Professional Documents
Culture Documents
Managing Mining
Project
1 Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Major Thermal Coal Importing countries
2 Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Managing Integration
• The integration effort also involves making trade-offs among competing objectives and alternatives.
• The project management processes are usually presented as discrete components with well-defined
interfaces while, in practice, they overlap and interact in ways that cannot be completely detailed in any
guide.
• By managing actual changes when they occur, scope management ensures that changes are
integrated with other control processes and support the timely delivery of deliverables
identified in a project scope.
The size of the project dynamically changes when any one of the three dimensions of cost, quality and time is
changed. The Project scope is the set of constraints to contain this size.
• Managing project time and schedule essentially involves estimating duration for each activity
based on the quantity of resources expected to be used on the activity.
• Once the updated schedule and budget have been calculated, they are compared with the
baseline schedule and budget and necessary control measures are undertaken.
• Typical tools for project scheduling include Work Breakdown Structure (WBS) and Gantt Chart as
explained in the subsequent slides.
Quality
Policy
Quality Manual
Procedures
Procedures
• During the planning stage, ensure that time and resources are kept
aside for safety aspects. There should be no compromise on this front
• Contractors too should include a similar budget in their estimates
• Resource & time allocation to be made in customized software like
Microsoft Project or Primavera
• Dedicated team to be formed at head-office and local offices/mines for
allocation of human resources. Tracking must be done using
professional software
• Weekly reports of time spent by resources, under-utilization, over-
utilization must be generated and submitted to head office
• There is also a tendency to look at business cases through a very simplistic NPV perspective and
high/low/base-case scenarios
• Risk assessment is also treated as a qualitative assignment without focusing on quantification of the
key risk factors
Key takeaways
Executives and project managers need not transform into financial risk
mathematicians; but need to change thinking from discrete and finite numbers (like
NPV) into uncertainties/likelihoods/expected returns
• Thus, risk is passed on to parties who are not equipped to manage the level of risk and thus
jeopardize the project
• Assess on a project by project basis the needs related to risk sharing and
contracting
1. Coal Block and Iron Ore Blocks are for Captive Mining – Coal and iron ore
to be consumed for the specified end use in their own plants.
2. Time frame for mine development and risks of delay in development
indicate likely synergies in MDO route for development and operations of
mines.
3. Mining being a highly regulated activity, development of captive mine will
have regulatory risks and raw materials security issues.
4. Coal and iron ore mining being highly specialized engineering activity, mine
development may necessitate organizational development.
29 Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Boundaries of the Strategic Decision
• The engagement will be to select a strategic partner for coal and iron ore
mining within the confines of legal permissibility, economic benefits, and
environmental and social responsibility.
30 Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Pertinent Questions for the Way Forward
31 Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Market Place – Contract mining companies in India
• Private participants in contract mining in India are fewer in number and smaller
in size. But there has been significant interest in contract mining by major
business houses.
• A large number of foreign participants are awaiting de-regulation. Indian
participants are keen in bidding through joint ventures and consortiums.
32 Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Process of Selection of MDO
33 Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Issues sought to be addressed through the Processes
34 Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Risks in Pre-mature Bidding Process
1. Risk of lack of interest from the prospective bidders – lower number of bids
may necessitate re-bidding.
2. Conditional bidding may lead to disputes and legal issues – conditions may
be reserve estimate, stripping ratio, coal/ore quality, geo-technical
parameters, etc.
3. The risk of error of judgement will have to be born in some measure by the
Client.
4. Contract negotiations may be difficult in absence of reliable data and
benchmarks.
35 Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Prudent Approach to Bidding Process - Preparatory
36 Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Inputs to Contract Design
Arbitration Mechanism
Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Identification of Counterparty Risk
Post-contract Phase
• Owner – Mining lease revocation, financial losses and time delays
• Contractor – Investment losses, lower returns
Production Phase
• Owner – Financial losses due to operational failure of contractor
• Contractor – Financial losses due to payment default by the owner
Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Effective Contracts and Mine Performance
Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.
Contacts
Contacts
Dipesh Dipu
Director | Consulting | Mining
Main: +91 (0) 40 4031 2000
Direct: +91 (0) 98495 53404
Email : ddipu@deloitte.com
41 Winning. In challenging markets and beyond. © 2011 Deloitte Touche Tohmatsu India Pvt. Ltd.