Professional Documents
Culture Documents
Waterline
repair after it had its hull
pierced sufficiently enough
to let seawater enter its
water ballast tank.
32 MARCH 2013
pumped into the tanks. Nobody knew the vessel was fully loaded, dry-docking aged — Fig. 3.
that a submerged obstacle, most likely in was out of the question. The repairs The bilge keel and grounding bar had
the form of a broken pile, was hidden needed to be performed with the vessel to be trimmed back to allow for the in-
below the waterline, invisible to the offi- afloat. It was discussed with the owner stallation of the cofferdam and the insert
cers and crew of the vessel. While in- and class to sail to Curaçao and perform plate. The trimmed bilge keel and
creasing her draft through the increasing the repairs with the vessel at berth in the grounding bar were mechanically pro-
weight of the cargo, the submerged pil- clear waters of the sheltered Caracas Bay. filed to match the original form.
ing finally pierced its way through the Miami Diver’s engineering department
hull of the vessel, allowing the ingress of developed a detailed repair procedure Templating, Engineering,
seawater into the portside water ballast that was submitted and agreed to by the
wing tank. owner and class, suggesting a no condi- and Building the
tion once the repair was completed. Cofferdam
Damage Assessment
Attending the Vessel To allow the repair work to be per-
Despite the damage, the tanker left formed under dry conditions, a coffer-
Venezuela and sailed to Aruba in the With the arrival of the vessel in Cu- dam was engineered by Miami Diver.
Caribbean Sea, where an initial evalua- raçao, a team of divers, welders, and the To ensure that the cofferdam would
tion of the damage was performed by a welding engineer were deployed from be large enough to enclose the area of
local dive company. After the assess- Miami, Long Beach, and Curaçao to at- the deformed hull, divers laid out the
ment, the owner of the tanker contacted tend the vessel. The initial inspection area the cofferdam needed to cover and
the Miami Diver office in Curaçao. dive revealed an approximate 400- × 500- communicated the measurements to the
The damage proved to be severe (Fig. mm hole in the hull of the vessel and de- engineering department.
2), preventing the vessel from sailing to formed hull plating in the vicinity of the Since the damage was in the turn of
its destination. Class would only allow hull breach. In addition to the aforemen- the bilge, the transition between the flat
the vessel to continue the journey if the tioned damages, the bilge keel and bottom and sidewall of the ship, divers
hull breach was fixed permanently. Since grounding bar were also found to be dam- templated the contour of the area to be
WELDING JOURNAL 33
Fig. 3 — Schematic of the vessel showing where the hull was pierced and bilge keel damage.
34 MARCH 2013
Fig. 5 — Diver welder welding
a lifting lug to the hull.
WELDING JOURNAL 35
Fig. 6 — Grinding performed to prepare the joint for welding. Fig. 7 — Insert plate being installed.
36 MARCH 2013
Fig. 9 — Large and small inserts as
they appeared from the water side.
of the intersection between the web of peared that the ceramic was emerged in Reinstalling the Manhole
the frame and weld joint of the insert the seawater for too long, picking up
plate, weld access holes were removed moisture that could not be released CutOut
from the web member, sufficient in size through preheating.
to allow unrestricted access to the weld It was discussed with the owner and The weld joint of the insert plate for
joint to be welded and tested. surveyors to cut a 510- × 660-mm man- the manhole was prepared and welded
hole into the center of the insert plate, on ceramic backing. It was subject to vi-
Installing the New Shell backgouge the root pass from the insert sual and ultrasound inspection after com-
plate to remove all inclusions, and reweld
Plating the root from inside the cofferdam. The
pletion. The welds passed without re-
jectable indications — Fig. 9.
After preparation of the weld joint, manhole was welded on ceramic backing. All temporary removed frames were
the insert plate was pulled tight against Both classification societies DNV and reinstalled with weld sizes matching the
the outside of the shell plating with a con- RINA agreed to the proposal. original weld sizes.
sistent root opening of about 10 mm. The After completion of the weld between
plate was secured in place with weld fix- the insert plate and hull, the manhole was
cut in the center of the insert plate to gain
tures — Fig. 7. Prior to welding the in-
sert plate, the previously cropped and/or access to the root side of the original joint. Welding
removed frame members were rein- The root pass was removed by carbon
stalled and tack welded into place. The arc gouging, followed by cleaning the Underwater Wet Welding
preheat temperature of 80°C was con- joint by grinding and rewelding the root
trolled through heat-indicating crayons. with the SMAW process (Fig. 8) in the
overhead position. Underwater wet welding was only per-
formed to attach installation aids for the
Root Opening with cofferdam, which were removed after
Ceramic Backing Welding the Root from completion of the work.
Inside the Cofferdam All underwater wet welding was based
Ceramic Inclusion on AWS D3.6:1998 Class A welding pro-
After welding was completed, visual cedure qualifications (WPQ), employing
While welding the root, welders expe- and ultrasound inspection was per- the wet shielded metal arc welding
rienced a “popping” of the ceramic back- formed on the weld between the insert process with Hydroweld FS electrodes.
ing resulting in undesirable rejectable in- plate and hull plating. The weld did not All welds were executed as multilayer fil-
clusions in the root of the weld. It ap- reveal rejectable indications. let welds in T- and lap joints.
WELDING JOURNAL 37
Fig. 10 — Divers removing the
cofferdam.
Removing the
Cofferdam
After removal of the coffer-
dam (Fig. 10), previously welded
installation aids were removed
and any weld metal remaining on
the hull was ground flush.
Underwater magnetic particle
(MT) testing was performed on
the ship hull where installation
aids for the cofferdam were re-
moved.
Corrosion Protection
After welding was completed
and the welds passed nondestruc-
tive examination, corrosion pro-
tection in the form of Hycote 151,
an underwater, two-component,
polyamine-cured epoxy coating,
was applied over the welds, areas
adjacent to the welds, and areas
where the corrosion protection
had been removed or burned off
during welding. This assisted in
the protection and reduction of
metal wastage in those areas due
to immersion in saltwater by
providing a permanent anticorro-
sive protection. Preparation of the
coating of the internal paint
system was performed by the ves-
sel’s crew.◆
38 MARCH 2013