SUMMARY OF BILL OF QUANTITY AND SPECIFICATION

FOR GIMBI CAMPUS MASSONRY FENCE

1 Excavation and earth work................ Birr


2 Concrete work............................... Birr
3 Masonary work.............................Birr
4 Metal Work…………………………… Birr
5 Finishing..................................... Birr
6 Painting...................................... Birr
7 Electrical Instalation...................... Birr

Tota..... Birr
Birr
Grand Total Birr

Prepared By: Oliyad Ch.


Sign ______ With regards
SUMMARY OF BILL OF QUANTITY AND ENGINEERING

ESTIMATIONFOR GIMBI MASSONRY FENCE

1 Excavation and earth work................351545.45 Birr


2 Concrete work...............................
1573782.23 Birr
3 Masonary work.............................2496560 Birr
4 Metal Work…………………………… 1867764.61 Birr
5 Finishing.....................................
493096.36 Birr
6 Painting......................................
281594.88 Birr
7 Electrical Instalation......................716500Birr

Tota.....7780843.53Birr
1167126.53 Birr
Grand Total With8947970.0595
Vat Birr

Prepared By: Oliyad Ch.


Sign ______ With regards
SUMMARY OF BILL OF QUANTITY AND SPECIFICATION

FOR GIMBI CAMPUS SLAB CULVERT

1 Excavation and earth work................ Birr


2 Concrete work............................... Birr
3 Masonary work.............................Birr
4 Metal Work…………………………… Birr
5 Finishing..................................... Birr

Tota..... Birr
Birr
Grand Total Birr

Prepared By: Oliyad Ch.


Sign ______ With regards
SUMMARY OF BILL OF QUANTITY AND ENGINEERING ESTIMATION

FOR GIMBI CAMPUS SLAB CULVERT

1 Excavation and earth work................


32130.9 Birr
2 Concrete work...............................
239136.18 Birr
3 Masonary work.............................
194880 Birr
4 Metal Work…………………………… 2184 Birr
5 Finishing.....................................
17295 Birr

Tota.....485626.08 Birr
72843.91 Birr
Grand Total 558469.99 Birr

Prepared By: Oliyad Ch.


Sign ______ With regards
BOQ AND SPECIFICATION FOR GIMBIU NIVERSITY MASSONRY

Area=211103SqM Perimeter=1981.03
m (Front L=495.26) and (The other side L=1485.77)
Uni
Quantity
Description t
No. A-Sub structure
1.EXCAVATION
Clear & EARTH
the site to remove WORK
the topsoil
to an average depth of 20cm.The site
clearance shall include cutting &
uprooting of trees on the site and
1.1 also
Trench demolishing
anyexcavation for works.
Masonry wall m² 4952.5
in ordinary soil for a depth not
exceeding 1000mm below gound
1.2 level.
Pit excavation for isolated footing in m 2179.13
3

ordinary soil for a depth not


exceeding 1400mm below ground
1.3 level
Backfill with non expansive selected m 1042.65
3

material from site well rolled and


compacted in layers not exceeding
1.4 200mm thick
a) Around foundation m3 695.1
b) Around massonary wall m3 990.5
Load and cart away surplus
excavated material and the
demolished material out of the
compound upto 6km by the
1.5 guidance of site supervisor. m3 1536.18
TOTAL CARRIED TO SUMMARY
2.CONCRETE WORK
50mm lean concrete quality c-5,
with minimum cement content of
2.1 150 kg/m3, of concrete
a) Under trench masonary m² 1188.618
b) Under footing pad m² 400.51
To 10cm thick Mass concrete quality
c-25 for copping at the top of
2.2 massonry and columns M3 140.706
Reinforced concrete quality c-
25,360kg of cement/m3 filled in to
form work and vibrated around rod
reinforcement (Formwork and
2.3 reinforcement measured separately)
a) To footing m3 49.65
b) To foundation column m3 49.65
c) To Elevation
Provide, column
cut and fix in position sawn m 139.02
3

