POLIGONAL BÁSICA DE APOYO Y GEOREFERENCIACIÓN ........................................................................... 6
6.5 RELLENO TOPOGRÁFICO .......................................................................................................................... 7
6.6 TRABAJO DE GABINETE ............................................................................................................................ 8
6.7 PERSONAL Y EQUIPO ............................................................................................................................... 8
6.8 PLANOS DEL LEVANTAMIENTO TOPOGRÁFICO .......................................................................................... 9

ANEXOS

PANEL FOTOGRAFICO

REPORTE DE COORDENADAS

PLANOS TOPOGRÁFICOS

ESTUDIOS DE INFRAESTRUCTURA SOCIAL


“CONSTRUCCION DE CICLO VIA LA CALLE BENJAMINVIZQUERRA, PJE. EL PARAISO, PROLONG. 1° DE
MAYO, AV. RUSSVELT, ANTIGUA CARRETERA PANAMERICANA NORTE. DISTRITO CHANCAY - HUARAL -
LIMA”.

1. INTRODUCCIÓN
La Municipalidad Distrital de Chancay comprometida con su deber de velar por sus
ciudadanos, contribuye dentro del rol que le compete, con el reto de cambiar el ornato de la
ciudad y pista en valor de las propiedades, a través de la construcción e implementación de
CICLOVIA.
En este contexto, la actual gestión municipal preocupada por la situación de vulnerabilidad que
atraviesa un número considerable de pobladores limeños, que residen en zonas, ha planteado
la necesidad de planificar, formular y ejecutar
Los estudios básicos que se describen en la presente memoria descriptiva forman parte del
Plan de comienzo.

2. NOMBRE DEL PROYECTO


“CONSTRUCCION DE CICLO VIA LA CALLE BENJAMINVIZQUERRA, PJE. EL PARAISO, PROLONG. 1° DE
MAYO, AV. RUSSVELT, ANTIGUA CARRETERA PANAMERICANA NORTE DE CHANCAY DISTRITO CHANCAY -
HUARAL - LIMA”.

3. UBICACIÓN DEL PROYECTO


Distrito : Chancay
Provincia : Huaral
Departamento : Lima
El presente Proyecto se encuentra ubicado en la ANTIGUA CARRETERA PANAMERICANA NORTE
DE CHANCAY

ESTUDIOS DE INFRAESTRUCTURA SOCIAL


4. DESCRIPCIÓN DEL PROYECTO
Con la finalidad de mitigar el riesgo a la que se encuentran sometidas la población del lugar y
para mejorar las condiciones de TRANSITABILIDAD, el presente Proyecto consiste en la
elaboración de los estudios básicos para la construcción de CICLOVIA que faciliten el
desplazamiento DE CICLISTAS Y PEATONES.

5. OBJETIVOS DE LOS ESTUDIOS BÁSICOS


Los principales objetivos de los estudios básicos de Ingeniería como parte del Proyecto general,
son los que detallamos a continuación:

 Realizar los trabajos de campo para generar la base topográfica que servirá para el
desarrollo del estudio de Ingeniería del Proyecto.
 Establecer puntos de referencia para el replanteo durante la construcción.

6. LEVANTAMIENTO TOPOGRÁFICO
Para realizar las labores de topografía, se ha establecido un programa de trabajo cuya
metodología permitió obtener una adecuada información técnica, en tal sentido se ha logrado
el desarrollo de los trabajos de campo con un cronograma apropiado para inmediatamente con
el análisis competente procesar los trabajos en gabinete con prontitud y precisión que el caso
requiere.
Este proceso ha permitido finalmente la realización del presente estudio topográfico.

ESTUDIOS DE INFRAESTRUCTURA SOCIAL


6.1 OBJETIVOS DEL LEVANTAMIENTO TOPOGRÁFICO
Los trabajos topográficos se han realizado con el objeto de obtener información actualizada de
la zona del Proyecto, que permita desarrollar los diseños de las estructuras proyectadas para
facilitar mejores condiciones del acceso peatonal y reducir el riesgo por los peligros de
deslizamientos en las laderas de la zona.
Los trabajos de topografía, han permitido contar con alturas de niveles absolutas, basándonos
en métodos topográficos convencionales y utilizando los equipos de medición electrónica,
asimismo han permitido contar con la posición real de cada punto tomado en el sistema de
coordenadas planas y geodésicas.

6.2 AREA DE LEVANTAMIENTO Y ALCANCES


El área del levantamiento de este Proyecto comprende:

Vía Limites de Referencia


CALLE BENJAMIN VIZQUERRA Longitud de 950 ml aprox

PJE. EL PARAISO Cuadras 1


PROLONG. 1° DE MAYO Cuadras 7
AV. 1° DE MAYO Cuadra 1
AV. 1° DE MAYO Cuadra 2
AV. 1° DE MAYO Cuadra 3
AV. 1° DE MAYO Cuadra 4
AV. 1° DE MAYO Cuadra 5
AV. 1° DE MAYO Cuadra 6
AV. 1° DE MAYO Cuadra 7

ANTIGUA CARRETERA P.N. Hasta la nueva carretera panamericana norte

En lo posible se han identificado y levantado los límites de propiedad existentes para ser
compatibilizados con información oficial, sin embargo esto no ha sido posible en gran parte de
los casos debido a la irregularidad de las construcciones y linderos físicos que se encuentran
en el terreno.
Como parte de los levantamientos en campo se registraron las edificaciones existentes, muros,
calzadas, postes, buzones, escaleras y mobiliario urbano existente, interferencias que puedan
ser de interés para el Proyecto.
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
6.3 SISTEMA DE COORDENADAS
El sistema de coordenadas empleado para los trabajos de topografía está referido al Sistema de
Coordenadas UTM, (Universal Transversal Mercator), con el Datum WGS 84 Se determinó trabajar con
este sistema de coordenadas LA CALLE BENJAMINVIZQUERRA, PJE. EL PARAISO, PROLONG. 1° DE
MAYO, AV. RUSSVELT, ANTIGUA CARRETERA PANAMERICANA NORTE DE CHANCAY

CUADRO DE CONTROL DE BMS


PUNTO NORTE ESTE COTA DESCRIPCION
311 8721268.14 252299.221 48.015 BM1
360 8721223.96 252172.832 46 BM2
474 8721030.07 252232.035 44.835 BM3
559 8720830.68 252228.983 41.817 BM4
801 8720517 252223.089 39.637 BM5
916 8720363.62 252247.715 38 BM6
971 8720315.19 252270.649 37.443 BM7
1098 8720200.41 252338.4 36.047 BM8
1214 8720089.7 252406.132 34.592 BM9
1341 8719995.97 252462.12 33.87 BM10
1447 8719930.58 252485.855 33.14 BM11
1566 8719534.11 252511.627 27.12 BM12
1598 8719627.51 252507.131 27.656 BM13
1640 8718193.68 252629.637 27.285 BM14
1673 8719759.64 252500.592 29.017 BM15
1716 8719841.37 252496.357 31.196 BM16
1891 8718477.76 252625.324 22.92 BM17
1922 8718736.46 252607.1 22.099 BM18
1924 8718843.01 252598.555 22.714 BM19
2275 8718094.32 252738.256 28.627 BM20
2458 8717919.51 253184.012 26.289 BM21
2614 8717890.46 253338.933 25.598 BM22
2928 8717542.07 253763.344 23.244 BM23
3061 8717396.33 253864.075 23.415 BM24
3178 8717181.64 254143.839 24.792 BM25
4028 8717698.94 253640.555 23.412 BM26
4203 8717080.92 254384.048 25.48 BM27

