WORK METHOD STATEMENT

WMS Rev.No

CONSTRUCTION OF
G-FORCE POST and
ACTIVITY: COMPANY NAME xxxxx DATE 13-06-2018
BEAM PILE
FOUNDATION

DESCRIPTION OF G-FORCE POST & BEAM PILE FOUNDATION (Pilling, Steel Casing, PROJECT SITE/ LOCATION
xxxxx
WORK Reinforcement steel, Form works, Scaffolding, Concrete pouring,
Concrete Repairing, Grouting & Steel Structure )
CONTACT NO. xxxxx

JHA REF. NO.


PERSON COMPLETING THIS STATEMENT: xxx
JHA REV. NO.

Task Step
Tool and Equipment Required Description of Work (In detail)
(Activity)

1. Start-up checks 1. Surveying Equipment’s 1. Ground conditions to be assessed by the soil investigation reports 1. Refer to the procedures BNPP-HSE-
prior to work 2. Clearance from the relevant authorities to be taken P28.
3. Preliminary Survey to be carried out to plot the existing ground profile 2. Before start the activity conduct TBM
4. Necessary Road signage’s & safety signage’s & barricading to be 3. Barricading the area and visible
done signed.
4. First Aider to be available.
5. Methods to be available and followed.

Page 1 of 7
2. Pile case driving 1. Drilling Rig 1. The pile casing then will be installed and driven at the center of the
& drilling by using
vibro hammer. 2. Steel Casing reference peg.
3. Crawler Crane (45, 55 & 2. The supervisor will check the location of the setting from the reference
65 ton) peg.
4. Vibro-Hammer
3. At first, we will drill and drive a pile casing.
5. Hiab
4. If the casing location is within the tolerable off-set limit from any direction,
then it will be driven drown by means of vibro-hammer. 5. Verticality of the
casing is being checked always during driving of the casing.
2.a. Drilling of 1. Drilling rig The steel casing shall be rotated into the ground by drilling rig itself
boreholes
2.Crawler Crane (45, 55 & 65 and shall be installed to soil layer of the designed depth.
ton)
3.Power pack After installed of the temporary casing, the borehole will be drilled
using appropriate drilling tools. The borehole will be drilled down to
its final level by means of bucket auger
3. Excavation & 1.Backhoe loader 1. The area to be excavated shall be properly mark and clear before
Backfilling 2.JCB starting the work
3.Excavator 2. The depth of excavated shall be periodically checked by a surveyor to
avoid over excavation. The bank of excavated area shall be slope 30
degrees and shall be maintained to avoid collapse of bank into the
excavated area.
3. All excavated materials shall be kept minimum of 1.0 meter from the
edge of excavation or shall be shock piled to the area designated by the
engineer
4. For all excavation activities, adequate safety barriers, sign boards,
advance warning signs would be used.

Page 2 of 7
4.Post Installation for 1. Mobile Crane 1. Column Anchor Bolts will be installed using a steel frame work on 1. Follow KEPCO Procedure P-22 for steel
steel Structure the exact locations as per the drawings. erection.
2. Boom Lift
3. Man Basket 2. Column base plates shall be set at the specified elevations within
the specified tolerance
4. Grinder machine
3. Fabricated columns will be kept in position by crane & fixed with
5. TC bolt tightening Machine
nuts to the anchor bolts.
6. Hand and power tools
4. Columns shall be aligned vertically before the erection of
connection beams.
5. Beams, Roof Trusses will be lifted by mobile crane fixed to columns
with nuts and bolts.
6. Turnbuckles & bracings will be installed, where mentioned in the
shop drawings.
7. RSH sections for cladding frame work will be installed on the
concrete beam with set anchors. Purlins for the same will be bolted
to RHS sections.
8. RHS columns, Purlins will be lifted up manually with wire ropes &
fixed to the roof beams/trusses with nuts & bolts.
9. Maximum manual lifting weight shall be 25 kg.s.
10. Temporary bolts, if used for erection of beams shall be identified
and replaced with new bolts after erection.
11. Connections shall be as indicated on design drawings or shop
drawings.
12. Unless otherwise shown on design drawings, field connections shall
be made with high strength bolts / TC bolts of size and type
indicated and specified.
13. Field welded connections will be permitted only where indicated on
drawings or where authorized by KEPCO. Field welding shall
conform to paragraph 7.6 .
14. Section III. A of AISC “ Quality Criteria and Inspection Standards.

Page 3 of 7
5.Installation Rebar
1. The surface of the reinforcing steel bar to be placed shall be free from
loss mortar, dirt, mud, oil, ice, snow or other nonmetallic coatings that
1.moblie crane
adversely affect bonding capacity
2.tower crane
3.Hiab 2. Reinforcing steel bars shall be securely tied with No.16 or heavier
gauge tie wires and shall be held in position by approved supports
3. All size of reinforcing steel bars shall be in accordance to Drawing.