sctructural wood or steel formwork


2.4 which ever is apropriate;
a) To footing m² 264.80
b) To foundation column m² 529.6
c) To Elevation column m² 1482.88
d) To 10cm thick copping m² 594.3
Reinforced steel bars according to
the structural drawing, price include
cutting,bending,pacing in position
and tying with soft iron wire of
2.5 diameter 1.5mm
a) Diameter 8mm deformed bar kg 3922.35
b) Diameter 10mm deformed bar kg 3267.63
C) Diameter 12mm deformed bar kg 15024.09
TOTAL CARRIED TO SUMMARY--------
3)
500MASONRY WORK or equivalent
mm thick basaltic
type stone masonry bedded in
cement mortar(1:3) mix below
3.1 ground
500 mmsurface.
thick basaltic or equivalent m3 990.5
type stone masonry bedded in
cement mortar(1:3) mix above
3.2 ground surface. m3 1506.06
TOTAL CARRIED TO SUMMARY----------
4.METALand
Supply, fabricate WORKS
mount RHS
50x30x3mm of horizontal member of
metal frame with vertical mesh of
angle iron metal 50X50X4mm for
(front side of fence) and the vertical
mesh of RHS 40x20x2.5mm ( for
other side part) with metal frame
according to arch. drawing.Price
shall include one coat of antirust
and two coats of synthetic enamel
painting and price also include all
other necessary accessories to
4.1 complete the work.
RHS for vertical mesh and for
horizontal member
a) 50x30x3mm Kg 13074.8
b) 40x20x2.5mm Kg 24128.58
c) Aluminium decoration of "xor"
according to it indicated on
architectural drawing over each RHS
with average length greater than
L=15cm and price shall include all
other necessary accessories to
complete the work. pcs 7429
with horizontal member of metal
frame according to architectural
drawing of maximum length=196cm
and the minimum length L=161cm
with average length of 1785mm and
price shall include all other
necessary accessories to complete
the work. ml 4853.45
TOTAL CARRIED TO SUMMARY-----------------------
5. FINISHING
Apply three coats of plastering in
cement mortar (1:3)Price shall
include exposed surface of copping
& column,pre-cleaning and
5.1 preparation of the surface.
a)
b) to exposed
three coats columns
of cementand copping
sand m² 3969.018
rendering to exposed elevation
columns m² 2780.4
Apply pointing to exposed massonry
5.2 wall both internal and external faces. m² 4754.472
TOTAL CARRIED TO SUMMARY-----------------------
6 PAINTING
Apply three coats of plastic emulsion
paint.Price shall include pre-cleaning
6.1 & preparation of the surface.
a)To exposed column m² 1482.88
b) To copping m² 1584.8
c) To exposed of massonry wall of
both internal and external parts. m² 4754.4
TOTAL CARRIED TO SUMMARY-----------------------
Sum 15%
VAT Grand Total With
Vat
BOQ AND SPECIFICATION FOR GIMBI CAMPUS SLAB CULVERT

Item
Unit Quantity
Description
No.
A-Sub structure
1.EXCAVATION
Clear the site to remove & EARTH
the topsoil WORK
to an average
depth of 20cm.The site clearance shall include
cutting & uprooting of trees on the site and also
1.1 any demolishing works. m² 50.58
Bulk excavation in ordinary soil to a depth of
1.2 1500 mm from reduced level including channel m3 92.4
excavation.
Ditto but exceeding 1500mm not exceeding
3000mm m3 92.4
Ditto but exceeding 3000mm not exceeding
4000mm m3 36.96
Fill around massonry wall and necessary areas to
match with the culvert slab with imported
selected materials from out side well rolled and
compacted in layers not exceeding 200 mm thick. m3 195
Fill hard core materials under footing well
rolled and compacted in layers not exceeding 200 m3 10.8
mm thick.
Load and cart away surplus excavated material
and the demolished material out of the compound
1.5 upto 6km by the guidance of site supervisor. m3 221.76
TOTAL CARRIED TO SUMMARY
2.CONCRETE WORK
50mm lean concrete quality c-5, with minimum
2.1 cement content of 150 kg/m3, of concrete
a) Under footing pad m² 33.72
b) Under beams m2 6.744
Reinforced concrete quality c-25,360kg of
cement/m3 filled in to form work and vibrated
around rod reinforcement. price include
formwork and all other necessary accessories to
2.3 complete the work.
a) To footing m3 10.8
b) To beams m3 3.64
c) To 4ocm thick culvert slab m3 14.4
d) To concrete post m3 0.54
Reinforced steel bars according to the structural
drawing, price include cutting,bending,pacing in
position and tying with soft iron wire of diameter
2.5 1.5mm
a) Diameter 8mm deformed bar kg 12.44
b) Diameter 12mm deformed bar kg 456.11
c) Diameter 16mm deformed bar kg 1306.98
d) Diameter 24mm deformed bar kg 3175.704
TOTAL CARRIED TO SUMMARY--------
3) MASONRY WORK
Basaltic or equivalent type stone masonry bedded
in cement mortar(1:3) mix. price also include all
3.1 other necessary accessories to complete the m3 162.4
work. TOTAL CARRIED TO SUMMARY----------
4.METAL WORKS
Φ 50mm,2.5mm CHS thick pipe hand rail fixed on
concrete post and all other necessary accessories
for completing the work. All according drawing
and shall be approved by the engineer. lm 52