CUADRO DE PUNTOS
PUNTO NORTE ESTE COTA DESCRIPCION
1 8722166.39 251962.263 52.255 NA

ESTUDIOS DE INFRAESTRUCTURA SOCIAL


2 8722159.98 251963.695 52.211 NA
3 8722158.9 251961.758 51.997 NA
4 8722156.68 251962.668 51.999 NA
5 8722155.87 251960.528 51.816 SAR
6 8722155.7 251958.519 51.37 P
7 8722146.67 251959.451 51.319 P
8 8722146.71 251975.367 52.56 NA
9 8722146.57 251976.407 52.563 NA
10 8722145.69 251975.025 52.507 SAR
11 8722145.7 251976.537 52.467 PAT
12 8722143.21 251959.721 51.439 LP
13 8722142.64 251979.571 52.493 SAR
14 8722141.94 251965.657 52.096 PISTA
15 8722140.68 251972.359 52.307 NA
16 8722140.25 251977.685 52.531 PAT
17 8722140.3 251980.91 52.624 NA
18 8722136.38 251981.451 52.554 NA
19 8722135.81 251979.575 52.498 SAR
20 8722135.49 251980.907 52.529 NA
21 8722132.05 251968.19 52.382 LP
22 8722130.92 251985.321 52.456 NA
23 8722129.09 251975.042 52.283 NA
24 8722127.51 251973.644 52.376 PAT
25 8722125.21 251983.025 52.275 R
26 8722123.89 251994.88 52.747 PISTA
27 8722121.61 251995.394 52.914 SAR
28 8722118.93 251982.379 52.295 R
29 8722118.34 251998.866 53.058 LP
30 8722118.34 252000.614 52.966 PISTA
31 8722113.62 251995.11 52.709 NA
32 8722113.45 251993.584 52.451 V
33 8722096.68 252000.488 52.671 NA
34 8722094.9 252003.2 52.641 NA
35 8722088.59 252003.871 52.61 NA
36 8722088.6 252027.847 53.355 V
37 8722087.86 252005.754 52.526 NA
38 8722082.26 252033.523 53.524 NA
39 8722081.29 252008.354 52.008 PAT
40 8722073.07 252011.833 52.547 NA
41 8722068.46 252012.762 52.442 NA
42 8722064.82 252015.299 52.552 NA
43 8722063.62 252014.664 52.539 NA
44 8722063.02 252014.46 52.533 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
45 8722060.46 252017.108 52.569 NA
46 8722057.46 252013.696 52.098 NA
47 8722057.09 252022.272 51.793 NA
48 8722054.61 252018.643 52.47 V
49 8722049.52 252024.355 51.681 NA
50 8722043.69 252013.947 51.483 NA
51 8722035.72 252029.532 51.494 NA
52 8722033.76 252026.249 51.437 NA
53 8722028.91 252033.661 51.65 NA
54 8722026.55 252028.279 51.342 NA
55 8722023.44 252032.803 51.293 NA
56 8722019.62 252029.786 51.242 NA
57 8722017.59 252022.567 51.524 NA
58 8722015.32 252035.259 51.221 AUX
59 8722010.53 252037.73 51.364 NA
60 8722008.53 252030.993 51.029 R
61 8722004.8 252024.091 51.205 NA
62 8722002.82 252022.609 51.2 NA
63 8722003.01 252040.177 51.438 POST
64 8722001.9 252035.68 51.006 NA
65 8721996.98 252024.212 51.069 NA
66 8721996.29 252026.548 51.114 NA
67 8721990.49 252045.592 51.272 LP
68 8721988.18 252040.282 50.848 R
69 8721986.1 252036.413 50.9 NA
70 8721985.17 252045.197 51.007 NA
71 8721984.01 252030.495 50.953 LP
72 8721982.43 252038.383 50.82 R
73 8721965.58 252050.22 50.932 NA
74 8721959.48 252055.599 51.108 NA
75 8721957.87 252049.557 50.664 R
76 8721953.32 252056.026 51.133 NA
77 8721951.1 252043.165 51.108 PAT
78 8721947.71 252041.946 50.952 LP
79 8721940.81 252046.401 50.777 PAT
80 8721929.51 252065.115 51.084 NA
81 8721927.57 252059.759 50.463 R
82 8721919.96 252051.054 50.796 LP
83 8721886.78 252079.154 50.411 NA
84 8721885.84 252073.911 50.326 R
85 8721881.45 252065.73 50.481 PAT
86 8721865.58 252073.45 50.332 R
87 8721864.2 252071.823 50.437 POST
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
88 8721851.07 252078.716 50.256 NA
89 8721845.06 252088.627 50.237 NA
90 8721836.4 252083.688 50.165 NA
91 8721833.16 252095.13 50.394 NA
92 8721832.16 252092.415 50.112 NA
93 8721823.69 252087.678 50.174 NA
94 8721819.85 252092.515 50.23 NA
95 8721817.01 252085.858 50.138 LP
96 8721814.94 252085.323 50.17 NA
97 8721813.84 252099.249 50.052 NA
98 8721811.49 252087.116 50.284 NA
99 8721810.1 252091.715 50.135 AUX
100 8721809.83 252088.048 50.245 NA
101 8721803.48 252102.039 49.969 NA
102 8721802.97 252102.455 49.982 NA
103 8721797.95 252093.9 50.205 PT
104 8721796.99 252095.689 50.033 NA
105 8721795.68 252100.023 50.055 NA
106 8721793.56 252104.759 49.928 NA
107 8721784.52 252112.329 50.122 LP
108 8721784.41 252111 50.151 NA
109 8721784.13 252110.95 50.105 LP
110 8721783.91 252107.336 49.855 NA
111 8721782.31 252104.314 50.008 NA
112 8721782.11 252097.304 50.001 NA
113 8721777.22 252103.438 49.962 NA
114 8721764.02 252105.417 49.888 PT
115 8721762.94 252116.615 49.963 NA
116 8721757.86 252110.545 49.964 NA
117 8721753.17 252116.307 50.219 NA
118 8721736.64 252127.769 50.071 LP
119 8721736.15 252126.493 49.955 NA
120 8721729.9 252116.814 49.939 PT
121 8721723.52 252124.494 49.817 R
122 8721710.62 252122.679 49.675 PAT
123 8721690.23 252144.925 50.087 LP
124 8721689.59 252143.373 49.752 PT
125 8721680.22 252133.06 49.555 PAT
126 8721674.97 252139.331 49.624 R
127 8721656.26 252141.976 49.438 PT
128 8721648.01 252144.464 49.28 PAT
129 8721639.46 252163.623 49.842 LP
130 8721638.91 252162.27 49.56 PT
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
131 8721626.84 252158.104 49.465 R
132 8721622.86 252166.3 49.274 NA
133 8721616.09 252156.518 49.464 PT
134 8721604.47 252168.104 49.228 NA
135 8721603.43 252173.555 49.185 NA
136 8721594.54 252171.585 49.174 NA
137 8721594.39 252171.902 49.189 R
138 8721593.54 252168.306 49.174 NA
139 8721591.53 252165.797 49.055 PAT
140 8721587.5 252181.723 49.307 PT
141 8721584.45 252168.507 48.966 PAT
142 8721582.22 252185.136 49.409 NA
143 8721582.03 252185.359 49.331 LP
144 8721578.34 252186.767 49.238 P
145 8721575.77 252182.557 48.937 NA
146 8721574.95 252177.422 49.047 NA
147 8721573.8 252169.159 49.025 P
148 8721566.58 252174.817 49.148 PAT
149 8721563.6 252187.588 49.223 NA
150 8721560.6 252183.424 49.252 NA
151 8721559.74 252180.013 49.175 NA
152 8721559.03 252193.911 49.184 NA
153 8721558.83 252193.748 48.837 NA
154 8721558.28 252191.514 49.145 NA
155 8721558.28 252191.581 48.699 NA
156 8721558.03 252194.201 48.718 NA
157 8721557.83 252194.371 49.184 NA
158 8721557.72 252191.77 48.697 NA
159 8721557.47 252191.893 49.161 NA
160 8721555.1 252175.956 49.229 LP
161 8721554.6 252181.011 49.119 CANAL
162 8721554.37 252180.959 48.711 NA
163 8721553.74 252181.294 48.673 NA
164 8721553.81 252185.844 49.486 R
165 8721553.65 252181.407 49.164 NA
166 8721553.36 252186.987 49.482 BZD
167 8721553.35 252186.908 49.465 R
168 8721553.1 252179.493 48.659 NA
169 8721553.05 252179.375 49.117 NA
170 8721552.89 252176.846 48.737 NA
171 8721552.82 252188.032 49.486 NA
172 8721552.46 252176.8 48.724 NA
173 8721552.24 252186.433 49.484 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
174 8721551.93 252178.994 48.574 NA
175 8721551.92 252178.986 49.133 NA
176 8721552.31 252194.396 49.418 NA
177 8721551.73 252179.945 48.727 NA
178 8721551.64 252178.69 48.602 NA
179 8721551.65 252180.026 49.137 NA
180 8721551.34 252179.632 48.671 NA
181 8721550.85 252183.273 49.301 NA
182 8721550.57 252178.424 48.899 NA
183 8721550.51 252178.601 48.494 NA
184 8721550.47 252179.56 48.939 NA
185 8721550.47 252179.359 48.623 NA
186 8721550.05 252177.567 49.359 NA
187 8721545.79 252188.927 49.18 NA
188 8721545.34 252185.544 49.168 NA
189 8721542.25 252200.184 49.4 LP
190 8721541.42 252198.352 49.346 NA
191 8721541.05 252185.643 49.012 AUX
192 8721540.65 252182.814 48.958 NA
193 8721540.54 252182.731 48.517 NA
194 8721540.33 252182.054 48.96 NA
195 8721540.29 252182.2 48.52 NA
196 8721539.99 252181.735 49.128 LP
197 8721539.87 252181.314 49.32 NA
198 8721539.75 252181.306 49.369 NA
199 8721538.12 252187.004 49.009 SAR
200 8721537.83 252191.986 48.986 NA
201 8721537.48 252183.845 49.052 NA
202 8721537.34 252183.804 48.477 NA
203 8721537.22 252183.195 49.043 NA
204 8721537.2 252183.303 48.494 NA
205 8721536.81 252182.4 49.327 P
206 8721531.96 252199.163 48.813 NA
207 8721531.73 252202.403 49.159 PT
208 8721530.85 252191.613 48.972 NA
209 8721525.56 252191.628 48.947 NA
210 8721524.82 252188.657 48.896 R
211 8721514.21 252204.407 48.754 NA
212 8721510.63 252193.865 48.852 CANAL
213 8721510.6 252193.7 48.357 NA
214 8721510.52 252193.161 48.357 NA
215 8721510.38 252193.221 48.877 NA
216 8721510.5 252199.101 48.868 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
217 8721510.42 252202.706 48.783 NA
218 8721500.78 252200.783 48.884 SAR
219 8721499.68 252198.07 48.854 SAR
220 8721499.66 252197.934 48.892 NA
221 8721499.6 252197.322 48.264 NA
222 8721499.59 252197.792 48.267 NA
223 8721499.5 252197.246 48.966 NA
224 8721499.31 252197.356 48.986 NA
225 8721499.11 252196.633 48.986 LP
226 8721495.24 252208.683 48.976 BZD
227 8721494.95 252208.9 48.952 NA
228 8721486.16 252216.743 48.591 NA
229 8721483.92 252205.577 48.628 PAT
230 8721482.34 252210.708 48.662 R
231 8721482.6 252222.529 48.978 LP
232 8721481.94 252220.864 48.776 PT
233 8721456.22 252216.1 48.677 PAT
234 8721454.23 252220.834 48.472 NA
235 8721452.8 252214.962 48.217 LP
236 8721451.7 252227.179 48.429 R
237 8721431.72 252239.461 48.424 PT
238 8721429.85 252242.46 48.595 LP
239 8721428.43 252233.299 48.532 R
240 8721428.2 252226.391 48.465 PAT
241 8721420.15 252236.288 48.577 BZD
242 8721420.18 252243.36 47.291 NA
243 8721420.2 252246.007 47.995 NA
244 8721419.94 252242.396 48.275 CANAL
245 8721419.43 252243.72 47.413 NA
246 8721418.94 252243.014 48.271 NA
247 8721417.03 252234.602 48.301 CANAL
248 8721415.68 252233.706 46.856 NA
249 8721415.41 252234.991 48.235 NA
250 8721412.56 252230.027 48.159 NA
251 8721400.06 252236.888 48.252 PT
252 8721399.94 252246.097 48.173 R
253 8721393.19 252256.117 48.458 LP
254 8721387.61 252255.916 48.132 PT
255 8721373 252247.24 48.341 PAT
256 8721371.32 252245.364 47.938 LP
257 8721365.16 252259.964 48.076 R
258 8721354.79 252270.642 48.558 LP
259 8721346.18 252263.576 48.166 BZD
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
260 8721345.73 252270.279 47.876 NA
261 8721345.58 252270.041 48.391 CANAL
262 8721345.45 252274.321 48.948 LP
263 8721344.36 252270.986 47.847 NA
264 8721344.08 252270.776 48.37 NA
265 8721343.06 252258.28 48.492 PAT
266 8721338.26 252260.501 48.344 NA
267 8721338.19 252260.54 47.71 NA
268 8721336.93 252261.206 47.617 NA
269 8721336.8 252261.334 48.356 NA
270 8721335.12 252259.123 47.641 NA
271 8721335.04 252259.169 48.431 NA
272 8721327.79 252275.469 48.148 NA
273 8721327.23 252269.032 48.184 NA
274 8721320.44 252269.146 48.12 R
275 8721317.85 252284.07 48.078 V
276 8721317.23 252282.239 48.108 NA
277 8721316.66 252280.828 48.064 NA
278 8721315.36 252269.026 48.183 PAT
279 8721312.95 252271.15 48.027 SAR
280 8721312.9 252269.431 48.198 PAT
281 8721312.03 252267.956 48.233 COLE
282 8721311.92 252283.575 48.129 NA
283 8721311.91 252283.576 48.129 A
284 8721308.41 252280.504 47.94 BZD
285 8721297.54 252288.996 48.057 NA
286 8721296.36 252288.517 47.924 SAR
287 8721296.42 252292.099 48.063 NA
288 8721296.35 252290.058 47.983 V
289 8721295.94 252277.947 47.972 SAR
290 8721294.76 252274.827 48.057 COLE
291 8721294.62 252276.94 47.948 V
292 8721293.54 252284.303 47.916 PISTA
293 8721291.96 252273.615 48.085 COLE
294 8721291.96 252273.616 48.085 NA
295 8721290.26 252294.507 48.035 LP
296 8721289.26 252292.731 48.06 NA
297 8721287.82 252291.722 47.902 SAR
298 8721287.74 252293.584 48.045 PT
299 8721284.91 252280.863 47.974 PAT
300 8721284.77 252282.399 47.88 SAR
301 8721284.62 252280.717 48.019 PAT
302 8721283.17 252279.4 48.059 COLE
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
303 8721283.53 252294.221 48.013 NA
304 8721275.57 252285.333 48.021 NA
305 8721271.65 252298.668 48.007 NA
306 8721270.9 252284.308 48.037 COLE
307 8721270.65 252287.893 48 SAR
308 8721270.15 252286.648 48.007 V
309 8721268.25 252283.151 48.036 NA
310 8721267.91 252287.543 47.797 V
311 8721268.14 252299.221 48.015 AUX
312 8721267.02 252303.28 48.004 LP
313 8721266.76 252296.086 47.874 BZD
314 8721266.34 252301.493 47.945 V
315 8721265.38 252280.225 47.965 NA
316 8721265.71 252300.032 47.835 SAR
317 8721265.03 252280.21 47.671 NA
318 8721262.04 252289.897 47.79 V
319 8721260.66 252291.784 47.944 NA
320 8721260.13 252290.653 47.94 NA
321 8721259.88 252288.589 48.019 LP
322 8721259.15 252290.682 48.05 PL
323 8721258.24 252280.789 47.828 PT
324 8721258.7 252297.755 47.843 NA
325 8721258.36 252292.107 48.05 NA
326 8721257.39 252260.045 47.633 PL
327 8721257.42 252306.825 47.972 LP
328 8721257.18 252304.874 47.893 V
329 8721256.57 252303.505 47.786 SAR
330 8721254.77 252293.478 48.062 NA
331 8721254.66 252305.137 47.963 NA
332 8721252.31 252255.792 47.235 BZD
333 8721251.31 252295.74 47.796 SAR
334 8721250.32 252294.561 47.927 V
335 8721249.09 252256.684 47.227 PL
336 8721247.99 252230.982 47.089 NA
337 8721247.92 252253.748 47.151 V
338 8721248.78 252293.092 48 LP
339 8721247.76 252257.119 47.361 NA
340 8721246.8 252232.481 47.101 PL
341 8721246.18 252228.601 47.04 V
342 8721246.67 252254.192 47.304 LP
343 8721245.21 252229.384 46.79 V
344 8721245.07 252225.753 47.011 NA
345 8721244.8 252222.613 46.984 COLE
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
346 8721243.84 252225.708 46.742 NA
347 8721243.98 252243.955 47.083 PT
348 8721244.06 252294.883 47.994 NA
349 8721240.87 252226.801 46.67 R
350 8721235.81 252204.499 46.77 PL
351 8721236.34 252224.499 46.68 NA
352 8721234.03 252198.752 46.657 NA
353 8721233.84 252199.711 46.369 V
354 8721230.62 252199.556 46.296 BZD
355 8721229.69 252206.89 46.455 PT
356 8721228.64 252207.561 46.492 LP
357 8721225.58 252176.66 46.153 PL
358 8721224.91 252171.681 46.066 COLE
359 8721225.22 252185.917 46.036 NA
360 8721223.96 252172.832 46 2
361 8721224.49 252193.757 46.344 PT
362 8721223.47 252172.113 45.758 V
363 8721223.16 252167.139 45.973 LP
364 8721222.26 252177.788 45.909 NA
365 8721221.79 252166.758 45.886 NA
366 8721221.69 252167.321 45.9 NA
367 8721219.57 252170.362 45.753 NA
368 8721218.86 252178.869 45.896 V
369 8721218.65 252178.848 46.021 SAR
370 8721218.18 252180.429 46.209 LP
371 8721217.63 252178.584 45.927 NA
372 8721217.16 252178.193 45.949 NA
373 8721215.42 252147.164 45.508 NA
374 8721215.08 252149.479 45.511 V
375 8721215.23 252168.876 45.722 NA
376 8721214.98 252170.349 45.79 NA
377 8721214.79 252167.854 45.872 NA
378 8721214.15 252169.953 45.734 PALM
379 8721213.54 252167.949 45.938 LP
380 8721213.08 252163.874 45.809 PL
381 8721211.31 252175.868 45.778 NA
382 8721210.84 252180.701 45.835 NA
383 8721208.75 252152.347 45.524 NA
384 8721207.79 252153.143 45.595 LP
385 8721207.8 252172.238 45.817 NA
386 8721206.73 252184.237 45.966 NA
387 8721206.11 252171.687 45.979 PL
388 8721204.32 252172.931 45.821 PT
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
389 8721203.6 252183.193 45.81 NA
390 8721202.04 252180.053 45.691 BZD
391 8721200.59 252174.636 45.687 NA
392 8721198.93 252183.573 46.043 NA
393 8721198.63 252180.124 45.67 NA
394 8721196.13 252185.618 45.7 NA
395 8721193.12 252177.109 45.608 NA
396 8721186.56 252177.147 45.855 LP
397 8721185.58 252179.637 45.578 NA
398 8721183.98 252185.2 45.534 NA
399 8721181.8 252192.541 45.735 NA
400 8721180.93 252190.555 45.499 NA
401 8721180.17 252192.014 45.69 PT
402 8721179.2 252193.386 45.697 LP
403 8721178.75 252192.17 45.657 NA
404 8721178.38 252181.964 45.564 NA
405 8721178.08 252181.106 45.753 PL
406 8721178.27 252190.781 45.457 SAR
407 8721177.43 252193.714 45.466 V
408 8721171.21 252184.518 45.449 NA
409 8721171.49 252195.912 45.618 LP
410 8721170.07 252194.797 45.514 NA
411 8721170.01 252194.303 45.58 NA
412 8721163.73 252186.948 45.453 NA
413 8721162.86 252196.584 45.51 NA
414 8721158.6 252188.322 45.531 PT
415 8721157.86 252186.808 45.641 NA
416 8721156.29 252189.546 45.337 NA
417 8721156.18 252198.713 45.453 NA
418 8721149.49 252200.906 45.417 NA
419 8721148.91 252191.89 45.361 NA
420 8721144.61 252204.777 45.554 NA
421 8721143.41 252193.797 45.378 NA
422 8721137.3 252195.782 45.333 NA
423 8721137.03 252196.518 45.264 SAR
424 8721136.22 252195.613 45.412 V
425 8721135.27 252194.496 45.516 P
426 8721132.1 252206.553 45.108 NA
427 8721131.85 252207.206 45.282 NA
428 8721131.71 252209.03 45.56 NA
429 8721131.4 252206.199 45.182 SAR
430 8721129.33 252196.446 45.24 NA
431 8721128.87 252198.111 45.387 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
432 8721128.38 252199.462 45.246 NA
433 8721128.12 252198.813 45.281 NA
434 8721125.49 252210.688 45.179 LP
435 8721125.42 252210.701 45.173 SAR
436 8721125.04 252211.185 45.315 NA
437 8721123.94 252211.491 45.438 LP
438 8721123.31 252210.028 45.312 V
439 8721122.89 252209.002 45.15 SAR
440 8721122.2 252210.09 45.415 PL
441 8721115.57 252212.078 45.237 NA
442 8721113.34 252209.262 45.168 BZD
443 8721107.97 252205.662 45.29 NA
444 8721103.74 252206.896 45.288 PT
445 8721101.24 252207.998 45.194 NA
446 8721094.51 252210.247 45.2 NA
447 8721094.43 252219.672 45.28 NA
448 8721094.05 252218.278 45.033 SAR
449 8721087.73 252212.518 45.132 NA
450 8721065.71 252233.036 45.203 NA
451 8721065.61 252230.574 45.127 LP
452 8721065.21 252232.456 45.186 NA
453 8721065.05 252229.331 45.092 PL
454 8721064.11 252232.999 45.143 V
455 8721062.74 252231.395 45.115 NA
456 8721061.97 252228.968 44.884 SAR
457 8721057.56 252223.309 44.914 NA
458 8721054.09 252227.506 44.87 BZD
459 8721052.98 252221.997 45.147 LP
460 8721052.94 252222.05 45.119 LP
461 8721051.74 252231.193 44.807 PT
462 8721051.4 252220.025 44.944 LP
463 8721051.44 252232.679 45.077 LP
464 8721047.84 252223.843 45.068 PT
465 8721045.5 252222.438 45.035 NA
466 8721043.64 252231.501 45.039 PL
467 8721040.55 252228.228 44.664 R
468 8721036.83 252224.568 44.876 V
469 8721035.56 252223.075 44.9 NA
470 8721034.43 252231.712 44.902 V
471 8721034.47 252233.325 44.974 LP
472 8721032.99 252224.346 44.833 NA
473 8721032.82 252224.807 44.488 V
474 8721030.07 252232.035 44.835 AUX
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
475 8721028.24 252223.554 44.734 LP
476 8721025.19 252233.577 44.74 LP
477 8721022.92 252229.146 44.372 NA
478 8721021.96 252232.197 44.638 NA
479 8721019.33 252225.607 44.551 V
480 8721018.35 252224.191 44.572 LP
481 8721012.18 252228.959 44.097 BZD
482 8721012.25 252232.736 44.422 PL
483 8721011.38 252233.936 44.401 LP
484 8721007.86 252229.978 44.006 NA
485 8720997.31 252225.685 44.023 LP
486 8720997.13 252226.756 44.015 PT
487 8720990.43 252230.156 43.604 R
488 8720984 252235 43.724 LP
489 8720982.75 252226.52 43.384 V
490 8720982.93 252234.615 43.668 LP
491 8720979.37 252225.139 43.63 LP
492 8720975.4 252225.189 43.34 LP
493 8720970.94 252234.615 43.379 PT
494 8720969.36 252230.559 43.149 BZD
495 8720966.61 252226.605 43.11 V
496 8720950.35 252236.029 43.054 PL
497 8720949.39 252227.075 42.787 NA
498 8720949.36 252227.073 42.787 V
499 8720949.45 252231.691 42.794 BZD
500 8720938.19 252226.896 42.969 PT
501 8720915.33 252232.193 42.677 R
502 8720905.49 252240.673 42.82 NA
503 8720904.63 252241.866 42.82 LP
504 8720903.53 252239.36 42.648 V
505 8720902.89 252241.681 42.817 V
506 8720902.38 252240.566 42.672 V
507 8720901.5 252228.088 42.692 PAT
508 8720901.43 252226.588 42.811 LP
509 8720897.65 252220.364 42.92 LP
510 8720897.02 252234.468 42.655 BZD
511 8720893.59 252241.446 42.565 V
512 8720893.1 252242.842 42.788 NA
513 8720883.66 252243.065 42.68 PL
514 8720881.43 252242.697 42.616 NA
515 8720881.36 252242.155 42.453 SAR
516 8720879.66 252218.36 42.563 LP
517 8720878.31 252232.211 42.39 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
518 8720872.23 252243.613 42.336 SAR
519 8720870.8 252232.783 42.321 NA
520 8720870.02 252228.517 42.325 R
521 8720869.91 252245.189 42.523 PT
522 8720869.44 252243.974 42.277 NA
523 8720866.98 252235.416 42.288 NA
524 8720864.9 252231.483 42.274 NA
525 8720861.93 252224.128 42.263 NA
526 8720861.66 252245.819 42.427 NA
527 8720860.09 252228.294 42.285 BZD
528 8720860.51 252246.674 42.451 PL
529 8720860.24 252245.494 42.237 SAR
530 8720859.74 252246.67 42.41 NA
531 8720857.57 252247.018 42.433 V
532 8720856.94 252245.964 42.203 SAR
533 8720856.59 252235.12 42.25 NA
534 8720856.38 252234.382 42.215 SAR
535 8720851.41 252225.933 42.134 V
536 8720850.17 252213.283 41.901 LP
537 8720850.91 252247.498 42.335 NA
538 8720850.28 252226.005 42.104 NA
539 8720849.98 252223.144 42.179 LP
540 8720849.21 252225.992 42.101 NA
541 8720848.24 252213.153 41.533 V
542 8720848.84 252247.907 42.211 PT
543 8720847.8 252213.117 41.504 PT
544 8720847.88 252223.133 41.944 V
545 8720847.95 252247.389 42.177 NA
546 8720846.79 252236.809 42.479 PAT
547 8720840.21 252217.56 41.437 PL
548 8720840.64 252238.185 42.153 NA
549 8720838.36 252217.491 41.412 NA
550 8720838.17 252217.55 41.406 LP
551 8720836.52 252224.815 41.784 R
552 8720835.06 252220.662 41.44 NA
553 8720834.29 252239.243 42.046 PAT
554 8720831.89 252223.82 41.481 P
555 8720832.55 252250.417 42.271 NA
556 8720832.15 252239.709 42.11 NA
557 8720831.25 252238.888 41.817 SAR
558 8720831.35 252251.191 42.25 PL
559 8720830.68 252228.983 41.817 2
560 8720829.68 252227.941 41.907 PT
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
561 8720829.51 252234.324 41.787 NA
562 8720829.62 252239.158 41.79 NA
563 8720829.47 252241.405 42.103 NA
564 8720828.64 252228.631 41.805 V
565 8720828.54 252227.191 42.013 LP
566 8720828.35 252228.375 41.986 PL
567 8720828.41 252241.542 42.109 NA
568 8720828.34 252250.502 42.047 NA
569 8720827.73 252240.645 42.232 NA
570 8720827.93 252251.727 42.266 V
571 8720826.04 252234.994 41.727 NA
572 8720825.75 252252.092 42.232 NA
573 8720824.98 252251.039 42.04 SAR
574 8720821.53 252252.158 42.207 NA
575 8720820.07 252230.963 41.633 NA
576 8720819.75 252241.838 42.218 NA
577 8720818 252235.488 41.611 NA
578 8720816.3 252253.101 42.184 NA
579 8720815.57 252242.229 42.226 PAT
580 8720815.26 252241.034 41.613 PL
581 8720814.8 252240.482 41.608 B
582 8720814.6 252241.201 42.004 NA
583 8720814.29 252253.402 42.198 NA
584 8720813.19 252242.78 42.208 NA
585 8720811.12 252253.258 41.999 NA
586 8720811.02 252253.968 42.19 NA
587 8720807.01 252243.698 42.23 NA
588 8720806.65 252238.056 41.479 NA
589 8720806.58 252255.162 42.212 NA
590 8720805.55 252230.28 41.48 NA
591 8720804.45 252233.784 41.449 NA
592 8720803.18 252255.164 42.25 NA
593 8720801.16 252244.69 42.261 NA
594 8720800.83 252242.501 41.44 NA
595 8720800.82 252242.501 41.44 B
596 8720800.68 252242.611 41.802 NA
597 8720800.09 252228.25 41.616 V
598 8720799.68 252243.395 41.806 NA
599 8720799.52 252243.469 42.246 NA
600 8720799.51 252243.683 42.257 NA
601 8720798.29 252228.007 41.63 PL
602 8720794.94 252245.517 42.241 NA
603 8720793.66 252245.802 42.24 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
604 8720792 252228.165 41.356 V
605 8720791.69 252256.402 41.991 NA
606 8720790.06 252246.197 42.246 NA
607 8720788.65 252238.154 41.273 R
608 8720787.75 252257.673 42.273 NA
609 8720785.39 252246.869 42.364 PALM
610 8720785.16 252245.36 41.66 NA
611 8720782.25 252230.532 41.209 NA
612 8720780.29 252248.152 42.239 NA
613 8720780.43 252258.814 42.237 A
614 8720780.12 252248.398 42.228 NA
615 8720779.52 252246.252 41.615 NA
616 8720779.46 252245.559 41.199 B
617 8720779.11 252258.453 41.99 SAR
618 8720778.64 252259.724 42.217 PL
619 8720778.45 252261.784 42.226 LP
620 8720777.51 252249.456 42.06 SAR
621 8720777.69 252259.862 42.002 V
622 8720777.33 252248.597 42.246 NA
623 8720777.11 252246.655 41.178 B
624 8720776.67 252247.161 42.219 NA
625 8720776.61 252245.407 41.144 NA
626 8720776.56 252246.067 41.417 NA
627 8720776.57 252246.635 41.773 B
628 8720776.5 252246.673 41.762 NA
629 8720776.3 252246.18 41.738 NA
630 8720776.26 252245.462 41.398 NA
631 8720776.68 252262.251 42.03 V
632 8720776.01 252246.89 42.286 NA
633 8720771.78 252254.526 42.004 NA
634 8720770.72 252263.124 42.056 V
635 8720769.57 252263.35 42.241 LP
636 8720768.37 252227.588 41.327 PL
637 8720769.17 252261.294 41.999 SAR
638 8720767.68 252261.393 42.142 V
639 8720767.61 252260.265 42.004 SAR
640 8720767.59 252261.262 42.236 TB
641 8720767.23 252249.247 42.291 NA
642 8720766.92 252248.423 42.32 NA
643 8720766.91 252248.059 41.779 NA
644 8720766.9 252248.082 42.323 NA
645 8720766.81 252247.451 41.41 B
646 8720766.81 252247.491 41.76 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
647 8720766.76 252246.728 41.085 B
648 8720766.65 252246.052 41.081 NA
649 8720766.37 252247.301 42.108 RAMPA
650 8720764.49 252249.805 42.294 NA
651 8720763.72 252251.279 42.196 SAR
652 8720763.34 252249.057 42.256 RAMPA
653 8720763.22 252248.808 42.125 NA
654 8720763.02 252247.562 42.107 RAMPA
655 8720762.03 252226.441 41.28 LP
656 8720760.95 252262.234 42.276 PT
657 8720757.65 252249.967 42.199 PL
658 8720757.39 252263.491 42.199 PL
659 8720749.34 252264.86 42.235 V
660 8720748.26 252249.68 40.995 RAMPA
661 8720748.05 252248.708 40.973 B
662 8720741.06 252248.054 40.931 NA
663 8720738.36 252227.317 41.175 PL
664 8720735.92 252227.56 40.948 V
665 8720735.91 252227.585 40.94 V
666 8720736.32 252252.592 40.993 MURO
667 8720735.53 252233.447 40.957 NA
668 8720735.13 252226.07 40.688 LP
669 8720735.61 252259.456 42.064 R
670 8720734.03 252252.543 40.997 NA
671 8720733.13 252222.287 40.463 P
672 8720733.66 252264.532 42.195 NA
673 8720723.98 252236.298 40.919 NA
674 8720724.15 252244.809 40.897 NA
675 8720724 252254.588 42.131 SAR
676 8720723.69 252251.805 40.946 MURO
677 8720722.23 252259.447 42.117 NA
678 8720720.63 252222.261 40.468 NA
679 8720721.45 252264.219 42.281 V
680 8720720.68 252250.141 40.923 NA
681 8720720.68 252250.246 41.249 NA
682 8720720.58 252250.972 41.66 NA
683 8720720.56 252250.865 41.269 NA
684 8720720.57 252251.622 40.943 NA
685 8720720.8 252263.057 42.083 SAR
686 8720720.47 252251.633 41.671 NA
687 8720720.4 252254.227 42.103 NA
688 8720720.33 252252.036 42.068 B
689 8720718.84 252225.843 40.754 LP
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
690 8720718.99 252252.913 42.092 NA
691 8720718.11 252227.292 40.883 V
692 8720717.54 252263.393 42.181 NA
693 8720717.09 252262.773 42.068 NA
694 8720715.74 252233.91 40.901 NA
695 8720715.93 252263.792 42.214 V
696 8720714.99 252244.538 40.87 NA
697 8720714.6 252252.62 42.125 NA
698 8720712.7 252263.703 42.261 NA
699 8720711.7 252262.397 42.048 SAR
700 8720710.85 252252.313 42.162 NA
701 8720710.72 252262.893 42.144 NA
702 8720710.05 252263.295 42.255 TB
703 8720709.87 252258.371 42.025 NA
704 8720709.87 252262.253 42.017 NA
705 8720708.23 252226.925 41.088 PL
706 8720707.72 252251.77 42.098 2
707 8720708.05 252265.4 42.244 LP
708 8720707.91 252263.922 40.076 V
709 8720707.37 252272.601 42.112 NA
710 8720707.13 252264.696 40.082 NA
711 8720706.69 252265.512 40.088 NA
712 8720706 252244.984 40.856 NA
713 8720706.52 252269.186 42.104 NA
714 8720705.13 252272.1 42.138 NA
715 8720704.38 252261.274 42.02 NA
716 8720703.08 252234.074 40.835 NA
