From: Eng.

Kamal Al Maqadma Date: 18/12/2018


(Project Manager-C032) Ref: CGC-C032-KA-AA-004-18

To: Eng. Imad Daher


(Construction Manager)
MEMO
Subject: MEP Damages

Dear Eng. Imad,

You are requested to investigate about the MEP (Electrical and Mechanical) sleeves

damages at site through civil work, this matter is not accepted and not allowed to be

repeated again.

Any charges we will receive from MEP department it had to be deducted from the

subcontractor who was the cause of that damages.

Note: see the attachment to check which area.

Best Regards,

Kamal Al Makadma
Signature

Position Project Manager

CC:
- Memo File

Tel.: +971 2 612 1999, Fax: +971 2 612 1900, P.O.Box: 112364, Abu Dhabi, United Arab Emirates
E-mail: info.uae@combinedgroup.net | website: www.combinedgroup.net
Form No. QMF 103-2 Rev. 3 Date: Dec. 07, 2015