TOTAL CARRIED TO SUMMARY-----------------------


Apply three coats5.ofFINISHING
plastering in cement mortar
(1:3)Price shall include exposed surface of
copping & column,pre-cleaning and preparation
5.1 of the surface.
a) concrete post m² 25
50 mm thick rough finished cement screed(1:3)
5.2 finish Price include glass. All as per engineers m² 42
instruction.
Dim 100 pvc every 3m ml 90
Apply pointing to exposed stone massonry wall
5.3 both internal and external faces. m² 118
TOTAL CARRIED TO SUMMARY-----------------------
Total Sum
15% VAT
Grand Total With Vat
BOQ AND SPECIFICATION FOR GIMBI UNIVERSITY

SLAB CULVERT
Item
Unit Quantity
Description
No.
A-Sub structure
1.EXCAVATION
Clear the site to remove & EARTH
the topsoil WORK
to an average
depth of 20cm.The site clearance shall include
cutting & uprooting of trees on the site and also
1.1 any demolishing works. m² 50.58
Bulk excavation in ordinary soil to a depth of
1.2 1500 mm from reduced level including channel m3 92.4
excavation.
Ditto but exceeding 1500mm not exceeding m3 92.4
3000mm
Ditto but exceeding 3000mm not exceeding m3 92.4
4000mm
Fill around massonry wall and necessary areas to
match with the culvert slab with imported
selected materials from out side well rolled and
compacted in layers not exceeding 200 mm thick. m3 92.4
Fill hard core materials under footing well
rolled and compacted in layers not exceeding 200 m3 92.4
mm thick.
Load and cart away surplus excavated material
and the demolished material out of the compound
1.5 upto 6km by the guidance of site supervisor. m3 277.2
TOTAL CARRIED TO SUMMARY
2.CONCRETE WORK
50mm lean concrete quality c-5, with minimum
2.1 cement content of 150 kg/m3, of concrete
a) Under footing pad m² 33.72
b) Under beams m2 6.744
Reinforced concrete quality c-25,360kg of
cement/m3 filled in to form work and vibrated
around rod reinforcement. price include
formwork and all other necessary accessories to
2.3 complete the work.
a) To footing m3 10.8
b) To beams m3 3.64
c) To 4ocm thick culvert slab m3 14.4
d) To concrete post m3 0.54
Reinforced steel bars according to the structural
drawing, price include cutting,bending,pacing in
position and tying with soft iron wire of diameter
2.5 1.5mm
a) Diameter 8mm deformed bar kg 12.44
b) Diameter 12mm deformed bar kg 456.11
c) Diameter 16mm deformed bar kg 1306.98
d) Diameter 24mm deformed bar kg 3175.704
TOTAL CARRIED TO SUMMARY--------
3) MASONRY WORK
Basaltic or equivalent type stone masonry bedded
in cement mortar(1:3) mix. price also include all
3.1 other necessary accessories to complete the m3 162.4
work. TOTAL CARRIED TO SUMMARY----------
4.METAL WORKS
Φ 50mm,2.5mm CHS thick pipe hand rail fixed on
concrete post and all other necessary accessories
for completing the work. All according drawing
and shall be approved by the engineer. lm 52
TOTAL CARRIED TO SUMMARY-----------------------
Apply three coats5.ofFINISHING
plastering in cement mortar
(1:3)Price shall include exposed surface of
copping & column,pre-cleaning and preparation
5.1 of the surface.
a) To exposed part of concrete post and beam m² 25
50 mm thick rough finished cement screed(1:3)
5.2 finish Price include glass. All as per engineers m² 42
instruction.
Dim 100 pvc every 3m ml 90
Apply pointing to exposed stone massonry wall
5.3 both internal and external faces. m² 118
TOTAL CARRIED TO SUMMARY-----------------------
Total Sum
15% VAT
Grand Total With Vat
BOQ AND ENGINEERING ESTIMATION FOR GIMBI MASSONRY FENCE
Area=211103SqM Perimeter=1981.03
(Front L=495.26) and (The other side L=1485.77)
Item
Unit Quantity
Description
No.
A-Sub structure