717 8720702.72 252251.753 42.089 NA
718 8720702.55 252273.403 40.127 NA
719 8720701.52 252252.787 42.185 NA
720 8720701.39 252273.853 40.284 LP
721 8720700.52 252250.101 41.649 NA
722 8720699.51 252262.49 42.013 SAR
723 8720699 252264.689 42.255 NA
724 8720698.37 252262.216 42.185 TB
725 8720698.08 252261.221 41.98 NA
726 8720697.73 252251.406 42.109 NA
727 8720697.58 252256.991 41.961 NA
728 8720697.08 252262.357 42.17 PL
729 8720694.2 252227.042 41.014 V
730 8720691.24 252245.138 40.822 NA
731 8720691.43 252256.226 41.856 NA
732 8720688.62 252238.759 40.812 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
733 8720688.57 252250.694 41.935 NA
734 8720688.04 252261.087 41.93 NA
735 8720684.97 252233.309 40.775 NA
736 8720684.95 252251.587 41.914 SAR
737 8720685.09 252260.201 41.739 NA
738 8720684 252261.237 41.919 V
739 8720683.82 252255.96 41.693 NA
740 8720680.79 252261.151 41.847 NA
741 8720679.15 252226.846 40.979 V
742 8720679.91 252259.802 41.64 SAR
743 8720678.16 252226.599 40.998 PL
744 8720677.34 252234.025 40.782 NA
745 8720677.49 252243.654 40.756 R
746 8720676.48 252238.668 40.768 NA
747 8720672.76 252249.582 41.611 NA
748 8720672.32 252247.942 41.565 PL
749 8720672.12 252246.691 40.793 B
750 8720672.05 252247.405 41.164 NA
751 8720672.01 252248.443 41.568 NA
752 8720671.99 252248.174 41.568 NA
753 8720670.82 252255.223 41.395 NA
754 8720667.79 252248.961 41.453 A
755 8720665.35 252226.681 40.754 NA
756 8720665.27 252225.29 40.987 RAMPA
757 8720665.91 252259.181 41.399 NA
758 8720663.45 252226.66 40.648 NA
759 8720663.27 252225.193 40.67 LP
760 8720661.08 252229.206 40.672 NA
761 8720660.61 252244.294 40.681 PL
762 8720659.68 252243.743 40.674 JUEGO
763 8720657.95 252258.006 41.041 SAR
764 8720656.92 252226.318 40.671 R
765 8720657.8 252259.273 41.28 V
766 8720656.47 252261.2 41.349 LP
767 8720645.46 252263.184 40.907 V
768 8720644.1 252259.329 40.746 V
769 8720643.74 252263.161 40.97 LP
770 8720642.29 252255.236 40.708 V
771 8720640.14 252256.883 40.935 NA
772 8720638.64 252242.303 40.881 PL
773 8720615.79 252225.787 40.644 NA
774 8720615.73 252233.772 40.661 JUEGO
775 8720614.5 252236.217 40.606 PL
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
776 8720614.09 252224.668 40.662 LP
777 8720612.7 252225.818 40.64 PL
778 8720612.94 252236.463 40.373 SAR
779 8720602.66 252233.815 40.311 SAR
780 8720592.11 252228.329 40.23 NA
781 8720578.97 252229.335 40.234 NA
782 8720576.17 252231.109 40.058 BZD
783 8720575.75 252225.406 40.042 R
784 8720572.9 252229.552 40.14 NA
785 8720565.98 252238.706 40.095 A
786 8720563.45 252229.119 39.946 NA
787 8720555.62 252223.574 39.76 PL
788 8720552.99 252225.885 39.816 NA
789 8720551.91 252245.923 39.889 HID
790 8720538.46 252220.943 39.913 LP
791 8720537.97 252223.004 39.855 V
792 8720531.44 252223.223 39.815 NA
793 8720525.23 252222.076 39.761 PL
794 8720524.84 252241.371 39.589 A
795 8720523.03 252222.221 39.638 NA
796 8720522.22 252243.882 39.547 V
797 8720521.8 252239.328 39.467 SAR
798 8720518.76 252246.267 39.621 LP
799 8720517.63 252241.617 39.439 V
800 8720518.08 252259.718 39.598 V
801 8720517 252223.089 39.637 2
802 8720517.02 252246.727 39.484 V
803 8720516.94 252259.307 39.602 SAR
804 8720515.09 252231.678 39.492 NA
805 8720515.35 252223.733 39.414 V
806 8720515.93 252246.477 39.406 NA
807 8720514.34 252223.109 39.388 NA
808 8720513.88 252222.054 39.57 V
809 8720513.63 252220.074 39.431 NA
810 8720513.3 252229.389 39.403 NA
811 8720512.68 252236.029 39.381 NA
812 8720510.56 252257.459 39.497 NA
813 8720509.79 252247.121 39.397 NA
814 8720509.19 252249.506 39.563 PL
815 8720508.8 252247.582 39.546 TB
816 8720508.17 252244.907 39.535 NA
817 8720507.52 252222.55 39.27 V
818 8720507.4 252220.549 39.442 P
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
819 8720508.61 252268.446 39.65 LP
820 8720506.8 252233.22 39.346 V
821 8720506.68 252231.338 39.345 NA
822 8720506.54 252226.858 39.317 NA
823 8720506.05 252224.54 39.323 SAR
824 8720506.33 252235.98 39.305 NA
825 8720504.93 252224.496 39.48 NA
826 8720504.69 252222.769 39.473 V
827 8720505.11 252245.346 39.483 NA
828 8720504.43 252223.621 39.387 NA
829 8720501.99 252232.863 39.437 PAT
830 8720496.11 252229.101 39.195 BZD
831 8720495.19 252240.529 39.224 SAR
832 8720494.2 252223.382 39.392 PL
833 8720490.6 252224.54 39.344 NA
834 8720490.91 252243.647 39.329 NA
835 8720483.1 252241.113 39.123 NA
836 8720481.21 252244.342 39.143 NA
837 8720476.26 252225.642 39.123 NA
838 8720474.73 252247.765 39.177 PL
839 8720469.75 252242.62 39.058 RAMPA
840 8720467.68 252242.883 39.056 NA
841 8720467.56 252241.818 38.954 NA
842 8720466.96 252250.361 39.109 LP
843 8720466.89 252250.228 39.099 V
844 8720465.87 252226.809 39.08 NA
845 8720465.14 252245.198 39.039 NA
846 8720463.12 252225.942 39.11 NA
847 8720462.53 252248.635 38.967 V
848 8720462.07 252233.721 38.881 V
849 8720461.16 252235.707 38.817 V
850 8720460.54 252226.861 39.005 NA
851 8720458.07 252253.631 39.049 NA
852 8720457.56 252245.666 38.995 NA
853 8720457.01 252227.25 38.997 A
854 8720457.72 252252.593 38.95 NA
855 8720456.4 252252.065 38.947 NA
856 8720449.94 252246.39 38.945 NA
857 8720447.23 252249.224 38.954 PL
858 8720445.73 252228.365 38.725 SAR
859 8720444.43 252260.214 38.872 LP
860 8720442.25 252247.062 38.869 A
861 8720440.97 252250.445 38.805 V
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
862 8720435.73 252243.306 38.847 V
863 8720434.9 252228.734 38.573 V
864 8720431.73 252228.699 38.748 PL
865 8720417.17 252237.632 38.606 PAT
866 8720414.31 252244.592 38.624 PL
867 8720414.16 252244.283 38.414 V
868 8720414.18 252246.223 38.635 LP
869 8720411.87 252233.51 38.336 NA
870 8720409.5 252229.714 38.553 PT
871 8720409.44 252228.219 38.579 LP
872 8720400.11 252230.249 38.482 NA
873 8720400.59 252249.211 38.441 LP
874 8720399.74 252242.451 38.2 NA
875 8720398.78 252244.998 38.226 V
876 8720398.18 252239.18 38.193 V
877 8720397.68 252246.476 38.228 V
878 8720397.07 252237.363 38.185 NA
879 8720391.95 252248.71 38.145 V
880 8720390.77 252231.74 38.154 V
881 8720390.55 252230.311 38.208 LP
882 8720390.11 252236.32 38.105 NA
883 8720390.4 252247.101 38.164 NA
884 8720389.66 252230.319 38.139 TB
885 8720387.73 252246.358 38.117 NA
886 8720386.64 252247.811 38.258 V
887 8720386.43 252247.213 38.269 TB
888 8720386.4 252246.775 38.188 NA
889 8720386.34 252249.276 38.307 LP
890 8720384.8 252238.936 38.127 V
891 8720383.92 252247.635 38.264 PL
892 8720382.75 252231.669 38.177 LP
893 8720382.59 252232.437 38.215 PT
894 8720382.2 252233.394 38.074 NA
895 8720381.73 252244.461 38.041 R
896 8720381.85 252249.097 38.258 PT
897 8720381.56 252249.066 38.126 NA
898 8720381.41 252247.849 38.041 SAR
899 8720381.45 252250.874 38.081 LP
900 8720379.5 252240.312 38.165 NA
901 8720379.03 252237.951 38.018 NA
902 8720377.32 252252.717 38.094 NA
903 8720375.53 252250.578 37.995 V
904 8720374.52 252253.959 38.217 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
905 8720374.25 252251.356 37.999 NA
906 8720372.06 252233.976 38.266 LP
907 8720372.17 252244.732 38.129 PAT
908 8720371.82 252245.333 38.096 NA
909 8720370.82 252243.136 38.08 NA
910 8720370 252253.148 37.929 V
911 8720369.01 252237.304 37.927 NA
912 8720369.32 252254.449 38.033 NA
913 8720368.75 252235.824 38.161 PL
914 8720368.92 252253.568 37.927 NA
915 8720365.97 252255.51 37.995 A
916 8720363.62 252247.715 38 0
917 8720363.38 252259.223 38.022 NA
918 8720361.66 252248.593 38.004 BZD
919 8720359.94 252254.095 37.785 NA
920 8720358.19 252237.629 37.859 LP
921 8720358.76 252258.938 37.897 NA
922 8720358.17 252241.408 37.859 V
923 8720357.43 252239.6 38.1 PT
924 8720356.15 252259.884 37.843 PL
925 8720355.69 252259.872 37.742 SAR
926 8720353.19 252262.003 37.875 V
927 8720352.59 252261.356 37.7 NA
928 8720351.73 252248.124 37.735 R
929 8720351.57 252257.46 37.691 NA
930 8720351.12 252262.634 37.811 NA
931 8720349.97 252265.296 37.846 LP
932 8720345.56 252256.996 37.798 A
933 8720340.67 252245.828 37.857 TB
934 8720339.21 252259.918 37.676 NA
935 8720338.89 252261.09 37.673 SAR
936 8720337.99 252244.75 37.359 LP
937 8720338.02 252256.706 37.688 NA
938 8720336.47 252261.135 37.772 PAT
939 8720335.98 252260.553 37.63 V
940 8720335.14 252258.797 37.717 V
941 8720335.01 252254.481 37.553 NA
942 8720334.3 252257.192 37.556 SAR
943 8720332.8 252251.336 37.535 V
944 8720332.4 252267.299 37.458 NA
945 8720331.28 252248.353 37.527 LP
946 8720331.93 252294.092 37.619 LP
947 8720330.77 252259.968 37.617 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
948 8720329.35 252294.513 37.555 V
949 8720328.43 252274.1 37.593 PL
950 8720328.13 252273.639 37.412 SAR
951 8720327.34 252295.944 37.294 SAR
952 8720325.29 252278.35 37.579 LP
953 8720324.99 252289.36 37.504 NA
954 8720324.1 252267.94 37.54 PAT
955 8720323.92 252276.545 37.547 NA
956 8720324 252280.498 37.531 NA
957 8720322.64 252282.196 37.519 PT
958 8720322.41 252281.568 37.524 PL
959 8720321.85 252276.847 37.362 SAR
960 8720321.9 252284.301 37.494 A
961 8720321.33 252269.182 37.484 PAT
962 8720320.98 252280.834 37.499 TB
963 8720319.75 252256.797 37.616 PT
964 8720320.16 252304.975 37.637 NA
965 8720318.91 252266.375 37.513 NA
966 8720319.06 252278.907 37.305 NA
967 8720318.83 252281.307 37.273 V
968 8720318.99 252301.069 37.322 SAR
969 8720316.93 252306.642 37.523 LP
970 8720315.51 252267.142 37.297 SAR
971 8720315.19 252270.649 37.443 AUX
972 8720315.48 252299.201 37.449 V
973 8720315.18 252301.124 37.468 PL
974 8720314.28 252270.888 37.315 SAR
975 8720312.84 252260.249 37.537 PL
976 8720311.39 252259.422 37.471 LP
977 8720311.87 252291.747 37.383 NA
978 8720310.22 252286.911 37.184 SAR
979 8720309.58 252286.307 37.236 V
980 8720308.48 252262.597 37.29 V
981 8720308.93 252285.757 37.231 NA
982 8720308.62 252277.478 37.21 NA
983 8720308.08 252259.962 37.394 TB
984 8720307.55 252258.817 37.259 NA
985 8720307 252258.576 37.323 PL
986 8720306.32 252261.006 37.214 V
987 8720306.7 252285.123 37.211 NA
988 8720306.01 252289.39 37.362 LP
989 8720305.06 252287.805 37.329 V
990 8720304.73 252285.661 37.185 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
991 8720303.84 252268.997 37.204 NA
992 8720299.31 252240.547 37.206 NA
993 8720300.53 252288.407 37.337 PL
994 8720299.71 252283.352 37.121 BZD
995 8720298.62 252246.631 37.075 FAROL
996 8720298.21 252241.476 37.194 PT
997 8720298.62 252260.323 37.111 BZD
998 8720297.17 252241.899 36.92 V
999 8720297.28 252265.281 37.167 NA
1000 8720297.17 252269.229 37.185 NA
1001 8720296.98 252265.449 37.371 PT
1002 8720295.23 252242.956 36.836 SAR
1003 8720295.84 252280.369 37.121 NA
1004 8720295.41 252266.435 37.282 NA
1005 8720295.03 252284.596 37.081 NA
1006 8720293.38 252268.418 37.398 LP
1007 8720292.3 252234.181 36.924 PL
1008 8720292.27 252257.177 36.995 SAR
1009 8720292.55 252270.544 37.391 NA
1010 8720291.93 252279.616 37.084 NA
1011 8720290.65 252287.281 37.058 SAR
1012 8720289.64 252285.533 37.094 V
1013 8720289.52 252285.726 37.188 TB
1014 8720288.71 252283.892 37.042 V
1015 8720287.86 252259.42 37.266 LP
1016 8720287.85 252284.223 37.156 NA
1017 8720287.56 252282.139 37.05 NA
1018 8720287.13 252275.033 37.307 NA
1019 8720287.28 252283.622 37.112 A
1020 8720284.51 252222.734 36.733 NA
1021 8720285.1 252301.241 37.1 NA
1022 8720284.62 252289.626 37.048 NA
1023 8720284.58 252300.288 36.999 NA
1024 8720283.68 252298.47 36.887 V
1025 8720282.51 252302.918 36.893 NA
1026 8720280.25 252240.091 36.878 FAROL
1027 8720281.9 252301.934 36.922 NA
1028 8720280.93 252300.239 36.837 NA
1029 8720280.92 252300.233 36.837 PL
1030 8720277.1 252209.096 36.546 PL
1031 8720276.91 252206.982 37.009 PT
1032 8720279.06 252293.003 36.893 NA
1033 8720275.33 252201.213 37.023 LP
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1034 8720277.07 252289.871 36.885 NA
1035 8720273.07 252202.318 36.386 V
1036 8720273.86 252296.188 36.836 NA
1037 8720271.01 252203.516 36.234 SAR
1038 8720272.91 252283.957 36.847 V
1039 8720271.81 252282.52 37.091 LP
1040 8720272.04 252292.938 36.866 NA
1041 8720269.38 252219.849 36.322 NA
1042 8720268.42 252299.444 36.756 NA
1043 8720266.85 252296.105 36.723 NA
1044 8720264.15 252221.166 36.492 LP
1045 8720262.96 252209.633 36.104 AUX
1046 8720263.93 252289.417 36.685 V
1047 8720263.87 252302.224 36.702 NA
1048 8720262.83 252287.922 36.918 LP
1049 8720262.18 252289.633 36.732 PL
1050 8720262.31 252298.887 36.606 NA
1051 8720262.24 252311.748 36.747 NA
1052 8720257.24 252302.005 36.497 NA
1053 8720255.43 252294.562 36.525 V
1054 8720254.89 252293.281 36.741 PT
1055 8720254.75 252307.907 36.529 NA
1056 8720250.26 252310.722 36.452 NA
1057 8720248.45 252307.438 36.436 NA
1058 8720245.27 252313.699 36.413 NA
1059 8720240.8 252316.679 36.278 NA
1060 8720238.55 252313.336 36.261 NA
1061 8720236.22 252304.791 36.439 NA
1062 8720236.27 252319.384 36.236 NA
1063 8720234.56 252315.878 36.243 NA
1064 8720232.2 252321.702 36.199 NA
1065 8720230.27 252318.495 36.18 NA
1066 8720229.95 252322.044 36.184 V
1067 8720228.27 252320.773 36.215 NA
1068 8720227.99 252334.873 36.288 LP
1069 8720227.6 252324.715 36.094 NA
1070 8720224.42 252322 36.135 NA
1071 8720223.77 252326.946 36.067 NA
1072 8720218.76 252330.219 36.09 NA
1073 8720216.6 252315.94 36.246 NA
1074 8720215.34 252327.855 36.102 NA
1075 8720215.1 252362.756 36.219 LP
1076 8720213.39 252333.479 36.136 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1077 8720214.22 252365.203 36.187 V
1078 8720211.48 252363.603 36.143 SAR
1079 8720210.3 252360.066 36.13 A
1080 8720209.26 252331.108 36.04 NA
1081 8720207.61 252350.125 36.102 LP
1082 8720206.78 252337.315 36.099 NA
1083 8720207.24 252354.746 36.106 NA
1084 8720206.42 252348.095 36.085 V
1085 8720205.36 252346.406 35.943 NA
1086 8720205.73 252367.86 36.01 NA
1087 8720205.24 252350.301 36.076 NA
1088 8720204.76 252333.93 36.012 NA
1089 8720205.25 252352.295 36.139 PAT
1090 8720204.44 252346.935 35.944 NA
1091 8720203.83 252350.977 35.877 NA
1092 8720204.15 252368.626 36.096 V
1093 8720203.34 252350.233 35.887 NA
1094 8720203.18 252348.592 35.92 NA
1095 8720202.79 252369.9 36.131 LP
1096 8720201.53 252336.867 36.143 NA
1097 8720201.06 252336.313 36.118 NA
1098 8720200.41 252338.4 36.047 AUX
1099 8720199.45 252359.336 36.064 NA
1100 8720197.83 252357.598 35.877 PT
1101 8720197.65 252354.526 35.866 NA
1102 8720196.8 252327.951 36.165 LP
1103 8720197.19 252353.803 35.854 NA
1104 8720196.76 252345.889 35.845 NA
1105 8720196.37 252355.527 35.923 V
1106 8720195.79 252355.821 36.018 PL
1107 8720195.64 252353.02 35.829 NA
1108 8720194.47 252331.713 35.934 NA
1109 8720193.5 252331.556 36.115 PT
1110 8720193.88 252355.266 36.005 LP
1111 8720193.02 252331.879 35.975 NA
1112 8720192.81 252326.667 36.163 LP
1113 8720192.72 252330.196 36.119 NA
1114 8720193.12 252353.951 35.796 NA
1115 8720191.94 252330.944 36.032 NA
1116 8720191.88 252329.703 36.067 NA
1117 8720191.15 252337.148 35.836 BZD
1118 8720189.94 252327.717 36.02 NA
1119 8720189.63 252321.762 35.997 LP
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1120 8720189.61 252321.772 35.996 NA
1121 8720189.97 252345.906 35.817 NA
1122 8720189.32 252349.12 35.763 NA
1123 8720188.48 252322.459 35.996 NA
1124 8720188.37 252348.953 35.944 NA
1125 8720188.17 252347.598 35.955 NA
1126 8720187.34 252322.569 35.991 TB
1127 8720187.83 252347.982 35.957 NA
1128 8720186.82 252322.504 35.993 NA
1129 8720187.32 252345.999 35.904 NA
1130 8720186.78 252346.204 35.969 NA
1131 8720186.57 252345.555 35.923 NA
1132 8720186.16 252344.336 35.789 NA
1133 8720185.25 252337.08 35.851 NA
1134 8720185.19 252335.196 35.973 NA
1135 8720184.52 252337.835 35.79 NA
1136 8720184.42 252334.485 35.959 NA
1137 8720183.8 252338.268 35.802 V
1138 8720182.93 252315.829 36.136 NA
1139 8720183.32 252338.103 35.975 NA
1140 8720182.72 252334.242 35.958 PL
1141 8720182.22 252335.991 36.005 LP
1142 8720180.01 252326.707 36.002 SAR
1143 8720180.01 252353.967 35.824 NA
1144 8720178.74 252309.017 35.933 NA
1145 8720179.34 252362.795 35.873 NA
1146 8720175.91 252320.012 35.974 NA
1147 8720175.55 252356.939 35.778 NA
1148 8720173.46 252353.344 35.774 NA
1149 8720171.7 252313.598 35.935 FAROL
1150 8720169.55 252315.133 35.909 LP
1151 8720170.44 252359.715 35.742 NA
1152 8720168.57 252356.259 35.675 NA
1153 8720163.14 252347.11 35.835 NA
1154 8720159.56 252361.662 35.552 NA
1155 8720158.3 252351.499 35.639 PL
1156 8720157.95 252375.692 35.36 PL
1157 8720150.34 252367.305 35.46 NA
1158 8720147.7 252373.459 35.368 NA
1159 8720145.51 252370.219 35.386 NA
1160 8720143.61 252375.689 35.309 NA
1161 8720141.13 252379.085 35.171 SAR
1162 8720140.07 252376.809 35.236 V
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1163 8720139.25 252375.164 35.237 NA
1164 8720138.88 252378.619 35.231 NA
1165 8720136.94 252375.224 35.247 NA
1166 8720134.28 252381.528 35.17 NA
1167 8720132.3 252378.042 35.144 NA
1168 8720130.31 252370.929 35.095 V
1169 8720130.1 252378.229 35.021 SAR
1170 8720129.25 252369.218 35.229 NA
1171 8720129.35 252384.445 35.073 NA
1172 8720127.04 252369.408 35.221 NA
1173 8720127.18 252381.134 35.09 NA
1174 8720124.16 252387.598 34.986 NA
1175 8720121.97 252375.666 34.938 NA
1176 8720121.57 252384.329 34.979 NA
1177 8720121.21 252374.386 35.128 NA
1178 8720119.1 252390.676 34.916 NA
1179 8720118.67 252377.649 34.901 NA
1180 8720117.59 252374.977 35.145 LP
1181 8720117.04 252387.265 34.916 NA
1182 8720114.59 252393.349 34.837 NA
1183 8720114.11 252380.431 34.814 NA
1184 8720113.15 252379.664 34.956 NA
1185 8720112.55 252390.001 34.804 NA
1186 8720110.79 252382.379 34.758 SAR
1187 8720110.83 252395.639 34.785 NA
1188 8720107.73 252392.868 34.752 NA
1189 8720107.09 252397.881 34.723 NA
1190 8720104.56 252394.804 34.658 NA
1191 8720103.05 252423.523 34.834 LP
1192 8720100.56 252384.576 34.854 NA
1193 8720100.27 252397.424 34.677 NA
1194 8720099.94 252402.309 34.624 NA
1195 8720099.62 252423.628 34.72 V
1196 8720096.93 252399.434 34.578 NA
1197 8720097.3 252414.331 34.699 LP
1198 8720097.13 252412.423 34.492 PL
1199 8720096.53 252404.464 34.593 NA
1200 8720095.35 252379.246 35.062 NA
1201 8720094.59 252414.086 34.468 V
1202 8720095 252428.97 34.691 NA
1203 8720094.63 252415.873 34.479 NA
1204 8720094.6 252427.094 34.501 SAR
1205 8720094.21 252415.133 34.45 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1206 8720093.77 252401.479 34.59 A
1207 8720093.29 252406.272 34.55 NA
1208 8720093.63 252427.713 34.625 V
1209 8720092.38 252425.033 34.643 NA
1210 8720092.15 252428.328 34.714 LP
1211 8720090.86 252404.016 34.594 TB
1212 8720090.21 252422.036 34.724 PL
1213 8720090.15 252421.046 34.62 NA
1214 8720089.7 252406.132 34.592 0.05
1215 8720089.43 252418.954 34.423 NA
1216 8720089.05 252418.302 34.424 NA
1217 8720088.47 252418.036 34.392 NA
1218 8720088.5 252419.669 34.606 V
1219 8720087.75 252410.484 34.413 BZD
1220 8720087.28 252420.502 34.591 V
1221 8720086.48 252419.427 34.586 PT
1222 8720085.01 252388.601 34.357 LP
1223 8720083.86 252398.643 34.408 SAR
1224 8720083.1 252394.794 34.668 NA
1225 8720082.63 252402.668 34.366 NA
1226 8720082.43 252396.93 34.408 V
1227 8720081.71 252395.641 34.416 NA
1228 8720081.48 252411.089 34.393 V
1229 8720080.89 252399.882 34.395 NA
1230 8720081.24 252415.207 34.334 NA
1231 8720080.18 252414.217 34.476 NA
1232 8720080.07 252413.166 34.463 NA
1233 8720078.29 252381.456 34.675 LP
1234 8720079 252411.411 34.39 NA
1235 8720077.9 252409.439 34.36 NA
1236 8720076.7 252400.689 34.34 PT
1237 8720076.69 252411.81 34.359 NA
1238 8720075.81 252399.108 34.338 V
1239 8720075.89 252416.965 34.226 NA
1240 8720074.83 252399.689 34.348 NA
1241 8720073.89 252404.682 34.347 SAR
1242 8720072.75 252402.789 34.309 SAR
1243 8720072.75 252402.789 34.309 PL
1244 8720072.73 252403.96 34.35 NA
1245 8720070.57 252419.942 34.301 NA
1246 8720070.05 252405.345 34.253 PALM
1247 8720069.6 252429.404 34.386 PL
1249 8720065.29 252384.143 34.233 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1250 8720065.04 252418.788 34.23 NA
1251 8720064.82 252423.696 34.203 NA
1252 8720064.44 252433.885 34.312 LP
1253 8720063.15 252425.539 34.287 PAT
1254 8720060.43 252421.57 34.165 NA
1255 8720060.35 252426.335 34.129 NA
1256 8720055.95 252424.136 34.115 NA
1257 8720055.89 252429.155 34.098 NA
1258 8720051.39 252426.859 34.052 NA
1259 8720051.49 252431.718 34.062 NA
1260 8720049.95 252419.191 34.113 SAR
1261 8720049.51 252417.002 34.085 PL
1262 8720048.76 252417.41 34.084 NA
1263 8720047 252420.933 34.072 NA
1264 8720046.13 252418.684 34.065 NA
1265 8720043.29 252451.111 34.023 LP
1266 8720042.77 252432.101 33.965 NA
1267 8720042.89 252436.666 33.968 NA
1268 8720042.07 252423.928 34.017 NA
1269 8720042.33 252445.857 34.087 PL
1271 8720042.29 252447.348 34.086 LP
1272 8720040.11 252448.819 33.979 V
1273 8720040.02 252451.05 33.779 SAR
1274 8720038.9 252435.617 34.03 TB
1275 8720038.9 252438.096 33.911 NA
1276 8720039.13 252447.669 33.827 V
1277 8720039.15 252449.412 33.8 NA
1278 8720038.56 252434.665 33.936 NA
1279 8720038.29 252426.24 33.982 NA
1280 8720038.67 252448.535 33.8 NA
1281 8720037.8 252436.309 33.956 NA
1282 8720036.6 252434.248 33.94 NA
1283 8720036.19 252438.257 33.855 NA
1284 8720033.45 252452.847 33.806 V
1285 8720032.71 252452.375 33.805 NA
1286 8720031.59 252452.391 33.782 V
1287 8720031.35 252454.274 33.986 LP
1288 8720029.74 252426.702 33.762 NA
1289 8720028.69 252432.068 33.891 NA
1290 8720026.82 252444.426 33.773 V
1291 8720026.46 252448.401 33.751 NA
1292 8720025.28 252446.386 33.859 NA
1293 8720024.63 252431.348 33.873 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1294 8720024.57 252448.029 33.786 NA
1295 8720024.24 252444.688 33.925 NA
1296 8720024.23 252447.099 33.904 TB
1297 8720022.99 252432.317 33.862 NA
1298 8720023.01 252442.773 33.829 NA
1299 8720022.67 252432.765 33.883 NA
1300 8720022.44 252444.617 33.822 NA
1301 8720021.84 252458.425 33.967 PL
1302 8720021.2 252450.15 33.784 NA
1303 8720020.26 252445.889 33.823 NA
1304 8720017.9 252447.209 33.847 NA
1305 8720016.22 252437.838 33.738 NA
1306 8720016.62 252452.98 33.779 NA
1307 8720015.16 252449.015 33.746 NA
1308 8720012.39 252455.46 33.789 NA
1309 8720011.71 252440.67 33.783 NA
1310 8720009.04 252457.489 33.754 NA
1311 8720006.56 252445.473 33.79 SAR
1312 8720005.43 252443.58 33.826 NA
1313 8720004.26 252455.435 33.773 NA
1314 8720004.26 252460.323 33.779 NA
1315 8720004.2 252476.931 33.981 LP
1316 8720003.42 252480.734 33.76 SAR
1317 8720002.78 252477.395 33.91 V
1318 8720001.35 252461.89 33.744 NA
1319 8720001.6 252472.373 33.932 LP
1320 8720001.71 252477.842 33.718 SAR
1321 8720000.6 252463.263 33.898 PAT
1322 8720001.08 252495.513 34.019 LP
1323 8719999.64 252449.59 33.785 NA
1324 8719999.63 252458.362 33.735 NA
1325 8719999.53 252463.171 33.754 A
1326 8719999.46 252464.749 33.831 V
1327 8719999.58 252473.473 33.91 PT
1328 8719999.85 252488.412 33.81 NA
1329 8719999.24 252471.998 33.72 V
1330 8719999.21 252473.531 33.734 NA
1331 8719998.81 252462.444 33.87 NA
1332 8719998.32 252447.733 33.777 NA
1333 8719998.9 252472.557 33.704 NA
1334 8719997.9 252448.896 33.792 NA
1335 8719998.12 252462.653 33.866 NA
1336 8719997.68 252460.608 33.864 TB
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1337 8719997.26 252461.005 33.843 NA
1338 8719996.43 252449.804 33.783 PALM
1339 8719996.26 252448.706 33.814 PT
1340 8719996 252459.055 33.857 NA
1341 8719995.97 252462.12 33.87 AUX
1342 8719995.3 252449.02 33.837 PL
1343 8719995.72 252481.556 33.694 V
1344 8719994.51 252450.951 33.661 NA
1345 8719994.72 252482.297 33.823 NA
1346 8719993.97 252479.428 33.832 PAT
1347 8719993.1 252477.385 33.629 V
1348 8719992.4 252476.559 33.619 NA
1349 8719991.66 252476.548 33.636 NA
1350 8719991.29 252468.224 33.659 BZD
1351 8719990.93 252479.002 33.788 LP
1352 8719989.93 252455.206 33.689 SAR
1353 8719990.14 252477.605 33.782 PL
1354 8719987.16 252453.533 33.687 NA
1355 8719986.89 252460.6 33.663 NA
1356 8719985.6 252452.372 33.722 LP
1357 8719984.98 252468.951 33.594 V
1358 8719984.05 252473.984 33.583 NA
1359 8719983.19 252469.923 33.618 NA
1360 8719983.02 252472.289 33.603 NA
1361 8719981.54 252454.639 33.67 NA
1362 8719981.3 252468.687 33.635 NA
1363 8719980.46 252466.965 33.572 NA
1364 8719979.71 252457.895 33.642 PT
1365 8719979.69 252460.455 33.589 SAR
1366 8719979.08 252472.152 33.552 A
1367 8719977.53 252460.035 33.562 NA
1368 8719977.59 252485.217 33.408 V
1369 8719976.18 252462.142 33.558 SAR
1370 8719974.81 252459.897 33.617 NA
1371 8719975.03 252486.671 33.407 NA
1372 8719974.61 252474.557 33.581 NA
1373 8719972.61 252463.814 33.529 NA
1374 8719972.34 252478.807 33.491 CSTA
1375 8719971.57 252461.137 33.522 NA
1376 8719970.53 252461.837 33.44 PL
1377 8719971.42 252504.546 33.361 LP
1378 8719969.39 252474.399 33.536 CSTA
1379 8719968.98 252463.63 33.428 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1380 8719968.27 252481.178 33.537 NA
1381 8719968 252483.366 33.493 PAT
1382 8719968.23 252502.983 33.265 V
1383 8719965.52 252479.437 33.531 NA
1384 8719965.39 252476.335 33.51 CSTA
1385 8719965.86 252498.037 33.471 PL
1386 8719965.42 252494.532 33.528 LP
1387 8719964.39 252465.811 33.369 NA
1388 8719963.94 252493.549 33.284 V
1389 8719963.1 252494.736 33.293 V
1390 8719962.48 252481.032 33.517 NA
1391 8719962.38 252487.205 33.326 NA
1392 8719961.38 252485.363 33.359 NA
1393 8719960.71 252469.477 33.391 SAR
1394 8719959.9 252467.6 33.323 NA
1395 8719959.36 252482.599 33.432 A
1396 8719959.49 252500.612 33.274 V
1397 8719958.38 252479.6 33.344 NA
1398 8719958.28 252483.055 33.362 NA
1399 8719957.74 252470.63 33.392 NA
1400 8719958.31 252498.646 33.276 V
1401 8719958.38 252502.048 33.478 LP
1402 8719957.37 252477.885 33.296 V
1403 8719957.2 252498.026 33.276 NA
1404 8719956.28 252467.184 33.321 V
1405 8719956.91 252499.777 33.458 LP
1406 8719956.37 252483.744 33.273 NA
1407 8719956.49 252489.162 33.264 BZD
1408 8719955.57 252465.39 33.401 LP
1409 8719955.39 252464.706 33.388 NA
1410 8719956.27 252498.138 33.26 NA
1411 8719954.51 252465.427 33.335 V
1412 8719954.89 252499.293 33.462 PL
1413 8719948.46 252470.472 33.266 NA
1414 8719948.45 252470.854 33.241 V
1415 8719948.21 252471.845 33.265 NA
1416 8719947.8 252468.478 33.32 NA
1417 8719947.53 252472.432 33.244 NA
1418 8719947.37 252470.767 33.435 LP
1419 8719947.39 252471.96 33.437 NA
1420 8719947.21 252471.096 33.437 NA
1421 8719946.71 252468.777 33.42 NA
1422 8719946.26 252472.251 33.421 PT
