Professional Documents
Culture Documents
1. Pure Helium India Pvt. Ltd. v. Oil and Natural Gas Commission
2003 8 SCC 593
1
contract and performance under the contract is certainly a possible
view.”
A….- Held, the 1996 Act makes provision for the supervisory role of
courts and for the review of the arbitral award only to ensure fairness
– This supervisory role is to be kept at a minimum level and interference
is envisaged only in cases of fraud or bia s, violation of natural justice,
etc. – Interference on ground of “patent illegality” is permissible only
if the same goes to the root of the matter, and a public policy violation
should be so unfair and unreasonable as to shock the conscience of the
court.
112. It is trite that the terms of the contract can be express or implied.
The conduct of the parties would also be a relevant factor in the matter
of construction of a contract. The construction of the contract
agreement, is within the jurisdiction of the arbitrators having regard
to the wide nature, scope and ambit of the arbitration agreement and
they cannot, be said to have misdirected themselves in passing the
award by taking into consideration the conduct of the parties. It is also
trite that correspondences exchanged by the parties are required to be
taken into consideration for the purpose of construction of a contract.
4. Harish Chandra & Co. v. State of U.P. , (2016) 9 SCC 478 : 2016
SCC OnLine SC 915 at page 485
2
“4. … The award is a speaking one. The arbitrator has assigned
sufficient and cogent reasons in support thereof. Interpretation of
a contract, it is trite, is a matter for the arbitrator to determine
(see Sudarsan Trading Co. v. State of Kerala[Sudarsan Trading
C o . v . S t a t e o f K e r a l a , ( 1 9 8 9 ) 2 S C C 3 8] ) . S e c t i o n 3 0 o f t h e
Arbitration Act, 1940 providing for setting aside an award is
restrictive in its operation. Unless one or the other condition
contained in Section 30 is satisfied, an award cannot be set aside.
The arbitrator is a Judge chosen by the parties and his d ecision
is final. The court is precluded from reappraising the evidence.
Even in a case where the award contains reasons, the interference
herewith would still be not available within the jurisdiction of the
court unless, of course, the reasons are totally perverse or the
judgment is based on a wrong proposition of law. An error
apparent on the face of the records would not imply closer
scrutiny of the merits of documents and materials on record. Once
it is found that the view of the arbitrator is a plausib le one, the
court will refrain itself from interfering….”
………..
26. The grounds such as inadequacy of reasons in support of an award,
error committed by the arbitrator on facts, alternate and/or more
plausible view could be taken then what is taken by the arbitrator,
improper appreciation of evidence done by the arbitrator in recording
any finding, etc. are not the grounds on which any award much less a
reasoned award can be set aside. In other words, none of these
grounds can be made the foundation for set ting aside the award
because they do not fall within the four corners of any of the three
sub-clauses of Section 30 of the 1940 Act.”
25. From the aforesaid decision of this Court. and the last one in
particular. it is clear that when the arbitrator is required to construe
a contract then merely because another view may be possible the court
would not be justified in construing the contract in a different manner
3
and then to set aside the award by observing that the arbitrator has
exceeded the jurisdiction in making the award.
6. Satya Jain (D) Thr. L.Rs. and Ors. V. Anis Ahmed Rushdie (D)
Thr. L.Rs. and Ors. (2013) 8 SCC 131
4
and others had considered the circumstances when reading an
unexpressed term in an agreement would be justified on the basis that
such a term was always and obviously intended b y and between the
Parties thereto. Certain observations in this regard expressed by
Courts in some foreign jurisdictions were noticed by this court in
para 51 of the report. As the same may have application to the present
case it would be useful to notice the said observations:
“Prima facie that which in any contract is left to be implied and need
not be expressed is something so obvious that it goes without saying;
so that, if, while the Parties were making their bargain, an officious
bystander, were to suggest some express provision for it in their
agreement, they would testily suppress him with a common ‘Oh, of
course! Shirlaw v. Southern Foundries (1926) Ltd. (1939) 2 All ER
113 (CA)
-----------------------------------------------------------------
-----------------
An expressed term can be implied if and only if the court finds that
the Parties must have intended that term to form part of their
contract: it is not enough for the court to find that such a term would
have been adopted by the Parties a s reasonable men if it had been
suggested to them: it must have been a term that went without saying,
a term necessary to give business efficacy to the contract, a term
which, although tacit, formed part of the contract which the Parties
made for themselve s. Trollope and Colls Ltd. v. North West
Metropolitan Regl. Hospital Board (1973) 2 All ER 260 (HL)”
35. The business efficacy test, therefore, should be applied only in
cases where the term that is sought to be read as implied is such
which could have been clearly intended by the Parties at the time of
making of the agreement.”
(Award Internal Page 60 -61 Paragraph 184)
5
EWHC 722 (Comm) at (13) : 2008(2) All. E. R. (Comm) 612 at (13), was
again the subject matter of agreement, and I repeat and incorporate it:
6
E. Brief Order is concluded contract:
7
Furthermore, clause 8.0 also finalized the date of commence ment of
activities under the contract, as the date of issuance of the
‘notification of award’
12. United India Insurance Co. Ltd. v. Pushpalaya Printers 2004 (3)
SCC 694
8
14. Kranti Associates Private Limited V. Masood Ahmed Khan And
Others (2010)9 SCC 496
9
16. ABL International Ltd. And Another V. Export Credit Gurantee
Corporation of India Ltd. And Others (2004)3 SCC 553
23. It is clear from the above observations of the Court, once the
State or an instrumentality of the state is the party of the contract, it
has an obligation in law to act fairly, justly and reasonably which is
requirement of Article 14 of the Constitution of India. Therefore, if
by the impugned repudiation of the claim of the appellant the first
respondent as an instrumentality of the State has acted in
contravention of the above said requirement of Article 14, then we
have no hesitation in holding that a writ court can issue suitable
directions to set right the arbitrary actions of the first respondent.
