Here I will describe the Solution for BBH on MBB Project, this solution has two kind of

main Scenarios Relaxed and Ideal Backhaul.

Inside or Ideal Backhaul we have two subdivisions Centralized and Distributed Closud

BBU, We will show Centralized scenario to show the commson scenario according to

experience in the Project.


Centralized Cloud BBU

 A Cloud BB network supports a maximum of 2 second-level USUs, 12 first-level

USUs, and 60 BBUs.

 The length of a cable connecting a BBU to a first-level USU must not exceed 100

m.

 The length of a cable connecting a first-level USU to a second-level USU must not

exceed 90 m.

 The length of a cable connecting two second-level USUs must not exceed 100 m.

Distributed Cloud BBU

 A Cloud BB network supports a maximum of 1 second-level USU, 6 first-level

USUs, and 300 BBUs.

 The length of a fiber optic cable connecting a BBU to a first-level USU must not

exceed 10 km.
 The total length of the cables transmitting signals between two BBUs through

first- and second-level USUs must not exceed 20 km.

Main equipment:

BBU 3910

USU3910
IBC10

WDM equipment

In the following picture we can see the interconection from BBH to Remote Site, we will

have BBU and O&M in the BBH and the radio layer will be installed on Site:
In the folwloing picture we can show the complete scenario on the BBH, we had two

IBC10 cabinets and one NE68E cabinet for WDM and IP equipment:
Considerations for the deployment:

 Output a installation manual for BBH to standardize

 and agreed with customer.

 Output ATP format with customer approval.

 The LLD needs to include the interconnection between

 the equipment: OSN, BBUs, ODF.

 Include the IPPLAN for all the BBUs, OSN and X3.

 Include the RF planning.

 Include the site distribution per BBU to perform it the sites need to be mapped

trying to have the same TACor less possible distance to avoid excessive paging.

 Prepare script for each equipment.

 Train the people for installation and commissioning.

Conlcusion

With this solution we can cover many sites in a cluster, on site we only need to install the

power rectification, WDM equipment, RRU and Antenna, batteries (optional) we can

save space and money. The coordination

between all the sites into the BBH can be optimized and the user experience will be

improved avoying interference in the borders.