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1423 8719944.68 252472.687 33.296 NA
1424 8719942.87 252484.86 33.188 V
1425 8719940.9 252488.672 33.211 V
1426 8719940.6 252486.173 33.337 NA
1427 8719940.35 252484.262 33.3 NA
1428 8719940.11 252481.41 33.151 NA
1429 8719940.26 252487.925 33.328 NA
1430 8719940.64 252507.637 33.139 SAR
1431 8719939.69 252486.377 33.336 TB
1432 8719938.82 252483.29 33.292 NA
1433 8719938.06 252509.195 33.246 NA
1434 8719937.36 252508.47 33.164 SAR
1435 8719935.52 252483.285 33.182 NA
1436 8719935.82 252510.654 33.303 SAR
1437 8719934.24 252500.648 33.096 NA
1438 8719933.86 252500.461 33.088 NA
1439 8719933.87 252503.252 33.124 SAR
1440 8719933.48 252498.189 33.084 NA
1441 8719933.55 252501.803 33.181 NA
1442 8719932.52 252488.273 33.266 PAT
1443 8719932.56 252503.034 33.216 NA
1444 8719931.41 252475.353 33.064 V
1445 8719931.2 252473.726 33.269 LP
1446 8719931.54 252496.233 33.06 V
1447 8719930.58 252485.855 33.14 AUX
1448 8719930.24 252505.448 33.119 NA
1449 8719930.12 252504.49 33.205 V
1450 8719930 252502.545 33.303 LP
1451 8719929.77 252495.834 33.034 NA
1452 8719917.55 252476.499 33.06 PL
1453 8719995.97 252462.12 33.87 2
1454 8719928.55 252484.412 33.068 NA
1455 8719925.57 252489.074 33.033 A
1456 8719921.39 252484.942 32.959 NA
1457 8719918.4 252489.584 32.948 NA
1458 8719912.55 252485.974 32.784 NA
1459 8719905.5 252490.97 32.662 NA
1460 8719901.59 252491.295 32.523 NA
1461 8719898.94 252487.438 32.454 NA
1462 8719898.96 252491.669 32.484 NA
1463 8719614.47 252460.171 27.721 LP
1464 8719888.98 252492.957 32.359 NA
1465 8719885.69 252489.057 32.179 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1466 8719885.04 252493.463 32.283 NA
1467 8719625.12 252468.793 27.667 NA
1468 8719879.54 252493.862 32.166 NA
1469 8719877.44 252489.646 32.078 NA
1470 8718168.21 252594.053 23.311 NA
1471 8718175.51 252596.401 23.689 PISTA
1472 8719872.36 252490.369 31.961 NA
1473 8718177.52 252598.772 24.075 NA
1474 8718176 252598.961 23.955 NA
1475 8718176.69 252599.342 24.049 PL
1476 8718176.56 252599.94 24.046 PISTA
1477 8719542.77 252487.291 26.883 LP
1478 8719867.21 252495.104 31.893 NA
1479 8719861.53 252491.438 31.737 NA
1480 8718176.61 252610.421 24.97 NA
1481 8719542.83 252496.532 26.997 NA
1482 8718177.63 252610.579 25.026 NA
1483 8719537.96 252497.083 26.985 NA
1484 8719543.64 252496.844 26.995 LP
1485 8718175.95 252611.465 25.104 NA
1486 8719856.25 252491.998 31.622 NA
1487 8719510.52 252503.001 26.949 LP
1488 8719533.77 252501.882 27.183 NA
1489 8719548.57 252501.229 27.121 LP
1490 8719853.84 252499.146 31.345 LP
1491 8719533.6 252503.234 27.15 PISTA
1492 8718180.78 252616.332 25.784 NA
1493 8718181.32 252616.467 25.81 NA
1494 8718180.67 252616.817 25.792 NA
1495 8719567.62 252501.425 27.231 PL
1496 8718178.19 252617.606 25.875 NA
1497 8719616.7 252497.643 27.829 LP
1498 8718178.98 252617.848 25.863 NA
1499 8719627.2 252497.035 27.618 NA
1500 8719627.2 252497.036 27.618 LP
1501 8718181.24 252618.052 25.861 NA
1502 8718179.14 252618.279 25.859 NA
1503 8719599.26 252499.799 27.614 NA
1504 8718177.67 252618.453 25.879 NA
1505 8719597.61 252500.207 27.388 PT
1506 8718182.12 252618.385 25.91 NA
1507 8719616.5 252498.969 27.794 V
1508 8718178.73 252619.031 25.916 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1509 8719627.73 252498.156 27.694 PL
1510 8719627.37 252498.413 27.52 NA
1511 8718181.8 252619.256 26.006 NA
1512 8718179.66 252619.508 25.982 NA
1513 8719768.23 252486.979 28.954 LP
1514 8718183.77 252619.212 25.995 NA
1515 8719658.27 252496.231 27.808 PL
1516 8719658.66 252496.523 27.806 NA
1517 8718181.95 252620.124 26.428 NA
1518 8719841.08 252481.678 31.343 PL
1519 8719658.68 252496.929 27.71 V
1520 8719777.03 252487.087 28.941 NA
1521 8718183.78 252620.201 26.084 NA
1522 8719778.89 252487.139 29.578 LP
1523 8719769.63 252487.914 29.206 V
1524 8718177.77 252620.783 25.984 NA
1525 8718184.66 252620.251 26.159 NA
1526 8718180.37 252620.818 26.205 NA
1527 8718180.65 252620.86 26.414 NA
1528 8719769.57 252488.29 29.154 V
1529 8719719.57 252492.506 28.483 V
1530 8719777.22 252487.804 29.347 NA
1531 8718178.54 252621.399 26.073 V
1532 8718185.32 252620.894 26.166 NA
1533 8719840.64 252483.193 31.324 LP
1534 8718180.69 252621.727 26.134 NA
1535 8719510.87 252510.8 27.026 NA
1536 8719843.61 252483.086 31.367 LP
1537 8719769.25 252489.31 29.097 NA
1538 8718177.81 252622.133 26.266 NA
1539 8719777.89 252488.63 29.4 NA
1540 8718182.98 252621.822 26.149 NA
1541 8719749.89 252491.109 28.785 NA
1542 8718185.25 252621.807 26.248 NA
1543 8719883.01 252480.14 32.217 NA
1544 8719768.72 252489.76 29.157 NA
1545 8719622.39 252501.987 27.506 BZD
1546 8719530.25 252509.712 27.126 V
1547 8719778.64 252489.022 29.363 V
1548 8718183.82 252622.129 26.233 NA
1549 8718186.3 252621.938 26.288 NA
1550 8718180.34 252622.554 26.171 NA
1551 8718704 252579.125 21.009 LP
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1552 8719813.8 252486.526 30.597 PL
1553 8719549.69 252508.615 27.138 NA
1554 8718181.22 252623.01 26.279 NA
1555 8718183.51 252623.019 26.272 NA
1556 8719839.7 252484.974 31.116 V
1557 8719871.62 252482.436 31.991 PL
1558 8718187.29 252623.02 26.325 NA
1559 8719844.66 252484.909 31.214 PL
1560 8718178.53 252623.967 26.44 NA
1561 8719874.05 252482.541 31.877 V
1562 8718183.88 252623.875 26.296 NA
1563 8719542.44 252510.666 27.144 BZD
1564 8718184.38 252624.169 26.332 NA
1565 8719532.77 252511.676 27.138 NA
1566 8719534.11 252511.627 27.12 AUX
1567 8718188.49 252624.281 26.559 NA
1568 8718182.05 252624.851 26.289 NA
1569 8719586.59 252507.754 27.376 NA
1570 8719614.78 252505.603 27.463 NA
1571 8719601.62 252506.958 27.401 NA
1572 8719628.74 252504.76 27.553 NA
1573 8719607.19 252506.669 27.606 NA
1574 8719610.56 252506.553 27.503 PALM
1575 8718185.11 252625.637 26.506 NA
1576 8718198.78 252624.533 26.423 PISTA
1577 8718200.72 252624.43 26.594 NA
1578 8719511.06 252515.087 27.086 V
1579 8719530.55 252514.016 27.139 NA
1580 8719630.22 252505.728 27.654 NA
1581 8718200.12 252625.092 26.543 NA
1582 8719614.65 252507.048 27.587 NA
1583 8718182.38 252626.599 26.591 V
1584 8719634.86 252505.391 27.505 NA
1585 8719614.92 252507.167 27.572 V
1586 8719619.55 252506.822 27.485 NA
1587 8718221.08 252623.556 26.765 LP
1588 8719639.89 252505.16 27.49 NA
1589 8718182.98 252626.909 26.604 NA
1590 8719549.22 252512.992 27.172 SAR
1591 8719644.65 252505.087 27.64 NA
1592 8719628.86 252506.482 27.7 NA
1593 8719649.14 252504.908 27.756 NA
1594 8719594.46 252509.529 27.458 TB
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1595 8719653.49 252504.666 27.788 NA
1596 8719658.56 252504.417 27.816 NA
1597 8718178.16 252628.082 26.735 NA
1598 8719627.51 252507.131 27.656 AUX 19
1599 8719616.88 252508.131 27.469 NA
1600 8719590.43 252510.396 27.368 NA
1601 8719614.83 252508.557 27.558 NA
1602 8719597.21 252510.072 27.512 NA
1603 8718706.23 252584.437 21.119 PAT
1604 8718706.3 252584.463 21.015 SAR
1605 8719614.68 252508.671 27.592 NA
1606 8719601.74 252509.818 27.517 NA
1607 8719609.99 252509.231 27.381 A
1608 8718202.88 252626.769 26.754 LP
1609 8719628.97 252508.003 27.65 NA
1610 8719699.81 252502.31 28.182 NA
1611 8718353.94 252614.631 24.586 NA
1612 8718210.61 252626.601 26.759 V
1613 8719761.56 252497.181 28.928 V
1614 8719614 252509.515 27.563 A
1615 8719708.27 252501.715 28.211 NA
1616 8719717.73 252501.119 28.329 NA
1617 8719782.77 252495.868 29.49 NA
1618 8719630.1 252508.653 27.658 NA
1619 8719630.08 252508.663 27.767 NA
1620 8718221.23 252626.297 26.715 LP
1621 8718685.45 252587.637 20.834 LP
1622 8718190.79 252629.077 26.402 V
1623 8719614.93 252510.246 27.493 V
1624 8718378.9 252613.408 23.388 LP
1625 8719640.23 252508.271 27.691 NA
1626 8718203.62 252628.217 26.76 V
1627 8719741.34 252499.927 28.639 NA
1628 8719747.62 252499.445 28.682 NA
1629 8719645.05 252508.025 27.779 NA
1630 8719753.75 252499.097 28.743 NA
1631 8719757.22 252498.861 28.896 NA
1632 8719750.87 252499.393 28.689 NA
1633 8718717.02 252585.676 21.355 LP
1634 8718327.82 252618.161 24.554 NA
1635 8719649.33 252507.935 27.791 NA
1636 8719628.99 252509.656 27.566 V
1637 8719760.34 252498.797 29.013 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1638 8718194.93 252629.492 26.77 NA
1639 8719654.12 252507.746 27.824 NA
1640 8718193.68 252629.637 27.285 AUX 27
1641 8718690.74 252588.229 20.762 V
1642 8719842.29 252492.138 31.136 NA
1643 8719658.53 252507.554 27.927 PALM
1644 8719805.25 252495.596 30.218 NA
1645 8719792.94 252496.659 29.851 NA
1646 8719844.26 252492.416 31.134 NA
1647 8719670.98 252506.988 28.001 NA
1648 8718195.21 252630.174 26.864 NA
1649 8719786.95 252497.389 29.672 NA
1650 8719801.9 252496.145 30.126 NA
1651 8718158.09 252633.332 26.753 V
1652 8718215.5 252628.649 26.823 NA
1653 8719815.19 252495.188 30.503 NA
1654 8718416.73 252611.913 22.661 NA
1655 8719761.57 252499.719 29.034 NA
1656 8718187.15 252631.121 26.723 V
1657 8719844.62 252492.864 31.166 V
1658 8718157.26 252633.688 26.747 LP
1659 8719679.31 252506.681 28.064 NA
1660 8719820.53 252494.953 30.694 NA
1661 8719679.11 252506.799 28.026 NA
1662 8719825.16 252494.699 30.776 NA
1663 8718715.3 252587.447 21.064 V
1664 8719830.57 252494.387 30.893 NA
1665 8718712.4 252587.749 21.043 NA
1666 8719687.54 252506.376 28.087 A
1667 8719687.71 252506.377 28.057 NA
1668 8718229.18 252628.097 26.607 NA
1669 8719835.45 252494.05 30.961 NA
1670 8718194.85 252630.968 26.965 V
1671 8719782.86 252498.463 29.589 NA
1672 8718185.17 252631.874 26.698 NA
1673 8719759.64 252500.592 29.017 AUX 18
1674 8719840.68 252493.975 30.9 NA
1675 8718289.93 252623.439 25.599 PAT
1676 8719780.27 252499.281 29.409 NA
1677 8718353.95 252618.358 24.742 LP
1678 8718722.93 252587.599 21.148 LP
1679 8718444.16 252610.901 22.871 LP
1680 8718264.52 252626.133 25.966 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1681 8719711.49 252505.394 28.302 NA
1682 8719510.26 252522.205 27.032 PT
1683 8719764.65 252500.996 29.019 NA
1684 8718723.87 252587.983 21.513 V
1685 8718239.19 252628.503 26.503 NA
1686 8719719.36 252505.082 28.427 NA
1687 8719859.74 252493.383 31.695 NA
1688 8719842.31 252494.905 31.203 V
1689 8719761.76 252501.693 29.108 NA
1690 8718228.55 252629.741 26.648 NA
1691 8719553.11 252519.229 27.587 PL
1692 8718223.25 252630.219 26.706 PISTA
1693 8718725.56 252588.373 21.524 LP
1694 8719549.59 252519.618 27.223 PT
1695 8718165.93 252635.115 27.012 BZD
1696 8718169.81 252634.929 27.07 NA
1697 8719735.14 252504.347 28.604 NA
1698 8719525.44 252521.865 27.219 NA
1699 8718190.33 252633.355 27.11 NA
1700 8718210.95 252631.684 26.905 NA
1701 8718178.39 252634.412 27.184 NA
1702 8719782.98 252500.529 29.599 NA
1703 8718392.06 252616.617 24.256 SAR
1704 8719544.78 252520.507 27.262 NA
1705 8719742.88 252503.989 28.689 NA
1706 8718483.23 252609.167 22.456 LP
1707 8719760.77 252502.58 28.986 PALM
1708 8719510.18 252523.499 27.141 LP
1709 8719751.1 252503.443 28.812 NA
1710 8719534.93 252521.502 27.247 V
1711 8718177.19 252634.968 27.105 NA
1712 8719757.52 252503.117 28.945 A
1713 8718199.47 252633.169 27.014 NA
1714 8719581.97 252517.935 27.494 PL
1715 8719585.49 252517.702 27.34 V
1716 8719841.37 252496.357 31.196 AUX 17
1717 8718722.68 252589.718 21.236 V
1718 8718350.58 252620.927 24.783 PAT
1719 8718348.58 252621.176 24.816 PAT
1720 8718407.94 252616.317 23.262 SAR
1721 8718430.02 252614.571 23.617 R
1722 8719851.65 252495.948 31.338 BZD
1723 8719804.54 252499.896 30.228 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1724 8719562.91 252520.061 27.274 NA
1725 8719545.69 252521.522 27.29 NA
1726 8719533.54 252522.584 27.462 LP
1727 8719568.22 252519.744 27.339 SAR
1728 8719842.62 252496.87 31.163 NA
1729 8719589.58 252518.039 27.584 PT
1730 8719789.67 252501.343 29.804 A
1731 8719545.52 252521.821 27.504 NA
1732 8719606.36 252516.752 27.428 V
1733 8719584.68 252518.583 27.447 SAR
1734 8718252.87 252629.739 26.118 NA
1735 8719859.98 252495.679 31.694 TB
1736 8719544.16 252522.058 27.257 V
1737 8719615.33 252516.231 27.645 NA
1738 8718177.39 252636.249 27.245 NA
1739 8719815.87 252499.557 30.282 NA
1740 8719563.66 252520.636 27.383 NA
1741 8719567.52 252520.43 27.341 NA
1742 8718448.27 252613.915 23.08 NA
1743 8719762.09 252504.347 28.99 V
1744 8718229.01 252632.323 26.548 NA
1745 8718179.79 252636.519 27.316 PAT
1746 8718726.05 252590.976 21.565 V
1747 8718726.88 252590.908 21.599 PL
1748 8719830.47 252498.903 30.866 NA
1749 8719837.73 252498.299 30.994 A
1750 8719585.7 252519.401 27.561 NA
1751 8719820.31 252499.89 30.531 A
1752 8718178.31 252636.956 27.274 NA
1753 8719840.83 252498.23 31.156 A
1754 8719607.33 252517.906 27.58 NA
1755 8719783.02 252503.246 29.499 NA
1756 8718699.13 252593.706 21.09 PT
1757 8719610.26 252517.682 27.56 LP
1758 8719607.02 252518.046 27.563 NA
1759 8718472.42 252612.856 22.735 NA
1760 8718462.62 252613.821 22.89 NA
1761 8719845.12 252498.493 31.154 NA
1762 8719865.93 252496.778 31.86 PAT
1763 8718553.59 252606.395 21.609 LP
1764 8718724.35 252592.278 21.313 NA
1765 8718193.28 252636.694 27.167 NA
1766 8718253.4 252631.721 26.091 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1767 8718560.76 252606.118 21.63 LP
1768 8719649.58 252515.485 27.686 V
1769 8718420.91 252618.034 23.512 SAR
1770 8719844.58 252499.278 31.143 NA
1771 8718214.91 252635.315 26.712 NA
1772 8719544.53 252524.419 27.555 PT
1773 8718423.48 252617.978 23.768 PAT
1774 8719842.87 252499.611 31.107 V
1775 8718162.88 252639.833 26.736 V
1776 8718481.99 252613.395 22.582 NA
1777 8718162.13 252640.274 26.775 LP
1778 8718202.74 252637.042 26.93 NA
1779 8718445.55 252617.04 23.441 PAT
1780 8718513.8 252611.434 22.107 NA
1781 8718168.52 252640.279 27.403 PISTA
1782 8719649.67 252516.72 27.828 V
1783 8718239.69 252634.5 26.468 PISTA
1784 8718702.88 252595.853 21.193 PL
1785 8719673.57 252514.862 27.989 PL
1786 8718184.75 252639.162 27.321 NA
1787 8718497.15 252613.194 22.342 SAR
1788 8718467.91 252616.244 22.974 PAT
1789 8718233.2 252636.53 26.55 NA
1790 8718172.21 252641.718 27.523 BZD
1791 8718262.76 252634.179 26.241 PAT
1792 8719694.83 252514.787 28.294 PT
1793 8718494.59 252614.964 22.456 NA
1794 8718637.51 252603.198 22.84 LP
1795 8718489.6 252615.553 22.769 PAT
1796 8718249.94 252635.692 26.266 NA
1797 8719705.8 252514.319 28.418 PL
1798 8718227.98 252637.767 26.769 PAT
1799 8718500.01 252615.198 22.402 NA
1800 8718317.67 252630.655 25.127 PISTA
1801 8718708.78 252598.144 21.296 NA
1802 8719736.52 252512.43 28.788 PT
1803 8718292.8 252633.061 25.723 PL
1804 8718548.42 252611.735 21.939 SAR
1805 8718526.22 252613.706 22.138 PAT
1806 8718526.4 252613.861 22.215 NA
1807 8719741.3 252512.561 28.868 PL
1808 8718318.09 252631.342 25.146 PISTA
1809 8718560.91 252611.246 22.027 SAR
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1810 8719766.54 252510.649 29.279 PL
1811 8719776.31 252509.993 29.305 V
1812 8718260.18 252636.636 26.638 LP
1813 8718353.36 252628.878 24.749 PISTA
1814 8718707.28 252599.542 21.395 LP
1815 8718219.42 252640.393 26.757 NA
1816 8718243.36 252638.467 26.79 NA
1817 8719797.46 252508.859 30.075 NA
1818 8719741.02 252513.752 28.848 LP
1819 8719793.11 252509.642 29.971 PT
1820 8718324.44 252632.261 25.425 NA
1821 8718514.12 252616.482 22.272 NA
1822 8719827.95 252506.959 30.901 PL
1823 8718455.93 252621.566 23.17 NA
1824 8719831.38 252506.782 30.789 V
1825 8719535.56 252531.497 27.668 PL
1826 8718709.64 252600.484 21.47 NA
1827 8719769.49 252512.205 29.395 LP
1828 8718533.94 252615.459 22.054 NA
1829 8719850.1 252505.775 31.306 NA
1830 8718330.09 252632.659 25.304 GRAD
1831 8719858.9 252505.098 31.547 V
1832 8718588.95 252611.119 22.094 PAT
1833 8719776.38 252512.068 29.49 NA
1834 8719860.21 252505.083 31.731 PL
1835 8718746.89 252598.148 22.079 PAT
1836 8719858.02 252505.506 31.493 NA
1837 8719841.83 252506.883 31.279 PL
1838 8719850.9 252506.153 31.344 NA
1839 8718354.36 252631.122 24.86 PL
1840 8718418.36 252625.985 23.686 NA
1841 8718211.41 252643.387 26.854 NA
1842 8718469.53 252621.918 23.025 NA
1843 8718560.75 252614.531 21.936 PISTA
1844 8718403.49 252627.691 23.914 R
1845 8719830.17 252508.737 30.988 LP
1846 8719857.66 252506.506 31.479 NA
1847 8718654.25 252606.966 22.21 LP
1848 8719775.68 252513.446 29.474 LP
1849 8719859.4 252506.627 31.702 LP
1850 8718489.93 252620.985 22.694 NA
1851 8719851.45 252507.365 31.345 V
1852 8718328.66 252634.573 25.506 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1853 8719880.4 252505.121 32.215 LP
1854 8718381.94 252630.232 24.405 PAT
1855 8719848.47 252507.856 31.478 LP
1856 8718754.25 252599.176 21.744 NA
1857 8719850.08 252507.754 31.49 PAT
1858 8718749.72 252599.591 21.947 NA
1859 8718315.48 252635.831 25.579 NA
1860 8718205.01 252645.303 27.046 PT
1861 8718516 252619.617 22.335 NA
1862 8718626.65 252610.404 21.97 PAT
1863 8718156.33 252649.666 27.347 LP
1864 8718457.92 252624.553 23.094 NA
1865 8718644.01 252609.034 22.224 PAT
1866 8718723.96 252602.453 21.784 SAR
1867 8718654.39 252608.444 22.228 PT
1868 8718707.31 252604.178 22.455 LP
1869 8718709.5 252604.1 21.822 V
1870 8718400.98 252630.016 24.122 NA
1871 8718414.45 252628.916 23.975 PL
1872 8718407.7 252629.54 24.252 PT
1873 8718403.12 252629.923 24.04 GRAD
1874 8718679.1 252607.007 22.24 V
1875 8718752.65 252601.147 21.93 NA
1876 8718429.5 252628.279 23.832 NA
1877 8718436.62 252627.748 23.599 R
1879 8718749.98 252601.727 21.961 V
1880 8719850.17 252509.979 31.478 NA
1881 8718754.18 252601.668 21.954 NA
1882 8718193.36 252648.478 27.16 NA
1883 8718721.48 252604.471 21.854 NA
1884 8718443.56 252627.691 23.686 PL
1885 8718187.51 252649.102 27.288 PAT
1886 8718688.04 252607.334 22.816 LP
1887 8718179.3 252649.821 27.174 PISTA
1888 8718768.23 252600.687 21.741 LP
1889 8718157.66 252651.744 27.874 LP
1890 8718705.65 252606.127 22.19 V
1891 8718477.76 252625.324 22.92 AUX 26
1892 8718683.27 252608.27 22.21 NA
1893 8718704.74 252606.496 22.242 PAT
1894 8718437.2 252628.866 23.838 LP
1895 8718177.6 252650.627 27.221 PISTA
1896 8718514.82 252622.528 22.308 PISTA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1897 8718485.86 252624.983 22.756 R
1898 8718195.24 252649.343 27.355 LP
1899 8718496.1 252624.307 22.61 NA
1900 8718162.02 252652.213 27.761 PISTA
1901 8718472.96 252626.493 23.383 PL
1902 8718184.07 252650.616 27.215 R
1903 8718566.02 252619.145 21.957 NA
1904 8718700.52 252607.94 22.16 NA
1905 8718474.32 252627.031 23.178 NA
1906 8718474.35 252627.036 21.152 GRAD
1907 8718526.21 252622.79 22.169 NA
1908 8718154.29 252654.1 27.926 NA
1909 8718756.14 252604.117 22.006 NA
1910 8718477.5 252627.418 21.02 NA
1911 8718703.47 252608.709 22.147 PISTA
1912 8718741.89 252605.503 22.021 NA
1913 8718768.5 252603.299 22.162 NA
1914 8718768.5 252603.302 22.163 PAT
1915 8718154.65 252655.097 27.881 V
1916 8718723.26 252607.768 22.431 SAR
1917 8718506.9 252625.829 22.608 MURO
1918 8718722.91 252607.866 22.167 NA
1919 8718758.78 252604.956 22.037 NA
1920 8718735.1 252606.932 22.506 SAR
1921 8718860.57 252596.665 22.828 LP
1922 8718736.46 252607.1 22.099 AUX 25
1923 8718541.43 252623.447 22.091 PAT
1924 8718843.01 252598.555 22.714 AUX 24
1925 8718153.23 252656.319 27.98 PL
1926 8718734.91 252607.802 22.12 NA
1927 8718478.74 252629.32 23.75 NA
1928 8718861.52 252597.643 22.857 LP
1929 8718508.49 252627.149 23.421 A
1930 8718505.09 252627.509 22.986 NA
1931 8718169.98 252655.503 27.354 NA
1932 8718783.79 252604.449 22.054 NA
1933 8718570.1 252622.317 22.025 PL
1934 8718486.75 252629.415 22.958 NA
1935 8718767.48 252606.255 22.049 NA
1937 8718479.13 252630.532 23.301 V
1938 8718525.53 252626.86 23.657 PALM
1939 8718513.17 252627.965 23.504 NA
1940 8718850.26 252599.837 22.785 PAT
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1941 8718594.46 252621.217 22.143 PAT
1942 8718820.79 252602.78 22.276 BZD
1943 8718751.94 252608.711 22.172 NA
1944 8718507.42 252629.133 23.555 PAT
1945 8718479.31 252631.626 23.35 NA
1946 8718474.79 252632.043 24.129 LP
1947 8718146.86 252659.41 28.127 LP
1948 8718506.4 252629.421 23.183 NA
1949 8718596.53 252621.982 22.191 NA
1950 8718149.33 252659.313 27.995 NA
1951 8718176.44 252657.189 28.089 PT
1952 8718658.31 252617.068 22.153 PISTA
1953 8718850.49 252601.342 22.547 NA
1954 8718623.44 252620.337 22.26 PL
1955 8718173.4 252657.924 28.184 NA
1956 8718161.66 252658.91 27.577 R
1957 8718877.19 252599.63 22.82 R
1958 8718741.34 252611.007 22.18 NA
1959 8719858.44 252517.865 31.603 V
1960 8718177.23 252658.172 28.357 LP
1961 8718481.6 252633.013 23.16 V
1962 8718900.77 252598.126 22.98 NA
1963 8718521.51 252629.864 23.579 V
1964 8718648.29 252619.369 22.218 PAT
1965 8718168.73 252659.725 28.02 NA
1966 8718490.09 252632.941 23.044 PL
1967 8718153.43 252661.401 27.898 NA
1968 8718665.94 252618.998 22.102 PT
1969 8718676.71 252618.183 22.274 PL
1970 8718524.47 252630.956 23.828 NA
1971 8718149.81 252662.512 28.028 MURO
1972 8718992.22 252592.337 23.906 LP
1973 8718921.55 252598.574 22.962 NA
1974 8719860.41 252520.343 31.759 LP
1975 8718665.74 252620.051 22.168 SAR
1976 8718753.96 252613.093 22.08 PISTA
1977 8718756.54 252612.993 22.105 PISTA
1978 8718908.69 252600.304 22.971 NA
1979 8718681.29 252619.371 22.044 SAR
1980 8718601.63 252626.211 22.585 NA
1981 8718685.39 252619.248 22.051 SAR
1982 8718721.36 252616.394 22.278 R
1983 8718692.07 252618.96 22.111 SAR
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
1984 8718504.06 252634.855 23.07 V
1985 8718711.92 252617.532 22.423 PT
1986 8718729.54 252616.237 22.379 PL
1987 8718701.68 252618.6 22.117 NA
1988 8718627.26 252624.875 22.29 V
1989 8718707.74 252618.35 22.164 SAR
1990 8719046.36 252590.119 24.332 NA
1991 8718607.85 252626.724 22.411 GRAD
1992 8719005.99 252593.559 24.025 PAT
1993 8718159.44 252664.224 27.525 NA
1994 8718636.03 252624.531 22.274 NA
1995 8718974.63 252596.307 23.506 R
1996 8718700.85 252619.19 22.073 NA
1997 8718503.68 252635.679 23.45 LP
1998 8718139.42 252666.104 29.986 NA
1999 8718693.85 252619.859 22.065 NA
2000 8718609.9 252626.864 22.32 LP
2001 8718540.51 252632.663 24.041 NA
2002 8719057.77 252589.686 24.426 NA
2003 8718601.87 252627.741 22.807 MURO
2004 8718665.74 252622.427 22.192 V
2005 8718754.15 252615.106 22.218 PAT
2006 8718604.48 252627.606 22.626 GRAD
2007 8719015.74 252593.365 24.061 V
2008 8718675.56 252621.899 22.076 NA
2009 8718760.24 252614.886 22.084 NA
2010 8718627.26 252626.059 22.298 NA
2011 8718733.24 252617.222 22.279 NA
2012 8719007.73 252594.386 23.794 NA
2013 8718636.09 252625.414 22.288 V
2014 8718681.39 252621.647 22.108 V
2015 8718685.51 252621.507 22.088 NA
2016 8718700.27 252620.312 22.03 NA
2017 8719040.43 252592.008 24.251 NA
2018 8719030.54 252592.99 24.082 NA
2019 8718639.98 252625.605 22.183 P
2020 8718645.46 252625.315 22.3 NA
2021 8718779.3 252614.152 22.26 PL
2022 8719046.39 252592.089 24.28 NA
2023 8718687.8 252622.244 22.092 NA
2024 8718789.97 252613.756 22.247 NA
2025 8719025.07 252594.264 23.891 NA
2026 8719037.27 252593.276 23.954 BZD
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2027 8719057.98 252591.632 24.422 NA
2028 8718665.55 252624.388 22.295 V
2029 8718141.39 252668.146 29.979 R
2030 8718519.35 252636.64 23.468 PL
2031 8718804.43 252612.861 22.467 PAT
2032 8718694.65 252622.03 22.013 V
2033 8718849.57 252609.225 22.495 V
2034 8718700.99 252621.712 22.065 V
2035 8718699.9 252621.842 22.009 NA
2036 8718776.57 252615.451 22.074 NA
2037 8718799.35 252613.599 22.324 PT
2038 8718707.59 252621.463 22.1 V
2039 8718867.46 252608.321 22.636 NA
2040 8718807.68 252613.397 22.428 SAR
2041 8719081.89 252590.517 24.596 PAT
2042 8718695 252622.893 22.006 P
2043 8718557.38 252634.389 24.277 NA
2044 8719030.42 252595.12 23.902 PISTA
2045 8719185.2 252582.204 25.418 LP
2046 8718559.86 252634.581 24.321 PT
2047 8718833.24 252611.788 22.704 PL
2048 8718707.46 252622.36 22.23 NA
2049 8718750.79 252618.904 21.671 PALM
2050 8718754.53 252618.703 21.73 NA
2051 8718160.71 252668.394 28.919 NA
2052 8718873.92 252608.938 22.728 NA
2053 8719201.11 252581.741 24.997 LP
2054 8719059.79 252593.795 24.15 PISTA
2055 8718848.71 252611.459 22.565 SAR
2056 8718908.97 252606.48 22.969 PISTA
2057 8718846.7 252611.727 22.781 PT
2058 8718861 252610.638 22.805 NA
2059 8718770.19 252618.273 22.238 A
2060 8719102.09 252590.645 24.54 NA
2061 8718863.88 252610.608 22.687 NA
2062 8718824.01 252613.98 22.582 NA
2063 8718137.49 252671.531 28.841 MURO
2064 8718835.25 252613.487 22.649 NA
2065 8719184.99 252584.429 25.488 NA
2066 8718759.54 252620.068 21.962 LP
2067 8718808.02 252616.154 22.519 NA
2068 8719192.77 252584.076 25.122 V
2069 8718765.26 252619.803 21.979 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2070 8718846.52 252613.037 22.657 NA
2071 8718889.36 252609.567 23.043 PL
2072 8718143.38 252671.998 28.049 NA
2073 8719158.72 252587.351 25.202 PAT
2074 8719202.45 252583.722 25.406 SAR
2075 8718887.37 252610.08 22.876 PT
2076 8718475.04 252644.592 25.1 LP
2077 8718861.77 252612.731 22.718 NA
2078 8718910.43 252608.763 23.184 NA
2079 8719167.69 252587.407 25.204 NA
2080 8719267.41 252579.366 26.207 NA
2081 8718918.48 252608.548 23.423 NA
2082 8718849.91 252614.395 22.682 NA
2083 8718807.66 252618.055 22.707 LP
2084 8719191.89 252586.08 25.252 V
2085 8718137.29 252674.229 28.522 PAT
2086 8719190.24 252586.399 25.376 PT
2087 8719203.25 252585.631 25.478 V
2088 8719287.72 252578.678 26.331 NA
2089 8718925.76 252608.899 23.431 NA
2090 8718929.62 252608.581 23.62 PAT
2091 8718939.81 252607.863 23.386 PL
2092 8718868.14 252613.923 22.829 NA
2093 8718868.14 252613.923 22.829 NA
2094 8718860.39 252614.583 22.765 NA
2095 8718936.04 252608.289 23.36 PT
2096 8718156.84 252673.473 29.971 NA
2097 8718593.45 252637.134 24.855 PL
2098 8718858.6 252615.043 22.728 NA
2099 8719267.43 252581.013 26.228 NA
2100 8718958.54 252606.97 23.63 PAT
2101 8718595.61 252637.499 24.974 V
2102 8718850.46 252616.314 22.832 NA
2103 8718874.63 252614.302 22.894 NA
2104 8719030.55 252601.385 23.981 NA
2105 8718853.69 252616.207 22.778 NA
2106 8718592.35 252638.076 24.971 PAT
2107 8718967.48 252606.852 23.795 PL
2108 8719041.72 252600.687 24.067 NA
2109 8719287.85 252580.156 26.344 SAR
2110 8718881.28 252614.135 22.904 NA
2111 8718858.58 252616.058 22.817 V
2112 8719057.86 252599.469 24.188 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2113 8719239.83 252584.34 25.786 PAT
2114 8719190.09 252588.702 25.336 PISTA
2115 8718971.41 252606.957 23.587 NA
2116 8719062.01 252599.582 24.296 NA
2117 8719215.32 252586.816 25.412 NA