10
consumes valuable time which could be used for settling more
important disputes. We unhesitatingly deprecate this practice.”
It is correct that the learned single Judge has not decided this
Objection of the Board, may be for any reason, but after examining it,
we find that the counter claims have rightly not been awarded by the
Arbitrators. In its co unter claim
Part-1, the Board has claimed penalty of Rs. 41,29.350.50 purporting
to be in terms of Clause 2 of the contract agreement and interest
thereon at the rate of 18% per annum from 1 -11 -1988 till the date of
actual payment and in Part II it has claimed an amount of Rs.
3,70,20,000/by way of loss of net revenue, additional cost to the Board
on account of escalation of prices and loss of interest on the blocked
up capital restricted to a period of 9 months only out of the extended
period of 51 mont hs and 21 days and also interest thereon @ 18% per
annum from 1-1-1988 till the date of actual payment. These two
counter claims are inter-linked with the question of extension of time
from 11-4-1985 till the work was actually completed on 31 -7-1989 i.e.
51 months and 21 days after the stipulated date of completion on 10 -
4-1985. It is not in dispute that "provisional extensions" were granted
from time to time up to 30 -6-1989 by the Superintending Engineer by
which date the work was completed. No doubt, in these letters the
extension was qualified as provisional subject to the right of the Board
"to recover liquidated damages" in accordance with the provisions of
Clause 2 of the contract agreement and also subject to the time being
the essence of the agreemen t. The completion certificate was also
11
issued provisionally, without prejudice to the rights of the Board to
recover liquidated damages in accordance with the provisions of the
Contract Agreement by the Executive Engineer, Bhaba Construction
Division No. 4, HPSEB, Bhabanagar on 31-10-1989 certifying that the
contracted work has been completed to his general satisfaction.
Thereafter, the claimants by their letter dated 31 -10 1990 (Ex. C-22(6)
before the Arbitrators) represented to the Chairman of the Board to
finally settle all their pending claims and also to ratify the provisional
extensions granted to them by the Superintending Engineer from 30 -
9-1987 to 31-7-1989.
This letter was replied to by the Chief Engineer (P & M) of the Board
on 21-2-1991 (Ex. C-20 before the Arbitrators) informing the
claimants that their claims were not tenable, hence rejected and also
that the case relating to extension of time was under consideration of
the Board and the decision thereon will be communicated shortly but
after the claimants invoked the arbitration Clause 25 of the Contract
Agreement, by their letter dated 4 -3-1991 (Ex. C-14 (36), before the
Arbitrators), the Board informed them by its letter dated 8 -10-1991
that "keeping in view the fact that the Contractor has already gone
into arbitration in the case". It rejected the proposal to extend the
time up to 31-7-1989. Considering these facts and circumstances on
record in the light of Clauses 2, 5, 12 and 29A of the Contract
Agreement, the Arbitrators came to the conclusion that:-
12
Superintending Engineer and ta citly approved by the Chief
Engineer, is not only unjustified but is also, invalid and
inoperative in law.
51. The Arbitrators have relied upon the Judgment of the Supreme
Court in Hind Construction Contractors v. State of Maharashtra AIR
1979 SC 720 to come to the conclusion that time of two years was
never intended by the parties to be the essence of the contract and
the time as extended up to 31 -7-1989 was the essence of the contract,
till which date the work was completed. In the aforesaid case.
Tulzapurkar, J. said that the question whether or not "time was of the
13
essence of the contract would essentially be a ques tion of the
intention of the parties to be gathered from the terms of the contract."
It is further observed that: (at page 725)
"....... even where the parties have expressly provided that time
is of the essence of the contract such a stipulation will hav e to
be read along with other provisions of the Contract and such
other provisions may, on construction of the Contract, exclude
the inference that the completion of the work by a particular
date was intended to be fundamental, for instance. If the
contract were to include clauses providing for extension of time
in certain contingencies or for payment of fine or penalty for
every day or week the work undertaken remains unfinished on
the expiry of the time provided in the contract such clauses
would be construed as rendering ineffective the express
provisions relating to the time being of the essence of contract."
52. By holding that there was no delay on the part of the claimants,
as they have completed the work within the time extended, the counte r
claims for penalty compensation and loss of net revenue was not
maintainable. It is also held by the Arbitrators that despite reserving
the right to claim liquidated damages in terms of Clause 2 of the
Contract, this right was never exercised by the Boar d till written
statement was filed before the Arbitrator which shows that the
counterclaims were after thought. Above all for the compensation for
loss of revenue, the Board has not produced any evidence on record
that the other components of the project e xecuted by the other
agencies were completed prior to the completion of the work by the
claimants and, therefore, the Board could not generate electricity or
suffered in any other manner for the alleged delay in execution of the
component of the project entrusted to the claimants.”
(Emphasis supplied)
Filed by :
[MAKARAND D. ADKAR]
Advocate for the Respondent
232, M.C. Setalwad Lawyers Chamber
Supreme Court, New Delhi -110001
14
New Delhi
Filed on :
15