Professional Documents
Culture Documents
7 days
7 days
If no contradiction in writing
Engineer to make a letter to
within 7 days, it shall be
contradict
deemed to be an instruction of
the Engineer.
Engineer
____________________________________________________________________________________
Issuance of Letter of Intent Issuance of Defects liability
Certificate
Page 2 of 16
Contractor shall obtain and
provide to the Employer a
28 days
performance security and notify Performance Security to be
the engineer of doing so retained back to the Contractor
Procedures and Notices required Under FIDIC 1987
14 days
Engineer
____________________________________________________________________________________
Page 4 of 16
Procedures and Notices required Under FIDIC 1987
Engineer to determine an
addition to the Contract
with a copy to the Employer
Engineer to determine an
addition to the Contract Combination of risks causing loss or damage and
with a copy to the Employer both Contractor and Engineer is at fault
Proportional
responsibility of the
Contractor & Employer
Commencement Date
____________________________________________________________________________________
84 days
Page 6 of 16 Contractor shall provide the
insurance policy to the
employer and to notify the
engineer of doing so.
Procedures and Notices required Under FIDIC 1987
____________________________________________________________________________________
Page 7 of 16
Procedures and Notices required Under FIDIC 1987
84 days
28 days
Suspension affect part of the scope, this part can be Suspension affects the full project; this will
considered by the contractor as omitted and shall be entitle the contractor to termination of the
treated under clause 51 contract and shall be treated under clause
69.1, 69.2 & 69.3
Notice of Commencement
____________________________________________________________________________________
Page 8 of 16
Procedures and Notices required Under FIDIC 1987
28 days 28 days
____________________________________________________________________________________
Page 9 of 16
Procedures and Notices required Under FIDIC 1987
21 days Engineer
____________________________________________________________________________________
Page 10 of 16
Procedures and Notices required Under FIDIC 1987
Contractor
During Defects
Contractor to pay for the cost if in the Liability Period or
opinion of the Engineer, due to: within 14 days after
the use of materials, Plant or its expiration
workmanship not in accordance with
the Contract, or
where the Contractor is responsible for
the design of part of the Permanent To deliver the Works to the Employer
Works, any fault in such design, or Execute all work of amendment,
the neglect or failure on the part of the reconstruction and remedying
Contractor to comply with any defects, shrinkages or other faults
obligation, expressed or implied, on the
Contractor's part under the Contract.
Employer
____________________________________________________________________________________
Page 11 of 16
Procedures and Notices required Under FIDIC 1987
14 days
Engineer to value
variations
____________________________________________________________________________________
Page 12 of 16
Procedures and Notices required Under FIDIC 1987
28 days
28 days
Page 13 of 16
Procedures and Notices required Under FIDIC 1987
L.O.I
28 days
28 days
28 days of receipt of
the certified payment
____________________________________________________________________________________
Page 14 of 16
Procedures and Notices required Under FIDIC 1987
84 days
Defects liability
Contractor shall submit the period + 28 days
statement of completion
56 days
Performance security to be
returned back to the contractor
and the contractor should give a
written discharge
28 days
Page 15 of 16
Procedures and Notices required Under FIDIC 1987
84 days
70 days
____________________________________________________________________________________
Page 16 of 16