2118 8719247.77 252584.139 25.855 BZD
2119 8719247.77 252584.14 25.855 NA
2120 8718978.11 252606.823 23.75 NA
2121 8719266.43 252582.821 26.103 V
2122 8718992.41 252605.761 23.935 PAT
2123 8718983.59 252606.552 23.86 PT
2124 8718147.65 252676.489 27.745 NA
2125 8719391.32 252572.863 27.269 LP
2126 8719057.07 252600.807 24.207 NA
2127 8719379.48 252574.323 27.217 LP
2128 8718904.18 252614.089 22.96 LP
2129 8719288.11 252582.083 26.358 NA
2130 8719018.28 252604.622 23.906 NA
2131 8719006.74 252605.824 24.114 NA
2132 8719233.25 252586.953 25.744 NA
2133 8719274.98 252583.649 26.175 V
2134 8719037.47 252603.511 24.252 NA
2135 8719041.19 252603.737 24.372 PAT
2136 8719309.31 252581.416 26.55 PAT
2137 8719426.93 252571.635 27.485 LP
2138 8719031.01 252604.746 24.081 PT
2139 8718481.23 252650.847 25.639 NA
2140 8719300.45 252582.504 26.335 NA
2141 8719024.29 252605.789 24.058 NA
2142 8719379.29 252576.284 26.722 NA
2143 8719379.46 252576.29 27.13 V
2144 8719546.84 252562.512 28.63 PT
2145 8719046.54 252604.453 24.178 NA
2146 8719068.77 252602.987 24.438 PL
2147 8719548.29 252563.069 28.67 LP
2148 8719057.09 252604.07 24.267 NA
2149 8719069.51 252603.173 24.494 PL
2150 8718569.4 252645.035 24.708 LP
2151 8719437.67 252572.895 27.555 V
2152 8719574.08 252561.604 29.082 NA
2153 8719057.04 252604.902 24.338 V
2154 8719058.09 252604.82 24.336 SAR
2155 8719345.89 252580.856 26.69 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2156 8719372.87 252578.727 26.975 PAT
2157 8719162.16 252596.573 25.169 NA
2158 8719392.52 252577.379 27.387 PT
2159 8719099.47 252602 24.732 NA
2160 8719110.95 252601.107 25.251 PL
2161 8719190.62 252594.998 25.517 NA
2162 8719006.87 252610.389 24.006 LP
2163 8719412.89 252576.665 27.495 NA
2164 8719425.82 252575.588 27.486 V
2165 8719415.09 252576.547 27.593 PAT
2166 8719137.73 252599.975 25.409 PL
2167 8719352.19 252582.08 26.835 PISTA
2168 8719446.02 252574.441 27.918 NA
2169 8719048.43 252607.772 24.224 NA
2170 8719536.02 252567.419 28.649 LP
2171 8719548.65 252566.415 28.722 NA
2172 8719471.73 252572.859 28.121 PT
2173 8719045.42 252608.981 24.307 LP
2174 8718591.34 252647.096 24.651 V
2175 8719496.6 252571.553 28.308 PAT
2176 8719210.15 252595.579 25.807 NA
2177 8719048.99 252609.09 24.248 NA
2178 8719547.11 252567.663 28.52 V
2179 8719230.17 252594.258 25.769 NA
2180 8719058.23 252608.641 24.412 LP
2181 8719528.72 252569.636 28.602 PT
2182 8718126.22 252686.765 28.554 MURO
2183 8719171.96 252599.587 25.51 PL
2184 8719538.53 252569.074 28.475 LP
2185 8719548.76 252568.613 28.583 NA
2186 8719195.38 252598.115 25.638 PT
2187 8719047.56 252610.466 24.583 NA
2188 8719254.29 252593.251 25.947 AUX 22
2189 8719245.07 252594.04 25.874 NA
2190 8719272.22 252591.816 26.05 V
2191 8719558.96 252567.978 28.901 PL
2192 8719217.25 252596.733 25.657 SAR
2193 8718129.86 252687.996 28.26 NA
2194 8719224.8 252596.758 26.234 PL
2195 8719484.27 252575.187 28.052 NA
2196 8719544.41 252570.258 28.561 BZD
2197 8719279.71 252592.597 26.123 R
2198 8719166.75 252602.067 25.168 PAT
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2199 8719256.2 252595.178 26.136 NA
2200 8719252.48 252595.552 26.333 PL
2201 8719270.43 252594.449 26.091 NA
2202 8719256.13 252595.721 26.701 LP
2203 8719269.27 252595.052 26.13 NA
2204 8719351.55 252588.369 26.83 NA
2205 8719277.45 252594.615 26.504 PL
2206 8719271.86 252595.124 26.461 PT
2207 8719049.3 252613.886 24.286 NA
2208 8719296.72 252593.48 26.52 NA
2209 8719268.56 252595.875 26.188 SAR
2210 8719304.68 252593.428 26.528 PL
2211 8719196.74 252602.883 25.776 NA
2212 8719128.7 252608.646 26.121 PT
2213 8719217.53 252601.534 25.872 NA
2214 8719378.82 252588.451 27.049 NA
2215 8719333.3 252592.284 26.95 PL
2216 8718134.29 252692.415 27.93 NA
2217 8719267.07 252598.766 26.329 V
2218 8719360.22 252591.124 27.127 PL
2219 8718142.7 252693.297 30.478 NA
2220 8719485.34 252581.464 28.12 PISTA
2221 8719386.48 252589.876 27.67 PL
2222 8719266.54 252599.971 26.399 LP
2223 8719413.9 252588.579 27.836 PL
2224 8719297.31 252598.885 26.389 SAR
2225 8719560.58 252576.977 28.721 PISTA
2226 8719422.02 252588.571 27.801 PT
2227 8719440.33 252587.535 28.062 PL
2228 8719509.31 252581.785 28.349 NA
2229 8719487.48 252583.711 28.086 NA
2230 8719536.96 252580.611 28.595 AUX 21
2231 8719529.67 252581.234 28.548 R
2232 8719496.68 252585.105 28.499 PL
2233 8719508.84 252584.991 28.588 NA
2234 8719519.2 252584.395 28.718 PT
2235 8719533.21 252584.333 28.843 NA
2236 8719552.64 252582.78 28.817 PL
2237 8719456.73 252591.029 28.388 LP
2238 8719527.36 252586.795 29.043 LP
2239 8719527.39 252586.803 29.066 LP
2240 8719536.56 252586.274 29.225 LP
2241 8719550.59 252585.491 29.081 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2242 8718112.99 252705.704 28.645 NA
2243 8718126.81 252711.464 30.196 NA
2244 8719059.37 252634.105 24.459 NA
2245 8719059.37 252634.109 24.443 NA
2246 8718104.5 252714.224 30.107 NA
2247 8718104.51 252714.551 29.87 NA
2248 8718105 252714.927 29.396 NA
2249 8719058.18 252635.942 24.311 V
2250 8718110.84 252715.018 28.35 NA
2251 8718106.26 252715.811 29.015 NA
2252 8718106.73 252716.153 28.852 GRAD
2253 8718102.96 252716.484 30.019 NA
2254 8718103.73 252717.042 29.452 NA
2255 8718116.96 252716.003 28.248 PISTA
2256 8718095.59 252717.808 30.154 LP
2257 8718096.35 252718.358 30.082 V
2258 8718104.77 252717.816 29.06 NA
2259 8718105.43 252718.269 28.892 NA
2260 8718115.1 252718.505 28.269 PISTA
2261 8718101.73 252723.62 30.03 R
2262 8718117.5 252724.901 30.096 NA
2263 8718091.31 252728.647 29.696 PL
2264 8718110.16 252727.259 28.391 NA
2265 8718086.65 252732.603 29.802 LP
2266 8718114.42 252730.682 28.956 NA
2267 8718087.51 252733.153 29.795 V
2268 8718098.33 252732.507 28.6 NA
2269 8718095.38 252733.861 29.743 NA
2270 8718105.54 252734.463 28.412 NA
2271 8718115.38 252734.139 29.279 V
2272 8718114.97 252734.974 29.155 NA
2273 8718090.18 252737.111 29.478 NA
2274 8718115.27 252735.935 29.283 PISTA
2275 8718094.32 252738.256 28.627 AUX 28
2276 8718079.84 252741.081 29.369 LP
2277 8718103.3 252739.418 28.428 PISTA
2278 8718080.99 252741.979 29.355 NA
2279 8718110.99 252740.464 29.256 PISTA
2280 8718086.4 252742.759 29.368 NA
2281 8718109.27 252740.954 29.126 PT
2282 8718120.37 252740.557 30.162 V
2283 8718108.73 252741.644 29.045 NA
2284 8718120.32 252740.719 30.16 PT
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2285 8718110.57 252741.552 29.574 V
2286 8718109.95 252741.863 31.193 NA
2287 8718109.06 252742.161 31.224 NA
2288 8718107.94 252742.532 28.866 MURO
2289 8718113.66 252742.398 29.689 NA
2290 8718111.73 252743.398 30.317 MURO
2291 8718093.02 252745.257 28.582 NA
2292 8718092.24 252746.416 28.579 NA
2293 8718089.88 252746.859 28.635 R
2294 8718077.89 252748.076 29.036 NA
2295 8718086.66 252747.54 29.328 R
2296 8718107.14 252746.062 31.002 NA
2297 8718087.02 252748.067 28.794 MURO
2298 8718098.22 252748.535 28.498 NA
2299 8718080 252750.672 28.859 NA
2300 8718097.5 252749.75 28.49 NA
2301 8718080.51 252755.738 28.841 PL
2302 8718100.2 252755.769 28.739 MURO
2303 8718083.75 252758.076 28.72 NA
2304 8718087.86 252759.173 28.649 NA
2305 8718094.86 252763.974 28.593 PT
2306 8718090.85 252766.7 28.562 NA
2307 8718070.87 252769.281 28.631 NA
2308 8718094.35 252767.429 31.66 MURO
2309 8718085.93 252779.976 28.828 GRAD
2310 8718084.95 252781.648 28.859 NA
2311 8718085.33 252781.948 29.004 NA
2312 8718084.56 252783.282 30.103 NA
2313 8718085.82 252783.936 30.12 NA
2314 8718083.74 252784.684 30.658 NA
2315 8718083.03 252785.914 31.225 NA
2316 8718083.94 252787.151 31.245 NA
2317 8718068.25 252791.655 28.736 NA
2318 8718065.61 252793.302 28.828 R
2319 8718073.11 252794.943 28.6 NA
2320 8718069.45 252807.504 28.778 PT
2321 8718047.52 252829.418 28.843 PISTA
2322 8718055.9 252832.569 28.816 MURO
2323 8718038.92 252840.682 28.896 V
2324 8718037.03 252840.903 28.941 NA
2325 8718046.76 252851.141 28.729 MURO
2326 8718031.93 252854.831 28.887 PAT
2327 8718031.05 252856.929 28.877 PAT
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2328 8718031.17 252862.875 28.691 PISTA
2329 8718037.08 252864.775 28.508 NA
2330 8718039.41 252866.055 28.682 GRAD
2331 8718018.29 252883.85 28.743 PL
2332 8718012.63 252889.78 28.825 LP
2333 8718011.91 252891.363 28.844 NA
2334 8718013.64 252891.787 28.403 V
2335 8718020.49 252902.323 28.405 NA
2336 8718013.37 252909.225 28.545 NA
2337 8718003.33 252914.169 28.797 NA
2338 8718018.35 252913.658 28.599 NA
2339 8718004.31 252915.654 28.798 V
2340 8718004.4 252916.732 28.651 PAT
2341 8718005.39 252922.529 28.517 NA
2342 8718014.62 252925.807 28.577 MURO
2343 8718013.92 252927.986 28.448 NA
2344 8718000.08 252935.388 28.515 PISTA
2345 8717999.02 252939.417 28.443 NA
2346 8718001.56 252940.212 28.405 NA
2347 8718007.15 252939.856 28.655 PISTA
2348 8718008.26 252940.466 28.878 V
2349 8717991.82 252942.257 28.392 LP
2350 8718011.54 252941.834 29.032 MURO
2351 8718003.12 252944.297 28.246 NA
2352 8718004.31 252949.483 28.297 PT
2353 8717991.12 252953.206 28.41 NA
2354 8717996.29 252955.46 28.239 NA
2355 8717998.65 252955.267 28.156 NA
2356 8717992.32 252957.151 28.3 R
2357 8717994.13 252957.784 28.259 NA
2358 8718001.41 252958.663 29.966 R
2359 8718000.81 252959.951 28.358 NA
2360 8717984.68 252962.614 28.447 NA
2361 8717987.05 252962.435 28.311 NA
2362 8718002.83 252961.376 31.223 MURO
2363 8718001.42 252962.912 30.378 PAT
2364 8717985.48 252964.312 28.411 NA
2365 8717985.88 252967.589 28.491 BZD
2366 8717993.63 252969.381 28.108 AUX 29
2367 8717996.8 252970.805 29.851 R
2368 8717982.81 252972.698 28.577 PAT
2369 8717998.95 252972.575 30.568 NA
2370 8717978.12 252977.268 28.494 LP
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2371 8717978.66 252977.74 28.421 PT
2372 8717980.35 252977.602 28.372 V
2373 8717998.14 252976.961 30.77 NA
2374 8717989.11 252980.194 27.983 PISTA
2375 8717993.9 252979.992 29.965 NA
2376 8717982.13 252981.617 28.251 NA
2377 8717992.93 252980.912 28.099 R
2378 8717986.3 252981.651 28.038 NA
2379 8717989.57 252982.602 27.976 NA
2380 8717977.14 252986.215 28.354 V
2381 8717977.14 252986.216 28.354 NA
2382 8717975 252986.488 28.475 NA
2383 8717974.87 252987.573 28.341 NA
2384 8717995.83 252986.017 31.169 NA
2385 8717991.52 252987.311 30.074 NA
2386 8717980.77 252988.505 28.168 NA
2387 8717982.69 252993.315 27.964 NA
2388 8717987.26 252995.697 28.529 PT
2389 8717987.78 252996.047 28.697 MURO
2390 8717970.81 252998.96 27.932 LP
2391 8717987.43 252999.25 30.157 NA
2392 8717990.58 253000.711 31.917 NA
2393 8717971.25 253004.688 28.358 PL
2394 8717971.83 253010.2 27.943 NA
2395 8717968.37 253012.827 28.157 V
2396 8717966.7 253012.975 28.266 NA
2397 8717987.94 253012.213 32.746 A
2398 8717974.89 253020.56 27.796 NA
2399 8717964.17 253021.97 28.087 LP
2400 8717977.13 253022.94 27.733 NA
2401 8717965.24 253024.419 28.017 V
2402 8717965.41 253028.204 28.085 PAT
2403 8717963.95 253037.155 28.004 BZD
2404 8717971.58 253050.605 27.766 R
2405 8717971.53 253050.661 27.779 E
2406 8717972.43 253050.926 27.984 MURO
2407 8717970.67 253053.598 27.726 NA
2408 8717971.58 253054.033 27.905 MURO
2409 8717956.13 253060.231 27.793 PL
2410 8717958.71 253063.601 27.51 NA
2411 8717964.28 253065.511 27.442 PISTA
2412 8717966.32 253066.173 27.496 NA
2413 8717951.2 253071.225 27.66 LP
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2414 8717966.96 253070.107 27.787 MURO
2415 8717952.44 253071.769 27.426 V
2416 8717948.69 253084.874 27.291 V
2417 8717949.82 253085.351 27.388 PAT
2418 8717948.42 253089.84 27.406 PL
2419 8717944.9 253093.157 27.403 LP
2420 8717946.5 253093.155 27.401 PT
2421 8717959.65 253093.747 27.452 PT
2422 8717943.1 253098.905 27.392 V
2423 8717944.17 253100.648 27.29 NA
2424 8717957.04 253105.19 27.576 MURO
2425 8717951.17 253110.939 27.236 PISTA
2426 8717944.39 253111.859 27.138 PISTA
2427 8717939.62 253118.571 27.324 PL
2428 8717949.79 253130.002 27.187 GRAD
2429 8717949.18 253132.218 27.258 NA
2430 8717933.11 253133.669 27.076 NA
2431 8717934.6 253133.741 27.02 V
2432 8717934.67 253134.123 27.021 PT
2433 8717935.1 253138.531 26.816 NA
2434 8717946.22 253139.121 27.095 PAT
2435 8717946.04 253139.834 27.109 PT
2436 8717930.82 253147.087 26.83 PT
2437 8717945.4 253145.981 27.507 MURO
2438 8717927.95 253148.064 26.573 LP
2439 8717936.59 253148.524 26.868 NA
2440 8717940.55 253149.15 26.832 NA
2441 8717928.24 253154.294 26.445 NA
2442 8717944 253154.488 27.011 NA
2443 8717931.49 253158.967 26.658 NA
2444 8717939.05 253158.882 26.764 NA
2445 8717938.77 253167.504 26.713 NA
2446 8717934.6 253168.082 26.68 PISTA
2447 8717923.25 253171.281 26.431 NA
2448 8717929.84 253173.272 26.635 NA
2449 8717936.44 253174.895 26.631 NA
2450 8717944.44 253175.628 27.007 MURO
2451 8717932.62 253176.83 26.553 PISTA
2452 8717922.32 253178.684 26.397 NA
2453 8717912.5 253180.528 25.011 LP
2454 8717913.41 253180.852 24.982 NA
2455 8717914.21 253180.856 25.319 NA
2456 8717914.42 253181.215 25.267 PT
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2457 8717940.07 253180.212 26.702 NA
2458 8717919.51 253184.012 26.289 AUX 30
2459 8717934.29 253183.372 26.543 NA
2460 8717910.47 253188.089 24.954 LP
2461 8717911.41 253188.181 24.988 V
2462 8717916.51 253188.853 25.973 NA
2463 8717928.98 253188.171 26.455 NA
2464 8717946.25 253188.355 27.55 NA
2465 8717945.11 253188.779 27.274 V
2466 8717900.91 253192.482 24.475 NA
2467 8717949.65 253188.806 28.793 NA
2468 8717920.23 253191.465 26.135 NA
2469 8717947.81 253190.034 28.071 NA
2470 8717938.05 253191.459 26.742 NA
2471 8717946.27 253191.2 27.529 NA
2472 8717914.77 253195.14 25.699 NA
2473 8717955.89 253193.588 28.459 SAR
2474 8717909.37 253198.293 25.177 NA
2475 8717945.72 253195.519 27.491 NA
2476 8717960.49 253194.931 29.152 V
2477 8717941.88 253197.675 27.178 NA
2478 8717923 253199.61 26.167 NA
2479 8717912.98 253200.595 25.895 NA
2480 8717916.7 253201.275 26.086 NA
2481 8717903.81 253202.367 24.662 PL
2482 8717959.66 253197.898 29.047 NA
2483 8717920.85 253201.326 26.293 NA
2484 8717930.66 253200.604 26.555 NA
2485 8717925.1 253202.538 26.288 NA
2486 8717954.88 253200.055 28.256 SAR
2487 8717907.79 253204.4 24.893 NA
2488 8717936.6 253202.506 27.076 RM
2489 8717936.89 253202.883 27.012 NA
2490 8717933.28 253204.747 26.616 NA
2491 8717934.79 253205.216 26.747 V
2492 8717957.62 253203.719 28.428 NA
2493 8717918.45 253207.044 27.22 NA
2494 8717954.78 253204.103 28.201 SAR
2495 8717928.11 253206.359 26.388 R
2496 8717944.17 253205.961 27.643 NA
2497 8717910.93 253209.175 25.983 NA
2498 8717954.58 253205.896 28.243 NA
2499 8717939.04 253207.601 27.277 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2500 8717930.82 253209.916 26.411 A
2501 8717899.09 253212.788 24.112 NA
2502 8717925.23 253213.229 26.233 NA
2503 8717928.39 253214.516 26.277 PAT
2504 8717904.51 253217.519 24.477 NA
2505 8717899.6 253218.648 24.201 NA
2506 8717959.99 253215.128 29.163 LP
2507 8717957.58 253215.363 28.7 NA
2508 8717921.37 253219.944 26.135 NA
2509 8717960.76 253217.13 29.037 NA
2510 8717960.07 253218.104 28.989 NA
2511 8717909.3 253223.065 25.857 NA
2512 8717897.33 253225.104 24.287 PL
2513 8717950.23 253221.119 28.576 NA
2514 8717926.78 253223.433 26.23 NA
2515 8717954.79 253222.962 28.876 PISTA
2516 8717895.98 253227.99 24.288 PT
2517 8717926.25 253226.255 26.203 NA
2518 8717888.87 253231.485 23.647 NA
2519 8717909.72 253230.728 25.703 NA
2520 8717892.85 253232.435 23.784 R
2521 8717924.47 253231.916 26.185 NA
2522 8717886.72 253235.431 23.922 V
2523 8717888.52 253236.002 23.937 V
2524 8717888.48 253236.656 23.963 LP
2525 8717908.75 253236.522 25.852 NA
2526 8717908.55 253237.465 25.88 NA
2527 8717922.67 253237.683 26.143 NA
2528 8717914.89 253238.459 25.959 NA
2529 8717914.79 253239.178 25.962 NA
2530 8717898.34 253242.406 24.608 NA
2531 8717905.71 253242.31 25.977 NA
2532 8717890.35 253245.623 24.26 PL
2533 8717891.92 253245.635 24.31 NA
2534 8717937.7 253243.814 26.856 NA
2535 8717935.54 253249.198 26.642 NA
2536 8717900.92 253252.471 25.486 NA
2537 8717929.75 253250.585 26.345 A
2538 8717882.98 253256.519 24.123 LP
2539 8717883.96 253256.97 24.123 V
2540 8717913.91 253262.853 26.023 PAT
2541 8717879.43 253269.667 24.237 NA
2542 8717880.17 253269.895 24.221 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2543 8717914.2 253267.522 25.832 NA
2544 8717881.66 253274.296 24.338 PL
2545 8717909.67 253273.204 25.603 NA
2546 8717912.96 253273.432 25.647 V
2547 8717914.59 253273.431 25.799 V
2548 8717883.67 253276.519 24.319 R
2549 8717906.08 253275.012 25.674 NA
2550 8717903.71 253278.297 25.599 PISTA
2551 8717914.18 253278.727 25.607 V
2552 8717916.17 253279.204 25.726 NA
2553 8717895.68 253282.626 25.548 NA
2554 8717885.11 253291.431 24.923 NA
2555 8717923.68 253289.371 25.966 NA
2556 8717922.73 253290.641 25.817 NA
2557 8717871.51 253296.811 24.346 PT
2558 8717916.47 253297.012 25.85 NA
2559 8717910.88 253298.354 25.85 V
2560 8717907.54 253302.604 25.851 SAR
2561 8717906.11 253305.619 25.843 NA
2562 8717883.4 253309.882 24.953 NA
2563 8717934.75 253305.79 26.222 NA
2564 8717879.98 253311.386 24.977 NA
2565 8717897.86 253309.905 25.674 NA
2566 8717919.08 253308.321 26.113 NA
2567 8717938.17 253307.103 26.466 NA
2568 8717932.26 253307.649 26.232 SAR
2569 8717887.3 253312.195 25.396 PISTA
2570 8717937.47 253308.262 26.433 NA
2571 8717916.22 253310.04 26.061 NA
2572 8717866.52 253314.632 24.364 V
2573 8717935.07 253308.922 26.385 PL
2574 8717935.12 253309.301 26.316 V
2575 8717867.29 253314.982 24.361 NA
2576 8717923.87 253310.423 26.072 NA
2577 8717902.29 253312.795 25.806 PAT
2578 8717878.48 253316.965 24.854 NA
2579 8717873.34 253317.574 24.558 NA
2580 8717904.38 253317.477 25.86 NA
2581 8717884.97 253320.269 25.329 PISTA
2582 8717884.97 253320.281 25.329 NA
2583 8717914.28 253320.782 26.077 NA
2584 8717892.13 253324.85 25.524 NA
2585 8717900.4 253324.681 26.05 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2586 8717895.53 253325.227 25.603 NA
2587 8717862.67 253328.021 24.317 NA
2588 8717875.53 253327.019 24.819 NA
2589 8717863.06 253330.334 24.298 NA
2590 8717903.18 253327.683 25.811 NA
2591 8717888.93 253329.644 25.535 NA
2592 8717897.46 253329.497 25.729 A
2593 8717897.54 253329.537 25.753 NA
2594 8717899.23 253330.095 25.759 NA
2595 8717906.8 253329.472 25.959 NA
2596 8717901.57 253331.097 25.915 NA
2597 8717893.92 253331.969 25.695 NA
2598 8717893.68 253332.992 25.713 NA
2599 8717876.55 253334.783 24.976 NA
2600 8717887.46 253334.165 25.509 V
2601 8717887.46 253334.166 25.509 NA
2602 8717860.07 253336.645 24.443 LP
2603 8717904.94 253333.221 25.966 NA
2604 8717902.17 253333.927 26.065 PALM
2605 8717896.96 253334.713 25.763 NA
2606 8717892.6 253335.287 25.696 NA
2607 8717907.43 253334.223 25.92 NA
2608 8717899.45 253335.343 26 NA
2609 8717871.97 253337.84 24.816 NA
2610 8717891.96 253336.174 25.688 NA
2611 8717895.79 253336.986 25.755 NA
2612 8717902.99 253337.159 25.965 NA
2613 8717898.2 253338.193 25.961 NA
2614 8717890.46 253338.933 25.598 AUX 31
2615 8717907.33 253337.539 26.018 NA
2616 8717905.01 253338.75 25.939 NA
2617 8717870.89 253341.765 24.849 NA
2618 8717901.55 253339.852 25.957 NA
2619 8717915.31 253339.832 25.85 NA
2620 8717908.34 253340.486 25.9 NA
2621 8717903.97 253341.048 26.003 NA
2622 8717891.1 253343.414 25.673 NA
2623 8717918.18 253341.33 26.046 LP
2624 8717907.22 253342.645 25.864 NA
2625 8717915.13 253342.057 25.849 NA
2626 8717867.56 253346.9 24.986 NA
2627 8717918.65 253343.238 26.027 NA
2628 8717916.53 253343.788 25.864 V
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2629 8717851.85 253351.194 24.402 LP
2630 8717902.18 253347.753 26.026 NA
2631 8717921.26 253346.537 26.119 PL
2632 8717883.64 253352.112 25.525 NA
2633 8717874.71 253352.922 25.046 PISTA
2634 8717877.74 253353.034 25.216 R
2635 8717888.16 253352.405 25.67 V
2636 8717913.24 253350.584 25.837 NA
2637 8717929.81 253349.998 26.348 LP
2638 8717883.79 253353.925 25.572 NA
2639 8717909.54 253351.97 25.819 NA
2640 8717890.43 253353.619 25.899 NA
2641 8717879.39 253354.6 25.358 NA
2642 8717918.73 253352.713 26.019 V
2643 8717908.28 253353.966 25.798 NA
2644 8717868.24 253357.739 24.923 NA
2645 8717931.33 253352.879 26.199 V
2646 8717918.01 253354.043 26.112 LP
2647 8717897.81 253356.653 25.914 NA
2648 8717887.63 253359.38 25.596 NA
2649 8717913.3 253359.141 25.859 NA
2650 8717891.39 253361.597 25.726 NA
2651 8717868.98 253363.957 24.947 NA
2652 8717877.45 253364.076 25.411 R
2653 8717887.64 253363.59 25.723 NA
2654 8717878.85 253364.584 25.492 SAR
2655 8717842.12 253368.575 24.437 LP
2656 8717881.8 253365.527 25.533 NA
2657 8717891.53 253365.957 25.709 NA
2658 8717889.77 253369.533 25.778 V
2659 8717860.14 253373.275 24.81 NA
2660 8717864.54 253373.253 24.916 PISTA
2661 8717875.91 253376.988 25.459 V
2662 8717873.96 253380.666 25.409 NA
2663 8717866.88 253381.998 25.136 PISTA
2664 8717873.52 253383.48 25.378 NA
2665 8717886.72 253382.515 25.61 NA
2666 8717867.33 253384.986 25.17 V
2667 8717874.24 253385.462 25.463 NA
2668 8717881.84 253384.866 25.466 V
2669 8717898.69 253384.067 25.879 NA
2670 8717869.19 253387.583 25.37 V
2671 8717878.99 253387.132 25.522 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2672 8717845.83 253390.444 24.311 PT
2673 8717868.88 253389.883 25.313 V
2674 8717873.55 253390.279 25.45 NA
2675 8717847.67 253392.723 24.44 NA
2676 8717871.05 253391.234 25.462 NA
2677 8717874.54 253393.009 25.479 NA
2678 8717859.93 253396.056 24.886 NA
2679 8717850.21 253397.887 24.622 PISTA
2680 8717857.14 253403.666 25.024 SAR
2681 8717833.24 253407.201 23.913 LP
2682 8717860.46 253405.421 25.37 V
2683 8717856.07 253405.972 25.106 NA
2684 8717863.04 253405.995 25.368 NA
2685 8717886.45 253404.875 25.355 PT
2686 8717835.75 253409.577 24.179 NA
2687 8717835.75 253409.578 24.179 PL
2688 8717859.31 253407.67 25.317 V
2689 8717866.39 253407.828 25.362 V
2690 8717866.44 253407.863 25.378 NA
2691 8717861.52 253408.935 25.129 V
2692 8717853.5 253409.949 24.863 SAR
2693 8717834.92 253412.59 24.106 PT
2694 8717867.2 253412.028 25.406 V
2695 8717859.36 253412.914 25.257 NA
2696 8717871.53 253411.941 25.27 NA
2697 8717860.3 253415.38 25.22 NA
2698 8717876.62 253415.415 25.235 SAR
2699 8717860.95 253418.29 25.206 V
2700 8717832.36 253428.758 24.228 PISTA
2701 8717839.62 253434.344 24.525 SAR
2702 8717844.6 253436.769 24.796 NA
2703 8717851.54 253441.134 24.988 V
2704 8717855.14 253443.251 24.985 SAR
2705 8717863.66 253444.696 25.027 PL
2706 8717843.21 253446.887 24.683 V
2707 8717839.75 253456.058 24.641 NA
2708 8717826.41 253457.354 24.346 NA
2709 8717813.5 253461.094 23.979 NA
2710 8717813.19 253461.688 23.971 NA
2711 8717802.06 253464.119 23.713 PL
2712 8717818.89 253464.251 24.135 RM
2713 8717818.28 253465.092 24.128 NA
2714 8717854.16 253464.45 25.107 LP
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2715 8717796.42 253470.035 23.717 NA
2716 8717842.02 253466.439 24.825 V
2717 8717841.88 253466.488 24.825 NA
2718 8717798.14 253470.978 23.683 V
2719 8717826.86 253469.222 23.886 NA
2720 8717816.06 253478.46 23.721 NA
2721 8717797.03 253488.938 23.639 PISTA
2722 8717813.36 253490.646 23.9 NA
2723 8717817.73 253491.827 24.033 NA
2724 8717793.43 253496.165 23.279 R
2725 8717779.42 253497.717 22.99 NA
2726 8717780.31 253498.298 22.97 NA
2727 8717785.73 253499.576 23.005 NA
2728 8717830.69 253497.153 24.838 V
2729 8717830.41 253499.195 24.798 NA
2730 8717834.04 253499.22 24.978 NA
2731 8717775.19 253504.28 22.99 LP
2732 8717776.14 253504.943 22.981 V
2733 8717788.75 253504.267 23.477 NA
2734 8717833.33 253500.555 24.937 LP
2735 8717802.43 253504.32 23.848 NA
2736 8717832.55 253501.822 24.882 NA
2737 8717773.92 253508.914 22.319 PT
2738 8717784.42 253508.95 23.48 PISTA
2739 8717792.32 253508.655 23.688 NA
2740 8717826.69 253506.463 24.774 NA
2741 8717829.54 253506.886 24.924 V
2742 8717824.75 253507.841 24.764 NA
2743 8717775.54 253512.577 22.881 PAT
2744 8717828.85 253508.135 24.885 NA
2745 8717826.62 253508.761 24.821 V
2746 8717828.08 253509.411 24.916 LP
2747 8717774.37 253514.264 23.015 NA
2748 8717788.69 253513.457 23.706 PISTA
2749 8717778.04 253516.711 23.257 R
2750 8717832.55 253513.418 25.231 LP
2751 8717766.55 253520.01 22.464 LP
2752 8717768.69 253522.552 23.019 PL
2753 8717783.51 253521.713 23.697 NA
2754 8717787.64 253521.789 23.791 AUX 32
2755 8717787.64 253521.789 25.246 NA
2756 8717787.64 253521.789 25.246 NA
2757 8717787.64 253521.789 25.246 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2758 8717787.64 253521.789 25.246 NA
2759 8717767 253523.678 22.813 PISTA
2760 8717774.59 253523.489 23.292 PISTA
2761 8717757.38 253527.051 21.856 NA
2762 8717773.17 253518.054 22.619 PALM
2763 8717780.17 253526.266 23.615 NA
2764 8717780.14 253526.572 23.636 NA
2765 8717765.67 253531.391 22.97 PISTA
2766 8717759.59 253532.698 22.125 NA
2767 8717765.57 253532.916 23.137 V
2768 8717767.38 253532.918 23.237 PISTA
2769 8717760.21 253533.733 22.295 V
2770 8717770.42 253533.703 23.509 R
2771 8717803.39 253531.781 24.378 NA
2772 8717792.32 253534.65 23.976 NA
2773 8717804.93 253540.831 24.272 V
2774 8717786.5 253542.848 23.94 NA
2775 8717773.3 253544.399 23.694 NA
2776 8717804.45 253542.1 24.252 NA
2777 8717807.88 253544.253 24.504 LP
2778 8717806.91 253545.495 24.38 V
2779 8717807.99 253545.549 24.562 PAT
2780 8717800.74 253550.202 24.255 V
2781 8717798.02 253551.908 24.23 NA
2782 8717804.93 253551.89 24.416 V
2783 8717788.85 253553.58 24.107 NA
2784 8717799.66 253553.301 24.36 NA
2785 8717803.98 253553.127 24.76 LP
2786 8717801.25 253553.562 24.392 NA
2787 8717808.81 253556.115 23.699 R
2788 8717785.61 253566.409 24.086 SAR
2789 8717787.5 253568.038 24.201 NA
2790 8717751.05 253565.14 23.173 NA
2791 8717752.55 253590.718 23.905 NA
2792 8717754.67 253606.066 24.101 NA
2793 8717732.47 253571.002 22.929 NA
2794 8717754.61 253606.079 24.111 LP
2795 8717754.85 253608.577 24.272 LP
2796 8717732.85 253574.248 22.761 PISTA
2797 8717752.82 253608.729 23.965 V
2798 8717751.47 253606.622 23.862 NA
2799 8717743.01 253596.877 23.677 NA
2800 8717749.13 253612.644 23.954 V
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2801 8717747.35 253611.663 23.839 NA
2802 8717748.13 253613.61 24.126 NA
2803 8717748.13 253613.61 24.126 LP
2804 8717745.03 253612.409 23.735 NA
2805 8717726.95 253590.962 23.116 PISTA
2806 8717721.04 253584.333 22.826 NA
2807 8717724.21 253597.839 23.108 NA
2808 8717729.47 253613.137 23.673 NA
2809 8717711.48 253595.036 22.661 NA
2810 8717719.13 253615.358 23.345 NA
2811 8717723.15 253623.145 23.653 NA
