In other words, what are all the basic steps to create and implement a new work schedule rule
successfully?
Holiday Calendar
Holiday calendar comprises of list of paid holidays to be given to employees on festivals by the
company.
Go to SPRO --> Time Management --->Work Schedules --> Personnel SubArea Groupings
i.e. Suppose in Mumbai you have WS = GEN ( 10 to 6) and in Chennai you have WS = NORM ( 8 to
4)
Work Schedule
Daily Work Schedule is actually your office timings with breaks (paid /unpaid) i.e. Planned Working
Time which is then included
Go to SPRO --> Time Management --->Work Schedules -->Work Schedule Rules and Work
Schedules
You will maintain this work schedule in infotype 0007 - Planned Working Time of employee via
transaction code - PA30