VALORIZACION Nº 01

OBRA : CONSTRUCCIÓN DE AULA PRESUPUESTO BASE : 45,234.92


PROPIETARIO : UPAO PRESUPUESTO CONTRATADO : 48,500.00
EJECUTOR :
FECHA : PLAZO EJECUCION : 90 DIAS CALENDARIO
FORMULA :
PRESUPUESTO AVANCE
SALDO
ITEM DESCRIPCIÓN DE PARTIDA ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO TOTAL
UNID MET. P.U. P. TOTAL
% MET. VALOR. % MET. VALOR. % MET. VALOR. % MET. VALOR.

01.00.00 CONSTRUCCION DE PISOS


01.01.00 cortes y rellenos
cortes de terreno M3 1,800.00 10.00 18,000.00 1,800.00 18,000.00 1,800.00 18000.00 - -
01.02.00 relleno con hormigon M3 600.00 50.00 30,000.00 150.00 7,500.00 150.00 7500.00 450.00 22,500.00
relleno con afirmado M3 1,200.00 45.00 54,000.00 100.00 4,500.00 100.00 4500.00 1,100.00 49,500.00
02.00.00 ADOQUINADO - 0.00 - -
02.01.00 relleno con arena gruesa M3 600.00 55.00 33,000.00 50.00 2,750.00 50.00 2750.00 550.00 30,250.00
02.02.00 soministro de aduquin M2 6,000.00 45.00 270,000.00 2,000.00 90,000.00 2,000.00 90000.00 4,000.00 180,000.00
02.02.01 colocacion de adoquin M2 600.00 25.00 15,000.00 250.00 6,250.00 250.00 6250.00 350.00 8,750.00
02.02.02 ELININACION MATERIAL EXEDENTE - 0.00 - -
02.03.00 elininacion material exedente M3 2,250.00 15.00 33,750.00 1,000.00 15,000.00 1,000.00 15000.00 1,250.00 18,750.00
03.00.00 limpieza general M2 6,000.00 1.00 6,000.00 2,500.00 2,500.00 2,500.00 2500.00 3,500.00 3,500.00
COSTO DIRECTO S/. 459,750.00 146,500.00
GASTOS GENERALES FIJOS (10%) S/. 45,975.00 S/. 14,650.00
GASTOS GENERALES VARIABLES (5%) S/. 22,987.50 S/. 7,325.00
UTILIDAD (10%) S/. 45,975.00 S/. 14,650.00
SUB-TOTAL S/. 574,687.50 183,125.00
IGV 18% 103443.75000 32,962.50000
TOTAL PRESUPUETO S/. 678,131.25 S/. 216,087.50

Página 1
OBRA : CONSTRUCCIÓN DE AULA
PROPIETARIO : UPAO
EJECUTOR :
FECHA :
FORMULA :
PRESUPUESTO
ITEM DESCRIPCIÓN DE PARTIDA
UNID MET. P.U. P. TOTAL

01.00.00 CONSTRUCCION DE PISOS


01.01.00 cortes y rellenos
cortes de terreno M3 1,800.00 10.00 18,000.00
01.02.00 relleno con hormigon M3 600.00 50.00 30,000.00
relleno con afirmado M3 1,200.00 45.00 54,000.00
02.00.00 ADOQUINADO
02.01.00 relleno con arena gruesa M3 600.00 55.00 33,000.00
02.02.00 soministro de aduquin M2 6,000.00 45.00 270,000.00
02.02.01 colocacion de adoquin M2 600.00 25.00 15,000.00
02.02.02 ELININACION MATERIAL EXEDENTE
02.03.00 elininacion material exedente M3 2,250.00 15.00 33,750.00
03.00.00 limpieza general M2 6,000.00 1.00 6,000.00
COSTO DIRECTO S/. 459,750.00
GASTOS GENERALES FIJOS (10%) S/. 45,975.00
GASTOS GENERALES VARIABLES (5%) S/. 22,987.50
UTILIDAD (10%) S/. 45,975.00
SUB-TOTAL S/. 574,687.50
IGV 18% 103443.75000
TOTAL PRESUPUETO S/. 678,131.25
PRESUPUESTO BASE
PRESUPUESTO CONTRATADO

PLAZO EJECUCION

AVANCE
ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO TOTAL
% MET. VALOR. % MET. VALOR. % MET.

1,800.00 18000.00 - - 1,800.00


150.00 7500.00 250.00 12,500.00 400.00
100.00 4500.00 600.00 27,000.00 700.00
0.00 - -
50.00 2750.00 300.00 16,500.00 350.00
2,000.00 90000.00 3,000.00 135,000.00 5,000.00
250.00 6250.00 200.00 5,000.00 450.00
0.00 - -
1,000.00 15000.00 500.00 7,500.00 1,500.00
2,500.00 2500.00 2,000.00 2,000.00 4,500.00
205,500.00
S/. 20,550.00
S/. 10,275.00
S/. 20,550.00
256,875.00
46,237.50000
S/. 303,112.50

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
: 45,234.92
: 48,500.00

: 90 DIAS CALENDARIO

SALDO
ULADO TOTAL
VALOR. % MET. VALOR.

18000.00 - -
20000.00 200.00 10,000.00
31500.00 500.00 22,500.00
0.00 - -
19250.00 250.00 13,750.00
225000.00 1,000.00 45,000.00
11250.00 150.00 3,750.00
0.00 - -
22500.00 750.00 11,250.00
4500.00 1,500.00 1,500.00
-
-

-
SIMBOLO ELEMENTO

Mano de obra
cementoportaltipo1
bloque y ladrillo
madera nacional para econfrado y carpinter
agregado grueso
acero de construccion corrugado
maquinaria y equipo importado
herramienta manual
maquinaria y equipo nacional
indice general de precios a consumidor

R= V(K-1)
R= 0

SIMBOLO ELEMENTO

Mano de obra
cementoportaltipo1
bloque y ladrillo
madera nacional para econfrado y carpinter
agregado grueso
acero de construccion corrugado
maquinaria y equipo importado
herramienta manual
maquinaria y equipo nacional
indice general de precios a consumidor

FR=factor de relacion
FR=(monto del contrato/valor referencial)
Vp=valorizacion preriodo

R1=Vp1(K1-1)

R2=Vp2(K2-1)
TABLA N°1
IU COEFC INCIDENCIA% IU BASE novi-2017 IU abril-2017 COEFIC

0.47 0.222 580.9 582.520 0.223


0.21 0.477 465.71 476.040 0.488
0.17 624.31 626.790
0.43 719.16 726.590
0.05 0.078 449.54 449.530 0.078
0.03 469.92 406.470
0.49 0.051 293.18 295.180 0.051
0.37 298.08 304.110
0.48 363.3 365.550
0.39 0.172 442.48 446.140 0.173
K1 1.012968

K1-1 0.012968

TABLA N°2
IU COEFC INCIDENCIA% IU BASE novi-2017 IU mayo-2017 COEFIC

0.47 0.222 580.9 582.52 0.223


0.21 0.477 465.71 476.04 0.488
0.17 624.31
0.43 719.16
0.05 0.078 449.54 450.08 0.078
0.03 469.92
0.49 0.051 293.18 294.12 0.051
0.37 298.08
0.48 363.3
0.39 0.172 442.48 445.52 0.173
K2 1.012638

K2-1 0.012638
FR= 0.9591801
Vp1= 175649.856
Vp2= 246389.388

R1= 2277.90045
R2= 3113.97998