2812 8717706.44 253600.801 22.674 NA
2813 8717705.58 253599.829 22.773 NA
2814 8717704.33 253602.765 22.679 ESC
2815 8717703.27 253601.734 22.589 NA
2816 8717710.4 253613.873 23.111 NA
2817 8717737.05 253657.238 25.187 LP
2818 8717735.34 253658.575 24.894 PISTA
2819 8717721.69 253641.434 23.952 PL
2820 8717700.57 253608.066 22.474 NA
2821 8717707.65 253620.602 23.268 V
2822 8717722.64 253644.701 23.959 LP
2823 8717719.55 253641.862 23.778 V
2824 8717716.07 253636.722 23.732 NA
2825 8717720.81 253645.607 23.87 V
2826 8717714.95 253638.645 23.7 NA
2827 8717698.92 253613.758 22.629 PISTA
2828 8717710 253631.413 23.647 NA
2829 8717713.98 253638.752 23.641 NA
2830 8717703.51 253625.589 23.35 NA
2831 8717703.12 253625.333 23.294 NA
2832 8717701.13 253624.618 23.127 NA
2833 8717720.68 253656.044 24.156 NA
2834 8717701.7 253626.947 23.258 NA
2835 8717701.68 253627.794 23.259 NA
2836 8717702.1 253628.472 23.258 NA
2837 8717715.75 253651.727 23.943 NA
2838 8717714.77 253651.396 23.906 NA
2839 8717714.09 253651.623 23.917 NA
2840 8717709.08 253645.556 23.687 V
2841 8717705.22 253639.855 23.499 NA
2842 8717716.4 253660.589 24.309 NA
2843 8717691 253621.977 22.647 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2844 8717697.9 253633.46 23.28 NA
2845 8717711.09 253654.645 23.966 NA
2846 8717697.01 253633.034 23.268 NA
2847 8717696.31 253632.288 24.499 NA
2848 8717711.45 253656.352 24.033 SAR
2849 8717710.89 253655.518 24.002 NA
2850 8717701.61 253640.857 23.672 CAPLLA
2851 8717695.91 253633.477 23.272 NA
2852 8717687.5 253621.979 22.532 SAR
2853 8717705.16 253650.097 23.746 V
2854 8717687.18 253621.95 21.844 R
2855 8717702.02 253646.49 23.797 NA
2856 8717704.55 253650.517 23.732 NA
2857 8717703.47 253650.318 23.699 NA
2858 8717684.77 253621.059 21.734 NA
2859 8717699.02 253643.797 23.689 NA
2860 8717687.69 253626.606 22.642 NA
2861 8717686.23 253625.424 22.639 SAR
2862 8717683.44 253623.412 22.208 NA
2863 8717690.44 253634.563 23.102 R
2864 8717706.49 253661.612 23.955 NA
2865 8717691.66 253638.241 23.308 NA
2866 8717691.3 253639.241 23.318 NA
2867 8717691.63 253640.05 23.306 NA
2868 8717704.67 253660.747 23.901 NA
2869 8717683.25 253628.755 22.76 NA
2870 8717704.72 253663.284 24.04 LP
2871 8717681.18 253626.484 22.755 NA
2872 8717699.01 253655.117 23.731 V
2873 8717699.42 253656.455 23.769 NA
2874 8717679.61 253626.581 22.754 NA
2875 8717698.72 253657.497 23.775 NA
2876 8717702.36 253663.343 23.996 NA
2877 8717701.39 253662.426 23.897 NA
2878 8717686.12 253643.703 23.249 NA
2879 8717684.97 253643.214 23.187 V
2880 8717683.92 253644.585 23.313 AUX 33
2881 8717677.68 253637.775 22.658 PISTA
2882 8717687.86 253654.41 23.688 NA
2883 8717676.39 253636.333 22.642 V
2884 8717673.58 253633.078 22.797 NA
2885 8717673.35 253634.81 22.755 NA
2886 8717681.74 253650.494 23.429 R
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2887 8717671.94 253638.713 22.746 SAR
2888 8717682.63 253658.846 23.685 NA
2889 8717677.03 253664.539 23.742 NA
2890 8717663 253642.366 21.902 SAR
2891 8717681.02 253671.699 23.974 NA
2892 8717668.32 253662.374 23.347 NA
2893 8717660.52 253668.401 23.161 SAR
2894 8717658.74 253666.686 23.087 NA
2895 8717654.94 253661.809 22.695 PISTA
2896 8717652.81 253659.356 22.491 R
2897 8717661.37 253692.276 24.04 NA
2898 8717655.02 253687.6 23.735 NA
2899 8717660.52 253702.546 24.435 V
2900 8717656.52 253701.358 24.329 V
2901 8717654.64 253699.682 24.291 NA
2902 8717635.55 253671.874 22.63 R
2903 8717651.3 253698.035 24.369 NA
2904 8717636.19 253676.39 22.644 NA
2905 8717641.94 253685.962 23.128 NA
2906 8717639.92 253684.272 23.078 PISTA
2907 8717636.65 253679.182 22.726 NA
2908 8717617.97 253705.7 23.09 SAR
2909 8717603.48 253705.988 22.614 PISTA
2910 8717607.66 253713.719 23.004 SAR
2911 8717605.88 253751.748 24.88 V
2912 8717585.57 253730.717 23.004 SAR
2913 8717583.23 253728.93 22.868 PISTA
2914 8717583.22 253728.936 22.867 NA
2915 8717579.22 253724.284 22.671 NA
2916 8717597.57 253760.11 24.888 V
2917 8717596.86 253759.018 24.81 NA
2918 8717598.38 253761.829 24.94 LP
2919 8717595.3 253760.798 24.846 V
2920 8717595.37 253763.193 24.976 NA
2921 8717590.94 253767.439 25.061 NA
2922 8717593.09 253770.988 25.576 V
2923 8717585.1 253758.696 24.769 V
2924 8717588.49 253766.298 24.897 NA
2925 8717591.29 253771.88 25.732 NA
2926 8717590.31 253772.335 25.885 LP
2927 8717586.24 253766.794 24.873 V
2928 8717542.07 253763.344 23.244 AUX 34
2929 8717553.13 253786.008 25.264 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2930 8717553.97 253787.765 25.689 NA
2931 8717549.38 253781.688 25.001 NA
2932 8717554.18 253789.726 25.861 LP
2933 8717548.3 253780.449 24.734 V
2934 8717552.05 253788.03 25.402 NA
2935 8717552.37 253790.578 25.626 V
2936 8717536.58 253790.398 25.013 SAR
2939 8717555.06 253733.79 23.003 NA
2940 8717566.39 253753.765 24.558 NA
2941 8717562.43 253747.548 24.142 NA
2942 8717548.47 253728.264 20.822 SAR
2943 8717551.65 253733.387 20.972 V
2944 8717549.51 253737.307 21.652 NA
2945 8717548.52 253736.763 21.498 V
2946 8717553.89 253747.236 23.9 NA
2947 8717544.06 253732.447 22.845 NA
2948 8717548.21 253739.809 22.057 SAR
2949 8717548.9 253742.999 22.486 SAR
2950 8717546.99 253741.002 22.1 V
2951 8717542.49 253734.354 21.494 NA
2952 8717547.81 253743.539 22.444 NA
2953 8717540.03 253735.838 21.402 NA
2954 8717555.65 253762.971 23.837 NA
2955 8717540.99 253741.532 22.788 R
2956 8717536.55 253735.36 20.878 NA
2957 8717546.81 253756.235 22.958 NA
2958 8717545.5 253755.324 22.96 NA
2959 8717547.94 253760.042 23.489 NA
2960 8717538.61 253746.682 22.53 NA
2961 8717538.06 253745.813 22.277 V
2962 8717540.51 253751.992 22.89 NA
2963 8717553.09 253772.11 24.234 NA
2964 8717537.78 253748.278 22.935 PL
2965 8717540.56 253753.488 22.946 NA
2966 8717540.56 253753.498 22.946 PISTA
2967 8717534.98 253747.373 23.05 LP
2969 8717544.43 253767.323 23.545 V
2970 8717536.39 253754.778 22.953 NA
2971 8717546.52 253771.364 24.226 NA
2972 8717548.66 253775.31 24.229 NA
2973 8717549.76 253778.19 24.563 NA
2974 8717529.91 253753.163 23.11 PT
2975 8717530.87 253758.782 22.95 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
2976 8717532.62 253765.498 23.081 NA
2977 8717526.63 253756.693 23.111 SAR
2978 8717534.2 253773.907 23.582 SAR
2979 8717549.58 253799.093 26.134 NA
2980 8717532.3 253772.563 23.381 NA
2981 8717526.21 253768.733 23.14 NA
2982 8717543.49 253796.263 25.653 NA
2983 8717528.69 253772.969 23.159 NA
2984 8717528.32 253772.903 23.176 NA
2985 8717522.37 253764.647 23.114 R
2986 8717538.74 253796.978 25.466 NA
2987 8717538.82 253800.401 25.647 V
2988 8717518.04 253768.138 23.105 NA
2989 8717512.35 253767.524 23.157 V
2990 8717511.72 253766.779 23.177 NA
2991 8717511 253766.893 23.19 PL
2992 8717504.83 253770.202 23.214 LP
2993 8717510.32 253786.182 23.059 NA
2994 8717505.86 253779.386 23.094 PISTA
2995 8717524.38 253812.426 25.646 V
2996 8717521.97 253811.149 25.566 NA
2997 8717516.84 253813.005 25.546 NA
2998 8717515.18 253819.545 25.904 LP
2999 8717508.57 253829.504 26.166 NA
3000 8717507.28 253829.983 26.127 NA
3001 8717508.15 253832.595 26.197 NA
3002 8717503.14 253825.315 25.931 NA
3003 8717494.77 253812.899 25.318 NA
3004 8717487.55 253803.471 23.13 ESC
3005 8717512.31 253843.566 27.39 V
3006 8717513.01 253844.733 28.032 LP
3007 8717505.26 253834.239 26.106 LP
3008 8717499.77 253826.26 25.842 V
3009 8717506.7 253837.579 26.158 NA
3010 8717485.87 253804.814 23.121 NA
3011 8717479.72 253798.795 23.147 PISTA
3012 8717494.22 253822.923 25.473 NA
3013 8717497.22 253827.938 25.734 NA
3014 8717498.41 253833.301 25.782 NA
3015 8717498.4 253835.817 25.803 NA
3016 8717500.55 253840.361 25.952 NA
3017 8717477.19 253849.396 25.548 NA
3018 8717450.75 253820.962 23.197 PISTA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3019 8717468.08 253849.815 25.51 V
3020 8717446.59 253816.721 23.027 NA
3021 8717445.12 253817.198 23.033 NA
3022 8717444.47 253816.779 23.006 NA
3023 8717444.03 253816.124 22.931 NA
3024 8717462.91 253846.207 25.391 NA
3025 8717449.09 253832.992 23.217 NA
3026 8717448.82 253833.717 23.269 NA
3027 8717439.83 253819.859 23.02 NA
3028 8717439.14 253818.912 22.924 NA
3029 8717440.33 253821.193 23.162 NA
3030 8717442.98 253827.075 23.305 PISTA
3031 8717455.08 253846.24 24.971 NA
3032 8717439.47 253822.106 23.22 V
3033 8717449.27 253841.619 24.465 NA
3034 8717442.36 253839.924 23.398 NA
3035 8717442.52 253840.507 23.578 NA
3036 8717441.79 253840.269 23.302 NA
3037 8717454.58 253862.296 25.962 V
3038 8717452.41 253861.316 25.628 NA
3039 8717453.73 253864.329 25.927 NA
3040 8717440.76 253844.428 23.226 MURO
3041 8717451.75 253863.639 25.726 NA
3042 8717454.69 253870.506 26.167 NA
3043 8717455.19 253872.13 26.449 LP
3044 8717453.94 253871.205 26.164 NA
3045 8717453.99 253872.5 26.178 V
3046 8717442.5 253855.184 24.918 NA
3047 8717439.53 253852.911 24.707 NA
3048 8717442.44 253864.647 25.534 NA
3049 8717450.66 253881.637 26.645 NA
3050 8717453.43 253887.028 27.068 NA
3051 8717446.63 253878.315 26.241 NA
3052 8717452.03 253887.518 27.13 V
3053 8717420.65 253840.605 23.269 NA
3054 8717436.76 253878.43 26.099 NA
3055 8717438.4 253882.217 26.367 NA
3056 8717409.51 253849.315 23.145 NA
3057 8717412.81 253857.459 23.33 NA
3058 8717402.47 253860.264 23.337 NA
3059 8717399.7 253859.818 23.209 NA
3060 8717419.07 253899.744 26.587 NA
3061 8717396.33 253864.075 23.415 AUX
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3062 8717413.99 253898.189 26.318 NA
3063 8717396.55 253873.58 23.342 NA
3064 8717414.98 253903.881 27.037 LP
3065 8717412.31 253900.473 26.351 NA
3066 8717390.96 253870.072 23.294 R
3067 8717412.06 253903.865 26.578 NA
3068 8717414.22 253908.451 26.903 NA
3069 8717406.22 253905.948 26.451 NA
3070 8717405.18 253905.112 26.376 NA
3071 8717408.72 253911.272 26.885 NA
3072 8717403.94 253905.371 26.291 NA
3073 8717404.78 253906.874 26.659 NA
3074 8717411.05 253919.308 27.476 V
3075 8717396.9 253897.694 25.128 NA
3076 8717395.74 253898.679 25.16 NA
3077 8717385.78 253883.467 23.415 NA
3078 8717392.5 253896.412 24.351 V
3079 8717399.73 253908.38 26.054 NA
3080 8717393.02 253897.96 24.421 V
3081 8717400.18 253909.994 26.422 NA
3082 8717396.12 253903.623 25.806 NA
3083 8717395.12 253902.393 25.769 NA
3084 8717380.25 253880.193 23.32 NA
3085 8717377.48 253900.078 23.381 MURO
3086 8717371.4 253893.819 23.496 PISTA
3087 8717369.09 253891.08 23.575 R
3088 8717361.36 253899.006 23.483 NA
3089 8717366.12 253916.651 23.494 NA
3090 8717369.58 253922.233 23.887 NA
3091 8717365.55 253921.278 23.602 NA
3092 8717370.23 253929.008 24.156 NA
3093 8717370.92 253930.344 24.175 NA
3094 8717372.51 253933.61 24.563 NA
3095 8717369.52 253929.998 24.178 NA
3096 8717369.71 253931.199 24.18 NA
3097 8717371.07 253934.099 24.544 NA
3098 8717366.64 253936.057 24.187 V
3099 8717365.22 253934.417 23.949 NA
3100 8717365.5 253936.699 23.636 LP
3101 8717358.49 253927.211 23.618 V
3102 8717363.72 253936.168 23.688 LP
3103 8717362.55 253935.338 23.708 NA
3104 8717358.75 253930.549 23.591 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3105 8717340.72 253929.6 23.549 PISTA
3106 8717337.57 253957.233 23.601 V
3107 8717334.01 253953.401 23.503 NA
3108 8717339.36 253964.452 23.652 V
3109 8717333.9 253957.668 23.576 NA
3110 8717338.79 253969.196 23.663 LP
3111 8717328.45 253964.802 23.556 V
3112 8717332.41 253975.844 23.847 PAT
3113 8717331.45 253974.598 23.669 NA
3114 8717331.36 253974.549 23.642 V
3115 8717323.93 253966.168 23.562 SAR
3116 8717316.81 253958.588 23.628 PISTA
3117 8717314.01 253955.374 23.629 PT
3118 8717313.57 253954.968 23.711 NA
3119 8717312.92 253957.27 23.739 PL
3120 8717298.47 253982.663 23.75 PISTA
3121 8717295.47 253978.718 23.888 PL
3122 8717303.83 253992.489 23.747 NA
3123 8717304.18 253995.438 23.7 V
3124 8717309.35 254004.663 23.934 LP
3125 8717295.96 254002.691 23.828 NA
3126 8717285.36 253999.846 23.894 PISTA
3127 8717247.19 254082.952 24.282 LP
3128 8717246.12 254082.115 24.108 V
3129 8717245.55 254083.196 24.156 NA
3130 8717247.97 254087.542 24.461 NA
3131 8717237.39 254081.43 24.188 V
3132 8717237.6 254083.297 24.195 NA
3133 8717235.39 254081.426 24.243 SAR
3134 8717229.53 254072.629 24.225 PISTA
3135 8717237.52 254093.023 24.228 V
3136 8717236.64 254097.12 24.445 LP
3137 8717232.98 254100.333 24.465 NA
3138 8717213.17 254113.859 24.491 NA
3139 8717212.11 254113.137 24.481 V
3140 8717211.97 254114.427 24.477 NA
3141 8717215.87 254124.013 24.882 LP
3142 8717214.16 254122.395 24.55 V
3143 8717203.99 254107.24 24.742 PISTA
3144 8717196.69 254097.504 24.533 NA
3145 8717213.09 254124.345 24.62 NA
3146 8717199.37 254102.792 24.73 NA
3147 8717213.82 254127.999 24.712 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3148 8717227.17 254154.564 27.583 LP
3149 8717207.74 254128.322 24.674 V
3150 8717187.18 254098.972 23.832 LP
3151 8717228.97 254165.785 27.413 NA
3152 8717206.52 254130.284 24.833 V
3153 8717231.64 254172.715 27.511 SAR
3154 8717196.58 254119.104 24.816 PISTA
3155 8717225.44 254165.298 27.421 NA
3156 8717223.26 254163.641 27.052 NA
3157 8717201.34 254131.274 24.821 SAR
3158 8717200.16 254129.997 24.653 NA
3159 8717224.48 254173.335 27.516 BZD
3160 8717224.7 254174.477 27.548 SAR
3161 8717193.4 254125.716 24.718 NA
3162 8717188.27 254121.039 24.745 NA
3163 8717199.1 254138.424 25.576 R
3164 8717219.35 254171.611 27.3 V
3165 8717185.75 254119.921 24.608 NA
3166 8717222.31 254182.827 28.107 V
3167 8717219.45 254178.621 27.772 NA
3168 8717197.11 254143.948 25.699 NA
3169 8717183.93 254125.397 24.3 NA
3170 8717188.51 254133.41 24.813 NA
3171 8717217.82 254180.514 27.696 NA
3172 8717201.38 254157.916 26.56 NA
3173 8717217.98 254185.44 27.822 NA
3174 8717184.38 254135.36 24.65 NA
3175 8717205.52 254174.129 27.033 NA
3176 8717192.54 254157.459 26.056 NA
3177 8717202.91 254174.462 27.174 NA
3178 8717181.64 254143.839 24.792 AUX
3179 8717181.64 254143.839 26.302 NA
3180 8717191.61 254159.803 26.056 E
3181 8717189.19 254156.31 24.986 SAR
3182 8717176.73 254138.653 24.19 NA
3183 8717188.17 254158.413 24.992 NA
3184 8717191.9 254166.034 26.367 NA
3185 8717205.35 254189.143 27.554 NA
3186 8717202.94 254188.727 27.548 V
3187 8717193.21 254178.079 26.723 NA
3188 8717184.39 254160.17 24.884 NA
3189 8717207.34 254201.103 27.85 NA
3190 8717186.62 254176.214 26.104 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3191 8717205.92 254200.074 27.885 NA
3192 8717204.31 254199.263 28.026 NA
3193 8717202.6 254198.713 27.956 NA
3194 8717188.12 254188.046 26.762 NA
3195 8717167.2 254145.153 23.662 NA
3196 8717178.02 254162.567 24.94 NA
3197 8717199.58 254198.858 27.843 NA
3198 8717174.33 254160.831 24.741 NA
3199 8717196.27 254200.848 27.79 NA
3200 8717164.02 254150.208 23.647 LP
3201 8717180.84 254189.782 26.148 NA
3202 8717184.61 254197.094 27.037 NA
3203 8717168.61 254163.104 24.471 NA
3204 8717171.65 254168.767 24.913 PISTA
3205 8717194.33 254206.16 27.942 NA
3206 8717196.93 254211.362 27.792 NA
3207 8717195.06 254208.567 27.89 NA
3208 8717175.58 254201.972 26.54 NA
3209 8717169.33 254171.354 24.938 NA
3210 8717163.37 254163.807 24.468 PT
3211 8717162.88 254163.273 24.364 LP
3212 8717165.85 254170.91 24.883 NA
3213 8717168.52 254212.833 26.151 NA
3214 8717152.68 254156.941 23.819 LP
3215 8717160.16 254172.183 24.717 PT
3216 8717165.99 254185.553 25.064 NA
3217 8717158 254175.288 24.776 PL
3218 8717158.26 254188.507 24.924 NA
3219 8717151.65 254192.548 24.879 R
3220 8717178.78 254238.166 27.561 NA
3221 8717177.7 254237.024 27.793 V
3222 8717170.43 254231.54 26.641 NA
3223 8717146.21 254199.425 24.8 PL
3224 8717144.71 254198.554 24.77 LP
3225 8717157.32 254223.219 25.403 SAR
3226 8717158.25 254231.519 25.468 NA
3227 8717158.23 254232.463 25.662 V
3228 8717156.12 254231.126 25.407 E
3229 8717155.8 254232.113 25.623 NA
3230 8717153.84 254230.472 25.42 SAR
3231 8717144.12 254227.549 25.227 PISTA
3232 8717157.31 254249.443 26.484 NA
3233 8717132.98 254220.934 24.955 V
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3234 8717134.17 254224.816 25.223 PL
3235 8717133.04 254224.39 25.176 LP
3236 8717151.6 254278.229 27.38 NA
3237 8717150.24 254277.155 27.296 NA
3238 8717149.17 254276.801 27.374 V
3239 8717146.68 254276.437 27.109 NA
3240 8717144.82 254276.823 27.35 NA
3241 8717143.28 254277.582 27.377 NA
3242 8717139.64 254275.771 27.418 NA
3243 8717137.28 254272.762 25.553 E
3244 8717141.44 254279.636 27.444 NA
3245 8717134.56 254271.59 25.553 SAR
3246 8717138.59 254277.977 27.41 NA
3247 8717145.18 254288.632 27.252 NA
3248 8717122.04 254251.998 25.105 PT
3249 8717121.63 254251.578 25.238 V
3250 8717120.84 254251.212 25.241 NA
3251 8717143.67 254287.91 27.242 NA
3252 8717136.16 254276.611 25.59 NA
3253 8717140.82 254284.16 27.351 NA
3254 8717132.81 254275.216 25.59 NA
3255 8717126.67 254278.878 25.305 NA
3256 8717120.64 254277.454 25.332 PISTA
3257 8717113.63 254268.519 25.007 V
3258 8717112.97 254267.978 25.116 V
3259 8717124.44 254290.105 25.52 PAT
3260 8717126.72 254319.423 26.965 V
3261 8717125.32 254318.299 26.952 NA
3262 8717121.83 254317.566 27.071 NA
3263 8717117.3 254319.892 27.128 NA
3264 8717116.3 254322.158 27.008 NA
3265 8717112.89 254317.573 25.52 SAR
3266 8717120.06 254330.599 26.99 NA
3267 8717118.9 254329.069 26.975 NA
3268 8717116.34 254325.605 26.942 NA
3269 8717111.75 254319.991 25.493 SAR
3270 8717087.24 254385.88 26.332 NA
3271 8717085.71 254385.085 26.266 NA
3272 8717082.14 254383.344 25.501 SAR
3273 8717083.1 254386.017 25.873 SAR
3274 8717080.6 254382.899 25.458 V
3275 8717082.37 254387.558 25.786 V
3276 8717077.75 254381.668 25.317 PISTA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3277 8717068.67 254387.946 25.378 NA
3278 8720629.24 252204.794 40.671 LP
3279 8720644.21 252214.714 40.541 LP
3280 8720663.43 252225.194 40.403 LP
3281 8720619.01 252204.625 40.477 LP
3282 8720700.29 252250.043 41.664 PL
3283 8720672.12 252247.874 41.563 PL
3284 8720671.59 252250.555 41.417 SAR
3285 8720614.09 252224.668 40.662 LP
3286 8720659.72 252247.58 40.964 NA
3287 8720657.63 252247.076 40.951 NA
3288 8720613.79 252226.014 40.644 V
3289 8720661.65 252249.449 41.191 SAR
3290 8720659.53 252249.111 41.136 NA
3291 8720657.16 252248.242 41.289 TB
3292 8720657.42 252248.706 41.088 NA
3293 8720651.4 252246.477 40.932 NA
3294 8720652.64 252247.561 40.942 SAR
3295 8720651.27 252246.932 40.933 SAR
3296 8720638.41 252242.29 41.804 PL
3297 8720642.74 252244.671 40.695 SAR
3298 8720633.27 252241.86 40.645 SAR
3299 8720609.33 252230.489 40.443 NA
3300 8720623.35 252239.058 40.545 SAR
3301 8720602.97 252229.905 40.431 NA
3302 8720615.89 252236.285 40.662 SAR
3303 8720611.07 252234.039 40.536 PALM
3304 8720613.79 252236.319 40.645 V
3305 8720606.53 252232.879 40.461 PALM
3306 8720588.53 252225.129 40.426 PL
3307 8720609.18 252235.278 40.385 SAR
3308 8720588.21 252225.335 40.211 V
3309 8720601.36 252231.967 40.508 NA
3310 8720596.21 252231.169 40.474 NA
3311 8720600.26 252233.468 40.306 SAR
3312 8720590.94 252230.392 40.382 NA
3313 8720640.59 252254.838 40.898 NA
3314 8720642 252255.863 40.921 PT
3315 8720591.26 252232.026 40.244 SAR
3316 8720586.08 252229.804 40.352 NA
3317 8720640.21 252256.349 40.945 TB
3318 8720640.25 252257.221 40.91 NA
3319 8720652.94 252263.972 40.888 V
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3320 8720632.62 252254.623 40.817 A
3321 8720636.57 252256.694 40.879 PL
3322 8720642.67 252259.738 40.879 LP
3323 8720577.82 252228.77 40.333 NA
3324 8720627.29 252253.345 40.797 NA
3325 8720622.02 252252.478 40.766 NA
3326 8720575.22 252230.174 40.058 SAR
3327 8720591.06 252238.164 40.242 SAR
3328 8720617.46 252251.498 40.781 NA
3329 8720591.3 252238.872 40.244 NA
3330 8720590.94 252239.17 40.237 SAR
3331 8720612.15 252250.581 40.572 NA
3332 8720614.15 252252.465 40.689 PL
3333 8720658.36 252274.51 41.38 LP
3334 8720582.51 252237.829 40.417 PAT
3335 8720604.25 252249.067 40.555 NA
3336 8720578.01 252237.444 40.213 NA
3337 8720593.72 252245.832 40.291 SAR
3338 8720601.05 252249.819 40.567 V
3339 8720592.4 252245.695 40.275 SAR
3340 8720596.37 252247.643 40.504 NA
3341 8720604.9 252252.609 40.617 LP
3342 8720571.96 252236.865 40.136 NA
3343 8720600.88 252251.968 40.582 LP
3344 8720592.11 252248.222 40.487 SAR
3345 8720588.32 252246.686 40.332 NA
3346 8720565.06 252235.481 39.964 SAR
3347 8720589.77 252248.147 40.447 PL
3348 8720565.18 252236.226 40.071 NA
3349 8720562.3 252236.772 39.893 SAR
3350 8720598.97 252254.605 40.451 NA
3351 8720559.43 252235.682 40 NA
3352 8720596.57 252254.153 40.513 LP
3353 8720587.7 252249.884 40.446 LP
3354 8720553.25 252234.955 39.97 NA
3355 8720572.38 252245.923 40.212 NA
3356 8720516.72 252219.871 39.647 LP
3357 8720516.09 252221.848 39.61 V
3358 8720541.06 252234.094 39.81 NA
3359 8720563.59 252245.056 40.135 NA
3360 8720514.93 252223.269 39.37 SAR
3361 8720535.14 252233.463 39.731 NA
3362 8720529.14 252232.975 39.651 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3363 8720556.74 252246.612 40.006 PL
3364 8720556.74 252246.613 40.006 NA
3365 8720587.11 252263.718 40.49 LP
3366 8720515.73 252230.545 39.442 SAR
3367 8720537.25 252243.443 39.791 A
3368 8720515.55 252232.996 39.443 SAR
3369 8720533.72 252245.331 39.704 PL
3370 8719766.29 252423.347 14.063 NA
3371 8719769.27 252422.335 14.443 NA
3372 8719796.89 252413.365 21.44 MURO
3373 8719805.73 252409.998 21.174 MURO
3374 8719906.59 252367.056 10.534 MURO
3375 8719925.07 252359.292 9.89 V
3376 8719916.89 252362.936 10.144 MURO
3377 8719953.87 252347.222 10.726 MURO
3378 8719958.69 252345.283 10.913 MURO
3379 8719902.49 252369.466 10.588 MURO
3380 8719797.46 252414.422 21.409 MURO
3381 8719811.06 252408.665 21 MURO
3382 8719938.21 252354.285 10.061 MURO
3383 8719940.44 252353.392 10.401 MURO
3384 8719792.2 252417.007 21.652 MURO
3385 8719806.15 252411.094 21.183 V
3386 8719919.66 252362.579 9.836 MURO
3387 8719907.17 252368.206 10.423 V
3388 8719938.52 252354.983 10.03 V
3389 8719917.73 252364.06 9.864 E
3390 8719954.33 252348.458 10.727 V
3391 8719968.28 252342.59 11.414 MURO
3392 8719959.21 252346.593 10.865 V
3393 8719919.98 252363.416 9.857 E
3394 8719903.3 252370.566 10.61 V
3395 8719773.74 252426.018 16.219 NA
3396 8719941.01 252354.539 10.306 V
3397 8719811.32 252410.066 21.04 V
3398 8719771.03 252427.896 15.643 NA
3399 8719895.57 252374.886 11.156 MURO
3400 8719968.59 252343.877 11.303 V
3401 8719819.96 252407.469 20.431 MURO
3402 8719939.27 252356.806 10.127 E
3403 8719939.62 252356.677 10.252 E
3404 8719940.92 252356.188 10.284 E
3405 8719941.25 252356.053 10.202 E
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3406 8719771.92 252428.555 15.649 NA
3407 8719824.83 252406.327 20.031 NA
3408 8719896.3 252375.933 11.193 V
3409 8719789.19 252421.758 21.619 MURO
3410 8719773.01 252428.805 15.83 MURO
3411 8719820.13 252408.778 20.369 V
3412 8719982.85 252339.396 12.215 MURO
3413 8719833.54 252403.414 18.819 MURO
3414 8719825.24 252407.546 19.918 V
3415 8719790.35 252422.513 21.669 AUX
3416 8719799.76 252419.193 21.773 NA
3417 8719992.78 252336.809 13.066 MURO
3418 8719852.44 252396.871 16.063 MURO
3419 8719834.11 252404.756 18.747 V
3420 8719997.44 252335.208 13.408 MURO
3421 8719857.52 252395.32 15.234 NA
3422 8719788.82 252424.896 21.72 MURO
3423 8719796.86 252421.743 21.938 NA
3424 8719880.54 252385.959 12.742 MURO
3425 8719866.64 252392.064 14.14 MURO
3426 8719789.29 252425.269 21.841 TB
3427 8719852.83 252398.14 16.078 V
3428 8719993.23 252338.113 12.971 V
3429 8719997.8 252336.529 13.343 V
3430 8719857.89 252396.598 15.253 V
3431 8720006.92 252333.257 14.058 MURO
3432 8719881.19 252387.173 12.669 V
3433 8719867.14 252393.2 14.064 V
3434 8719960.66 252353.459 10.908 R
3435 8719947.21 252359.52 10.294 R
3436 8720083.95 252301.409 19.527 MURO
3437 8719911.92 252375.193 10.273 MURO
3438 8719811.09 252418.333 21.563 MURO
3439 8720074.92 252305.518 18.881 MURO
3440 8719904.02 252378.649 10.619 MURO
3441 8720007.02 252334.612 13.983 V
3442 8719807.26 252420.172 21.702 LP
3443 8720061.42 252311.863 17.892 MURO
3444 8719930.5 252367.946 10.028 MURO
3445 8719820.14 252415.265 20.491 MURO
3446 8719804.31 252422.181 21.94 LP
3447 8719973.33 252349.979 11.562 R
3448 8720052.67 252316.377 17.366 MURO
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3449 8720084.63 252302.77 19.435 V
3450 8720075.37 252306.738 18.765 V
3451 8720014.77 252332.704 14.48 E
3452 8720097.96 252297.148 20.609 AUX
3453 8719829.61 252412.011 19.512 MURO
3454 8720097.93 252297.253 20.48 V
3455 8719792.65 252428.177 22.303 NA
3456 8720061.95 252313.104 17.849 V
3457 8720016.88 252332.565 14.529 E
3458 8719801.3 252424.981 22.149 NA
3459 8720044.15 252321.135 16.861 MURO
3460 8719840.75 252408.178 17.992 MURO
3461 8720053.34 252317.685 17.272 V
3462 8720014.78 252334.191 14.449 E
3463 8720026.49 252329.343 15.672 MURO
3464 8719985.63 252346.888 12.324 R
3465 8720028.64 252328.502 15.902 MURO
3466 8719787.1 252431.981 22.783 R
3467 8720017.15 252333.909 14.508 E
3468 8719853.28 252404.188 16.142 MURO
3469 8720044.63 252322.337 16.755 V
3470 8719798.86 252427.831 22.348 NA
3471 8720026.9 252330.585 15.538 V
3472 8720029.21 252329.679 15.744 V
3473 8719864.66 252400.304 14.542 MURO
3474 8720148.02 252279.276 24.504 E
3475 8719995.07 252344.919 13.04 R
3476 8719782.71 252436.144 23.541 MURO
3477 8719796.7 252430.953 22.616 NA
3478 8720101.95 252294.114 20.956 MURO
3479 8720102.36 252295.336 20.836 V
3480 8720076.76 252311.794 18.692 V
3481 8720148.1 252281.381 24.603 E
3482 8720090.16 252306.332 19.605 R
3483 8719780.01 252439.151 23.69 MURO
3484 8720139.91 252285.384 23.983 R
3485 8719779.28 252439.921 24.207 LP
3486 8720152.98 252280.058 25.713 MURO
3487 8720100.46 252302.916 20.508 R
3488 8720064.52 252318.34 17.922 R
3489 8720132.65 252289.55 23.239 NA
3490 8719794.64 252434.18 22.909 NA
3491 8720008.69 252343.026 14.024 R
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3492 8720054.41 252323.818 17.156 R
3493 8719982.55 252355.571 22.696 NA
3494 8720046.15 252328.506 16.708 R
3495 8720034.25 252335.018 15.94 R
3496 8720129.88 252294.514 23.553 MURO
3497 8720151.35 252285.559 33.472 NA
3498 8720120.84 252299.737 22.637 NA
3499 8720108.73 252305.371 22.745 MURO
3500 8720022.07 252342.52 14.972 R
3501 8720109.37 252292.134 21.317 E
3502 8720001.78 252351.612 22.676 NA
3503 8719776.35 252448.114 25.632 LP
3504 8720109.59 252292.729 21.314 E
3505 8720109.75 252293.372 21.361 V
3506 8719790.57 252442.32 23.756 NA
3507 8720109.85 252291.995 20.978 E