1.EXCAVATION & EARTH WORK


Clear the site to remove the topsoil to an average
depth of 20cm.The site clearance shall include
cutting & uprooting of trees on the site and also
1.1 any demolishing
Trench excavation works.
for Masonry wall in ordinary m² 4952.5
soil for a depth not exceeding 1000mm below
1.2 gound level. for isolated footing in ordinary soil
Pit excavation m3 2179.13
for a depthwith
Backfill not exceeding 1000mm
non expansive below material
selected ground
1.3 level
from site well rolled and compacted in layers not m3 1042.65
1.4 exceeding 200mm thick
a) Around foundation m3 695.1
b) Around massonary wall m3 990.5
Load and cart away surplus excavated material
and the demolished material out of the compound
1.5 upto 6km by the guidance of site supervisor. m3 1536.18
TOTAL CARRIED TO SUMMARY
2.CONCRETE WORK
50mm lean concrete quality c-5, with minimum
2.01 Reinforced
cement contentconcrete quality
of 150 kg/m3, c-25,360kg of
of concrete
cement/m3 filled in to form work and vibrated
a) under Footing
around pad
rod reinforcement (Formwork and M
2
1188.618
2.02 B) Under trench
reinforcement masonary
measured separately) M 2
400.51
Reinforced concrete quality c-25,360kg of
cement/m3 filled in to form work and vibrated
around rod reinforcement (Formwork and
2.3 reinforcement measured separately)
a) To footing m3 49.65
b) To foundation column m3 49.65
c) To Elevation column m3 139.02
Provide, cut and fix in position sawn sctructural
2.4 wood or steel formwork which ever is apropriate;
a) To footing m² 264.80
b) To foundation column m² 529.6
c) To Elevation column m² 1482.88
d) To copping
Reinforced steel bars according to the structural m² 594.3
drawing, price include cutting,bending,pacing in
position and tying with soft iron wire of diameter
2.5 1.5mm
a) Diameter 8mm deformed bar kg 3922.35
b) Diameter 10mm deformed bar kg 3267.63
C) Diameter 12mm deformed bar kg 15024.09
TOTAL CARRIED TO SUMMARY--------
3)
500MASONRY WORK or equivalent type stone
mm thick basaltic
masonry bedded in cement mortar(1:3) mix
3.1 below
500 mm ground
thick surface.
basaltic or equivalent type stone m3 990.5
masonry bedded in cement mortar(1:3) mix
3.2 above ground surface. m3 1506.06
TOTAL CARRIED TO SUMMARY----------
4.METAL WORKS
horizontal member of metal frame with vertical
mesh of angle iron metal 50X50X4mm for (front
side of fence) and the vertical mesh of RHS
40x20x2.5mm ( for other side part) with metal
frame according to arch. drawing.Price shall
include one coat of antirust and two coats of
synthetic enamel painting and price also include
all other necessary accessories to complete the
4.1 work.
RHS for vertical mesh and for horizontal
member
a) 50x30x3mm Kg 13074.798

b) 40x20x2.5mm Kg 24128.58
c) Aluminium decoration of "xor" according to it
indicated on architectural drawing over each
RHS with average length greater than L=15cm
and price shall include all other necessary
accessories to complete the work. pcs 7429
d) angle iron metal 50x50x4mm fixed with
horizontal member of metal frame according to
architectural drawing of maximum
length=196cm and the minimum length
L=161cm with average length of 1785mm and
price shall include all other necessary
accessories to complete the work. ml 4853.45
TOTAL CARRIED TO SUMMARY-----------------------