6.. FORMWORK – 1. mobile crane/crawler 1. Form design shall include considerations of the following
fabrication, installation &
de shuttering crane/tower crane/Hiab Truck i. Rate and method of placing concrete
etc.
ii. Density of concrete
iii. Construction loads including vertical, horizontal and
impact loads
2. Forms shall be readily removable, without the injury of concrete.
Forms shall be wood, metal, structural hardboard or other suitable
material that will produce the required surface finish

Page 4 of 7
7. PLACING OF 1. Concrete Pump Car 1. Placing equipment shall be of adequate size and capacity to handle the concrete
CONCRETE & Grout
Lean concrete, Screed 2. Conveyors mixes furnished. Conveying and placing shall be in accordance with the ACI
concrete, Mud mat, 3. Chutes regulations.
2. Before depositing concrete, all placing equipment shall be cleaned. All compacted
soil, rock or concrete surfaces to receive concrete shall be thoroughly moistened
before placement
3. The free fall of concrete shall be limited to approximately 6ft. (1892mm). The
horizontal flow within the mass from the point of deposition shall be limited to
approximately 5ft.(1524mm)
4. The concrete placing shall be completed within 1 ½ hours after introduction of
the mixing water to the cement and aggregates
5. Concrete shall be deposited in layers not deeper than 24 in. (610mm), the step
method of placement as described in Section 5.6 in ACI 304R shall be followed
for mass concreting in order to minimize the occurrence of cold joints
6. Concrete shall be deposited at or near its final placement position and shall not
be caused to flow such that the lateral movement will permit or cause segregation
of the coarse aggregate, mortar or water from the concrete mass.
7. Concrete and the exposed surface of fresh concrete shall be protected from rain
and snow during and after placement

8.Repair of concrete s 1) Imperfections in formed concrete shall be repaired as soon as practicable after removal
urface 1. Grinders
of forms, imperfections in sound concrete shall be removed by chipping with
2. Pneumatic Chisel heads
perpendicular chip edges.
3. Power Tools
2) No feather edges shall be permitted
4. Drilling & Grinding
3) Application of the adhesive shall conform to the manufacturer’s written instruction.
Machine
After repair, all filling shall be bonded tightly to the surface of the holes.
5. Leak injection machine 4) Repair, except for tie rod holes shall be cured in accordance to curing section
mentioned above

Page 5 of 7
9.Erection &
Dismantling Of  Mobile Crane 1. Mobilization of materials shall be done with due safety and care 1. Refer to the procedures BNPP-HSE-
2. Remind all workers through TBM to use only the right tools for the P21 and BNPP-HSE-P25, P39.
Scaffolding  Boom Truck
job. 2. The workers shall be physically &
 Hand Tools
3. Examine each tools for any signs of damage and removed psychologically fit.
 Spirit level. immediately from service if found defective. 3. Closely monitored the supervisor by
4. Keep tools in good condition and store it properly at designated qualified experienced and trained.
storage room or tool box after usage
5. Timber shall be placed at the base to support the scaffold
6. The standards, and the entire cup lock system shall be set up as
per approved drawings and by authorized personnel.
7. Bracing tubes, universal clamps other such support mechanisms
shall be placed at designated areas for proper supports
8. To provide protection to the workers guard rails shall be provided
at appropriate heights and also toe board shall be installed to
prevent the falling of objects from scaffolding heights
9. Lifting area to be covered and appropriate signages to be
posted.Tag line to be placed at corners of loads,
10. Ensure load is balance, stable and secure during lifting.
11. All working platforms to be erected by competent personnel as
close as possible to reinforcement bar locations to prevent steel
fixers over reaching
12. Remove all obstruction in pathways.
13. Tools and materials to be secured with tool tie or place din
secured storage container.
14. Competent supervision and tool box meeting
15. PPE (Safety helmet, Coverall, Safety glass, Safety shoes, Hand
gloves)

Page 6 of 7
10. Welding, Gas 1. Welding Machine 1. PPE (Safety helmet, Coverall, High visibility vest, Safety glass, Safety 1. Fire watcher must be present on
cutting, grinding 2. Grinding Machine shoes, Hand gloves, Full face shield ,Apron) site.
operations 2. Flammable materials must be removed from areas where pip cutting 2. Fire Extinguishers must be kept near
3. Diesel Generator
works is to be undertaken. the hot work area and near to the
1. Oxygen Acetylene gas
3. Flashback arrestors and flash guard to be fitted to cylinder. equipment.
2. Cylinder Trolley
3. The work area shall be Properly
4. Hand tools barricaded and sign board must be
provided on which is shown “HOT
WORK IN PROGRESS”

Prepared by: Approved by: KEPCO


Check by: HSJV Discipline Dept.
Discipline Dept.

Page 7 of 7