3508 8720141.66 252292.591 33.617 NA
3509 8719781.07 252447.302 24.702 NA
3510 8720110.72 252291.682 21.186 E
3511 8720111.21 252291.417 21.437 E
3512 8720111.4 252292.091 21.443 E
3513 8719776.06 252452.201 25.61 LP
3514 8719776.06 252452.205 25.61 V
3515 8720016.14 252351.149 22.033 NA
3516 8720142.86 252297.924 34.439 NA
3517 8720099.5 252316.908 33.224 NA
3518 8720115.6 252289.132 22.092 MURO
3519 8720116.22 252290.253 22.054 V
3520 8719985.73 252366.335 30.463 NA
3521 8719786.35 252451.791 24.993 LP
3522 8719775.92 252456.253 25.811 V
3523 8719780.29 252454.536 25.387 NA
3524 8720088.75 252323.165 34.425 NA
3525 8720108.28 252315.248 32.789 NA
3526 8719996.16 252364.118 30.928 NA
3527 8719772.82 252460.149 26.092 LP
3528 8720067.76 252334.451 34.127 R
3529 8720115.83 252315.205 33.042 NA
3530 8720120 252285.818 22.773 MURO
3531 8720140.01 252305.241 35.579 NA
3532 8720120.78 252286.865 22.665 V
3533 8719771.51 252463.757 26.689 MURO
3534 8720134.26 252309.623 35.145 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3535 8719782.51 252460.592 26.179 LP
3536 8720010.92 252363.203 30.554 NA
3537 8720128.22 252313.315 34.823 NA
3538 8719771.11 252467.033 27.116 LP
3539 8720123.44 252282.472 23.189 MURO
3540 8720124.23 252283.622 23.087 V
3541 8719782.44 252463.146 26.66 NA
3542 8720127.44 252279.707 23.516 MURO
3543 8720128.13 252280.847 23.392 V
3544 8719775.3 252477.424 27.614 R
3545 8720136.88 252287.242 23.495 R
3546 8720136.36 252275.547 23.984 V
3547 8719758.69 252487.73 28.988 LP
3548 8719758.77 252488.506 29.067 LP
3549 8719768.13 252486.98 29.018 LP
3550 8720139.92 252272.086 24.324 MURO
3551 8719768.05 252488.257 29.146 AUX
3552 8720140.54 252273.194 24.221 V
3553 8719747.49 252499.29 28.692 PALM
3554 8719777.1 252487.179 28.96 V
3555 8719778.91 252487.12 29.578 LP
3556 8719750.81 252499.16 28.744 NA
3557 8719777.89 252488.623 29.395 NA
3558 8719753.74 252498.966 28.785 NA
3559 8719779.66 252488.546 29.594 PL
3560 8719778.8 252488.923 29.402 NA
3561 8719757.22 252498.396 28.87 NA
3562 8719785.06 252486.956 29.645 LP
3563 8719770.91 252493.344 29.159 BZD
3564 8719760.61 252498.427 28.915 NA
3565 8719759.64 252500.592 29.017 AUX
3566 8720148.77 252266.963 24.766 MURO
3567 8720149.42 252268.098 24.738 V
3568 8719761.02 252502.61 29.067 NA
3569 8720156.79 252262.891 25.165 E
3570 8720157.31 252264.224 25.217 V
3571 8720157.8 252262.54 25.244 E
3572 8720159.29 252269.477 25.309 MURO
3573 8720162.88 252260.263 25.74 NA
3574 8720163.48 252261.349 25.652 V
3575 8720167.55 252271.106 33.083 LP
3576 8720171.38 252263.267 26.259 MURO
3577 8720176.41 252254.936 26.612 V
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3578 8720185.1 252249.72 27.325 MURO
3579 8720185.63 252250.868 27.352 LP
3580 8720187.76 252256.15 27.451 R
3581 8720191.72 252260.119 32.412 LP
3582 8720192.68 252261.837 33.51 LP
3583 8720193.59 252244.633 28.139 MURO
3584 8720194.19 252245.818 28.141 V
3585 8720196.36 252251.719 28.05 R
3586 8720198.09 252242.759 28.527 MURO
3587 8720198.56 252243.876 28.522 V
3588 8720207.36 252238.734 29.357 MURO
3589 8720208.15 252239.884 29.3 V
3590 8720210.66 252244.598 29.449 R
3591 8720211.73 252236.316 29.731 MURO
3592 8720212.41 252237.438 29.739 V
3593 8720215.82 252233.519 30.09 MURO
3594 8720216.56 252234.472 30.073 V
3595 8720223.55 252226.947 30.918 MURO
3596 8720224.27 252228.065 30.872 V
3597 8720228.72 252236.344 30.933 R
3598 8720227.89 252224.581 31.226 MURO
3599 8720228.71 252225.574 31.218 V
3600 8720233.83 252220.326 31.666 MURO
3601 8720234.48 252221.553 31.654 V
3602 8720236.17 252219.241 31.84 NA
3603 8720236.79 252220.429 31.807 V
3604 8720238.13 252219.919 31.969 TB
3605 8720241.15 252217.838 32.357 MURO
3606 8720241.65 252219.02 32.256 V
3607 8720243.29 252220.872 32.355 MURO
3608 8720244.81 252228.377 32.119 R
3609 8720242.96 252230.763 33.791 V
3610 8720243.58 252231.796 33.811 LP
3611 8720248.64 252213.148 32.316 R
3612 8720253.04 252215.792 33.537 MURO
3613 8720251.42 252224.96 33.745 V
3614 8720252.34 252226.662 33.907 NA
3615 8720256.26 252206.762 33.036 NA
3616 8720253.34 252228.436 34.035 NA
3617 8720267.35 252220.93 36.492 TB
3618 8720265.22 252198.422 33.417 NA
3619 8720275.71 252211.138 36.259 NA
3620 8720277.19 252213.566 36.301 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3621 8720280.98 252219.689 36.394 NA
3622 8720282.22 252221.707 36.446 NA
3623 8720316.01 252253.583 37.503 PL
3624 8720334.18 252274.91 37.638 LP
3625 8717055.36 254431.243 25.856 PAT
3626 8717068.66 254404.911 23.585 NA
3627 8717034.74 254439.574 25.411 PAT
3628 8717099.74 254349.177 26.757 A
3629 8717112.21 254335.21 26.868 PAT
3630 8717054.02 254392.354 24.712 PT
3631 8717051.5 254395.089 24.575 PL
3632 8717112.49 254326.819 26.986 A
3633 8717055.79 254384.045 24.542 LP
3634 8717120.82 254311.706 26.94 A
3635 8717141.8 254287.83 27.399 PAT
3636 8717064.29 254368.648 25.152 PL
3637 8717133.47 254291.352 27.233 PL
3638 8717131.61 254292.009 27.065 A
3639 8717066.17 254362.414 25.186 LP
3640 8717136.28 254283.641 27.175 A
3641 8717075.1 254348.997 24.542 PT
3642 8717144.76 254269.144 26.916 A
3643 8717077.9 254341.941 24.896 PL
3644 8717089.79 254327.844 25.273 PALM
3645 8717092.4 254324.187 25.233 A
3646 8717136.64 254274.198 25.593 V
3647 8717137.12 254269.817 26.576 PAT
3648 8717101.51 254306.137 25.25 A
3649 8717102.88 254302.689 25.25 A
3650 8717149.39 254249.864 26.212 A
3651 8717169.12 254227.77 26.233 A
3652 8717103.35 254300.424 25.326 NA
3653 8717105.74 254296.267 25.273 NA
3654 8717108.71 254291.588 25.295 A
3655 8717111.84 254285.576 25.253 A
3656 8717099.24 254298.945 25.192 PT
3657 8717115.43 254278.597 25.215 NA
3658 8717160 254229.016 25.387 NA
3659 8717160.62 254226.04 25.416 V
3660 8717102.69 254289.171 25.221 V
3661 8717101.73 254289.21 25.198 LP
3662 8717106.86 254282.974 25.186 PL
3663 8717123.63 254259.525 25.185 A
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3664 8717125.18 254256.612 25.194 NA
3665 8717127.51 254252.578 25.303 PINO
3666 8717113.86 254266.652 25.038 V
3667 8717129.22 254248.983 25.341 A
3668 8717112.26 254267.198 25.133 LP
3669 8717112.02 254265.801 25.114 PT
3670 8717119.01 254257.624 25.122 PL
3671 8717116.95 254259.176 25.007 NA
3672 8717133.38 254240.939 25.303 A
3673 8717133.38 254240.936 24.403 NA
3674 8717117.6 254258.24 25.057 V
3675 8717116.14 254259.11 24.955 NA
3676 8717116.21 254258.654 25.131 V
3677 8717116.73 254257.786 25.182 LP
3678 8717136.21 254235.356 25.245 A
3679 8717114.54 254258.367 24.993 PL
3680 8717140.29 254227.014 25.205 PALM
3681 8717145.4 254215.364 25.284 A
3682 8717109.36 254255.088 24.765 V
3683 8717133.71 254226.332 25.071 PT
3684 8717148.44 254209.174 25.489 A
3685 8717108.46 254253.492 24.967 LP
3686 8717101.23 254261.218 24.93 LP
3687 8717134.29 254223.979 25.094 V
3688 8717133.11 254223.985 25.172 LP
3689 8717100.81 254259.596 24.692 V
3690 8717139.86 254212.874 25.085 V
3691 8717132.77 254219.853 25.157 V
3692 8717139.07 254211.341 25.175 LP
3693 8717136.54 254212.919 24.847 V
3694 8717137.13 254212.061 25.191 LP
3695 8717131.48 254210.207 24.456 V
3696 8717131.5 254209.131 24.604 LP
3697 8719960.01 252376.559 31.312 R
3698 8719948.52 252386.436 30.426 R
3699 8719933.6 252391.823 30.569 R
3700 8719925.5 252392.809 30.192 R
3701 8719920.26 252393.742 29.999 R
3702 8719910.8 252398.736 30.487 R
3703 8719898.49 252403.372 30.324 R
3704 8719893.22 252409.189 31.683 R
3705 8719871.33 252419.216 30.837 R
3706 8719860.98 252419.91 30.376 R
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3707 8719850.82 252425.113 30.95 R
3708 8719839.39 252428.099 31.717 R
3709 8719830.52 252434.084 31.377 R
3710 8719820.56 252432.869 30.66 R
3711 8719812.01 252426.708 22.722 R
3712 8719805.45 252427.888 22.591 R
3713 8720788.03 252286.65 42.788 R
3714 8720710.47 252285.124 42.104 R
3715 8719886.33 252392.225 12.508 R
3716 8717996.97 252928.691 28.321 CD
3717 8717993.51 252937.676 27.992 CA
3718 8717990.17 252949.25 28.192 CA
3719 8717989.97 252949.796 28.187 CD
3720 8717987.13 252958.196 28.134 CD
3721 8717984.04 252965.467 28.135 CD
3722 8717983.88 252965.938 28.132 CA
3723 8717982.59 252969.326 28.097 CA
3724 8717980.78 252973.358 28.055 CD
3725 8717976.36 252984.956 28.108 CD
3726 8717976.29 252985.477 28.054 CA
3727 8717976.29 252985.477 28.054 NA
3728 8717976.24 252985.521 28.107 CA
3729 8717975.32 252988.425 28.02 NA
3730 8717971.41 253000.437 27.864 CD
3731 8717970.75 253000.77 27.891 CA
3732 8717969.54 253005.24 27.887 CD
3733 8717968.35 253009.44 27.834 CA
3734 8717967.65 253011.648 27.806 CA
3735 8717967.48 253012.236 27.84 CD
3736 8717967.3 253013.084 27.831 CA
3737 8717963.33 253027.181 27.684 CA
3738 8717963.24 253027.601 27.679 CD
3739 8717963.08 253028.429 27.668 CA
3740 8717962.99 253028.854 27.665 CD
3741 8717958.94 253044.158 27.522 CA
3742 8717958.81 253044.57 27.52 CD
3743 8717957.97 253047.923 27.513 CA
3744 8717957.68 253048.408 27.507 CD
3745 8717955.56 253056.411 27.462 CD
3746 8717955.53 253056.733 27.458 CA
3747 8717954.29 253061.646 27.401 CA
3748 8717954.23 253062.114 27.417 CD
3749 8717952.63 253067.902 27.357 CA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3750 8717950.6 253074.538 27.015 CD
3751 8717948.38 253083.302 26.939 CD
3752 8717947.9 253083.633 26.934 CA
3753 8717944.48 253095.775 26.775 CD
3754 8717944.47 253096.285 26.77 CA
3755 8717941.72 253104.564 27.09 CA
3756 8717941.43 253106.166 27 CD
3757 8717937.7 253118.734 27.047 CA
3758 8717937.03 253121.238 27 CD
3759 8717935.48 253126.488 26.915 CA
3760 8717934.54 253129.715 26.874 CD
3761 8717933.24 253134.681 26.818 CA
3762 8717932.41 253137.259 26.837 CD
3763 8717921.75 253158.044 25.949 CD
3764 8717920.8 253160.983 26.155 CA
3765 8717919.17 253166.334 25.924 CA
3766 8717915.37 253179.161 25.83 CA
3767 8717910.31 253187.971 24.918 LP
3768 8717933.28 253204.747 26.62 V
3769 8717895.89 253184.149 24.062 LP
3770 8717895.89 253184.148 24.062 NA
3771 8717899.16 253201.33 23.943 CD
3772 8717898.99 253201.688 23.941 CA
3773 8717916.74 253215.064 26.926 LP
3774 8717895.69 253213.139 23.913 CD
3775 8717893.35 253222.328 23.689 CA
3776 8717893.23 253222.871 23.666 CD
3777 8717888.49 253236.858 23.807 LP
3778 8717881.3 253264.982 24.052 CD
3779 8717872.05 253292.525 24.125 P
3780 8717870.87 253296.481 24.142 P
3781 8717864.86 253323.746 24.101 CD
3782 8717864.61 253325.079 24.087 CA
3783 8717861.52 253335.532 24.259 CA
3784 8717861.19 253336.837 24.26 CA
3785 8717860.89 253337.627 24.274 CD
3786 8717858.48 253342.226 24.305 CD
3787 8717858.24 253342.594 24.304 CA
3788 8717829.03 253415.862 22.74 CD
3789 8717829.29 253417.029 22.747 CA
3790 8717819.03 253432.946 22.837 CD
3791 8717818.82 253433.331 22.831 CA
3792 8717812.81 253443.536 22.882 CD
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3793 8717809.57 253449.655 23.505 CD
3794 8717809.31 253450.229 23.463 CA
3795 8717807.61 253453.82 23.552 CA
3796 8717807.14 253454.074 23.549 CD
3797 8717819.46 253468.023 24.019 A
3798 8717800.02 253465.911 23.565 CD
3799 8717799.75 253466.352 23.491 CA
3800 8717799.39 253467.085 23.491 CA
3801 8717795.8 253472.802 23.496 CD
3802 8717794.41 253475.857 23.541 CD
3803 8717791.82 253479.648 23.56 CD
3804 8717791.86 253480.229 23.561 CA
3805 8717791 253481.469 23.481 CD
3806 8717789.04 253484.485 23.497 CA
3807 8717787.05 253487.91 23.551 CA
3808 8717786.9 253488.697 23.577 CD
3809 8717780.97 253497.776 23.633 CA
3810 8717907.54 253302.604 25.852 NA
3811 8717920.03 253298.173 26.01 V
3812 8717893.39 253333.156 25.689 RAM
3813 8717923.78 253310.47 26.176 NA
3814 8717892.37 253335.381 25.666 NA
3815 8717905 253338.831 25.847 NA
3816 8717929.29 253320.901 26.137 CA
3817 8717928.96 253321.392 26.157 CD
3818 8717908.21 253340.399 26.024 RAM
3819 8717925.22 253327.706 26.09 CD
3820 8717925.2 253328.474 26.092 CA
3821 8717922.6 253332.218 26.056 CD
3822 8717881.8 253365.624 25.538 V
3823 8717921.04 253335.231 26.037 CA
3824 8717920.08 253336.478 26.016 CD
3825 8717875.97 253376.992 25.474 V
3826 8717876.68 253377.458 26.113 V
3827 8717889.63 253369.562 26.185 NA
3828 8717889.95 253369.601 25.834 V
3829 8717883.52 253381.149 26.153 V
3830 8717883.91 253381.314 25.758 V
3831 8717871.4 253391.231 25.451 V
3832 8717873.87 253390.384 25.454 V
3833 8717857.6 253403.863 25.13 RAM
3834 8717856.28 253406.103 25.078 NA
3835 8717912.85 253361.831 25.985 CD
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3836 8717874.9 253393.134 25.468 NA
3837 8717877.07 253394.265 25.555 NA
3838 8717907.56 253371.389 25.948 CD
3839 8717881.35 253392.836 25.63 V
3840 8717905.69 253373.804 25.912 CD
3841 8717898.89 253384.794 25.841 CA
3842 8717839.93 253434.462 24.781 V
3843 8717871.73 253411.636 25.534 NA
3844 8717870.5 253413.827 25.478 RAM
3845 8717827.83 253455.991 24.421 NA
3846 8717826.7 253457.47 24.39 RAM
3847 8717828.72 253456.632 24.634 NA
3848 8717843.36 253446.93 24.886 V
3849 8717830.32 253459.897 24.563 V
3850 8717837.76 253454.631 24.799 RAM
3851 8717877.38 253424.29 25.468 CD
3852 8717875.15 253426.765 25.428 CA
3853 8717830.87 253461.829 24.707 NA
3854 8717875.05 253427.554 25.426 CA
3855 8717839.39 253455.678 24.867 NA
3856 8717874.62 253428.036 25.431 CD
3857 8717855.47 253443.58 25.121 V
3858 8717838.87 253456.704 24.878 NA
3859 8717832.61 253462.782 24.713 NA
3860 8717834.43 253462.212 24.815 NA
3861 8717870.07 253436.15 25.333 CD
3862 8717835.85 253463.098 24.854 NA
3863 8717869.72 253436.978 25.316 CA
3864 8717836.16 253464.765 24.874 NA
3865 8717810.09 253485.728 24.276 V
3866 8717837.87 253465.831 24.912 NA
3867 8717839.88 253465.26 24.961 NA
3868 8717863.92 253447.324 25.226 CA
3869 8717863.71 253447.703 25.215 CD
3870 8717842.65 253464.288 25.01 NA
3871 8717843.01 253464.572 24.847 RAM
3872 8717813.73 253487.694 24.548 NA
3873 8717804.2 253495.749 24.176 NA
3874 8717816.23 253486.423 24.613 NA
3875 8717814.88 253487.685 24.538 NA
3876 8717842.14 253466.766 25.026 NA
3877 8717818 253487.449 24.652 NA
3878 8717817.22 253489.12 24.564 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3879 8717817.71 253489.984 24.675 V
3880 8717807.84 253497.767 24.406 NA
3881 8717808.51 253498.846 24.388 NA
3882 8717823.51 253487.171 25.372 LP
3883 8717819.43 253490.859 24.711 V
3884 8717808.33 253499.808 24.409 NA
3885 8717821.58 253489.419 24.75 V
3886 8717820.25 253490.831 24.724 NA
3887 8717853.63 253464.694 25.061 CA
3888 8717823.3 253490.422 24.811 NA
3889 8717810.13 253500.877 24.419 NA
3890 8717811 253500.258 24.409 NA
3891 8717811.82 253500.183 24.489 NA
3892 8717813.21 253500.98 24.428 NA
3893 8717823.52 253493.043 24.752 NA
3894 8717847.39 253475.41 24.992 CD
3895 8717813.77 253502.068 24.608 NA
3896 8717429.05 253829.991 22.203 CA
3897 8717846.05 253477.471 24.988 CA
3898 8717813.78 253502.944 24.617 V
3899 8717788.26 253523.06 23.955 NA
3900 8717825.85 253494.506 24.728 NA
3901 8717435.06 253826.159 22.226 CA
3902 8717457.32 253805.635 23.126 CD
3903 8717456.04 253807.008 22.978 CA
3904 8717464.44 253799.256 23.163 CA
3905 8717469.98 253794.18 23.016 CA
3906 8717448.57 253813.978 22.404 CA
3907 8717455.54 253807.564 22.99 CD
3908 8717824.8 253496.477 24.694 RAM
3909 8717815.49 253503.822 24.636 V
3910 8717816.34 253503.183 24.62 NA
3911 8717843.23 253482.632 24.97 CA
3912 8717460.16 253804.962 23.089 SAR
3913 8717465.71 253800.018 23.135 SAR
3914 8717842.99 253483.146 24.971 CD
3915 8717457.71 253807.497 23.06 SAR
3916 8717817.56 253503.234 24.565 NA
3917 8717472.46 253794.072 22.923 SAR
3918 8717792.39 253525.361 24.154 NA
3919 8717793.92 253524.316 24.133 NA
3920 8717793.11 253525.158 24.14 NA
3921 8717839.44 253488.914 24.948 CA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3922 8717839.32 253489.332 24.957 CD
3923 8717838.27 253491.185 24.955 CD
3924 8717795.51 253525.356 24.21 NA
3925 8717460.55 253810.151 23.243 SAR
3926 8717463.55 253807.687 23.202 SAR
3927 8717795.27 253526.217 24.217 NA
3928 8717469.11 253803.114 23.197 SAR
3929 8717475.07 253798.324 23.153 SAR
3930 8717492.44 253782.321 23.299 CA
3931 8717493.24 253781.688 23.286 CD
3932 8717795.53 253527.195 24.205 NA
3933 8717835.09 253496.48 24.951 CA
3934 8717773.91 253544.638 23.893 NA
3935 8717502.42 253774.212 23.364 CD
3936 8717504.37 253772.562 23.34 CD
3937 8717506.38 253771.106 23.329 CA
3938 8717508.09 253769.965 23.294 CA
3939 8717516.59 253762.834 23.259 CA
3940 8717518.93 253760.954 23.276 CD
3941 8717797.54 253528.266 24.209 NA
3942 8717522.72 253757.678 23.224 CD
3943 8717799.17 253527.365 24.313 NA
3944 8717523.98 253756.745 23.236 CA
3945 8717798.49 253528.164 24.338 NA
3946 8717535.82 253747.788 23.133 CA
3947 8717383.53 253879.578 25.35 A
3948 8717800.82 253528.382 24.343 V
3949 8717792.7 253534.819 24.015 NA
3950 8717801.33 253530.464 24.364 NA
3951 8717779.26 253548.034 23.95 NA
3952 8717787.19 253543.117 23.967 V
3953 8717825.71 253513.574 24.823 CD
3954 8717824.25 253515.71 24.813 CA
3955 8717803.9 253532.175 24.371 NA
3956 8717751.33 253574.583 23.691 NA
3957 8717781.83 253551.198 24.017 NA
3958 8717751.93 253574.98 23.683 V
3959 8717749.03 253577.367 23.671 NA
3960 8717733.06 253590.148 23.569 V
3961 8717749.97 253577.037 23.654 NA
3962 8717820.75 253521.556 24.71 CD
3963 8717783.92 253550.677 23.949 NA
3964 8717820.54 253522.075 24.718 CA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
3965 8717750.84 253577.188 23.755 V
3966 8717733.95 253590.969 23.617 NA
3967 8717732.57 253592.642 23.622 NA
3968 8717771.56 253562.435 23.932 NA
3969 8717754.65 253575.99 23.699 NA
3970 8717754.5 253577.019 23.71 NA
3971 8717754.49 253577.026 23.739 V
3972 8717736 253591.773 23.631 NA
3973 8717734.06 253594.004 23.608 NA
3974 8717768.47 253567.024 23.916 NA
3975 8717771.64 253564.597 23.873 V
3976 8717754.88 253577.9 24.034 V
3977 8717734.3 253595.286 23.657 NA
3978 8717733.32 253596.632 23.616 NA
3979 8717756.05 253578.989 24.068 NA
3980 8717736.33 253594.934 23.614 NA
3981 8717789.4 253553.731 24.21 NA
3982 8717757.12 253579.155 24.07 NA
3983 8717757.97 253578.638 24.096 V
3984 8717812.36 253535.99 24.512 NA
3985 8717812.36 253536.001 24.512 CA
3986 8717812.19 253536.566 24.52 CD
3987 8717839.9 253516.083 25.389 LP
3988 8717756.34 253581.975 24.037 V
3989 8717541.14 253763.715 23.2 A
3990 8717737.67 253597.106 23.902 NA
3991 8717707.39 253620.601 23.231 V
3992 8717809.35 253541.797 24.471 CD
3993 8717702.93 253625.543 23.265 NA
3994 8717714.13 253617.233 23.558 V
3995 8717701.7 253626.947 23.258 NA
3996 8717756.86 253584.248 24.029 NA
3997 8717701.48 253627.778 23.276 NA
3998 8717684.56 253644.103 22.976 V
3999 8717701.94 253628.657 23.292 NA
4000 8717715.01 253618.457 23.571 NA
4001 8717717.5 253616.511 23.6 V
4002 8717717.31 253617.389 23.617 NA
4003 8717741.05 253599.322 23.933 NA
4004 8717686.09 253644.45 23.174 V
4005 8717717.74 253618.035 23.608 NA
4006 8717715.21 253620.78 23.578 NA
4007 8717742.28 253599.532 23.914 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
4008 8717743.77 253598.762 23.929 NA
4009 8717800.34 253554.997 24.36 CA
4010 8717686.1 253646.927 23.226 NA
4011 8717800.18 253555.463 24.362 CD
4012 8717741.14 253602.162 23.906 NA
4013 8717648.13 253679.8 23.155 SAR
4014 8717686.34 253647.387 23.297 NA
4015 8717742.22 253601.602 23.901 NA
4016 8717618.42 253705.337 22.991 SAR
4017 8717686.16 253647.833 23.366 NA
4018 8717745.11 253600.098 23.953 V
4019 8717634.64 253692.342 22.887 NA
4020 8717643.97 253684.393 23.08 NA
4021 8717743.6 253601.665 23.91 NA
4022 8717795.5 253561.112 24.261 CA
4023 8717717.41 253622.669 23.584 NA
4024 8717719.42 253622.771 23.821 NA
4025 8717789.63 253568.033 24.303 CD
4026 8717746.87 253601.744 24.042 V
4027 8717688.28 253650.037 23.397 NA
4028 8717698.94 253640.555 23.412 A
4029 8717688.92 253649.608 23.358 NA
4030 8717787.47 253570.38 24.44 CA
4031 8717689.37 253649.795 23.353 NA
4032 8717253.03 254018.748 23.124 BZD
4033 8717721.18 253623.694 23.839 NA
4034 8717241.18 254030.243 21.923 CD
4035 8717241.01 254030.639 21.929 CA
4036 8717781.16 253577.024 24.252 CA
4037 8717781.88 253576.731 24.258 CD
4038 8717238.28 254034.265 21.995 CD
4039 8717777.22 253581.058 24.256 CA
4040 8717237.71 254035.133 21.969 CA
4041 8717621.6 253710.624 23.224 V
4042 8717622.64 253710.66 23.299 V
4043 8717231.76 254043.384 23.045 CA
4044 8717767.81 253591.681 24.196 CA
4045 8717769.71 253590.426 24.18 CD
4046 8717767.56 253592.2 24.172 CD
4047 8717361.68 253937.734 23.562 CD
4048 8717693.22 253652.979 23.576 NA
4049 8717360.92 253938.652 23.573 CA
4050 8717692.66 253653.544 23.586 NA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
4051 8717693.32 253653.356 23.622 NA
4052 8717358.73 253941.488 23.553 CD
4053 8717359.31 253941.031 23.546 CA
4054 8717226.63 254050.853 23.132 CA
4055 8717624.6 253712.967 23.274 V
4056 8717757.87 253602.619 24.25 CD
4057 8717757.47 253603.175 24.14 CA
4058 8717713.65 253638.477 23.614 NA
4059 8717762.15 253600.733 23.897 CD
4060 8717761.34 253601.449 23.884 CA
4061 8717714.57 253638.317 23.658 NA
4062 8717351.54 253951.921 23.588 CA
4063 8717351.06 253952.406 23.594 CD
4064 8717695.36 253655.789 23.674 NA
4065 8717695.84 253655.52 23.707 NA
4066 8717716.51 253636.95 23.615 NA
4067 8717715.33 253638.42 23.645 NA
4068 8717696.41 253655.714 23.703 NA
4069 8717345.48 253959.94 23.801 CA
4070 8717346.01 253959.643 23.795 CD
4071 8717213.31 254069.483 23.52 CD
4072 8717213 254069.926 23.534 CA
4073 8717699.38 253655.555 23.779 NA
4074 8717743.03 253619.984 23.848 CD
4075 8717627.07 253717.83 23.782 V
4076 8717743.82 253619.581 23.837 CA
4077 8717698.35 253657.361 23.787 NA
4078 8717698.58 253657.601 23.806 NA
4079 8717629.91 253716.216 23.858 V
4080 8717699.7 253656.92 23.682 NA
4081 8717739.89 253623.552 23.839 CA
4082 8717698.55 253658.182 23.836 NA
4083 8717699.35 253657.492 23.838 NA
4084 8717738.21 253625.336 23.792 CD
4085 8717191.41 254093.063 22.596 LP
4086 8717736.48 253627.504 23.807 CA
4087 8717207.37 254078.786 23.746 CD
4088 8717731.9 253632.281 23.81 NA
4089 8717205.39 254081.647 23.631 CA
4090 8717329.74 253978.329 23.828 CD
4091 8717330.44 253977.896 23.825 CA
4092 8717728.04 253636.06 23.791 NA
4093 8717727.6 253636.583 23.776 CD
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
4094 8717327.68 253981.188 23.875 CD
4095 8717327.76 253981.347 23.86 CA
4096 8717629.74 253720.708 23.946 V
4097 8717202.28 254086.359 23.641 CD
4098 8717723.33 253640.622 23.736 CA
4099 8717722.88 253641.109 23.719 CA
4100 8717324.04 253985.818 23.886 CA
4101 8717629.99 253721.566 23.951 NA
4102 8717720.67 253643.678 23.713 CD
4103 8717194.44 254094.975 23.347 LP
4104 8717321.88 253988.671 23.847 CD
4105 8717190.88 254099.019 23.22 LP
4106 8717209.68 254083.105 23.971 A
4107 8717556.74 253787.058 25.705 CA
4108 8717189.25 254102.464 23.086 CA
4109 8717561.24 253784.878 25.728 CA
4110 8717312.7 253999.753 23.886 CA
4111 8717205.03 254090.339 23.842 PT
4112 8717696.42 253671.622 23.882 CD
4113 8717201.52 254095.51 24.001 A
4114 8717569.52 253780.93 25.698 CA
4115 8717570.08 253780.555 25.687 CD
4116 8717569.75 253781.429 25.753 CA
4117 8717688.51 253680.436 23.996 CD
4118 8717574.83 253778.301 25.685 CA
4119 8717575.19 253778.247 25.713 CD
4120 8717686.8 253682.704 24.046 CA
4121 8717682.87 253686.746 24.049 NA
4122 8717682.54 253687.202 24.062 CD
4123 8717676.37 253694.13 24.146 CD
4124 8717600.71 253759.235 24.768 CA
4125 8717675.51 253695.237 24.173 CA
4126 8717601.27 253758.848 24.79 CD
4127 8717674.17 253696.625 24.157 CA
4128 8717290.89 254026.939 23.961 CD
4129 8717673.82 253697.034 24.167 CD
4130 8717585.33 253772.97 25.608 CD
4131 8717290.66 254027.33 23.966 CA
4132 8717584.76 253773.64 25.876 CA
4133 8717666.69 253704.745 24.307 CA
4134 8717667.57 253704.326 24.293 CD
4135 8717667.63 253704.346 24.289 NA
4136 8717284.96 254034.469 24.024 CA
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
4137 8717285.3 254034.153 24.019 CD
4138 8717608.19 253755.754 24.763 CA
4139 8717170.04 254134.906 22.985 CD
4140 8717169.41 254135.508 22.951 CD
4141 8717661.73 253710.478 24.361 CA
4142 8717661.38 253711.158 24.372 CD
4143 8717610.92 253754.407 24.792 CD
4144 8717279.83 254040.783 23.995 CD
4145 8717169.53 254137.65 23.119 V
4146 8717653.06 253720.382 24.516 CD
4147 8717652.63 253720.894 24.51 CA
4148 8717651.44 253722.162 24.539 CA
4149 8717651.24 253722.732 24.551 CD
4150 8717613.36 253755.886 24.992 CA
4151 8717615.87 253754.864 24.976 CD
4152 8717171.08 254139.719 23.078 CA
4153 8717170.53 254140.567 23.075 CD
4154 8717621.12 253751.115 24.958 CA
4155 8717620.59 253751.623 24.967 CD
4156 8717264.15 254060.622 24.229 CD
4157 8717263.88 254060.898 24.225 CA
4158 8717169.09 254145.501 23.16 V
4159 8717166.95 254147.801 23.137 CA
4160 8717258.06 254068.66 24.205 CA
4161 8717257.75 254069.078 24.184 CD
4162 8717155.21 254158.991 23.256 LP
4163 8717238.94 254093.006 24.367 CD
4164 8717234.03 254098.734 24.45 CD
4165 8717233.63 254099.115 24.45 CA
4166 8717233.04 254100.044 24.448 CA
4167 8717232.88 254100.458 24.448 CD
4168 8717183.26 254144.448 24.276 V
4169 8717228.35 254106.279 24.518 CD
4170 8717162.88 254163.273 23.819 LP
4171 8717228 254106.772 24.516 CA
4172 8717180.27 254151.321 24.288 V
4173 8717190.6 254148.322 24.401 A
4174 8717153.77 254183.4 24.36 CA
4175 8717142.58 254204.771 24.352 CD
4176 8717140.76 254209.806 24.613 CD
4177 8717139.9 254211.118 24.617 CA
4178 8717128.53 254234.471 23.281 CA
4179 8717125.21 254241.591 23.31 CD
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
4180 8717124.91 254242.042 23.353 CA
4181 8717120.28 254251.588 23.267 CA
4182 8717120.17 254251.906 23.27 CD
4183 8717105.41 254282.472 25.14 CA
4184 8717104.19 254285.382 25.136 CA
4185 8717103.58 254286.578 25.16 CD
4186 8717100.24 254293.592 25.064 CA
4187 8717099.8 254294.271 25.101 CD
4188 8717094.7 254304.677 24.987 CA
4189 8717079.48 254336.222 24.972 CD
4190 8717079.34 254336.747 24.974 CA
4191 8717075.44 254346.945 25.049 CD
4192 8717070.67 254356.229 25.08 CD
4193 8717070.12 254357.098 25.082 CA
4194 8717068.01 254359.844 25.076 CD
4195 8717058.21 254380.914 24.937 CD
4196 8717057.96 254381.468 24.938 CA
4197 8717054.17 254388.785 25.005 CD
4198 8717054.05 254389.38 24.99 CA
4199 8717047.89 254402.031 25.285 CD
4200 8717047.49 254403.019 25.294 CA
4201 8717044.48 254407.61 25.495 LP
4202 8717039.31 254413.818 25.075 NA
4203 8717080.92 254384.048 25.48 A
4204 8717040.21 254414.705 25.19 NA
4205 8717043.34 254417.959 25.317 R
4211 8722132.13 251975.339 52.28 R