Apply three coats5.ofFINISHING


plastering in cement mortar
(1:3)Price shall include exposed surface of
copping & column,pre-cleaning and preparation
5.1 of the surface.
a) to exposed columns and copping m² 3969.018
b) three coats of cement sand rendering to
exposed elevation columns m² 2780.4
Apply pointing to exposed massonry wall both
5.2 internal and external faces. m² 4754.472
TOTAL CARRIED TO SUMMARY-----------------------
6 PAINTING
Apply three coats of plastic emulsion paint.Price
shall include pre-cleaning & preparation of the
6.1 surface.
a)To exposed column m² 1482.88
b) To copping m² 1584.8
c) To exposed of massonry wall both internal and
external parts. m² 4754.4
TOTAL CARRIED TO SUMMARY-----------------------
Total Sum
15% VAT
Grand Total With Vat
RSITY MASSONRY FENCE

e L=1485.77)
Unit
Total
Rate
Amount

RY
-------
--------
----------

----------

----------Total
15%
and Total With
PUS SLAB CULVERT

Unit Rate Total


Amount
-
--

Total Sum
15% VAT
nd Total With Vat
BI UNIVERSITY

Unit Rate Total


Amount

252.9
5
3696
40
41 3788.4
42 3880.8

3973.2
43
4065.6
44

12474
45
32130.9

70 2360.4
70 472.08

3000 32400
3000 10920
3000 43200
3000 1620
30 373.2
30 13683.3
30 39209.28
30 95271.12
- 239136.18
194880
1200
-- 194880

2184
42
2184

31 775
2520
60
90 8100
5900
50
17295
Total Sum 485626.08
15% VAT 72843.912
nd Total With Vat 558469.992
I MASSONRY FENCE

Unit Rate Total


Amount

39620
8
108956.5
50

57345.75
55

42 29194.2
40 39620

76809
50
351545.45

70 83203.26
70 28035.7

2000 99300
2000 99300
2200 305844

72 19065.6
72 38131.2
72 106767.36
72 42789.6

30 117670.5
33 107831.856
35 525843.15
- 1573782.23
990500
1000
1506060
1000
-- 2496560

36 470692.728

36 868628.88

334305

45

194138

40
1867764.61

41 162729.738
130678.8
47
199687.824
42
493096.362
36 53383.68
36 57052.8
171158.4
36
281594.88
Total Sum 7064343.53
15% VAT 1059651.53
nd Total With Vat 8123995.05
BILL Nº 1

MASSONRY FENCE
BILL Nº 2

SLAB CULVERT
BOQ AND SPECIFICATION FOR MASSONRY FENCE AND SLAB

Location : GIMBI CAMPUS

BILL No1 MASSONRY FENCE…………………………………..

BILL No2 SLAB CULVERT……………………………………….

TOTAL……………………..

15 % VAT……………..…

GRAND TOTAL WITH VAT 15%..........


NCE AND SLAB CULVERT

BIRR

BIRR

BIRR

BIRR

BIRR
BOQ AND ENGINEERING ESTIMATION FOR MASSONRY

Location : GIMBI CAMPUS

BILL No1 MASSONRY FENCE…………………………………..

BILL No2 SLAB CULVERT……………………………………….

TOTAL……………………..

15 % VAT……………..…

GRAND TOTAL WITH VAT 15%..........


R MASSONRY FENCE AND SLAB CUL

BIRR 7780843.53Birr

BIRR 485626.08 Birr

BIRR 8266469.61 Birr

BIRR 1239970.4415 Birr

BIRR 9,506,440.05Birr