CHANCAY. A partir de los puntos de control se han referenciado BMs. en cada


levantamiento, los cuales se constituyen como hitos para el replanteo de las obras y están
marcado con pintura, e indicadas en los planos topográficos.

6.4 RELLENO TOPOGRÁFICO


Basado en los vértices de apoyo, se ha procedido a efectuar el levantamiento topográfico
absoluto, utilizando una estación total FOIF RTS 102R5 de 2 a 5 segundos de precisión, los
mismos que tienen capacidad de almacenamiento de hasta 5000 puntos de relleno.

ESTUDIOS DE INFRAESTRUCTURA SOCIAL


Estos puntos fueron transferidos para el procesamiento digital del terreno de modo que se
pueda obtener el levantamiento topográfico a la escala 1/1000.
Cada grupo de información ha sido ajustada a las coordenadas de los vértices de la poligonal y
también a la cota de los mismos.
El relleno topográfico ha permitido obtener las diferentes posiciones de los elementos
componentes del área en estudio tanto en altimetría como en planimetría.
6.5 TRABAJO DE GABINETE
Los datos de campo tomados se procesaron con ayuda de software adecuado para representar
el terreno mediante curvas de nivel.
Con toda la información consolidada han elaborado planos.
6.7 PERSONAL Y EQUIPO DE CAMPO
Para la ejecución de levantamientos topográficos se contó con la siguiente brigada topográfica:

 01 Ingeniero Monitor
 01 Topógrafo
 03 Ayudantes
 01 Seguridad
El equipo utilizado para el levantamiento topográfico fue:

 01 Estación Total FOIF RTS 102R5


 03 Prismas más porta prismas
 03 Jalones con Nivel tubular
 01 Trípode de Aluminio
 01 GPS Garmin
 01 Camioneta.
 0 Cámaras Digitales
 Pintura, etc.

6.8 PANEL FOTOGRAFICO

ESTUDIOS DE INFRAESTRUCTURA SOCIAL


ESTUDIOS DE INFRAESTRUCTURA SOCIAL
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
ESTUDIOS DE INFRAESTRUCTURA SOCIAL
ESTUDIOS DE INFRAESTRUCTURA SOCIAL

You might also like